Project Plan

for the

<insert name here>

Project

Version: 1.0.0
December 8, 2021

Sarasota County Government


Project Management Office
Sarasota County Government
<project name> Project Plan

Document Control

Document Approval
Approvals Signature Date

Document History
Revision Author/Reviser Comments Date

Document Storage

This document is created in Microsoft Word 2000 and is maintained in the <insert web
address or network drive/folder here>

Project Contact

The contact for this document is:

<project manager name>


Phone:
E-mail:
Sarasota County Government
Project Management Office (PMO)

PMO Ver. 1.0.0


ii
Sarasota County Government
<project name> Project Plan

Preface

This Project Plan defines the activities to be performed, the products to be developed, the
project schedule, and the resources required to develop the <project name here>. This
Project Plan will be used as a tool to track and manage the project.

Table 1 Initial Distribution List


Name Project Role Delivery
Information
Name Sponsor, Tester, E-mail, Web, etc.
etc

After Initial Distribution the lastest version of the project plan will be located on the EIT
Project Page located at <insert web address or network drive/folder here>

PMO Ver. 1.0.0


iii
Sarasota County Government
<project name> Project Plan

Table of Contents
Approvals............................................................................................................................... III
1 INTRODUCTION............................................................................................................. 6
1.1 Project Plan Purpose.............................................................................................................. 6
1.2 Evolution of the Project Plan................................................................................................6
2 PROJECT OVERVIEW....................................................................................................8
2.1 Project Scope........................................................................................................................... 8
2.2 Project Modules....................................................................................................................... 8
2.3 Project Assumptions and Constraints.................................................................................9
2.4 Software Life Cycle................................................................................................................. 9
2.5 Project Issues.......................................................................................................................... 9
2.6 Course Corrections................................................................................................................. 9
2.7 Testing.................................................................................................................................... 10
2.8 Training................................................................................................................................... 10
3 PROJECT MANAGEMENT...........................................................................................11
3.1 Project Management Objectives and Priorities...............................................................11
3.2 Procedures, Methods and Standards................................................................................11
3.3 Quality Assurance Plan........................................................................................................ 12
4 SYSTEM OVERVIEW....................................................................................................13
4.1 Figure 1 – System Connectivity........................................................................................ 13
5 CRITICAL COMPUTER RESOURCES.......................................................................15
5.1 Critical Computer Resource Assumptions........................................................................15
6 PROJECT SCHEDULE AND LEVEL OF EFFORT ESTIMATES............................15
7 RISK MANAGEMENT...................................................................................................17
8 EXTERNAL DEPENDENCIES......................................................................................18
APPENDIX A - MAJOR MILESTONE AND SCHEDULE SUMMARY.........................18
Appendix B – Initial Work Breakdown Structure.............................................................19

Index of Tables

Table 1 Reference Materials........................................................................................7


Table 2 Vendor Developed Modules..............................................................................8
Table 3 EIT Developed Modules...................................................................................8
Table 4 Project Roles................................................................................................12
Table 5 Project Contact List.......................................................................................12
Table 6 Summary of Critical Computer Resources for the Project...................................15
Table 7 Risk Management.........................................................................................17
Table 8 Major Milestone LOE and Schedule Summary...................................................18

PMO Ver. 1.0.0


iv
Sarasota County Government
<project name> Project Plan

1 Introduction

1.1 Project Plan Purpose


The purpose of this document is to provide a mechanism to communicate the
project scope, assumptions, constraints, project issues, risks, and Project
Management objectives as well as other pertinent project information. Project
details relating to work at the task level is in the Work Breakdown Structure
(Appendix B).

This project plan will be used to manage tasks, milestones, the project
schedule, project issues, risks, and resource assignments for the <project
name> project.

The Project Major Milestone and Schedule Summary can be found in Appendix
A. The Work Breakdown Structure, Schedule, and link to the Microsoft Project
Plan are contained in Appendix B. Appendix C contains the latest version of the
Project Issues Log.

1.2

1.3 Evolution of the Project Plan


This Project Plan will be reviewed and updated if necessary at the end of each
life cycle phase to ensure that it accurately reflects the status of the project.
The Project Plan will also be reviewed in the Weekly Project Status meeting and
modifications will be made if required.

If changes to the Project Plan’s Schedule Baseline are required, they will be
made once an approved Scope Change Request has been completed and
approved.

