Sie sind auf Seite 1von 6

Proceedings of the Institution of

Civil Engineers
Geotechnical Engineering 160
October 2007 Issue GE4
Pages 237–242
doi: 10.1680/geng.2007.160.4.237

Paper 14833
Received 26/06/2006
Accepted 04/04/2007
Guo Hui Lei Charles W. W. Ng
Keywords: field testing & Associate Professor, Professor, Department of Civil
monitoring/foundations/piles & Department of Civil Engineering, The Hong Kong
piling Engineering, Hohai University, University of Science and
Jiangsu, P. R. China Technology, Kowloon, Hong Kong

Rectangular barrettes and circular bored piles in saprolites


G. H. Lei MPhil, PhD and C. W. W. Ng MSc, PhD, CEng, MICE, MHKIE, MASCE

In the last two decades, many full-scale compression Rail Project. In addition to these pile loading tests with which
loading tests have been performed to verify the design the authors were involved, another 12 barrette and 16 bored
parameters of the shaft resistance of rectangular pile loading tests performed in Hong Kong were also critically
barrettes and large-diameter bored piles founding in reviewed and analysed. Details of the construction, load testing
deep-seated thick saprolites in Hong Kong. In this study, and interpreted test results of the 15 barrettes are reported by
comparisons are made between the results from the Lei 3 and Ng and Lei.4 For the 28 bored piles, shaft resistance
investigations of the behaviour of the mobilised shaft was analysed by Li5 and Ng et al.,6 and capacity and failure
resistance with respect to the relative pile–soil load criteria were studied by Yau 7 and Ng et al.8
movements (i.e. local displacements), the in situ soil
properties (i.e. standard penetration test values), and In this study, rectangular barrettes and circular bored piles,
the effective stress principle (with which the â values are which have their shaft resistance either fully mobilised (rating
estimated). Also, the behaviour of the mobilised shaft A, as explained later) or substantially mobilised (rating B), are
resistance for the barrettes and bored piles in Hong further reviewed, with the emphasis on a comparison of their
Kong is compared with that elsewhere. behaviour in terms of shaft resistance in Hong Kong saprolites
themselves and in soils elsewhere.
NOTATION
COV coefficient of variation 2. TYPICAL GEOLOGICAL CONDITIONS IN HONG
Ñ mean SPT value estimated over the whole saprolite KONG
layer The predominant rock types in Hong Kong are granitic,
â Bjerrum–Burland coefficient ¼ ôs =ó9v volcanic and sedimentary rocks. 9 Because of the subtropical
ó9v mean effective vertical stress of saprolite layer climate, with high temperature and heavy rainfall in the
ôs maximum unit shaft resistance at pile–saprolite summer, chemical and physical weathering processes have
interface been very active and have resulted in the formation of mantles
of alluvial, residual and saprolitic soils, which are up to 50 m
1. INTRODUCTION thick underlying, typically, fill and marine deposits and
In Hong Kong, excavated rectangular barrettes and large- overlying fresh rocks. The saprolites are also known locally as
diameter bored piles are commonly adopted as the foundations the Grade IV and V weathered rocks, which have decomposed
for tall buildings and heavy infrastructure projects. The to soil-like materials, but which retain the original texture,
founding strata for these piles are usually sound rocks, because fabric and structure of the parent rocks. 10,11 For a relatively
current design procedures assume a heavy reliance on end- detailed description of the geological formations of urban
bearing. Where competent rock is too deep to reach Hong Kong and the geotechnical phenomena associated with
economically, floating piles, founding in the overlying deep- piling in the various geological formations, see Malone. 12
seated thick saprolites and relying on shaft resistance, are
designed. However, design parameters for the shaft resistance 3. INTERPRETATION OF TEST DATA
must be verified by full-scale pile loading tests before they are
used in the final design. Without performing at least a test on 3.1. Unit shaft resistance
site, unit shaft resistance (i.e. side shear stress) in excess of Static maintained compression loading tests were carried out
10 kPa is not normally permitted by the local regulations. 1 on all the above-mentioned database barrettes and bored piles.
For details of the site locations, ground conditions,
In the last two decades, many full-scale compression loading instrumentation and loading test procedures for these piles, see
tests on instrumented barrettes and bored piles have been the source references.
performed in Hong Kong to verify design parameters. The
authors were heavily involved with the construction, testing In order to investigate the shaft resistance behaviour at the
and analyses of three barrettes and 12 bored piles. Among pile–saprolite interface, unit shaft resistance was interpreted
these, one barrette was tested at Kowloon Bay for purely from the test data using a consistent method. The unit shaft
research purposes, 2 and the remainder were tested for the West resistance is defined as the side shear stress acting on the pile

Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng 237

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.
shaft. For a pile segment in saprolite, the unit shaft resistance necessarily full mobilisation of the capacity. Rating C is
was calculated by dividing the axial load difference between assigned to results in which the degree of mobilisation is
the two ends of the segment by the perimeter surface area of unknown, or the local displacement is less than 1% of the
the segment. The axial load distribution along the depth of a diameter of the pile.
pile was obtained by multiplying the average vertical strain
measured from readings of the strain gauges at each level by a The mobilisation ratings assigned to the test piles have been
derived pile modulus. The vertical strains were calculated as shown in Ng et al.6 and Ng and Lei.4 Of the reviewed piles,
the differences between the readings and the initial readings seven barrettes (identified as B6–B9, B12, B13 and G2 in the
taken just before the loading test. The derived pile modulus is a source reference) and 11 bored piles (P1–P3, P18, P20, P22,
composite axial rigidity of pile concrete and steel. The Young’s P23a, P23b and P26–P28) were assigned rating A, and seven
modulus of the pile concrete was obtained by calibration barrettes (B1, B3–B5, B10, B11 and G1) and five bored piles
against the applied load at the pile head and the average (P4, P5, P8, P9 and P14) were assigned rating B. These barrettes
vertical strain at the top set of gauges. A best-fitting and bored piles have their shaft resistance fully or substantially
correlation between the Young’s modulus of pile concrete and mobilised at the pile–saprolite interface. All of the barrettes
the measured vertical strains at the virgin loading was applied were founded in granitic saprolites, and they were constructed
to derive the pile modulus for calculating the axial load under bentonite slurry using either hydraulic/mechanical grab
distribution. The virgin loading is one in which the applied or hydrofraise. Two barrettes (G1 and G2) were post-grouted at
loads are greater in magnitude than all previous loads at the the shaft in the granitic saprolites. Of the 11 bored piles with
time at which the load was applied during testing. In deriving rating A, four were founded in granitic saprolite, four in
the unit shaft resistance, the actual as-built cross-sectional area volcanic saprolite, and three in metasedimentary saprolite. The
of the piles from the concreting record was considered. bored piles were constructed using rope-operated grab and/or
reverse circulation drill (RCD). Stability of the excavated pile
In order to investigate the degree of mobilisation of the pile bores was maintained by the use of either temporary casings or
shaft resistance in saprolites, local displacement (i.e. relative bentonite slurry. Piles P18, P20 and P23 were post-grouted at
pile–soil movement) was also interpreted from the test data. the shaft in the granitic, volcanic and metasedimentary
The local displacement is that deduced at the vertical centre of saprolites respectively. A summary of these barrettes and bored
the pile segment in the saprolite layer. It was calculated by piles is given in Table 1. It should be noted that the results for
subtracting the measured pile head movement from the the bored piles constructed under bentonite slurry are very
shortening between the pile head and the mid-height of the limited and generally of poor quality. 5–8
segment. The shortening was estimated using measured vertical
strains. 4. MOBILISATION OF SHAFT RESISTANCE
Figure 1 shows the mobilisation of the unit shaft resistance
3.2. Mobilisation rating system with local displacement for the barrettes and for the bored piles
Among many other factors, it is well recognised that the constructed under water, with MR ¼ A and B: that is, with the
magnitude of the shaft resistance mobilised along the pile–soil mobilised maximum unit shaft resistance greater and less than
interface is also a function of the local displacement. A 90% of the ultimate unit shaft resistance respectively. As
minimum amount of local displacement is needed to mobilise expected, a fairly high degree of scatter of the mobilisation
the shaft resistance fully. In many circumstances, full capacity curves is observed. From the shapes of the shaft resistance
of the shaft resistance may not necessarily be achieved in full- mobilisation curves, no dilative soil behaviour can be
scale pile loading tests. In order to compare the interpreted identified, as otherwise it would be expected to produce a peak
values of the shaft resistance among the reviewed test piles at value of unit shaft resistance followed by strain-softening
similar degrees of mobilisation, a simple three-grade rather than unit shaft resistance gradually increasing towards
mobilisation rating (MR) system 6 is adopted to classify the an asymptote. The observed behaviour may be due to the
degree of mobilisation of the shaft resistance. method of testing. Dilative and strain-softening behaviour may
be more easily identified if displacement-controlled tests are
Mobilisation rating A (i.e. MR ¼ A) is assigned to test results carried out rather than maintained loading (i.e. stress-
that fall within 10% of the ultimate unit shaft resistance controlled) procedures.
determined using the Brinch Hansen 80% criterion. 13 This
defines failure as the stress (or the unit shaft resistance) at For nearly all of the barrettes and bored piles with MR ¼ A, at
which the strain (or the local displacement) is equal to four least 90% of the ultimate unit shaft resistance was mobilised at
times the strain at 20% smaller stress. The criterion assumes a an average value of local displacement equal to about 20 mm
hyperbolic relationship between stress and strain. (see Fig. 1). However, for most of the barrettes and bored piles
with MR ¼ B, the unit shaft resistance still tends to increase
Rating B is assigned to results that do not achieve a rating of A with increasing local displacement after 20 mm. Therefore, in
but which achieve or have been extrapolated to a local general, a moderately conservative local displacement for the
displacement of at least 1% of the diameter of a bored pile or mobilisation of the ultimate shaft resistance of the barrettes
equivalent diameter of a barrette assessed on an equal area and bored piles in saprolites can be identified to be about
basis. A displacement of 1% of the pile diameter is used as a 20 mm.
benchmark because of the availability of test results recorded
at and extrapolated to this displacement in the literature. It is In Singaporean and Malaysian residual soils, the shaft
also defined by GEO1 as corresponding to ‘substantial’ resistance of the bored piles was observed to be fully mobilised
mobilisation of the shaft resistance capacity, although not at local displacements of 4–10 mm 14 and 4–7 mm 15

