n 14 August last year, the city of Genoa in northwest Italy woke to a strong summer
storm. By 11.30am, the rain was so heavy that visibility had fallen dramatically.
Videos captured by security cameras show vehicles slowing down as they crossed
Morandi Bridge, which grew progressively more enveloped in a grey mist.

A few minutes later, a 200-metre section of the bridge collapsed, including one of its three
supporting towers. The tragedy killed 43 people and left 600 homeless.

It also dealt a hammer blow to Italy’s once-proud engineering history – and the country’s
confidence in its mastery of a key construction technology: concrete.
A little more than a kilometre long, crossing the Polcevera valley, a river, a railway depot, a
densely populated area and several large factories at an average height of 45 metres above the
ground, Morandi was one of the longest concrete bridges in the world when it opened in
September 1967.

The 1960s were Italy’s boom years. For the first time, many Italians could afford a car. But the
country’s roads – many of them narrow, meandering up mountains and twisting through city
centres – needed modernising. Morandi Bridge was the centrepiece of a brand-new network of
highways connecting Milan and Turin in the north to the tourist hotspots of the Ligurian
Riviera, bypassing a congested Genoa and ultimately completing the coastline highway that
runs from southern France to Tuscany.

Riccardo Morandi demonstrates a model of Morandi Bridge to the


then Italian president, Giuseppe Saragat, during the bridge’s
inauguration. Photograph: Handout/AFP/Getty Images

Named after Riccardo Morandi, the engineer who designed it, the new bridge was a multi-
span, cable-stayed bridge similar to the Brooklyn Bridge: regular towers, from which a series of
exposed steel cables stretched to the bridge’s deck.

But, although similar in shape, Morandi Bridge was very different in other ways. The deck was
entirely made of reinforced concrete, and it had only four cables per tower, instead of the
usual dozens. Crucially, the cables were covered in pre-stressed concrete – a type of treated
concrete invented by the French engineer Eugène Freyssinet. Unlike normal reinforced
concrete, which is generally best suited to resisting compression, the new pre-stressed
concrete was specifically designed to resist traction.

As a result, Morandi Bridge was stronger and lighter, with minimal use of steel, than any other
bridge of its era – and boasted a clean, distinct design that quickly became a symbol of Italian
engineering, tangible proof of the country’s technical abilities.

“The bridge’s concrete structure won’t need any maintenance,” boasted an article in La Stampa
newspaper ahead of the bridge’s opening. “Neither will its stayed cables, which are protected
from atmospheric agents by their concrete vest.”
Morandi Bridge under construction in 1965. Photograph:
Handout/AFP/Getty Images

Morandi himself became one of the most respected engineers in the nation – going on to use
the same technique elsewhere, including at Rome’s airport and a bridge over Libya’s Wadi el
Kuf that was the highest single-span bridge in the world – and helped Italy earn the reputation
as the nation that could bend concrete. He died in 1989.

The material was perfectly suited to postwar Italy. The country couldn’t afford the amount of
steel necessary to build something like the Brooklyn Bridge: steel was in short supply because
of international sanctions that had been placed against the fascist government, and Italy
lacked the resources to produce steel domestically. It was, however, rich in the clays and river
sediments necessary for concrete production. Led by Morandi, the country’s engineers learned
how to achieve the same results with concrete that they would with steel.

The legacy? Thousands of concrete viaducts, tunnels and bridges that together form a vast
engineering triumph.

Today, the country is still one of the top cement producers and is home to the eighth largest
cement company in the world.

“Morandi, for us engineers, is still a reference and considered to be a precursor,” says Marco di
Prisco, a professor of construction science at the Polytechnic Institute of Milan and researcher
on the life expectancy of concrete buildings.

But being an innovator, Di Prisco notes, often comes at a cost.

“Every time you create something new, you take some risks.”

In the 1960s little was known about the interaction of materials, or the effects of pollution and
climate on corrosion. Traffic volumes were very different, and concepts such as the durability
or lifespan of a building were not commonly discussed. “Back then, you didn’t really think in
terms of durability,” Di Prisco says. “Whereas today we focus much more on how to extend a
building’s life. We even come up with a maintenance guide to keep structures in good
conditions.”
Demolition work on Morandi Bridge in February 2019. A new
bridge designed by Renzo Piano is due to open in 2020.
Photograph: Luca Zennaro/EPA

Why exactly the bridge collapsed last August is yet to be understood. A team of experts
working with the investigators issued a report this month stating that the bridge samples
analysed showed evidence of corrosion and some construction errors, but they steered clear
from attributing a cause to the collapse.

“A bridge is like a car,” says Luigi Gambarotta, professor of structural mechanics at the
University of Genoa. “You can’t overload it, and to keep it working you need to change the
broken parts.”