PMO Ver. 1.0.0


5
Sarasota County Government
<project name> Project Plan

Table 1 Reference Materials

Document Overview Created Document File Location and/or Name


By

PMO Ver. 1.0.0


6
Sarasota County Government
<project name> Project Plan

2 Project Overview

2.1 Project Scope


This project will allow for planning, design, development, testing, and
implementation of a <project name/short description>

2.2 Project Modules

Table 2 Vendor Developed Modules

Vendor Module(s)

Table 3 Internally Developed Modules


Group Module(s)

PMO Ver.
1.0.0
7
Sarasota County Government
<project name> Project Plan

2.3 Project Assumptions and Constraints

2.3.1 Assumptions

2.3.2 Constraints

2.4 Software Life Cycle (If applicable, remove if not)


Example: The software life cycle chosen for this project is Rapid Application
Development (RAD). This life cycle was chosen because this project is on a
fast track and as such must be developed in the shortest amount of time.

2.5 Project Issues


Issues and problems will be tracked in the Project Issues Log as they arise.
(Appendix C). The issues log will be uploaded to the <Applicable Project Web
Site> every <day of week/time>.

2.6 Course Corrections


Course corrections will be made throughout the project. These course
corrections will be discussed in the Weekly Project Status Meetings.

PMO Ver.
1.0.0
8
Sarasota County Government
<project name> Project Plan

2.7 Testing

2.7.1 Testing

<organization name(s) here> will be responsible for testing the following


components:
1. Component One
2. Component Two
3. etc.

2.7.2 User Acceptance Testing

Example: Business Center and PMO personnel will be responsible for the
development and implementation of the user acceptance test. The User
Acceptance Test (UAT) will ensure the primary sponsor and stakeholders are
satisfied that the requirements have been me. A signoff of the UAT by the
project sponsor is required prior to implementation.

Example: The User Acceptance Test will test at a minimum the following:

1. All GUIs and backend functionality


2. Manager Portal, GUIs, and backend functionality
3. Administration Portal, GUIs and backend functionality
4. Merit Increase Process Functionality
5. Performance Review Process
6. Performance Review Process – Multi-Rater Feedback
7. Employee Information Update Process

2.8 Training
A training plan will be developed outlining the roles and responsibilities of
the <appropriate organizations here>.

PMO Ver.
1.0.0
9
Sarasota County Government
<project name> Project Plan

3 Project Management

3.1 Project Management Objectives and Priorities


Example

1. Ensure the project completes on the targeted implementation date.

2. Assist in obtaining needed development and support tools to support


EIT development.

3. Assist (as needed) the development manager in identifying and


distributing responsibilities to development resources by components.

4. Coordinate external issues through the appropriate departments.

5. Conduct and lead weekly Project Management status meetings to


gather and report accurate status.

6. Report project progress through the creation of weekly status


reporting.

3.2 Procedures, Methods and Standards


Example

1. Project status will be reported weekly. Status reports will be


available on the EIT Project Web Site every Wednesday.

2. Changes to milestone dates, risks, or resources, which have the


potential to result in a Scope Change Request (SCR), will be
communicated to the project stakeholders in the weekly status
report.

3. Project Schedule issues will be tracked and controlled by the project


manager and the project team.

4. Project Schedule actuals in regards to Milestone Actual Start and


Finished dates will be reported via the Project Status Report

5. Risk Management will be performed throughout this project.

6. Weekly Status meetings will be held with select members of the


project team.

PMO Ver.
1.0.0
10
Sarasota County Government
<project name> Project Plan

Table 4 Project Roles


Example- Delete and add applicable project information

Project Role Name Responsibilities

XXX General Manager Name Oversee EIT and External


Development Efforts
Development Manager Name Development responsibilities
Project Manager Name Day-To-Day Project Oversight
Department Manager Name Manage Development Resources
Analysis Name, Resource 2 Gather and document project
Gustafson, Resource 1 requirements
Development Developer/Vendor names Develop application processes,
reports, custom modules and GUIs
Database DBA Design, develop, and support the
Administration Database
Quality Team Names Quality Team
Members

