Sie sind auf Seite 1von 279

1 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC # 16
Plaster work Summary
Sr.# Location Unit No. Length Width Height Qty Request Nos Remarks

i- Plaster (Summary)

Plaster work on 100mm thick solid


A block wall

Lower Ground floor (Sub total a.) SM 3012.877

Ground floor (Sub total b.) SM 2711.179

First floor (Sub total c.) SM 376.843

2nd floor (Sub total d.) SM 622.908

3rd floor (Sub total e.) SM 474.638

Total Qty of plaster on 100mm thick


wall SM 7198.445
Plaster work on 150mm thick solid
B block wall

Lower Ground floor (Sub total a.) SM 703.856

Ground floor (Sub total b.) SM 769.973

First floor (Sub total c.) SM 663.437

2nd floor (Sub total d.) SM 443.259

3rd floor (Sub total e.) SM 739.224

Total Qty of plaster on 100mm thick


wall SM 3319.749
Plaster work on 200mm thick solid
C block wall

Lower Ground floor (Sub total a.) SM 379.395

Ground floor (Sub total b.) SM 4845.009

First floor (Sub total c.) SM 1928.733

2nd floor (Sub total d.) SM 333.148

3rd floor (Sub total e.) SM 2190.274

Total Qty of plaster on 100mm thick


wall SM 9676.559

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
2 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC # 16
Plaster work Summary
Sr.# Location Unit No. Length Width Height Qty Request Nos Remarks

Plaster work on 150mm thick Hollow


D block wall

Lower Ground floor (Sub total a.) SM 7572.933

Ground floor (Sub total b.) SM 18479.674

First floor (Sub total c.) SM 4503.555

2nd floor (Sub total d.) SM 3356.777

3rd floor (Sub total e.) SM 848.332

Total Qty of plaster on 100mm thick


wall SM 34761.271
Plaster work on 200mm thick Hollow
E block wall

Lower Ground floor (Sub total a.) SM 4170.846

Ground floor (Sub total b.) SM 1360.541

First floor (Sub total c.) SM 355.383

2nd floor (Sub total d.) SM 1311.266

3rd floor (Sub total e.) SM 899.653

Total Qty of plaster on 100mm thick


wall SM 8097.689

Deductions of walls tiles

Item
9.1.3 Porcelain tile on Lift walls SM -918.648
Item
9.1.5
(i) Porcelain tile dado (300x300) SM -1540.631
Item
9.1.5
(ii) Porcelain tile dado (600x300) SM -3454.400
Item
9.1.6
(i) Porcelain tile skirting (300x100) SM -761.567
Item
9.1.8
(i) Vitrified tile skirting (300x100) SM -23.140
Item
9.1.4 Terrazo tile Dado SM -500.000

Total Deduction SM -7198.386

Upto Date Qty of Plaster work 55,855.328 SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
3 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC # 16
Plaster work Summary
Sr.# Location Unit No. Length Width Height Qty Request Nos Remarks

Previous Paid Qty 37,877.931 SM

This Bill Qty 17,977.397 SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
4 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Internal Plaster Work


Plaster on 100mm thick solid block
wall
Wall 28 sq.m 2 2.425 3.800 18.430
Door Deduction D75 sq.m -2 0.750 2.150 -3.225
Wall 37 sq.m 2 0.450 3.800 3.420
Wall 38 sq.m 2 5.050 3.800 38.380
Wall 43 sq.m 2 1.300 3.800 9.880
Wall 44 sq.m 2 1.297 3.800 9.857
Wall 52 sq.m 2 3.300 3.800 25.080
Wall 53 sq.m 2 3.300 3.800 25.080
Wall 54 sq.m 2 3.300 3.800 25.080
Wall 55 sq.m 2 5.400 3.800 41.040
Wall 56 sq.m 2 3.600 3.800 27.360
Wall 58 sq.m 2 5.500 3.800 41.800
Door Deduction D10A sq.m -2 1.000 3.800 -7.600
Wall 68 sq.m 2 5.050 3.800 38.380
Wall 72 sq.m 2 4.400 3.800 33.440
Door Deduction D-75 sq.m -6 0.750 2.150 -9.675
Wall 73 sq.m 2 1.825 3.800 13.870
Wall 74 sq.m 2 1.825 3.800 13.870
Wall 75 sq.m 2 1.825 3.800 13.870
Wall 76 sq.m 2 1.825 3.800 13.870
Wall 77 sq.m 2 5.000 3.800 38.000
Door Deduction D-75 sq.m -6 0.750 2.150 -9.675
Wall 95 sq.m 2 3.350 3.800 25.460
Wall 100 sq.m 2 2.100 3.800 15.960
Wall 101 sq.m 2 8.100 3.800 61.560
Wall 102 sq.m 2 10.700 3.800 81.320
Door Deduction D10A sq.m -8 1.000 2.150 -17.200

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
5 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 103 sq.m 2 3.100 3.800 23.560


Wall 104 sq.m 2 2.300 3.800 17.480
Wall 105 sq.m 2 1.100 3.800 8.360
Wall 106 sq.m 2 6.000 3.800 45.600
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Wall 107 sq.m 2 2.200 3.800 16.720
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Wall 108 sq.m 2 5.100 3.800 38.760
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 110 sq.m 2 5.100 3.800 38.760
Wall 111 sq.m 2 7.188 3.800 54.629
Deduction Oppening sq.m -2 0.900 2.150 -3.870
Wall 112 sq.m 2 5.600 3.800 42.560
Wall 113 sq.m 2 7.190 3.800 54.644
Wall 120 sq.m 2 4.600 3.800 34.960
Wall 121 sq.m 2 8.300 3.800 63.080
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Deduction Oppening sq.m -2 2.325 2.150 -9.998
Wall 122 sq.m 2 3.388 3.800 25.749
Wall 123 sq.m 2 5.546 3.800 42.150
Wall 124 sq.m 2 12.846 3.800 97.630
Deduction Oppening sq.m -2 1.000 2.150 -4.300
Deduction for Column sq.m -2 1.000 3.800 -7.600
Wall 125 sq.m 2 5.500 3.800 41.800
Wall 126 sq.m 2 3.000 3.800 22.800
Wall 127 sq.m 2 3.000 3.800 22.800
Wall 128 sq.m 2 3.000 3.800 22.800
Wall 129 sq.m 2 5.500 3.800 41.800
Door Deduction D10A sq.m -4 1.000 2.150 -8.600
Wall 130 sq.m 2 11.850 3.800 90.060

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
6 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Door Deduction D10A sq.m -4 1.000 2.150 -8.600


Door Deduction D10C sq.m -2 1.000 2.150 -4.300
Wall 131 sq.m 2 4.246 3.800 32.270
Wall 132 sq.m 2 17.950 3.800 136.420
Door Deduction D10A sq.m -4 1.000 2.150 -8.600
Wall 133 sq.m 2 4.246 3.800 32.270
Deduction Column sq.m -2 0.800 3.800 -6.080
Wall 134 sq.m 2 4.246 3.800 32.270
Wall 135 sq.m 2 6.162 3.800 46.831
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 139 sq.m 2 2.024 3.800 15.382
Wall 142 sq.m 2 2.023 3.800 15.375
Wall 149 sq.m 2 7.000 3.800 53.200
Wall 159 sq.m 2 2.100 3.800 15.960
Wall 161 sq.m 2 15.600 3.800 118.560
Door Deduction D-10A sq.m -2 1.000 2.150 -4.300
Wall 162 sq.m 2 2.400 3.800 18.240
Wall 184 sq.m 2 2.325 3.800 17.670
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 185 sq.m 2 2.925 3.800 22.230
Wall 221 sq.m 2 1.079 3.800 8.200
Wall 259 sq.m 2 2.600 3.800 19.760
Wall 278 sq.m 2 1.500 3.800 11.400
Wall 285 sq.m 2 1.500 3.800 11.400
Wall 345 sq.m 2 6.600 3.800 50.160
Wall 346 sq.m 2 3.250 3.800 24.700
Door Deduction D-75 sq.m -4 0.900 3.800 -13.680
Wall 352 sq.m 2 3.250 3.800 24.700
Door Deduction D-75 sq.m -4 0.900 2.150 -7.740
Wall 353 sq.m 2 1.500 3.800 11.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
7 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 355 sq.m 2 1.500 3.800 11.400