238 Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.
Pile type Method of Saprolite type Sample size Ñ ôs /Ñ â ¼ ôs =ó9v
construction
95% Average COV 95% Average COV
confidence confidence
range range

Deep Construction by grab= Granitic 6A 24–119 1.18–1.42 1.30 0.12 0.16–0.36 0.26 0.49
rectangular hydrofraise under 6B 50–132 0.91–1.59 1.25 0.34 0.22–0.38 0.29 0.37
barrettes 3,4 bentonite slurry 6 A + 6 B 24–132 1.11–1.45 1.28 0.24 0.21–0.34 0.27 0.41
Shaft-grouted after Granitic 1A+1B 77 1.88 1.64 – 0.47 0.50 –
construction by 166 1.40 0.52
hydrofraise under
bentonite slurry
Large- Construction by RCD Granitic 1 A + 3 B 77–200 0.00–1.30 0.70 1.00 0.10–0.20 0.20 0.50
diameter under bentonite slurry
(1.0–1.5 m) Construction by grab/ Granitic 3 A + 3 B 65–140 0.60–1.30 1.00 0.40 0.20–0.40 0.30 0.33
bored RCD under water All saprolites: 8 A + 5 B 35–140 0.80–1.60 1.20 0.67 0.20–0.40 0.30 0.67
piles 5–7
with/without granitic, volcanic,
temporary casing metasedimentary
Shaft-grouted after construction by grab 3A 44–131 0.60–4.10 2.30 0.70 0.40–0.80 0.60 0.33
under water with temporary casing (all
saprolites)

Note: RCD ¼ reverse circulation drilling technique; A denotes MR ¼ A; B denotes MR ¼ B.