Table 5 Project Contact List


Example

Name Department Phone # E-mail Address Location

Diana Allen Human Resources/Payroll 316-1206 dallen@co.sarasota.fl.us 6700 Clark


Rd.
Brian Darley Enterprise Information 861-5418 bdarley@co.sarasota.fl.us SCTC
Technology
Barbara Human Resources/Personnel 861-5326 bthibaul@co.sarasota.fl.us 1600 Ringling
Thibault
Eleanor Zoppe Enterprise Information 650-9489 ezoppe@scgov.net SCTC
Technology
Resource 2 Enterprise Information 650-9196 egustaf@co.sarasota.fl.us SCTC
Gustafson Technology
Fred Dunayer Enterprise Information 650-2216 fdunayer@co.sarasota.fl.us SCTC
Technology
Gayle Gursky Finance and Administration 861-6176 ggursky@co.sarasota.fl.us 1301
Cattlemen
Nancy Fisher Administrative & Financial 861-6715 nfisher@co.sarasota.fl.us 2817
Services Cattleman
Nikki Snyder Payroll (Finance - Clerk) 861-5159 nsnyder@co.sarasota.fl.us 1660 Ringling

3.3 Quality Assurance Plan

PMO Ver.
1.0.0
11
Sarasota County Government
<project name> Project Plan

4 System Overview

4.1 Figure 1 – System Connectivity


Example Only

E-mailed HRMS Updates From Business


Center Rep to ABRA Administrator

SCG LAN

Business Center ABRA Administrator


HR Reps
HRMS ABRA
HRMS Database Full Access
Database Full Access
(Partial Update
Capability)

SCG
WAN

HRMS Note: Exporting Data from HRMS to ABRA


Database ABRA will not be attempted. There Database
will be no fall back plan to use the
Server Server
ABRA Database once HRMS has
been tested and implemented.

4.1.1 PLANNING
Example High-Level Planning Milestones

Task Status
Conduct a Database Model Review with the Complete – 02/07/03
Database Architect
Initial meeting with Web developers to discuss Scheduled – 02/10/03
details surrounding the GUIs
Meet with developers and Database Architect to Not scheduled. No resources
map GUI fields to database tables/fields identified as of 02/10/03.
Developers and Core team to meet to define Not started
data constraints
Define error processing for all GUIs Not started

PMO Ver.
1.0.0
12
Sarasota County Government
<project name> Project Plan

4.1.2 DATABASE CLEANUP ACTIVITIES


Example High-Level Planning Milestones

Task Status
Check for dates and numbers outside of normal Not started
ranges
Payroll/HR comparison (pay, classification, Not started
position from standard download)
Classification and Transaction updates Not started
Other Maintenance reports Not started
Entry of employee change transactions through Not started
last full pay period prior to implementation.

Example High-Level Estimate (optional)

Staff: Tom – Entry of Corrections; Entry of change transactions.


Resource 1 – Run Exception Reports and Comparisons; update code tables

Time: 40 hours

PMO Ver.
1.0.0
13
Sarasota County Government
<project name> Project Plan

5 Critical Computer Resources


The following table summarizes the list of the critical computer resources
required for this project for all impacted systems:

Table 6 Summary of Critical Computer Resources for the Project


Example

Resource New/Additional Type and/or Source


Application
Workstations N/A N/A N/A
(development,
testing, training,
production, user)
Servers (Production, 2 (Production) Microsoft IIS EIT
Test, Development, Microsoft SQL
and Training) Server 2000

Direct Access N/A N/A


Storage Device
(DASD)

Communications Connectivity Connectivity to SCG EIT


requirements from all SCG iNet
County Offices to
the Suncoast
Technology
Center
System Software, Development Identitech EIT
Utilities, Software Test Components
Tools Production SQL Server 2000
Software
Microsoft IIS
Software

5.1 Critical Computer Resource Assumptions


Example

1. The critical computer resources requirements as outlined above will be


required to complete Phase I of the HRMS project.
2. The EIT/Network Applications group created the above Critical Computer
Resource requirements.

6 Project Schedule and Level of Effort Estimates


Example

PMO Ver.
1.0.0
14
Sarasota County Government
<project name> Project Plan

 Level of effort (LOE) information would normally be documented in the


Milestone and Schedule Summary in the table of Appendix B. Since this
project follows a RAD approach, LOE information by Milestone will not be
supplied.