Wall 376 sq.m 2 3.575 3.800 27.170
Wall 377 sq.m 2 2.165 3.800 16.454
Wall 378 sq.m 2 2.875 3.800 21.850
Wall 379 sq.m 2 2.875 3.800 21.850
Wall 382 sq.m 2 2.875 3.800 21.850
Door Deduction D-09A sq.m -2 1.000 2.150 -4.300
Wall 383 sq.m 2 2.800 3.800 21.280
Wall 384 sq.m 2 2.100 3.800 15.960
Wall 385 sq.m 2 7.080 3.800 53.808
Door Deduction DD-88 sq.m -2 1.500 2.150 -6.450
Door Deduction D-09B sq.m -2 0.900 2.150 -3.870
Wall 386 sq.m 2 12.848 3.800 97.645
Door Deduction D-09B sq.m -6 0.900 2.150 -11.610
Wall 387 sq.m 2 3.410 3.800 25.916
Door Deduction D-09B sq.m -2 0.900 2.150 -3.870
Wall 388 sq.m 2 5.835 3.800 44.346
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Wall 389 sq.m 2 3.450 3.800 26.220
Wall 390 sq.m 2 3.042 3.800 23.119
Wall 391 sq.m 2 1.548 3.800 11.765
Door Deduction D-10 sq.m -2 1.000 2.150 -4.300
Wall 393 sq.m 2 2.390 3.800 18.164
Wall 394 sq.m 2 3.660 3.800 27.816
Wall 395 sq.m 2 2.739 3.800 20.816
Wall 396 sq.m 2 7.080 3.800 53.808
Wall 397 sq.m 2 2.100 3.800 15.960
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 398 sq.m 2 0.750 3.800 5.700
Wall 400 sq.m 2 2.063 3.800 15.679

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
8 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 400A sq.m 2 0.764 3.800 5.806


Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 402 sq.m 2 13.774 3.800 104.682
Door Deduction D-10A sq.m -2 1.000 2.150 -4.300
Wall 403 sq.m 2 4.490 3.800 34.124
Wall 406 sq.m 2 1.730 3.800 13.148
Door Deduction D-10A sq.m -2 1.000 2.150 -4.300
Wall 407 sq.m 2 0.704 3.800 5.350
Wall 408 sq.m 2 4.490 3.800 34.124
Wall 409 sq.m 2 5.410 3.800 41.116
Door Deduction D-88A sq.m -2 1.600 2.150 -6.880
Wall 410 sq.m 2 5.410 3.800 41.116
Wall 411 sq.m 2 0.750 3.800 5.700
Wall 414 sq.m 2 1.000 3.800 7.600
Wall 416 sq.m 2 2.398 3.800 18.225
Door Deduction D-10A sq.m -2 1.000 2.150 -4.300
Wall 417 sq.m 2 1.891 3.800 14.372
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 418 sq.m 2 4.164 3.800 31.646
Wall 419 sq.m 2 0.825 3.800 6.270
Wall 423 sq.m 2 7.515 3.800 57.114
Wall 424 sq.m 2 2.664 3.800 20.246
Door Deduction D-9A sq.m -2 0.900 2.150 -3.870
Wall 425 sq.m 2 4.851 3.800 36.868
Door Deduction D-9A sq.m -2 0.900 2.150 -3.870
Wall 426 sq.m 2 1.200 3.800 9.120
Plaster work Qty of Lower Ground Floor (Sub total a.) 3,012.877 SM

Ground Floor
Wall-18 SM 2 2.056 - 3.800 15.626
Wall-28 SM 2 1.859 - 3.800 14.128

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
9 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Window SM -1 1.280 - 1.000 -1.280


Wall-29 SM 2 1.960 - 3.800 14.896
Wall-31 SM 2 4.846 - 3.800 36.830
Wall-33 SM 2 1.450 - 3.800 11.020
D-9B SM -2 0.900 - 2.150 -3.870
Wall-34 SM 2 0.200 - 3.800 1.520
Wall-35 SM 2 0.200 - 3.800 1.520
Wall-36 SM 2 0.200 - 3.800 1.520
Wall-37 SM 2 0.200 - 3.800 1.520
Wall-39 SM 2 0.200 - 3.800 1.520
Wall-40 SM 2 1.835 - 3.800 13.946
Wall-41 SM 2 1.910 - 3.800 14.516
Wall-43 SM 2 5.078 - 3.800 38.593
Wall-44 SM 2 1.835 - 3.800 13.946
Wall-45 SM 2 0.200 - 3.800 1.520
Wall-47 SM 2 0.200 - 3.800 1.520
Wall-49 SM 2 0.200 - 3.800 1.520
Wall-51 SM 2 0.200 - 3.800 1.520
Wall-52 SM 2 1.753 - 3.800 13.323
Wall-53 SM 2 5.301 - 3.800 40.288
Wall-54 SM 2 2.355 - 3.800 17.898
Wall-56 SM 2 0.800 - 3.800 6.080
Wall-57 SM 2 5.013 - 3.800 38.099
D/d for Column SM -2 1.200 - 3.800 -9.120
Wall-58 SM 2 0.600 - 3.800 4.560
Wall-60 SM 2 7.500 - 3.800 57.000
Wall-61 SM 2 2.801 - 3.800 21.288
Wall-78 SM 14 1.500 - 3.800 79.800
Wall-81 SM 2 10.300 - 3.800 78.280
D-75 SM -16 0.750 - 2.150 -25.800

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
10 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-84 SM 2 0.100 - 3.800 0.760


Wall-86 SM 2 3.965 - 3.800 30.134
Wall-87 SM 2 7.100 - 3.800 53.960
Wall-88 SM 2 0.200 - 3.800 1.520
Wall-89 SM 2 0.200 - 3.800 1.520
Wall-91 SM 2 3.265 - 3.800 24.814
Wall-93 SM 2 0.100 - 3.800 0.760
Wall-95 SM 2 1.439 - 3.800 10.936
Wall-96 SM 2 0.200 - 3.800 1.520
Wall-97 SM 2 0.200 - 3.800 1.520
Wall-99 SM 2 3.500 - 3.800 26.600
D/d for Column SM -2 1.200 - 3.800 -9.120
Wall-100 SM 2 3.500 - 3.800 26.600
Wall-103 SM 2 12.300 - 3.800 93.480
Wall-104 SM 2 2.600 - 3.800 19.760
Wall-106 SM 2 1.545 - 3.800 11.742
Wall-107 SM 2 0.724 - 3.800 5.502
Wall-108 SM 2 0.365 - 3.800 2.774
Wall-109 SM 2 3.500 - 3.800 26.600
Wall-111 SM 2 3.625 - 3.800 27.550
D/d of Window SM -2 1.280 - 1.500 -3.840
Wall-112 SM 2 0.465 - 3.800 3.534
Wall-113 SM 2 0.407 - 3.800 3.093
Wall-122 SM 2 8.100 - 3.800 61.560
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-135 SM 2 0.250 - 3.800 1.900
Wall-136 SM 2 3.651 - 3.800 27.748
Wall-137 SM 2 3.551 - 3.800 26.988
Wall-138 SM 2 0.272 - 3.800 2.067
Wall-149 SM 2 0.222 - 3.800 1.687

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
11 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-151 SM 2 1.000 - 3.800 7.600


