Sie sind auf Seite 1von 2

SPECIAL PEOPLE INC.

FOUNDATION V NESTOR CANDA (1) PHIVOLCS certified that the project site had been
subjected to an Intensity VII earthquake in 1990;
The peremptory writ of mandamus is an extraordinary remedy that is
issued only in extreme necessity, and the ordinary course of (2) the CNC issued by the EMB to a similar waterworks
procedure is powerless to afford an adequate and speedy relief to one project of the DPWH in the same area was only for the
who has a clear legal right to the performance of the act to be construction of a unit spring box intake and pump house,
compelled. and the DENR issued a cease and desist order relative to
the DPWH’s additional project to put up a water filtration
FACTS: plant therein;

Petitioner was a proponent of a water resource development and (3) the determination of whether an area was environmentally
utilization project involving the purification of water from Loboc critical was a task that pertained to the EMB;
River (Bohol) and the distribution of the purified water to residents of
Loboc and other municipalities.
(4) the RTC would not interfere with the primary prerogative
of the EMB to review the merits of the petitioner’s
The petitioner applied for a Certificate of Non-Coverage (CNC) with application for the CNC;
the DENR-EMB seeking to be exempt from the requirement of the
Environmental Compliance Certificate (ECC) under Section 4 of
Presidential Decree No. 1586 because the filtration and purifying (5) there was already a pending appeal lodged with the DENR
process employs the latest technology—"electrocatalytic"— Secretary.
internationally accepted for safety and environment friendliness. No
waste is generated, as the electrocatalytic process dissolves all Hence, this appeal brought directly to the Court via petition for
impurities in the water. Thus, the project involves no destruction review on certiorari.
[n]or harm to the environment.
ISSUE:
Upon evaluating the nature and magnitude of the environmental
impact of the project, respondent Canda, then Chief of EMB in 1. WON petitioner is entitled to certificate of non-coverage
Bohol, found that since the project is within a critical area, Initial and thus ministerial on the part of EMB to issue such.
Environmental Examination is required. Moreover, the project is
socially and politically sensitive therefore proof of social
acceptability should be established. Proper indorsement from the Arguments:
Protected Area Management Bureau or PAMB should be secured. 2
 RD Lipayon and Canda aver that the act complained of
Petitioner appealed Canda’s findings to respondent EMB Region 7 involved an exercise of discretion that could not be
Director Lipayon (RD Lipayon), claiming that it should also be compelled by mandamus; that the petitioner’s proposed
issued a CNC because the project was no different from the Loboc- project was located within an environmentally critical area,
Loay waterworks project and Highways (DPWH) that had recently and the activities to be done were so significant that they
been issued a CNC. would create massive earth movement and environmental
degradation.
On April 3, 2002, RD Lipayon notified the petitioner that its
documents substantially complied with the procedural aspects of the  DENR Secretary - contends that the petition raises
EMB’s review. Later on, RD Lipayon informed the petitioner that an questions of fact that are not proper in a petition for review;
Initial Environmental Examination document was required for the that the petitioner should have appealed to the CA under
project due to its significant impact in the area. 5 Rule 41 of the Rules of Court;

On August 26, 2002, RD Lipayon required the petitioner to submit  COURT:


several documents to enable the EMB to determine whether the
project was within an environmentally critical area or not. (such as Petitioner’s appeal is improper under Rule 45, Rules of Court whose
certifications from PENRO, PAGASA, PHIVOLCS, etc.) Section 1 expressly requires that the petition shall raise only
questions of law which must be distinctly set forth. Yet, the petitioner
On January 28, 2003, the petitioner submitted eight certifications. hereby raises a question of fact concerning whether or not the
The petitioner failed to secure a certification from the Regional petitioner established that its project was not located in an
Office of the Mines and Geosciences Bureau (RO-MGB) to the effect environmentally critical area. For this reason, the Court is constrained
that the project area was not located along a fault line/fault zone or a to deny due course to the petition for review.
critical slope.
2. WON petitioner has exhausted available administrative
Subsequently, RD Lipayon declared that the project was within an remedies.
environmentally critical area, and that the petitioner was not entitled
to the CNC. The records show that the petitioner failed to exhaust the available
administrative remedies. At the time RD Lipayon denied the
On March 27, 2003, the petitioner filed a petition for mandamus and petitioner’s application for the CNC,Administrative Order No. 42
damages in the (RTC) alleging that it was now entitled to a CNC as a dated November 2, 200219 had just vested the authority to grant or
matter of right after having complied with the certification deny applications for the ECC in the Director and Regional Directors
requirements; and that the EMB had earlier issued a CNC to the of the EMB. Notwithstanding the lack of a specific implementing
DPWH for a similar waterworks project in the same area. RTC guideline to what office the ruling of the EMB Regional Director was
dismissed the petition: to be appealed, the petitioner could have been easily guided in that
regard by the Administrative Code of 1987, which provides that the
Director of a line bureau, such as the EMB, 20 shall have supervision
and control over all division and other units, including regional
offices, under the bureau. 21 Verily, supervision and control include
the power to "review, approve, reverse or modify acts and decisions
of subordinate officials or units." 22 Accordingly, the petitioner should
have appealed the EMB Regional Director’s decision to the EMB
Director, who exercised supervision and control over the former.

It is relevant to mention that the DENR later promulgated


Administrative Order No. 2003-3023 in order to define where appeals
should be taken, providing as follows:

Section 6. Appeal

Any party aggrieved by the final decision on the ECC/CNC


applications may, within 15 days from receipt of such decision, file
an appeal on the following grounds:

a. Grave abuse of discretion on the part of the deciding authority, or


b. Serious errors in the review findings.

The DENR may adopt alternative conflict/dispute resolution


procedures as a means to settle grievances between proponents and
aggrieved parties to avert unnecessary legal action. Frivolous appeals
shall not be countenanced.

Moreover, the petitioner states in its pleadings that it had a pending


appeal with the DENR Secretary.1âwphi1 However, the records
reveal that the subject of the appeal of the petitioner was an undated
resolution of the DENR Regional Director, Region VII, denying its
application for the CNC,24 not the decision of RD Lipayon.
Nonetheless, even assuming that the pending appeal with the DENR
Secretary had related to RD Lipayon’s decision, the petitioner should
still have waited for the DENR Secretary to resolve the appeal in line
with the principle of exhaustion of administrative remedies. Its failure
to do so rendered its resort to mandamus in the RTC premature. The
omission is fatal, because mandamus is a remedy only when there is
no appeal, nor any plain, speedy and adequate remedy in the ordinary
course of law.25

Another reason for denying due course to this review is that the
petitioner did not establish that the grant of its application for the
CNC was a purely ministerial in nature on the part of RD Lipayon.
Hence, mandamus was not a proper remedy. The CNC is a
certification issued by the EMB certifying that a project is not
covered by the Environmental Impact Statement System (EIS
System) and that the project proponent is not required to secure an
ECC

Das könnte Ihnen auch gefallen