 Schedule estimates would normally be derived by estimating the project


at a task level, using task decomposition techniques, and by interviewing
the resources on the development team. Since this project will utilize a
RAD approach, the schedule has been built using the project completion
date and backing into a schedule from there.

 Estimates and timeframes noted in the Microsoft Project Plan (MPP)


contain our best guesses as to when certain tasks will be complete. The
MPP will evolve over time and be adjusted as needed. Milestone
information is documented in Appendix B at a summary level and the
schedule is documented in detail in the Work Breakdown Structure
referenced in Appendix C.

PMO Ver.
1.0.0
15
Sarasota County Government
<project name> Project Plan

7 Risk Management
Example

1. Risks will be identified throughout the project and reviewed in weekly project
status meetings.
2. Risks that are discovered externally will be evaluated by the project
lead/development team and considered for inclusion, then prioritized and
addressed if necessary in the Risk Statement Table (below).
3. All action items resulting from the Risk assessments will be noted in the
Project Issues log and reviewed in the Weekly Project Status meeting.

Table 7 Risk Management (Example)


# Risk Risk Priority Risk resolution progress
Consequence High,
Medium
, Low
1 Creeping Delayed High  User interface prototype used to gather
requirements Implementation high-quality requirements.
 Staged delivery approach will be employed
Increased Scope to provide some ability to change features
if needed.
2 Requirements or Delayed High  Project Status Meetings will check for
developer gold- Implementation suspected “gold-plating” concerns or
plating Increased Scope evidence.
3 Unstable tools Delayed High  New tools are used on this project.
delay schedule Implementation NOTE: No resolution known
4 Released software Delayed Medium  User interface prototype developed to
has low quality Implementation assure users would accept software.
 Internal Technical reviews will be
Low Customer conducted in the EIT Network Applications
Satisfaction group for requirements, designs, and code.
 Test planning assures system testing will
cover all functionality.
 Independent testers perform system tests.
5 Unachievable Sponsor Medium  Schedule is re-estimated several times over
schedule dissatisfaction the course of the project.
 Active project tracking assures that
Customer schedule slips have better chance of being
dissatisfaction recognized.
 Staged delivery allows for delivery of partial
functionality even if whole project takes
longer than expected.
6 Friction between Customer Low  User interface prototype aligns developers
developers and dissatisfaction and customers on same vision.
customers  Staged deliveries provide customers with
Project Failure evidence of steady progress.

PMO Ver.
1.0.0
16
Sarasota County Government
<project name> Project Plan

8 External Dependencies

8.1.1 This project is dependent upon …

PMO Ver.
1.0.0
17
Sarasota County Government
<project name> Project Plan

Appendix A - Major Milestone and Schedule Summary


Example: The following high-level milestones will be tracked for this project. The
detailed schedule and resources can be found in the Work Breakdown Structure
referenced in Appendix C.

Table 8 Major Milestone LOE and Schedule Summary


Phase 1 Scheduled Actual Scheduled Actual
Start Date Start Date End End
Complete Draft RS/HLA 01/21/03 01/21/03 02/04/03