Wall-153 SM 2 2.600 - 3.800 19.760
Wall-154 SM 2 3.700 - 3.800 28.120
Wall-159 SM 2 1.500 - 3.800 11.400
Wall-161 SM 2 3.250 - 3.800 24.700
Wall-165 SM 2 1.000 - 3.800 7.600
Wall-166 SM 2 3.250 - 3.800 24.700
Wall-167 SM 2 1.500 - 3.800 11.400
Wall-171 SM 2 2.538 - 3.800 19.289
D-75 SM -4 0.750 - 2.150 -6.450
Wall-172 SM 2 1.301 - 3.800 9.888
Wall-173 SM 2 0.525 - 3.800 3.990
Wall-181 SM 2 0.425 - 3.800 3.230
Wall-182 SM 2 6.801 - 3.800 51.688
D/d for Column SM -2 1.200 - 3.800 -9.120
GD-1 SM -2 1.700 - 3.800 -12.920
Wall-183 SM 2 0.331 - 3.800 2.516
Wall-184 SM 2 4.750 - 3.800 36.100
Wall-193 SM 2 0.313 - 3.800 2.379
Wall-211 SM 2 0.101 - 3.800 0.768
Wall-223 SM 2 0.165 - 3.800 1.254
Wall-224 SM 2 0.175 - 3.800 1.330
Wall-245 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-246 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-248 SM 2 2.550 - 3.800 19.380
Wall-249 SM 2 2.550 - 3.800 19.380
Wall-250 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
12 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-251 SM 2 2.550 - 3.800 19.380


D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-297 SM 2 5.125 - 3.800 38.950
D-75 SM -2 0.750 - 2.150 -3.225
D-9A SM -2 0.900 - 2.150 -3.870
Wall-299 SM 2 1.500 - 3.800 11.400
Wall-300 SM 2 2.000 - 3.800 15.200
Wall-302 SM 2 1.500 - 3.800 11.400
Wall-304 SM 2 5.050 - 3.800 38.380
Wall-347 SM 2 2.250 - 3.050 13.725
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-348 SM 2 0.550 - 3.800 4.180
Wall-349 SM 2 1.450 - 3.800 11.020
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-350 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-351 SM 2 4.950 - 3.800 37.620
Wall-353 SM 2 4.150 - 3.800 31.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-355 SM 2 2.100 - 3.800 15.960
Wall-364 SM 2 1.800 - 3.800 13.680
Wall-366 SM 2 1.800 - 3.800 13.680
Wall-367 SM 2 2.900 - 3.800 22.040
D-75 SM -4 0.750 - 2.150 -6.450
Wall-368 SM 2 4.450 - 3.800 33.820
Wall-369 SM 2 2.900 - 3.800 22.040
D-75 SM -4 0.750 - 2.150 -6.450
Wall-382 SM 2 2.550 - 3.800 19.380
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-396 SM 2 5.251 - 3.800 39.908

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
13 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-400 SM 2 5.251 - 3.800 39.908


Wall-458 SM 2 1.500 - 3.800 11.400
Wall-459 SM 2 3.250 - 3.800 24.700
Wall-460 SM 2 3.250 - 3.800 24.700
Wall-461 SM 2 1.500 - 3.800 11.400
Wall-462 SM 2 2.600 - 3.800 19.760
D-75 SM -4 0.750 - 2.150 -6.450
Wall-463 SM 2 1.000 - 3.800 7.600
Wall-464 SM 2 2.100 - 3.800 15.960
D-10A SM -2 1.000 - 2.150 -4.300
Wall-465 SM 2 1.000 - 2.150 4.300
Wall-468 SM 2 2.600 - 3.800 19.760
D-75 SM -4 0.750 - 2.150 -6.450
Wall-470 SM 2 0.450 - 3.800 3.420
Wall-471 SM 2 5.525 - 3.800 41.990
Wall-516 SM 2 3.210 - 3.800 24.396
D-75 SM -4 0.750 - 2.150 -6.450
Wall-518 SM 2 1.800 - 3.800 13.680
Wall-521 SM 2 1.800 - 3.800 13.680
Wall-522 SM 2 3.110 - 3.800 23.636
D-75 SM -4 0.750 - 2.150 -6.450
Wall-523 SM 2 4.550 - 3.800 34.580
Wall-558 SM 2 7.050 - 3.800 53.580
Wall-585 SM 2 5.500 - 3.800 41.800
D/d of Window SM -2 1.700 - 1.000 -3.400
Wall-586 SM 2 7.700 - 3.800 58.520
RFD-12 SM -2 1.200 - 2.150 -5.160
Wall-589 SM 2 5.900 - 3.800 44.840
RFD-12 SM -2 1.200 - 2.150 -5.160
Wall-612 SM 2 2.205 - 3.800 16.758

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
14 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-613 SM 2 6.600 - 3.800 50.160


Wall-617 SM 2 0.725 - 3.800 5.510
Wall-626 SM 2 5.375 - 3.800 40.850
Wall-627 SM 2 5.375 - 3.800 40.850
D/d of Window SM -2 1.700 - 1.000 -3.400
Wall-672 SM 2 4.450 - 3.800 33.820
Wall-673 SM 2 3.200 - 3.800 24.320
D-75 SM -4 0.750 - 2.150 -6.450
Wall-676 SM 2 1.800 - 3.800 13.680
Wall-679 SM 2 1.800 - 3.800 13.680
Wall-680 SM 2 3.200 - 3.800 24.320
D-75 SM -4 0.750 - 2.150 -6.450
Wall-681 SM 2 3.975 - 3.800 30.210
Wall-700 SM 2 4.000 - 3.800 30.400
Wall-701 SM 2 5.100 - 3.800 38.760
D-75 SM -8 0.750 - 2.150 -12.900
Wall-702 SM 2 1.800 - 3.800 13.680
Wall-703 SM 2 1.800 - 3.800 13.680
Wall-712 SM 2 3.825 - 3.800 29.070
Wall-755 SM 2 2.250 - 3.800 17.100
Wall-756 Missing
Wall-757 SM 2 1.910 - 3.800 14.516
Wall-758 SM 2 2.250 - 3.800 17.100
Wall-759 SM 2 0.450 - 3.800 3.420
Wall-760 Missing
Wall-763 SM 2 5.380 - 3.800 40.888
Wall-794 SM 2 1.998 - 3.800 15.185
Wall-795 SM 2 0.853 - 3.800 6.483
Wall-800 SM 2 0.803 - 3.800 6.103

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
15 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-801 SM 2 1.998 - 3.800 15.185


D-9A SM -2 0.900 - 2.150 -3.870
Wall-817 SM 2 1.500 - 3.800 11.400

Qty Ground Floor= (Sub total b.) 2,711.179


First Floor
Wall-2 SM 2 8.250 - 2.600 42.900
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-14 SM 2 3.688 - 2.600 19.178
Wall-71 SM 2 7.200 - 2.600 37.440
Wall-81 SM 2 0.450 - 2.600 2.340
Wall-83 SM 2 5.050 - 2.600 26.260
Wall-95 SM 2 0.800 - 2.600 4.160
Wall-160 SM 2 5.360 - 2.600 27.872
Wall-164 SM 2 0.450 - 2.600 2.340
Wall-214 SM 2 6.950 - 2.600 36.140
Wall-244 SM 2 1.290 - 2.600 6.708
Wall-245 SM 2 2.250 - 2.600 11.700
Wall-247 SM 2 5.360 - 2.600 27.872
Wall-248 SM 2 0.450 - 2.600 2.340
Wall-255 SM 2 1.875 - 2.600 9.750
Wall-256 SM 2 1.875 - 2.600 9.750
Wall-319 SM 2 1.375 - 2.600 7.150
Wall-323 SM 2 1.375 - 2.600 7.150
Wall-358 SM 2 3.975 - 2.600 20.670
Wall-378 SM 2 2.205 - 2.600 11.466
Wall-379 SM 2 6.599 - 2.600 34.315
Wall-385 SM 4 2.425 - 2.600 25.220
Wall-388 SM 2 1.785 - 2.600 9.282