Table 1. Statistical results of maximum unit shaft resistance of barrettes and bored piles in Hong Kong saprolites

Kulhawy 18 suggest that the mobilisation of ultimate shaft


250
B Granitic resistance occurs at local displacements of 5–10 mm for piles
Unit shaft resistance: kPa

200 Granitic (shaft-grouted) in general. Generally speaking, compared with the cases
elsewhere, in Hong Kong larger local displacement is required
150 for full mobilisation of the shaft resistance capacity of barrettes
B
and bored piles. In other words, the ‘rate’ of shaft resistance
100 B BB B
mobilisation for these piles in Hong Kong is slower. The
50 B variation of local displacement may be due to the soil type, the
varying density and confining pressure, or the construction
0 workmanship, involving unknown levels of disturbance.
0 10 20 30 40 50 60 70 80 90 100
Local displacement: mm
(a) It is also shown in Fig. 1 that, compared with plain barrettes
and bored piles, shaft-grouted barrettes and bored piles show a
250 Granitic
Granitic (shaft-grouted) relatively stiffer unit shaft resistance response to local
Volcanic
Unit shaft resistance: kPa

Volcanic (shaft-grouted) displacement and a higher ultimate unit shaft resistance. This is
200
Metasedimentary because grouting increases both the lateral pressure (i.e. normal
Metasedimentary (shaft-grouted)
150 stress) on the pile–soil interface and the shear strength of the
interface.
100
B
5. MAXIMUM UNIT SHAFT RESISTANCE
50
Figure 2 shows the relationship between the maximum
0 mobilised unit shaft resistance, ôs , and the interpreted mean
0 10 20 30 40 50 60 70 80 90 100 uncorrected standard penetration test (SPT) values, Ñ, of
Local displacement: mm
saprolites for the barrettes and for the bored piles constructed
(b)
under water, with MR ¼ A and B. For plain barrettes (see Fig.
Fig. 1. Mobilisation of unit shaft resistance with local 2(a)), the maximum unit shaft resistance generally lies between
displacement: (a) for barrettes; (b) for bored piles 1.0Ñ and 1.5Ñ (kPa), with an average value of 1.28Ñ, a 95%
constructed under water (B denotes MR ¼ B, otherwise confidence range of 1.11Ñ to 1.45Ñ, and a coefficient of
MR ¼ A) variation (COV) of 0.24. The 95% confidence range of the
average value, used for assessing the precision and reliability
of the interpreted results from field measurements, is the
respectively. From three bored piles in sand constructed using interval for which there is a 95% chance that the average value
slurry, Touma and Reese 16 observed that failure of the sides of falls within the range. 19 The COV value, defined by the
the pile shaft takes place at a local displacement of about reciprocal of the ratio of the average value to its standard
10 mm. The Canadian Geotechnical Society 17 (CGS) and deviation, is an estimate of the scatter of the interpreted results

Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng 239

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.
Maximum unit shaft resistance, τs: kPa
bored piles in Hong Kong is generally low. It was observed that
300
τs/Ñ ⫽ 3·0 2·5 2·0 τs/Ñ ⫽ 1·5 τs/Ñ ⫽ 1·0 the maximum unit shaft resistance can be as high as 2.0Ñ (kPa)
250 for a barrette in weathered granite in Singapore, 24 and 2.7Ñ for
B
bored piles normally constructed by rotary drilling rigs and
200
short-flight augers in the same soil; 25 2.0Ñ for bored piles
τs/Ñ ⫽ 0·5
150 constructed generally dry in residual soils derived from
B
sedimentary rocks (consisting mainly of mudstone and
100 B B B
B sandstone) of the Jurong Formation in Singapore; 15 and 2.3Ñ
B Granitic
50 for bored piles constructed under both dry and wet conditions
Granitic (shaft-grouted)
0
in residual soils of weathered metasedimentary rocks of the
0 50 100 150 200 250 300 Kenny Hill Formation in Malaysia. 14 From loading tests on two
Mean SPT value, Ñ
barrettes in Singapore, 26,27 it was observed that the maximum
(a)
unit shaft resistance in old alluvium is also greater than 1.0Ñ.
Maximum unit shaft resistance, τs: kPa

300 The lower maximum mobilised unit shaft resistance obtained in


τs/Ñ ⫽ 3·0 2·5 2·0 τs/Ñ ⫽ 1·5 τs/Ñ ⫽ 1·0
Hong Kong may be caused by the difference in construction
250
practice.
200