Complete Draft Project Plan 01/24/03 01/23/03 02/07/03

Coding and Testing 02/18/03 02/18/03 05/24/02

Establish User Acceptance Test 05/26/03 05/28/03


(UAT) Environment
Promote Code/Tables to
Production

Execute UAT 05/28/03 06/21/03

Production Implementation 06/25/03 06/26/03

Warranty 06/26/03 07/26/03

Project Close-out 07/28/03 07/30/03

PMO Ver.
1.0.0
18
Sarasota County Government
<project name> Project Plan

Appendix B – Initial Work Breakdown Structure


<Next page>

PMO Ver. 1.0.0


19
<Project Name> Sarasota County Government

Example Only – Delete


ID Task Name Duration Start Date Finish Date Pred. Resource Names
1 HRMS Phase I WBS and Schedule 164 days? Fri 12/13/02 Thu 7/31/03    
2 Analysis 57 days? Fri 12/13/02 Tue 3/4/03    
3 Finalize Module Process Flows 27 days Fri 12/13/02 Tue 1/21/03    
Resource 1, Resource
4 Merit Increase 0 days Fri 12/13/02 Fri 12/13/02  
2
Resource 1, Resource
5 Performance Review 0 days Fri 12/13/02 Fri 12/13/02  
2
Resource 1, Resource
6 Review Process Flow with EIT 0 days Fri 12/13/02 Fri 12/13/02  
2
Resource 1, Resource
7 Performance Review (Multi-Rater Feedback Sub-Process) 0 days Fri 12/13/02 Fri 12/13/02  
2
Resource 1, Resource
8 Employee Update 0 days Fri 12/13/02 Fri 12/13/02  
2
9 Process Flows Complete 0 days Tue 1/21/03 Tue 1/21/03    
10            
11 Initial GUI Design 11.1 days Tue 1/21/03 Wed 2/5/03    
12 Design HR Admin Screens 10 days Tue 1/21/03 Mon 2/3/03   Resource 1
Send out HR Admin Screens and Business Center Data Cleanup
13 0.1 days Wed 2/5/03 Wed 2/5/03   Steve
Screens for Review
14 Design HR/Business Center Data Cleanup Screens for review 0.1 days Wed 2/5/03 Wed 2/5/03   Resource 1
15 Design Portal Screens 10 days Tue 1/21/03 Mon 2/3/03   Resource 2
16 Send Portal Screens out for review 0.1 days Wed 2/5/03 Wed 2/5/03   Resource 2
17 Portal Design Complete 0 days Wed 2/5/03 Wed 2/5/03 16  
18            
19 Initial Requirements Definition 18.2 days Tue 1/21/03 Fri 2/14/03    
20 Develop HRMS RS/HLA Document - First Cut 11 days Tue 1/21/03 Tue 2/4/03   Steve
21 Send out RS/HLA (ver.0.6) document for review 0.1 days Tue 2/4/03 Tue 2/4/03 20 Steve
Steve, Resource 1,
22 Meet with Identitech to clarify project scope and objectives 0.2 days Tue 2/4/03 Tue 2/4/03  
Resource 2
23 Send out meeting minutes from Identitech meeting 0.2 days Tue 2/4/03 Tue 2/4/03   Steve
24 Setup Kick-off Meeting 0.1 days Tue 2/4/03 Tue 2/4/03   Steve

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

25 Conduct Kick-off Meeting 0.2 days Thu 2/13/03 Thu 2/13/03 24 Steve
Update/Changes to RS/HLA document based on feedback from Kick-
26 1 day Thu 2/13/03 Fri 2/14/03 25 Steve
off Meeting
Baseline RS/HLA document established (the document is still a work
27 0 days Fri 2/14/03 Fri 2/14/03 26 Steve
in progress)
28            
29 HRMS Database 30 days? Tue 1/21/03 Tue 3/4/03    
Resource 2, Resource
30 Initial meeting to discuss HRMS Database requirements 0.2 days Thu 1/23/03 Thu 1/23/03  
1, Steve, Jim
31 Create Initial Design of Database Model 3 days Thu 1/23/03 Tue 1/28/03 30 Jim
32 Review Database Model with Analysis Team 0.2 days Tue 1/28/03 Tue 1/28/03 31 Resource 1, Jim
33 Create HRMS Database 13 days Tue 1/28/03 Fri 2/14/03 32 Jim
34 Populate new database with a few test records 1 day? Fri 2/14/03 Tue 2/18/03 33 Jim
35 Import ABRA data into HRMS Database 0 days Tue 1/21/03 Tue 1/21/03 34 Jim
Jim, Resource 2,
36 HRMS Test Database Ready 30 days Tue 1/21/03 Tue 3/4/03 35
Resource 1
37            
38 Coding 94 days? Tue 1/21/03 Mon 6/2/03    
39 HR Standalone Database Admin GUIs 50 days? Tue 1/21/03 Tue 4/1/03    
40 HR Business Center Cleanup GUIs 48 days? Tue 1/21/03 Fri 3/28/03    
41 Build Screens 18 days Mon 3/3/03 Wed 3/26/03   MethodFactory
Resource 2, Resource
42 Test Screens 2 days Thu 3/27/03 Fri 3/28/03 41
1
43 Screens Ready to Deploy 0 days Fri 3/28/03 Fri 3/28/03 42  
44            
45 Test Screens 1 day? Tue 1/21/03 Tue 1/21/03    
46 HR Administration GUIs 22 days Mon 3/3/03 Tue 4/1/03    
47 Build Screens 18 days Mon 3/3/03 Wed 3/26/03   MethodFactory
Resource 2, Resource
48 Test Screens 4 days Thu 3/27/03 Tue 4/1/03 47
1
49 Screens Ready to Deploy 0 days Tue 4/1/03 Tue 4/1/03 48  
50            
51 LDAP Functionality 28.2 days Tue 4/15/03 Fri 5/23/03    