Qty First Floor= (Sub total c.) 376.843

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
16 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Second Floor
Wall-1 SM 2 0.450 - 2.600 2.340
Wall-2 SM 2 5.360 - 2.600 27.872
Wall-5 SM 2 2.600 - 2.600 13.520
Wall-10 SM 2 0.600 - 2.600 3.120
Wall-11 SM 2 0.600 - 2.600 3.120
Wall-16 SM 2 0.600 - 2.600 3.120
Wall-18 SM 2 0.600 - 2.600 3.120
Wall-24 SM 2 0.600 - 2.600 3.120
Wall-26 SM 2 0.600 - 2.600 3.120
Wall-31 SM 2 0.600 - 2.600 3.120
Wall-32 SM 2 0.600 - 2.600 3.120
Wall-38 SM 2 0.600 - 2.600 3.120
Wall-39 SM 2 0.600 - 2.600 3.120
Wall-45 SM 2 0.600 - 2.600 3.120
Wall-46 SM 2 0.600 - 2.600 3.120
Wall-60 SM 2 5.050 - 2.600 26.260
Wall-62 SM 2 0.450 - 2.600 2.340
Wall-63 SM 2 0.800 - 2.600 4.160
Wall-87 SM 2 2.205 - 2.600 11.466
Wall-88 SM 2 6.676 - 2.600 34.715
Wall-92 SM 2 2.350 - 2.600 12.220
Wall-93 SM 2 1.836 - 2.600 9.547
Wall-94 SM 2 2.403 - 2.600 12.496
Wall-115 SM 2 0.400 - 2.600 2.080
Wall-116 SM 2 1.900 - 2.600 9.880
Wall-122 SM 2 1.900 - 2.600 9.880
Wall-125 SM 2 0.400 - 2.600 2.080

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
17 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-126 SM 2 1.900 - 2.600 9.880


Wall-131 SM 2 1.900 - 2.600 9.880
Wall-134 SM 2 0.400 - 2.600 2.080
Wall-135 SM 2 1.900 - 2.600 9.880
Wall-140 SM 2 1.900 - 2.600 9.880
Wall-142 SM 2 0.400 - 2.600 2.080
Wall-151 SM 2 5.260 - 2.600 27.352
Wall-152 SM 2 0.450 - 2.600 2.340
Wall-153 SM 2 0.400 - 2.600 2.080
Wall-157 SM 2 1.900 - 2.600 9.880
Wall-162 SM 2 1.900 - 2.600 9.880
Wall-164 SM 2 0.400 - 2.600 2.080
Wall-165 SM 2 1.900 - 2.600 9.880
Wall-169 SM 2 1.900 - 2.600 9.880
Wall-171 SM 2 0.400 - 2.600 2.080
Wall-180 SM 2 3.000 - 2.600 15.600
D-75 SM -4 0.750 - 2.150 -6.450
Wall-181 SM 2 1.200 - 2.600 6.240
Wall-182 SM 2 1.200 - 2.600 6.240
Wall-186 SM 2 1.200 - 2.600 6.240
Wall-188 SM 2 0.430 - 2.600 2.236
Wall-189 SM 2 1.200 - 2.600 6.240
Wall-190 SM 2 1.425 - 2.600 7.410
Wall-204 SM 2 6.950 - 2.600 36.140
Wall-207 SM 2 0.515 - 2.600 2.678
Wall-208 =1350+60 SM 2 1.410 - 2.600 7.332
Wall-216 SM 2 1.400 - 2.600 7.280
Wall-217 SM 2 1.826 - 2.600 9.495
Wall-221 SM 2 1.826 - 2.600 9.495
Wall-222 SM 2 1.400 - 2.600 7.280

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
18 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-291 SM 2 7.800 - 2.600 40.560


D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-301 SM 2 5.150 - 2.600 26.780
D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-304 SM 2 0.700 - 2.600 3.640
Wall-305 SM 2 2.300 - 2.600 11.960
D-75 SM -4 0.750 - 2.150 -6.450
Wall-306 SM 2 2.050 - 2.600 10.660
Wall-319 SM 2 0.700 - 2.600 3.640
Wall-320 SM 2 1.400 - 2.600 7.280
D/d of Drop Panel SM -2 0.300 - 0.200 -0.120
Wall-320 SM 2 1.400 - 2.600 7.280
D/d of Drop Panel SM -2 0.300 - 0.200 -0.120
Wall-325 SM 2 0.400 - 2.600 2.080
Wall-326 SM 2 1.900 - 2.600 9.880
Wall-334 SM 2 1.460 - 2.600 7.592
Wall-335 SM 2 1.460 - 2.600 7.592
Wall-338a SM 2 0.400 - 2.600 2.080
Wall-341 SM 2 1.900 - 2.600 9.880
Wall-342 SM 2 0.400 - 2.600 2.080
Wall-344 SM 2 1.900 - 2.600 9.880
Wall-356 SM 2 1.900 - 2.600 9.880
Wall-357 SM 2 0.400 - 2.600 2.080
Wall-359 SM 2 1.900 - 2.600 9.880
Wall-365A SM 2 1.900 - 2.600 9.880
Wall-366A SM 2 0.400 - 2.600 2.080

Qty Second Floor= (Sub total d.)


100mm thick wall 622.908

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
19 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor
Wall-5 SM 2 2.250 - 2.600 11.700
Wall-7 SM 2 0.450 - 2.600 2.340
Wall-10 SM 2 5.050 - 2.600 26.260
Wall-37 SM 2 5.360 - 2.600 27.872
Wall-38 SM 2 0.450 - 2.600 2.340
Wall-48 SM 2 5.299 - 2.600 27.555
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-49 SM 2 4.499 - 2.600 23.395
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-70 SM 2 3.300 - 2.600 17.160
D-75 SM -4 0.750 - 2.150 (6.450)
Wall-71 SM 2 1.900 - 2.600 9.880
Wall-72 SM 2 3.200 - 2.600 16.640
Wall-116 SM 2 2.500 - 2.600 13.000
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-120 SM 2 7.050 - 2.600 36.660
Wall-126 SM 2 2.205 - 2.600 11.466
Wall-127 SM 2 6.600 - 2.600 34.320
Wall-132 SM 2 2.450 - 2.600 12.740
Wall-133 SM 2 1.735 - 2.600 9.022
Wall-147 SM 2 3.975 - 2.600 20.670
Wall-149 SM 2 3.825 - 2.600 19.890
Wall-161 SM 2 7.800 - 2.600 40.560
D/d of opening SM -6 1.300 - 2.150 (16.770)
Wall-168 SM 2 5.150 - 2.600 26.780
D/d of opening SM -4 1.300 - 2.150 (11.180)
Wall-169A SM 2 2.000 - 2.600 10.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
20 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-196 SM 2 3.444 - 2.600 17.909


Wall-197 SM 2 1.800 - 2.600 9.360
Wall-198 SM 2 1.800 - 2.600 9.360
Wall-201 SM 2 2.750 - 2.600 14.300
Wall-203 SM 2 7.050 - 0.200 2.820
Wall-204 SM 2 7.000 - 0.200 2.800
Wall-205 SM 2 7.000 - 0.200 2.800
Wall-206 SM 2 7.050 - 0.200 2.820
Wall-209 SM 2 5.260 - 2.600 27.352
Wall-211 SM 2 0.600 - 2.600 3.120
Wall-212 SM 2 2.250 - 2.600 11.700
Wall-214 SM 2 1.290 - 2.600 6.708
Wall-217 SM 2 6.738 - 0.200 2.695
Wall-220 SM 2 6.909 - 0.200 2.764
Qty Third Floor= (Sub Total e.) 474.638

Plaster work Qty This Bill = 7,198.445

Plaster on 150mm thick solid block work


Lower Ground Floor
Wall 04 sq.m 2 2.550 6.300 32.130
Door Deduction D10C sq.m -2 1.000 2.150 -4.300
Wall 05 sq.m 2 2.550 6.300 32.130
Door Deduction D10C sq.m -2 1.300 2.150 -5.590
Wall 06 sq.m 2 2.550 6.300 32.130
Wall 09 sq.m 2 2.550 6.300 32.130
D/d sq.m -2 1.300 2.150 -5.590
Wall 10 sq.m 2 2.550 6.300 32.130
D/d sq.m -2 1.300 2.150 -5.590
Wall 39 sq.m 2 2.550 6.300 32.130

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
21 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Door Deduction sq.m -2 1.300 2.150 -5.590