150 τs/Ñ ⫽ 0·5 Figure 3 shows the relationship between the maximum
Granitic mobilised unit shaft resistance, ôs , and the mean effective
100 B Granitic (shaft-grouted)
B B Volcanic vertical stress, ó9v , at the mid-height of the corresponding
B Volcanic (shaft-grouted)
50 Metasedimentary
saprolite layer for the barrettes and for the bored piles
B
Metasedimentary (shaft-grouted) constructed under water, with MR ¼ A and B. For plain
0
0 50 100 150 200 250 300 barrettes, the Bjerrum–Burland â values 28–30 lie between 0.11
Mean SPT value, Ñ and 0.44, with an average value of 0.27, a 95% confidence
(b) range of 0.21–0.34, and a COV value of 0.41 (see also Table 1).
For the bored piles in granitic saprolites (as shown by the
Fig. 2. Relationship between maximum unit shaft resistance closed circles in Fig. 3(b)), the â values lie between 0.11 and
and mean SPT value, Ñ: (a) for barrettes; (b) for bored piles
constructed under water (B denotes MR ¼ B, otherwise 0.49, with an average value of 0.3, a 95% confidence range of
MR ¼ A) 0.2–0.4, and a COV value of 0.33. For all the bored piles in
granitic, volcanic and metasedimentary saprolites, the â values
lie between 0.11 and 0.66, with an average value of 0.3, a 95%
from the field measurements. The larger the COV value, the
more scattered are the results. These statistical results for
Maximum unit shaft resistance, τs: kPa

maximum unit shaft resistance for the barrettes and bored piles 300 β ⫽ 0·6 β ⫽ 0·5 β ⫽ 0·4
Granitic
with MR ¼ A and/or B are presented in Table 1. 250
Granitic
B β ⫽ 0·3
(shaft-grouted)
200 β ⫽ 1·0
The lower-bound value of the maximum unit shaft resistance
β ⫽ 0·2
for the barrettes (see Fig. 2(a)) is identical to the lower-bound 150
value of 1.0Ñ for bored piles in sand by Meyerhof 20 and B
B
100 B B β ⫽ 0·1
CGS. 17 However, this is different from the cases for bored piles B
B
constructed under water. For bored piles in granitic saprolites 50
(as shown by the closed circles in Fig. 2(b)), the maximum unit
0
shaft resistance lies in a relatively wide range of 0.5Ñ to 1.5Ñ 0 100 200 300 400 500 600 700 800
(kPa), with an average value of 1.0Ñ, a 95% confidence range Mean effective vertical stress: kPa
(a)
of 0.6Ñ to 1.3Ñ, and a COV value of 0.4. For all of the bored
Granitic
Maximum unit shaft resistance, τs: kPa

piles in granitic, volcanic and metasedimentary saprolites, the 300 Granitic (post-grouted) β ⫽ 0·5 β ⫽ 0·4
maximum unit shaft resistance generally lies between 0.5Ñ and Volcanic
250 Volcanic (post-grouted) β ⫽ 0·3
3.0Ñ (kPa), with an average value of 1.2Ñ, a 95% confidence Metasedimentary
range of 0.8Ñ to 1.6Ñ, and a COV value of 0.67. Clearly the 200 Metasedimentary (post-grouted)
β ⫽ 1·0 β ⫽ 0·6 β ⫽ 0·2
results for the bored piles are more scattered than those for the 150
barrettes, and the lower-bound value of the maximum unit
shaft resistance is smaller. Generally, the average value of 100 B B β ⫽ 0·1
B
ultimate unit shaft resistance mobilised with respect to the 50 B
B
mean SPT value for the barrettes is comparable to that for
0
bored piles constructed under water. This is consistent with the 0 100 200 300 400 500 600 700 800
results from various comparative studies performed Mean effective vertical stress: kPa
elsewhere, 21–23 which report no significant difference in (b)
performance with the use of bentonite slurry.
Fig. 3. Relationship between maximum unit shaft resistance
and mean effective vertical stress: (a) for barrettes; (b) for
However, compared with the barrettes and bored piles in
bored piles constructed under water (B denotes MR ¼ B,
tropically weathered soils in other Asian countries, the otherwise MR ¼ A)
maximum mobilised unit shaft resistance of the barrettes and