That was difficult in the case of Morandi Bridge: the cables were difficult to inspect, and it was
unclear how they were coping with increased traffic loads.

“When I visited the bridge in the early 1990s for a documentary on Morandi’s work, I was
[surprised] to see fissures and corrosion just 20 years after its completion,” says Giuseppe
Imbesi, an architect who worked with Morandi on a bridge proposal for the Strait of Messina.

Morandi himself was surprised to see the structure age faster than he had anticipated. In 1979
he issued a report detailing a number of interventions to protect the structure against
pollution from nearby factories and the salty sea air.

Little, however, was done, and by 1992 the trademark concrete cables were heavily corroded.
The company that managed the bridge, Autostrade per l’Italia – then owned by the state –
decided to add extra new cables around the corroded ones, rather than replace them. It also
neglected to retrofit the remaining two sets.

The collapsed Morandi bridge in August last year. Photograph:


Luca Zennaro/EPA
“It was a criminal, criminal act not to intervene,” says the architect Antonino Saggio, who is
leading a campaign to save what remains of the bridge. Despite Saggio’s efforts, the bridge is
currently being cut into pieces and torn down. A new bridge designed by Renzo Piano is due to
open in 2020.

Despite Italy’s rather notorious reputation for criminal infiltration into public works, few
suspect mafia involvement in the bridge’s collapse. According to the concrete historian Tullia
Iori, a professor of architectural engineering at the University of Roma Tor Vergata, the
concrete industry was largely family-owned at the time and was easier to investigate, and
there was a robust tendering system for public works, which were assigned directly by the
state and included a high level of technical scrutiny.

Instead, it was probably simple neglect that felled the bridge. In April 2018, Autostrade – now a
private company – finally decided there was no more time to waste, and issued a tender offer
to retrofit the bridge. The repairs were supposed to start last autumn.

“They waited 25 years and then the bridge collapsed. This is how things go in Italy – you start
something and you never finish it,” says Saggio.

Morandi’s legacy, and with it the Italian national myth of concrete mastery, is now in doubt.
“He was an engineer with an incredible creativity, and was the best Italian bridge designer we
ever had,” says Emanuele Codacci-Pisanelli, a bridge engineer who helped restore Morandi’s
Wadi el Kuf Bridge.

But his structural ideas, despite being sound on paper, were difficult to execute. “Imbuing
stayed cables in pre-stressed concrete is such a difficult technique. It’s pretty complex,”
explains Codacci-Pisanelli.

“Morandi’s bridge was the most beautiful, the largest and the most audacious bridge we had in
Italy,” says Iori.

“It was the symbol of the country’s rebirth. We should have preserved it.”

• This article was amended on 27 February 2019 to clarify that the sanctions placed on Italy’s
fascist government did not continue after the end of the second world war

Guardian Concrete Week investigates the shocking impact of concrete on the modern world.
Follow Guardian Cities on Twitter, Facebook and Instagram and use the hashtag
#GuardianConcreteWeek to join the discussion or sign up for our weekly newsletter

News is under threat…


… just when we need it the most. Millions of readers around the world are flocking to the
Guardian in search of honest, authoritative, fact-based reporting that can help them
understand the biggest challenge we have faced in our lifetime. But at this crucial moment,
news organisations are facing an unprecedented existential challenge. As businesses
everywhere feel the pinch, the advertising revenue that has long helped sustain our journalism
continues to plummet. We need your help to fill the gap.

We believe every one of us deserves equal access to vital public service journalism. So, unlike
many others, we made a different choice: to keep Guardian journalism open for all, regardless
of where they live or what they can afford to pay. This would not be possible without financial
contributions from those who can afford to pay, who now support our work from 180 countries
around the world.
We have upheld our editorial independence in the face of the disintegration of traditional
media – with social platforms giving rise to misinformation, the seemingly unstoppable rise of
big tech and independent voices being squashed by commercial ownership. The Guardian’s
independence means we can set our own agenda and voice our own opinions. Our journalism
is free from commercial and political bias – never influenced by billionaire owners or
shareholders. This makes us different. It means we can challenge the powerful without fear
and give a voice to those less heard.

Reader financial support has meant we can keep investigating, disentangling and
interrogating. It has protected our independence, which has never been so critical. We are so
grateful.

We need your support so we can keep delivering quality journalism that’s open and
independent. And that is here for the long term. Every reader contribution, however big or
small, is so valuable. Support the Guardian from as little as $1 – and it only takes a minute.
Thank you.

Support The Guardian


Topics
Cities
Guardian concrete week
Italy
Architecture
Europe
Genoa bridge collapse
features

Das könnte Ihnen auch gefallen