Wall 40 sq.m 2 4.149 6.300 52.277
Door Deduction FD12 sq.m -2 1.000 2.150 -4.300
Wall 65 sq.m 2 4.500 6.300 56.700
Wall 66 sq.m 2 2.550 6.300 32.130
Door Deduction sq.m -2 1.300 2.150 -5.590
Wall 67 sq.m 2 2.550 6.300 32.130
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 80 sq.m 2 0.800 6.300 10.080
Wall 82 sq.m 2 2.100 6.300 26.460
Wall 147 sq.m 2 2.550 6.300 32.130
Deduction Oppening sq.m -2 1.300 2.150 -5.590
Wall 148 sq.m 2 4.450 6.300 56.070
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 150 sq.m 4 1.058 5.100 21.583
Wall 151 sq.m 2 5.500 6.300 69.300
Wall 229 sq.m 2 2.550 5.100 26.010
Door Deduction sq.m -2 1.300 2.150 -5.590
Wall 295 sq.m 2 8.701 5.100 88.750
Door Deduction Lift sq.m -6 1.300 2.150 -16.770
Wall 296 sq.m 2 5.150 5.100 52.530
Door Deduction Lift sq.m -4 1.300 2.150 -11.180
Wall 297 sq.m 2 3.777 5.100 38.525
Door Deduction DD-88 sq.m -2 1.600 2.150 -6.880
Wall 298 sq.m 2 1.500 5.100 15.300
Door Deduction FD-12 sq.m -2 1.200 2.150 -5.160
Plaster work Qty of Lower Ground Floorl= (sub total a.) 703.856
Ground Floor
Wall-30 SM 2 4.150 - 0.200 1.660
Wall-32 SM 2 4.050 - 0.200 1.620

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
22 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-38 SM 2 3.600 - 0.200 1.440


Wall-46 SM 2 3.600 - 0.200 1.440
Wall-48 SM 2 4.100 - 0.200 1.640
Wall-50 SM 2 4.100 - 0.200 1.640
Wall-55 SM 2 7.400 - 0.200 2.960
Wall-59 SM 2 7.300 - 0.200 2.920
Wall-85 SM 2 2.800 - 0.200 1.120
Wall-90 SM 2 3.600 - 0.200 1.440
Wall-92 SM 2 3.050 - 0.200 1.220
Wall-98 SM 2 3.700 - 0.200 1.480
Wall-101 SM 2 3.700 - 0.200 1.480
Wall-102 SM 2 4.150 - 0.200 1.660
Wall-105 SM 2 3.150 - 0.200 1.260
Wall-110 SM 2 4.250 - 0.200 1.700
Wall-134 SM 2 5.075 - 0.200 2.030
Wall-148 SM 2 7.850 - 0.200 3.140
Wall-174 SM 2 5.250 - 0.200 2.100
Wall-176 SM 2 3.230 - 0.200 1.292
Wall-185 SM 2 3.620 - 0.200 1.448
Wall-187 SM 2 3.617 - 0.200 1.447
Wall-190 SM 2 3.230 - 0.200 1.292
Wall-191 SM 2 3.217 - 0.200 1.287
Wall-194 SM 2 3.712 - 0.200 1.485
Wall-207 SM 2 10.061 - 0.200 4.024
Wall-210 SM 2 6.651 - 0.200 2.660
Wall-222 SM 2 6.570 - 0.200 2.628
Wall-234 SM 2 4.650 - 3.800 35.340
Wall-236 SM 2 4.650 - 3.800 35.340
Wall-467 SM 2 4.500 - 3.800 34.200
FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
23 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-498 SM 2 2.650 - 3.800 20.140


Wall-501 SM 2 0.175 - 3.800 1.330
Wall-502 SM 2 6.700 - 0.200 2.680
Wall-503 SM 2 0.165 - 3.800 1.254
Wall-506 SM 2 0.165 - 3.800 1.254
Wall-507 SM 2 6.700 - 0.200 2.680
Wall-508 SM 2 0.165 - 3.800 1.254
Wall-510 SM 2 0.165 - 3.800 1.254
Wall-511 SM 2 6.700 - 0.200 2.680
Wall-512 SM 2 0.165 - 3.800 1.254
Wall-529 SM 2 0.165 - 3.800 1.254
Wall-530 SM 2 6.750 - 0.200 2.700
Wall-531 SM 2 0.165 - 3.800 1.254
Wall-533 SM 2 0.165 - 3.800 1.254
Wall-534 SM 2 6.915 - 0.200 2.766
Wall-535 SM 2 0.175 - 3.800 1.330
Wall-536 SM 2 0.165 - 3.800 1.254
Wall-539 SM 2 0.165 - 3.800 1.254
Wall-540 SM 2 0.165 - 3.800 1.254
Wall-544 SM 2 0.165 - 3.800 1.254
Wall-555 SM 2 6.870 - 0.200 2.748
Wall-559 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-564 SM 2 3.800 - 3.800 28.880
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-565 SM 2 1.450 - 3.800 11.020
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-572 SM 2 0.165 - 3.800 1.254
Wall-574 SM 2 0.165 - 3.800 1.254
Wall-575 SM 2 6.750 - 0.200 2.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
24 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-576 SM 2 7.080 - 0.200 2.832


Wall-577 SM 2 0.165 - 3.800 1.254
Wall-578 SM 2 0.165 - 3.800 1.254
Wall-579 SM 2 0.165 - 3.800 1.254
Wall-580 SM 2 6.915 - 0.200 2.766
Wall-582 SM 2 0.165 - 3.800 1.254
Wall-612 SM 2 2.205 - 3.800 16.758
Wall-614 SM 2 1.231 - 3.800 9.356
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-615 SM 2 2.250 - 3.800 17.100
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-616 SM 2 4.450 - 3.800 33.820
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-652 SM 2 0.125 - 3.800 0.950
Wall-653 SM 2 0.125 - 3.800 0.950
Wall-654 SM 2 0.125 - 3.800 0.950
Wall-705 SM 2 7.080 - 3.800 53.808
D/d of Window SM -6 1.300 - 2.150 -16.770
Wall-708 SM 2 5.174 - 3.800 39.322
Wall-709 SM 2 2.425 - 3.800 18.430
Wall-710 SM 2 6.273 - 3.800 47.675
D-9A SM -4 0.900 - 2.150 -7.740
Wall-711 SM 2 1.500 - 3.800 11.400
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-713 SM 2 3.827 - 3.800 29.085
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-714 SM 2 3.765 - 3.800 28.614
Wall-715 SM 2 2.231 - 3.800 16.956
Wall-716 SM 2 2.231 - 3.800 16.956
Wall-717 SM 2 2.231 - 3.800 16.956

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
25 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-718 SM 2 5.150 - 3.800 39.140


D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-719 SM 2 4.000 - 3.800 30.400
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-720 SM 2 8.700 - 3.800 66.120
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-721 SM 2 3.300 - 3.800 25.080
Wall-722 SM 2 3.300 - 3.800 25.080
Wall-761 SM 2 1.500 - 3.800 11.400
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-762 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-777 SM 2 4.450 - 3.800 33.820
FD-12 SM -2 1.200 - 2.150 -5.160

Qty Ground Floor= 769.973


First Floor
H = 9.825-6.225-0.225 = 3.375
Wall-13 SM 2 3.840 - 0.200 1.536
Wall-15A SM 2 3.699 - 0.200 1.480
Wall-39 SM 2 2.827 - 0.200 1.131
Wall-47 SM 2 1.805 - 0.200 0.722
Wall-52 SM 2 3.110 - 0.200 1.244
Wall-57 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-58 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-59 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
26 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-60 SM 2 2.550 - 2.600 13.260