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

52 Receive LDAP Module From Identitech 0.2 days Tue 4/15/03 Tue 4/15/03   Team
53 LDAP Testing with E-directory 10 days Tue 4/15/03 Tue 4/29/03 52 Team
54 Beta Testing with select users 8 days Tue 4/29/03 Fri 5/9/03 53 Beta Users
55 Testing with Large Test Group (100 plus users) 10 days Fri 5/9/03 Fri 5/23/03 54 Release Users
56 LDAP Module Ready 0 days Fri 5/23/03 Fri 5/23/03 55  
57            
58 NetFYI Modules 55.2 days? Tue 1/21/03 Wed 4/9/03    
59 Merit Increase Process 32.2 days? Tue 1/21/03 Fri 3/7/03    
60 Develop Detailed Requirements for Merit Increase Process 22.9 days? Tue 1/21/03 Fri 2/21/03    
61 Clarify and nail down exact process steps and included functionality 0.5 days Tue 2/18/03 Tue 2/18/03 34 Team
62 Identify Data Types used in process steps 1 day Tue 2/18/03 Wed 2/19/03 61 Team
Identify data elements to be read from/written to the HRMS
63 1 day Wed 2/19/03 Thu 2/20/03 62 Team
Database
64 Document operations on specific fields 1 day Wed 2/19/03 Fri 2/21/03 63 Team
Resource 1, Resource
65 Define IFAS data requirements 0.5 days Fri 2/21/03 Fri 2/21/03 64
2
66 Define flat file format for IFAS 1 day? Tue 1/21/03 Tue 1/21/03   Data Management
67 Coding 2.75 days Fri 2/21/03 Wed 2/26/03    
68 Build Search Classes 0.5 days Fri 2/21/03 Mon 2/24/03 65 Team
69 Build database indexes 0.5 days Mon 2/24/03 Mon 2/24/03 68 Team
70 Build Work Flow 0.5 days Tue 2/25/03 Tue 2/25/03 69 Team
71 Build other required sub processes and modules? 0.5 days Mon 2/24/03 Wed 2/26/03 70 Team
72 Build Prototype of Merit Increase Process 0.5 days Wed 2/26/03 Wed 2/26/03 71 Team
73 Test 32.2 days? Tue 1/21/03 Fri 3/7/03    
74 Test Prototype Process Flow utilizing test users in Roles database 0.5 days Wed 2/26/03 Thu 2/27/03 72 Team
Unit test of Merit Increase Process utilizing live Data in HRMS
75 0.5 days Thu 2/27/03 Thu 2/27/03 74 Team
Database
76 Test Prototype in Development Environment 0.5 days Thu 2/27/03 Fri 2/28/03 75 Team
77 Review Prototype and Functionality with Red Team 0.2 days Mon 3/3/03 Mon 3/3/03 76  
78 Rework Prototype into final Process/Workflow 4 days Mon 3/3/03 Fri 3/7/03 77  
79 Workflow ready for Testing 0 days Fri 3/7/03 Fri 3/7/03 78  
80      