240 Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.
confidence range of 0.2–0.4, and a COV value of 0.67. that for bored piles in Hong Kong, although the results for
Generally, similar to the ôs /Ñ value, the results for the bored bored piles are more scattered than those for barrettes.
piles are more scattered than those for the barrettes, and the (c) Compared with barrettes and bored piles in old alluvium,
average â value (¼ 0.27) for the barrettes is close to the residual soils and weathered granites in Singapore and
average â value (¼ 0.3) for the bored piles constructed under bored piles in residual soils in Malaysia, the ôs /Ñ values for
water. barrettes and bored piles in saprolites in Hong Kong are
generally low. The range of â values for barrettes and
From a loading test on a barrette in a residual soil named bored piles in Hong Kong is comparable only to the â
Guadalupe Tuff in the Philippines, a relatively low â value of values recommended for the design of bored piles in loose
about 0.2 was back-calculated by Fellenius et al. 31 For the sand elsewhere.
design of bored piles in loose sand, Davies and Chan 32 (d ) Compared with non-grouted barrettes and bored piles,
recommend â values of 0.15–0.3, and for the design of cast-in- shaft-grouted barrettes and bored piles show a relatively
place piles in loose sand, CGS 17 recommend â values of 0.2– stiffer unit shaft resistance response to local displacement
0.4. For the design of drilled shafts in sands, O’Neill and and a higher ultimate unit shaft resistance.
Reese 33 recommend that â values decrease with the square root
of depth (< 26 m), but that a constant minimum â value of ACKNOWLEDGEMENTS
0.25 for deeper levels be applied. This minimum â value would This research project is supported by a research grant (HIA96/
be implemented over the lower sections of the deep barrettes 97.EG03) from the Hong Kong University of Science and
and bored piles in Hong Kong. Compared with these Technology and a research grant (CRC96/99.EG04) from the
recommended â values, the range of the â values for the Research Grant Council of Hong Kong.
barrettes and bored piles in saprolites in Hong Kong is
comparable only to the â values for the design of bored piles in REFERENCES
loose sand overseas. 1. GEOTECHNICAL ENGINEERING OFFICE (GEO). Pile Design and
Construction. Geotechnical Engineering Office, Department
For the shaft-grouted barrettes G1 (Ñ ¼ 166) and G2 (Ñ ¼ 77), of Civil Engineering of the Hong Kong Government of the
the â values are 0.52 and 0.47 respectively, giving an average Special Administrative Region, China, 1996, GEO
value of about 0.5, which is about 1.34 times the average â Publication No. 1/96.
value of 0.37 for the plain barrettes in granitic saprolites with 2. NG C. W. W., RIGBY D. B., NG S. W. L. and LEI G. H. Field
Ñ values greater than 77. The increase in the â value due to studies of well-instrumented barrette in Hong Kong.
shaft grouting is consistent with the increase in the ôs /Ñ value, Journal of Geotechnical and Geoenvironmental Engineering,
because the average ôs /Ñ value for the shaft-grouted barrettes ASCE, 2000, 126, No. 1, 60–73.