D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-61 SM 2 5.450 - 2.600 28.340
Wall-77 SM 2 3.358 - 2.600 17.462
Wall-82 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-84 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-85 SM 2 4.150 - 2.600 21.580
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-88 SM 2 7.250 - 0.200 2.900
Wall-90 SM 2 2.100 - 2.600 10.920
Wall-95 SM 2 0.800 - 2.600 4.160
Wall-108 SM 2 6.350 - 0.200 2.540
Wall-109 SM 2 7.300 - 0.200 2.920
Wall-110 SM 2 7.300 - 0.200 2.920
Wall-112 SM 2 1.829 - 0.200 0.732
Wall-113 SM 2 4.540 - 0.200 1.816
Wall-119 SM 2 3.410 - 0.200 1.364
Wall-120 SM 2 1.210 - 0.200 0.484
Wall-121 SM 2 1.829 - 0.200 0.732
Wall-122 SM 2 4.540 - 0.200 1.816
Wall-128 SM 2 3.410 - 0.200 1.364
Wall-129 SM 2 1.260 - 0.200 0.504
Wall-130 SM 2 1.829 - 0.200 0.732
Wall-131 SM 2 4.540 - 0.200 1.816
Wall-138 SM 2 3.360 - 0.200 1.344
Wall-139 SM 2 1.260 - 0.200 0.504
Wall-140 SM 2 1.225 - 0.200 0.490
Wall-141 SM 2 7.300 - 0.200 2.920

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
27 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-142 SM 2 1.225 - 0.200 0.490


Wall-144 SM 2 1.829 - 0.200 0.732
Wall-145 SM 2 4.490 - 0.200 1.796
Wall-148 SM 2 3.910 - 0.200 1.564
Wall-149 SM 2 1.260 - 0.200 0.504
Wall-158 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-159 SM 2 4.500 - 2.600 23.400
Wall-161 SM 2 2.650 - 2.600 13.780
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-163 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-170 SM 2 2.335 - 0.200 0.934
Wall-172 SM 2 2.335 - 0.200 0.934
Wall-173 SM 2 2.335 - 0.200 0.934
Wall-175 SM 2 2.335 - 0.200 0.934
Wall-178 SM 2 2.838 - 0.200 1.135
Wall-179 SM 2 2.838 - 0.200 1.135
Wall-184 SM 2 2.335 - 0.200 0.934
Wall-186 SM 2 2.335 - 0.200 0.934
Wall-187A SM 12 2.335 - 0.200 5.604
Wall-190 SM 2 2.838 - 0.200 1.135
Wall-191 SM 2 2.838 - 0.200 1.135
Wall-198A SM 12 2.335 - 0.200 5.604
Wall-202 SM 2 2.838 - 0.200 1.135
Wall-203 SM 2 2.838 - 0.200 1.135
Wall-210 SM 2 1.150 - 2.600 5.980
Wall-212 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-213 SM 2 3.550 - 2.600 18.460

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
28 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 -5.160


Wall-215 SM 2 1.008 - 2.600 5.242
Wall-216 SM 2 1.058 - 2.600 5.502
Wall-217 SM 2 7.200 - 0.200 2.880
Wall-218 SM 2 6.750 - 0.200 2.700
Wall-219 SM 2 6.985 - 0.200 2.794
Wall-220 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-221 SM 2 3.150 - 2.600 16.380
Wall-222 SM 2 5.500 - 2.600 28.600
D-9A SM -2 0.900 - 2.150 -3.870
Wall-223 SM 2 2.500 - 2.600 13.000
Wall-224 SM 2 1.080 - 2.600 5.616
Wall-225 SM 2 1.058 - 2.600 5.502
Wall-226 SM 2 6.750 - 0.200 2.700
Wall-227 SM 2 0.165 - 2.600 0.858
Wall-228 SM 2 0.165 - 2.600 0.858
Wall-229 SM 2 0.165 - 2.600 0.858
Wall-230 SM 2 0.165 - 2.600 0.858
Wall-231 SM 2 0.165 - 2.600 0.858
Wall-232 SM 2 0.165 - 2.600 0.858
Wall-233 SM 2 6.750 - 0.200 2.700
Wall-234 SM 2 6.700 - 0.200 2.680
Wall-235 SM 2 6.725 - 0.200 2.690
Wall-236 SM 2 0.165 - 2.600 0.858
Wall-244 SM 2 1.290 - 2.600 6.708
Wall-245 SM 2 2.250 - 2.600 11.700
Wall-271 SM 2 6.650 - 0.200 2.660
Wall-278 SM 2 6.750 - 0.200 2.700
Wall-303 SM 2 6.750 - 0.200 2.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
29 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-315 SM 2 6.750 - 0.200 2.700


Wall-337 SM 2 6.750 - 0.200 2.700
Wall-338 SM 2 6.650 - 0.200 2.660
Wall-339 SM 2 6.650 - 0.200 2.660
Wall-346 SM 2 3.300 - 2.600 17.160
Wall-347 SM 2 3.300 - 2.600 17.160
Wall-348 SM 2 3.932 - 2.600 20.446
Wall-349 SM 2 8.700 - 2.600 45.240
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-350 SM 2 5.150 - 2.600 26.780
D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-351 SM 2 2.219 - 2.600 11.539
Wall-352 SM 2 2.225 - 2.600 11.570
Wall-353 SM 2 7.800 - 2.600 40.560
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-354 SM 2 2.231 - 2.600 11.601
Wall-355 SM 2 3.765 - 2.600 19.578
Wall-356 SM 2 3.827 - 2.600 19.900
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-357 SM 2 6.273 - 2.600 32.620
D-9A SM -4 0.900 - 2.150 -7.740
Wall-357A SM 2 2.425 - 2.600 12.610
Wall-368 SM 2 7.190 - 0.200 2.876
Wall-369 SM 2 7.300 - 0.200 2.920
Wall-378 SM 2 2.205 - 2.600 11.466
Wall-380 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-381 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-382 SM 2 4.450 - 2.600 23.140

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
30 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 -5.160

Qty first Floor= 663.437


Second Floor
H = 13.425-9.825-0.225 = 3.375
Wall-3 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-5 SM 2 2.600 - 2.600 13.520
Wall-6 SM 2 4.600 - 2.600 23.920
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-58 SM 2 4.150 - 2.600 21.580
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-59 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-61 SM 2 1.450 - 2.600 7.540
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-63 SM 2 0.800 - 2.600 4.160
Wall-64 SM 2 2.100 - 2.600 10.920
Wall-87 SM 2 2.205 - 2.600 11.466
Wall-89 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-90 SM 2 4.433 - 2.600 23.052
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-91 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.600 -6.760
Wall-108 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-109 SM 2 3.833 - 2.600 19.932
DD-88 SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
31 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-110 SM 2 8.700 - 2.600 45.240


D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-111 SM 2 3.300 - 2.600 17.160
Wall-112 SM 2 3.300 - 2.600 17.160
Wall-113 SM 2 8.060 - 2.600 41.912
D/d of Opening SM -2 2.300 - 2.600 -11.960
Wall-114 SM 2 7.576 - 2.600 39.395
DD-99 SM -2 1.800 - 2.150 -7.740
D/d for Column SM -2 1.000 - 2.600 -5.200
Wall-148 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-149 SM 2 4.450 - 2.600 23.140
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-150 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-154 SM 2 2.250 - 2.600 11.700
Wall-200 SM 2 2.250 - 2.600 11.700
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-201 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-202 SM 2 2.250 - 2.600 11.700
Wall-203 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-206 SM 2 6.865 - 0.200 2.746
Wall-212 SM 2 6.915 - 0.200 2.766
Wall-213 SM 2 7.080 - 0.200 2.832
Wall-291 SM 2 7.800 - 2.600 40.560
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-293 SM 2 2.225 - 2.600 11.570
Wall-294 SM 2 2.225 - 2.600 11.570

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
32 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-295 SM 2 2.425 - 2.600 12.610


Wall-299 SM 2 3.765 - 2.600 19.578
Wall-300 SM 2 2.225 - 2.600 11.570
Wall-301 SM 2 5.150 - 2.600 26.780
D/d of Opening SM -4 1.300 - 2.150 -11.180