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

81 Performance Management Process 23 days Fri 3/7/03 Wed 4/9/03    


Develop Detailed Requirements for Performance
82 12 days Fri 3/7/03 Tue 3/25/03    
Management Process
83 Clarify and nail down exact process steps and included functionality 2 days Fri 3/7/03 Tue 3/11/03 79 Team
84 Identify Data Types used in process steps 2 days Tue 3/11/03 Thu 3/13/03 83 Team
85 Document operations on specific fields 2 days Thu 3/13/03 Mon 3/17/03 84 Team
Identify data elements to be read from/written to the HRMS
86 2 days Mon 3/17/03 Wed 3/19/03 85 Team
Database
87 Define IFAS data requirements 2 days Wed 3/19/03 Fri 3/21/03 86 Team
88 Define/Update flat file format for IFAS 2 days Fri 3/21/03 Tue 3/25/03 87 Team
89 Code 6 days Tue 3/25/03 Wed 4/2/03    
90 Build Search Classes 1 day Tue 3/25/03 Wed 3/26/03 88 Team
91 Build database indexes 1 day Wed 3/26/03 Thu 3/27/03 90 Team
92 Build other required sub processes and modules? 1 day Thu 3/27/03 Fri 3/28/03 91 Team
93 Cleanup Efforts and final 1 day Fri 3/28/03 Mon 3/31/03 92 Team
94 Build Work Flow 1 day Mon 3/31/03 Tue 4/1/03 93 Team
95 Build Prototype of Performance Management Process 1 day Tue 4/1/03 Wed 4/2/03 94 Team
96 Test 5 days Wed 4/2/03 Wed 4/9/03    
97 Test Prototype Process Flow utilizing test users in Roles database 1 day Wed 4/2/03 Thu 4/3/03 95 Team
Unit test of Merit Increase Process utilizing live Data in HRMS
98 1 day Thu 4/3/03 Fri 4/4/03 97 Team
Database
99 Test Prototype in Development Environment 1 day Fri 4/4/03 Mon 4/7/03 98 Team
100 Review Prototype and Functionality with Management 1 day Mon 4/7/03 Tue 4/8/03 99 Team
101 Rework Prototype into final Process/Workflow 1 day Tue 4/8/03 Wed 4/9/03 100 Team
102 Workflow ready for System Testing 0 days Wed 4/9/03 Wed 4/9/03 101 Team
103            
104 Employee Information Update Process 45 days Tue 4/1/03 Mon 6/2/03    
Develop Detailed Requirements for Employee Information
105 6 days Tue 4/1/03 Tue 4/8/03    
Update Process
106 Clarify and nail down included functionality 1 day Tue 4/1/03 Tue 4/1/03   Web1
107 Identify Data Types 1 day Wed 4/2/03 Wed 4/2/03 106 Web1
108 Document operations on specific fields 1 day Thu 4/3/03 Thu 4/3/03 107 Web1

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

Identify data elements to be read from/written to the HRMS


109 1 day Fri 4/4/03 Fri 4/4/03 108 Web1
Database
110 Define IFAS data requirements 1 day Mon 4/7/03 Mon 4/7/03 109 Web1
111 Define/Update flat file format for IFAS 1 day Tue 4/8/03 Tue 4/8/03 110 Web1
112 Code 34 days Wed 4/9/03 Mon 5/26/03    
113 Build Search Classes 2 days Wed 4/9/03 Thu 4/10/03 111 Web1
114 Build database indexes 2 days Fri 4/11/03 Mon 4/14/03 113 Web1
115 Build other required sub processes and modules? 2 days Tue 4/15/03 Wed 4/16/03 114 Web1
116 Cleanup Efforts and final 2 days Thu 4/17/03 Fri 4/18/03 115 Web1
117 Employee Portal 26 days Mon 4/21/03 Mon 5/26/03    
118 Develop Prototype Screen(s) 3 days Mon 4/21/03 Wed 4/23/03 116 Web1
119 Route to HR Subject Matter Experts for Feedback/Approval 1 day Thu 4/24/03 Thu 4/24/03 118 Web1
120 Build Screens 10 days Fri 4/25/03 Thu 5/8/03 119 Web1
121 Integrate into Identitech Processes and HRMS Structure 12 days Fri 5/9/03 Mon 5/26/03 120 Web1
122 Test 5 days Tue 5/27/03 Mon 6/2/03    
123 Test of GUI and Employee Read/Update Processes 5 days Tue 5/27/03 Mon 6/2/03 121 Web1
124 Process ready for Testing 0 days Mon 6/2/03 Mon 6/2/03 123  
125            
126 Portal Development 30.5 days Tue 4/1/03 Tue 5/13/03    
127 Manager Portal 30.5 days Tue 4/1/03 Tue 5/13/03    
128 Develop Prototype Screen(s) 5 days Tue 4/1/03 Mon 4/7/03   Web2
129 Route to HR Subject Matter Experts for Feedback/Approval 0.5 days Tue 4/8/03 Tue 4/8/03 128 Web2
130 Build Screens 10 days Tue 4/8/03 Tue 4/22/03 129 Web2
131 Integrate into Identitech Processes 15 days Tue 4/22/03 Tue 5/13/03 130 Web2
132 Ready for Testing 0 days Tue 5/13/03 Tue 5/13/03 131  
133            
134 HR Administration Portal 30.5 days Tue 4/1/03 Tue 5/13/03    
135 Develop Prototype Screen(s) 5 days Tue 4/1/03 Mon 4/7/03   Web3
136 Route to HR Subject Matter Experts for Feedback/Approval 0.5 days Tue 4/8/03 Tue 4/8/03 135 Web3
137 Build Screens 10 days Tue 4/8/03 Tue 4/22/03 136 Web3
138 Integrate into Identitech Processes 15 days Tue 4/22/03 Tue 5/13/03 137 Web3