is about 1.28 times that for the plain barrettes (see Table 1). In 3. LEI G. H. Behaviour of Excavated Rectangular Piles
general, the average â and ôs /Ñ values for shaft-grouted (Barrettes) in Granitic Saprolites. PhD thesis, Hong Kong
barrettes are about 1.3 times those for plain barrettes. However, University of Science and Technology, 2001.
according to the limited data, the grouting effect on improving 4. NG C. W. W. and LEI G. H. Performance of long rectangular
the shaft resistance for the barrettes is not as effective as that barrettes in granitic saprolites. Journal of Geotechnical and
for the bored piles in saprolites in Hong Kong (see Table 1) and Geoenvironmental Engineering, ASCE, 2003, 129, No. 8,
in clay and sand in Bangkok, 34 because the measured 685–696.
maximum mobilised unit shaft resistance of the shaft-grouted 5. LI J. H. M. Side shear resistance of large diameter bored
bored piles is approximately double that of the non-grouted piles in weathered geomaterials. MPhil thesis, Hong Kong
bored piles. From loading tests on a bored pile and a deep University of Science and Technology, 2000.
barrette in Egypt, Hamza and Ibrahim 35 also observed that the 6. NG C. W. W., LI J. H. M. and YAU T. L. Y. Behaviour of large
unit shaft resistance derived in the grouted sand segment is diameter floating bored piles in saprolitic soils. Soils and
about 1.5 times that derived in the non-grouted sand segment. Foundations, 2001, 41, No. 6, 37–52.
7. YAU T. L. Y. Capacity and Failure Criteria of Bored Piles in
Soils and Rocks. MPhil thesis, Hong Kong University of
6. CONCLUSIONS Science and Technology, 2000.
The following conclusions can be drawn from the comparisons 8. NG C. W. W., YAU T. L. Y., LI J. H. M. and TANG W. H. New
of the interpreted shaft resistance behaviour for barrettes failure load criterion for large diameter bored piles in
constructed under bentonite and bored piles under water in weathered geomaterials. Journal of Geotechnical and
Hong Kong and barrettes and bored piles elsewhere. Geoenvironmental Engineering, ASCE, 2001, 127, No. 6,
488–498.
(a) For the barrettes and bored piles in saprolites in Hong 9. ALLEN P. M. and STEPHENS E. A. Report on the Geological
Kong, a moderately conservative local displacement can be Survey of Hong Kong, 1967–1969. Hong Kong
identified to be approximately 20 mm for the mobilisation Government Press, 1971.
of the shaft resistance capacity. This local displacement in 10. BRAND E. W. Written discussion: evolution of a
Hong Kong is relatively larger than that elsewhere, classification scheme for weathered rock. Proceedings of
according to the limited number of documented case the 2nd International Conference on Geomechanics in
histories. Tropical Soils, Singapore, 1988, vol. 2, pp. 515–518.
(b) The average ôs /Ñ and â values for barrettes are 1.28 and 11. GEOTECHNICAL CONTROL OFFICE (GCO). Guide to Rock and Soil
0.27, and for bored piles 1.2 and 0.30 respectively. The Descriptions (Geoguide 3). Geotechnical Control Office,
mobilised shaft resistance for the barrettes is comparable to Department of Civil Engineering of the Hong Kong

Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng 241

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.
Government of the Special Administrative Region, China, 24. HO C. E. Deep barrette foundation in Singapore weathered
1988. granite. Proceedings of the 11th Southeast Asian
12. MALONE A. W. Geotechnical phenomena associated with Geotechnical Conference, Singapore, 1993, pp. 529–534.
piling in Hong Kong. Quarterly Journal of Engineering 25. CHANG M. F. and WONG I. H. Axial load test behaviour of
Geology, 1990, 23, No. 4, 289–305. bored piles in weathered granite. Proceedings of the 10th
13. BRINCH HANSEN J. Discussion on ‘Hyperbolic stress–strain Asian Regional Conference on Soil Mechanics and
response: cohesive soil’, by R. L. Kondner. Journal of Soil Foundation Engineering, Beijing, 1995, vol. 1, pp.
Mechanics and Foundation Engineering, ASCE, 1963, 89, 185–188.
No. SM4, 241–242. 26. HO C. E. and TAN C. G. Barrette foundation constructed
14. BALAKRISHNAN E. G., BALASUBRAMANIAM A. S. and PHIEN- under polymer slurry support in old alluvium. Proceedings
WEJ N. Load deformation analysis of bored piles in residual of the 12th Southeast Asian Geotechnical Conference,
weathered formation. Journal of Geotechnical and Kuala Lumpur, 1996, pp. 379–384.
Geoenvironmental Engineering, ASCE, 1999, 125, No. 2, 27. HO C. E. and LIM C. H. Barrettes designed as friction
122–131. foundations: a case history. Proceedings of the 4th
15. CHANG M. F. and BROMS B. B. Design of bored piles in International Conference on Case Histories in Geotechnical
residual soils based on field-performance data. Canadian Engineering, St Louis, MO, 1998, pp. 236–241.
Geotechnical Journal, 1991, 28, No. 2, 200–209. 28. BJERRUM L. and JOHANNESSEN I. J. Measurements of the
16. TOUMA F. T. and REESE L. C. Behaviour of bored piles in compression of a steel pile to rock due to settlement of the
sand. Journal of Geotechnical Division, ASCE, 1974, 100, surrounding clay. Proceedings of the 6th International
No. 7, 749–761. Conference on Soil Mechanics and Foundation Engineering,
17. CANADIAN GEOTECHNICAL SOCIETY (CGS). Canadian Montreal, 1965, vol. 2, pp. 261–264.
Foundation Engineering Manual, 4th edn. Technical 29. BJERRUM L., JOHANNESSEN I. J. and EIDE O. Reduction of
Committee on Foundations, Canadian Geotechnical negative skin friction on steel piles to rocks. Proceedings of
Society, Bitech Publishers, Richmond, BC, 1995. the 6th International Conference on Soil Mechanics and
18. KULHAWY F. H. Limiting tip and side resistance: fact or Foundation Engineering, Mexico City, 1969, vol. 2, pp.
fallacy? Proceedings of the Symposium on Analysis and 27–34.
Design of Pile Foundations, ASCE, New York, 1984, pp. 30. BURLAND J. B. Shaft friction of piles in Clay. Ground
80–98. Engineering, 1973, 6, No. 3, 30–42.
19. RAWLINGS J. O., PANTULA S. G. and DICKEY D. A. Applied 31. FELLENIUS B. H., ALTAEE A., KULESZA R. and HAYES J. O-cell
Regression Analysis: A Research Tool, 2nd edn. Springer- testing and FE analysis of 28-m-deep barrette in Manila,
Verlag, New York, 1998. Philippines. Journal of Geotechnical and Geoenvironmental
20. MEYERHOF G. G. Bearing capacity and settlement of piled Engineering, ASCE, 1999, 125, No. 7, 566–575.
foundations. Journal of Geotechnical Engineering Division, 32. DAVIES R. V. and CHAN A. K. C. Pile design in Hong Kong.
ASCE, 1976, 102, No. GT3, 197–228. Hong Kong Engineer, 1981, 9, No. 3, 21–28.
21. BURLAND J. B. Discussion (Session 4: Drilling muds). In 33. O’NEILL M. W. and REESE L. C. Drilled Shafts: Construction
Proceedings of the Symposium on Grouts and Drilling Muds Procedures and Design Methods. US Department of
in Engineering Practice. Butterworths, London, 1963, pp. Transportation, 1999, Federal Highway Administration
223–225. Publication No. FHWA-IF-99-025.
22. KIENBERGER H. Diaphragm walls as load bearing 34. LITTLECHILD B. D., PLUMBRIDGE G. D. and FREE M. W. Shaft
foundations. In Proceedings of the Conference on grouted piles in sand and clay in Bangkok. Proceedings of
Diaphragm Walls and Anchorages. Institution of Civil the 7th International Conference and Exhibition on Piling
Engineers, London, 1975, pp. 19–21. and Deep Foundations, DFI, Vienna, 1998, 1.7.1–1.7.8.
23. FLEMING W. G. K. and SLIWINSKI Z. J. The Use and Influence 35. HAMZA M. and IBRAHIM M. H. Base and shaft grouted large
of Bentonite in Bored Pile Construction. Construction diameter pile and barrettes load tests. Proceedings of
Industry Research and Information Association, London, Geotech: Year 2000, Developments in Geotechnical
1977, CIRIA Report No. PG3. Engineering, Bangkok, 2000, vol. 2, pp. 219–228.

What do you think?


To comment on this paper, please email up to 500 words to the editor at journals@ice.org.uk
Proceedings journals rely entirely on contributions sent in by civil engineers and related professionals, academics and students. Papers
should be 2000–5000 words long, with adequate illustrations and references. Please visit www.thomastelford.com/journals for author
guidelines and further details.

242 Geotechnical Engineering 160 Issue GE4 Rectangular barrettes and circular bored piles in saprolites Lei • Ng

Downloaded by [ UNIVERSITY OF EXETER] on [11/09/16]. Copyright © ICE Publishing, all rights reserved.

Das könnte Ihnen auch gefallen