Qty Second Floor= 443.259


3rd Floor
H = 17.025-13.425-0.300 = 3.300
Wall-5 SM 2 2.250 - 2.600 11.700
Wall-51 SM 2 2.430 - 2.600 12.636
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-52 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM -4 0.950 - 0.200 (0.760)
Wall-53 SM 2 8.599 - 2.600 44.715
D-9A SM -6 0.900 - 2.150 (11.610)
Wall-54 SM 2 3.596 - 2.600 18.699
Wall-55 SM 2 3.595 - 2.600 18.694
Wall-56 SM 2 3.595 - 2.600 18.694
Wall-57 SM 2 4.951 - 2.600 25.745
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-58 SM 2 5.601 - 2.600 29.125
Wall-66 SM 2 7.300 - 2.600 37.960
D-10 SM -4 1.000 - 2.150 (8.600)
D/d of Drop Panel SM -4 0.950 - 0.200 (0.760)
Wall-69 SM 2 7.625 - 2.600 39.650
D-9A SM -4 0.900 - 2.150 (7.740)
Wall-74 SM 2 7.300 - 2.600 37.960
D-9A SM -2 0.900 - 2.150 (3.870)
DD-88 SM -2 1.600 - 2.150 (6.880)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
33 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)


Wall-75 SM 2 8.225 - 2.600 42.770
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-108 SM 2 3.600 - 2.600 18.720
D-10A SM -2 1.000 - 2.150 (4.300)
Wall-110 SM 2 3.000 - 2.600 15.600
Wall-111 SM 2 4.700 - 2.600 24.440
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-113 SM 2 7.300 - 2.600 37.960
FD-12 SM -2 1.200 - 2.150 (5.160)
D-9B SM -4 0.900 - 2.150 (7.740)
D/d of drop Panel SM -4 0.950 - 0.200 (0.760)
Wall-114 SM 2 3.149 - 2.600 16.375
Wall-115 SM 2 3.149 - 2.600 16.375
Wall-116 SM 2 2.500 - 2.600 13.000
D/d of drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-118 SM 2 2.550 - 2.600 13.260
D/d of opening SM -2 1.300 - 2.150 (5.590)
Wall-119 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-126 SM 2 2.205 - 2.600 11.466
Wall-128 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-129 SM 2 4.463 - 2.600 23.208
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-130 SM 2 2.550 - 2.600 13.260
D/d of opening SM -2 1.300 - 2.150 (5.590)
Wall-141 SM 2 4.400 - 0.200 1.760
Wall-142 SM 2 7.000 - 0.200 2.800
Wall-143 SM 2 7.000 - 0.200 2.800

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
34 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-143A SM 2 8.329 - 0.200 3.332


Wall-146 SM 2 5.025 - 0.200 2.010
D-10 SM -2 1.000 - 2.150 (4.300)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-148 SM 2 1.300 - 2.600 6.760
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-150 SM 2 3.827 - 2.600 19.900
DD-88 SM -2 1.600 - 2.150 (6.880)
Wall-161 SM 2 7.800 - 2.600 40.560
D/d of opening SM -6 1.300 - 2.150 (16.770)
Wall-162 SM 2 2.231 - 2.600 11.601
Wall-163 SM 2 2.231 - 2.600 11.601
Wall-164 SM 2 2.231 - 2.600 11.601
Wall-165 SM 2 3.300 - 2.600 17.160
Wall-166 SM 2 3.300 - 2.600 17.160
Wall-167 SM 2 8.700 - 2.600 45.240
D/d of Opening SM -6 1.300 - 2.150 (16.770)
Wall-168 SM 2 5.150 - 2.600 26.780
D/d of opening SM -4 1.300 - 2.150 (11.180)
Wall-169 SM 2 2.000 - 2.600 10.400
DD-99 SM -2 1.800 - 2.150 (7.740)
Wall-169A SM 2 2.000 - 2.600 10.400
Wall-186 SM 2 3.094 - 0.200 1.238
Wall-191 SM 2 10.827 - 0.200 4.331
Wall-193 SM 2 4.450 - 2.600 23.140
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-208 SM 2 2.550 - 2.600 13.260
D/d of opening SM -2 1.300 - 2.150 (5.590)
Wall-210 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
35 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-212 SM 2 2.250 - 2.600 11.700


Wall-214 SM 2 1.290 - 2.600 6.708
Wall-221 SM 2 0.820 - 2.600 4.264
Wall-222 SM 2 0.690 - 2.600 3.588
Wall-223 SM 2 0.820 - 2.600 4.264
Wall-225 SM 2 13.447 - 0.200 5.379
Qty Third Floor (Sub Total e) 739.224
Total Qty of Plaster on 150mm thick solid block work 3,319.749
Plaster work on 200mm thick solid wall
Lower Ground Floor
Wall 04 sq.m 2 2.550 3.800 19.380
Door Deduction D10C sq.m -2 1.300 2.150 -5.590
Wall 05 sq.m 2 2.550 3.800 19.380
Door Deduction D10C sq.m -2 1.300 2.150 -5.590
Wall 06 sq.m 2 2.550 3.800 19.380
Wall 07 sq.m 2 2.550 3.800 19.380
Wall 09 sq.m 2 2.550 3.800 19.380
D/d sq.m -2 1.300 2.150 -5.590
Wall 10 sq.m 2 2.550 3.800 19.380
D/d sq.m -2 1.300 2.150 -5.590
Wall 39 sq.m 2 2.550 3.800 19.380
Door Deduction sq.m -2 1.300 2.150 -5.590
Wall 40 sq.m 2 4.149 3.800 31.532
Door Deduction FD12 sq.m -2 1.200 2.150 -5.160
Wall 65 sq.m 2 4.500 3.800 34.200
Wall 66 sq.m 2 2.550 3.800 19.380
Door Deduction sq.m -2 1.300 2.150 -5.590
Wall 67 sq.m 2 2.550 3.800 19.380
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 80 sq.m 2 0.800 3.800 6.080

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
36 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 82 sq.m 2 2.100 3.800 15.960


Wall 147 sq.m 2 2.250 3.800 17.100
Deduction Oppening sq.m -2 1.300 2.150 -5.590
Wall 148 sq.m 2 4.450 3.800 33.820
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 229 sq.m 2 2.550 3.800 19.380
Door Deduction sq.m -2 1.300 2.150 -5.590
Wall 295 sq.m 2 8.701 3.800 66.128
Door Deduction Lift sq.m -6 1.300 2.150 -16.770
Wall 296 sq.m 2 5.150 3.800 39.140
Door Deduction Lift sq.m -4 1.300 2.150 -11.180
Wall 297 sq.m 2 3.777 3.800 28.705
Door Deduction DD-88 sq.m -2 1.000 2.150 -4.300
Wall 298 sq.m 2 1.500 3.800 11.400
Door Deduction FD-12 sq.m -2 1.200 2.150 -5.160
Plaster work Qty of Lower Ground Floor= (Sub total a) 379.395
Ground Floor
Wall-1 SM 2 0.284 - 2.6.8 0.570
Wall-2 SM 2 2.742.6 - 2.6.8 2.000
Wall-2.6 SM 2 7.695 - 2.6.8 15.390
D/d of Window SM -2 1.2.65 - 1.000 -2.000
Wall-4 SM 2 0.685 - 2.6.8 1.370
Wall-5 SM 2 0.42.64 - 2.6.8 2.000
Wall-6 SM 2 7.691 - 2.6.8 15.380
D/d of Window SM -2 1.2.65 - 1.000 -2.000
Wall-7 SM 2 0.685 - 2.6.8 1.370
Wall-8 SM 2 0.62.64 - 2.6.8 2.000
Wall-9 SM 2 7.699 - 2.6.8 15.400
D/d of Window SM -2 1.2.65 - 1.000 -2.000
Wall-10 SM 2 0.685 - 2.6.8 1.370

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
37 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-11 SM 2 0.62.64 - 2.6.8 2.000