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

139 Ready for Testing 0 days Tue 5/13/03 Tue 5/13/03 138  
140            
141 User Acceptance Testing (UAT)/System Test 22 days Mon 5/26/03 Tue 6/24/03    
142 Obtain/Create System test data 2 days Mon 5/26/03 Tue 5/27/03   Team
143 Performance Review 5 days Wed 5/28/03 Tue 6/3/03 142 Users
144 Performance Review (Multi-Rater Feedback Sub-Process) 4 days Wed 6/4/03 Mon 6/9/03 143 Users
145 Merit Increase 2 days Tue 6/10/03 Wed 6/11/03 144 Users
146 Employee Information Update Process 3 days Thu 6/12/03 Mon 6/16/03 145 Users
Resource 2, Resource
147 HR Administrators Portal 15 days Mon 5/26/03 Fri 6/13/03  
1
148 Manager's Portal 4 days Tue 6/17/03 Fri 6/20/03 146 Users
149 Employee's Portal 2 days Mon 6/23/03 Tue 6/24/03 148 Users
150 User Acceptance Testing Complete 0 days Tue 6/24/03 Tue 6/24/03 149  
151            
152 Implementation 2 days Wed 6/25/03 Thu 6/26/03    
153 Load Code in Production Environment 2 days Wed 6/25/03 Thu 6/26/03 150 Team
154 Load Production Data into Production Database 2 days Wed 6/25/03 Thu 6/26/03 150 Team
155 System Live in Production 0 days Thu 6/26/03 Thu 6/26/03 154,153 Team
156            
157 Project Closeout Activities 2 days Fri 6/27/03 Mon 6/30/03    
158 Archive all Project Documentation 2 days Fri 6/27/03 Mon 6/30/03 155 Team, PM
159 Place all code in Source Safe 1 day Fri 6/27/03 Fri 6/27/03 155 Team
Conduct Lesson's Learned and Project Close-out Meeting with
160 0.5 days Mon 6/30/03 Mon 6/30/03 159 PM
Stakeholders
161 Close-Out Activities Complete 0 days Mon 6/30/03 Mon 6/30/03 160  
162            
163 Warranty 24 days? Mon 6/30/03 Thu 7/31/03    
164 Warranty Period for Phase I 23 days Mon 6/30/03 Wed 7/30/03   Team
165 Warranty Period Complete 1 day? Thu 7/31/03 Thu 7/31/03 164  
166            
Project Complete - Warranty and Project Closeout Activities
167 0 days Thu 7/31/03 Thu 7/31/03 165  
Complete

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

APPENDIX C – PROJECT ISSUES LOG

<next page>

<project name WBS> 12/08/21


<Project Name> Sarasota County Government

Project Issues Log - Examples – Delete

Issue # Issue Type, Description and Priority Date Reported Assigned Date Status Resolution/Comments
Impact to Project (M/H/L Reported By To Resolved
)
1 Issue Type: Resource M 02/25/03 Jack Bill Open 02/25 – Will forward the list of
Description (revised) Need requested resources to EIT
resource commitments to fully staff management by COB on 02/28.
the “Red”, “Blue”, and “Quality” 03/03 – Have resource commitments
teams for Red Team, part of Blue Team,
Impact: If the resources that have and we are working on the rest of
been identified aren’t assigned to this the list. Resources that are needed
project, quality will suffer. that can’t be obtained will be
escalated to EIT management.

2 Issue Type: Resource H 02/26/02 Jack PMO Open 02/25 – Will forward this issue to the
Description: No resource Manager PMO Manager for action
commitments from development for
GUI development.
Impact: The project requires an
Internet Presence resource now to
review GUI requirements and
estimate resources and Level of Effort
(LOE).

<project name WBS> 12/08/21