RE Report – Foundation, ELS & Pile Cap Works

The Redevelopment of Block X at


The Hong Kong Polytechnic University

Resident Engineer Report For Site Meeting No.3


Foundation, ELS & Pile Cap (9 Dec. 2014)
Reporting Period: 25 Nov. 2014 to 8 Dec. 2014
Contract: Foundation, ELS & Pile Cap Works
Client: The Hong Kong Polytechnic University
Contract Commencement Date: 6 Nov. 2014
Contract Completion Date: 25 Dec. 2015
Contract Period: 415 Calendar Days
Contract Elapsed: 34 Calendar Days (8.2%)
Extension of Time Claims: 0 Days
Contractor: Yat Ming Construction & Engineering Ltd.

1.0 Progress / Programme of Works

Item ID Works Supposed construction period Completed Percentage Remark

Preliminary Works

1 19# Site set-up 6/11/14 to 19/11/14# 100% -

2 20# Detail condition survey 6/11/14 to 19/11/14# 100% -

3 21# CCTV drainage survey 8/11/14 to 8/11/14# 100% -

4 22# Site boundary survey 8/11/14 to 17/11/14# 100% -

5 23# Underground utilities detection 8/11/14 to 8/11/14# 100% -

6 24# Monitoring points installation 12/11/14 to 2/12/14# 100% Completed on 5 Dec. 14

7 25# Baseline monitoring 7/11/14 to 20/11/14# 100% -

8 26# Hoarding works 17/11/14 to 15/1/15# 60% on progress

Piling Works

9 39# BA10 Submission 20/11/14 to 26/11/14# 100% Submitted on 20 Nov. 14


48%
10 40# Predrilling Works at site area A 27/11/14 to 25/1/15# -
(12 / 25)

#Based on master programme (rev.00) dated 19 Nov. 2014

RE Report -Page 1 -
RE Report – Foundation, ELS & Pile Cap Works
The Redevelopment of Block X at
The Hong Kong Polytechnic University

2.0 Site Memo


Site Memo No. Description Issued Date
- - -

3.0 Outstanding Submission & Remedial Works


3.1 Contractor was requested to submit the Initial readings of monitoring points
3.2 Contractor was requested to submit the Method statement of sheet pile and other ELS works

4.0 Workmanship, Quality Assurance and Safety matter


4.1 Contractor was requested to provide and maintain safe, proper and tidy access for site personnel.
4.2 Contractor was requested to erect adequate temporary supports when demolition/ opening works is carried on.
4.3 Contractor was requested to erect barrier to protect against potential falling through voids of slab.
4.4 Contractor was requested to control breeding of mosquito on site.
4.5 Contractor was reminded to take adequate protection to the retained trees.
4.6 Contractor was requested to provide safe and adequate working platform on site, fence and toe board to
against falling of object.
4.7 Contractor was requested to provide adequate PPE to and ensure the use by the worker.

5.0 Material Delivery on Site


5.1 The following construction material was reported to be delivered on site in this reporting period.

5.1.1 Reinforcement
N/A

5.1.2 Concrete
N/A

6.0 Regulatory Visits (BD, GEO, etc.)


6.1 BD’s officers carried out site visit on 2 Dec. 2014.

7.0 Any Other Business


7.1 NIL

_______________________________
Resident Engineer – Helen Lu
Meinhardt (C & S) Ltd.

Date: 9 Dec. 2014


Dist: AT, WC, CP, CW, LT
Attachment A: Site photos for Reference

RE Report -Page 2 -
RE Report – Foundation, ELS & Pile Cap Works
The Redevelopment of Block X at
The Hong Kong Polytechnic University

Attachment A: Site photos for Reference

Site general view

Site general view

RE Report -Page 3 -
RE Report – Foundation, ELS & Pile Cap Works
The Redevelopment of Block X at
The Hong Kong Polytechnic University

Predrilling works & hoarding works at site area A

Hoarding works

RE Report -Page 4 -