Please answer the following question based on the information from the lecture notes, reference
books or journals.
Answer:
Ensure the efficient and effective delivery
Maximize value for money.
Focus on activities during contract execution/implementation.
Slide 13, week 1a.
Answer
Figure 1 – upstream and downstream phase, slide 14, week 1a.
Objective: time + quality + price, slide 15, week 1a.
3. According to Contract Act 1950, what are those 6 elements of legal contract?
Answer
• Offer
• Acceptance
• Consent
• Competency
• Consideration
• Legality
Answer
1
9. Advice client what are the suitable contract strategy to ensure the success
implementation of a project.
Answer
• To protect rights of contracting parties.
• To ensure parties deliver their commitments.
• To ensure
1. Delivery on time
2. Right quality
3. Within budget
Slide 23, week 1b
10. In all the conditions of contract, what are those similar conditions.
Answer
Instructions
Variations
Valuations
EOT,
Loss/expense,
Dispute resolution.
Contract document –
Correspondence forming part of Contract, Form of tender, Conditions of Contract,
Supplementary Conditions of Contract, Condition of Tendering, Special condition of
2
Appendices