Wall-12 SM 2 7.695 - 3.800 58.482
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-13 SM 2 0.685 - 3.800 5.206
Wall-14 SM 2 0.634 - 3.800 4.818
Wall-15 SM 2 7.695 - 3.800 58.482
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-16 SM 2 0.685 - 3.800 5.206
Wall-17 SM 2 0.634 - 3.800 4.818
Wall-19 SM 2 7.695 - 3.800 58.482
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-20 SM 2 0.634 - 3.800 4.818
Wall-21 Missing
Wall-22 Missing
Wall-23 SM 2 3.552 - 3.800 26.995
Wall-24 SM 2 4.769 - 3.800 36.244
Wall-25 SM 2 0.364 - 3.800 2.766
Wall-26 SM 2 4.375 - 3.800 33.250
D/d of Window SM -2 1.800 - 1.500 -5.400
Wall-27 SM 2 1.258 - 3.800 9.561
D-9B SM -2 0.900 - 2.150 -3.870
Wall-42 SM 2 0.685 - 3.800 5.206
Wall-64 SM 2 0.203 - 3.800 1.543
Wall-65 SM 2 2.804 - 3.800 21.310
Wall-66 SM 2 4.054 - 3.800 30.810
Wall-67 SM 2 1.863 - 3.800 14.159
Wall-68 SM 2 3.230 - 3.800 24.548
D/d of Window SM -2 2.700 - 1.500 -8.100
Wall-69 SM 2 0.700 - 3.800 5.320
Wall-70 SM 2 5.502 - 3.800 41.815

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
38 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-71 SM 2 1.317 - 3.800 10.009


Wall-72 SM 2 0.447 - 3.800 3.397
Wall-73 SM 2 3.430 - 3.800 26.068
D/d of Window SM -2 2.700 - 1.500 -8.100
Wall-79 SM 2 10.300 - 3.800 78.280
Wall-94 SM 2 11.304 - 3.800 85.910
Wall-114 SM 2 9.007 - 3.800 68.453
Wall-116 SM 2 6.434 - 3.800 48.898
Wall-122 SM 2 8.100 - 3.800 61.560
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-127 SM 2 0.332 - 3.800 2.523
Wall-128 SM 2 4.551 - 3.800 34.588
Wall-129 SM 2 1.416 - 3.800 10.762
Wall-130 SM 2 0.453 - 3.800 3.443
Wall-131 SM 2 3.430 - 3.800 26.068
D/d of Window SM -2 2.700 - 1.500 -8.100
Wall-141 SM 2 0.351 - 3.800 2.668
Wall-142 SM 2 4.555 - 3.800 34.618
Wall-143 SM 2 1.621 - 3.800 12.320
Wall-144 SM 2 3.230 - 3.800 24.548
D/d of Window SM -2 2.700 - 1.500 -8.100
Wall-145 SM 2 0.459 - 3.800 3.488
Wall-146 SM 2 5.236 - 3.800 39.794
Wall-147 SM 2 5.933 - 3.800 45.091
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-154 SM 2 3.700 - 3.800 28.120
Wall-177 SM 2 0.465 - 3.800 3.534
Wall-178 SM 2 5.236 - 3.800 39.794
Wall-188 SM 2 4.635 - 3.800 35.226
Wall-189 SM 2 0.432 - 3.800 3.283

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
39 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-192 SM 2 0.903 - 3.800 6.863


Wall-208 SM 2 0.949 - 3.800 7.212
Wall-209 SM 2 1.125 - 3.800 8.550
Wall-212 SM 2 0.467 - 3.800 3.549
Wall-213 SM 2 1.569 - 3.800 11.924
Wall-214 SM 2 1.069 - 3.800 8.124
Wall-215 SM 2 1.680 - 3.800 12.768
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-216 SM 2 0.407 - 3.800 3.093
Wall-217 SM 2 4.654 - 3.800 35.370
Wall-218 SM 2 0.505 - 3.800 3.838
D-9B SM -2 0.900 - 2.150 -3.870
Wall-219 SM 2 0.505 - 3.800 3.838
Wall-220 SM 2 4.749 - 3.800 36.092
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-221 SM 2 7.900 - 3.800 60.040
D-9B SM -2 0.900 - 2.150 -3.870
Wall-226 SM 2 0.600 - 3.800 4.560
Wall-227 SM 2 1.715 - 3.800 13.034
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-228 SM 2 0.600 - 3.800 4.560
Wall-229 SM 2 7.500 - 3.800 57.000
D/d of Wall SM -2 1.715 - 3.800 -13.034
Wall-230 SM 2 0.600 - 3.800 4.560
Wall-231 SM 2 1.715 - 3.800 13.034
Wall-232 SM 2 6.500 - 3.800 49.400
D/d of Wall SM -2 1.715 - 3.800 -13.034
Wall-233 SM 2 0.600 - 3.800 4.560
Wall-235 SM 2 7.300 - 3.800 55.480
Wall-237 SM 2 7.299 - 3.800 55.472

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
40 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Window SM -2 1.350 - 1.500 -4.050


Wall-238 SM 2 0.600 - 3.800 4.560
Wall-239 SM 2 0.600 - 3.800 4.560
Wall-245 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-246 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-248 SM 2 2.550 - 3.800 19.380
Wall-249 SM 2 2.550 - 3.800 19.380
Wall-250 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-251 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-254 SM 2 24.700 3.800 187.720
DD-88A SM -2 1.600 2.150 -6.880
Wall-268 SM 2 4.540 3.800 34.504
Wall-269 SM 2 7.300 3.800 55.480
Wall-270 SM 2 7.300 3.800 55.480
Wall-271 SM 2 7.491 3.800 56.932
Wall-272 SM 2 7.500 3.800 57.000
D-9B SM -2 0.900 2.150 -3.870
Wall-273 SM 2 1.564 3.800 11.886
Wall-274 SM 2 0.443 3.800 3.367
Wall-275 SM 2 6.017 3.800 45.729
D/d of Window SM -2 1.800 1.500 -5.400
Wall-276 SM 2 2.045 3.800 15.542
Wall-279 SM 2 15.900 3.800 120.840
Wall-296 SM 2 2.900 - 3.800 22.040
Wall-303 SM 2 2.900 - 3.800 22.040
Wall-311 SM 2 0.600 3.800 4.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
41 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-312 SM 2 0.600 3.800 4.560


Wall-315 SM 2 0.600 3.800 4.560
Wall-316 SM 2 0.600 3.800 4.560
Wall-319 SM 2 0.600 - 3.800 4.560
Wall-320 SM 2 0.600 - 3.800 4.560
Wall-321 SM 2 46.833 - 3.800 355.931
D/d of Window SM -10 1.350 - 1.500 -20.250
D/d of Column SM -6 0.800 - 3.800 -18.240
Wall-337 SM 2 0.600 - 3.800 4.560
Wall-338 SM 2 0.600 - 3.800 4.560
Wall-343 SM 2 0.600 - 3.800 4.560
Wall-347 SM 2 2.250 - 3.800 17.100
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-349 SM 2 1.450 - 3.800 11.020
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-350 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-353 SM 2 4.150 - 3.800 31.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-355 SM 2 2.100 - 3.800 15.960
Wall-356 Missing -
Wall-361 SM 2 18.550 - 3.800 140.980
D/d for Column SM -4 0.800 - 3.800 -12.160
Wall-365 & 365A SM 4 2.800 - 3.800 42.560
Wall-382 SM 2 2.550 - 3.800 19.380
D/d of Drop Panel SM
Wall-393 SM 2 0.600 - 3.800 4.560
Wall-394 SM 2 0.600 - 3.800 4.560
Wall-395 SM 2 4.651 - 3.800 35.348
D-75 SM -4 0.750 - 2.150 -6.450

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
42 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


Wall-399 SM 2 7.306 - 3.800 55.526
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-403 SM 2 7.306 - 3.800 55.526
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-404 SM 2 2.225 - 3.800 16.910
D-75 SM -2 0.750 - 2.150 -3.225
Wall-408 SM 2 0.600 - 3.800 4.560
Wall-409 SM 2 0.600 - 3.800 4.560
Wall-410 SM 2 7.306 - 3.800 55.526
D/d of Window SM -2 1.350 - 1.500 -4.050
Wall-412 SM 2 0.600 - 3.800 4.560
Wall-413 SM 2 0.600 - 3.800 4.560
Wall-455 SM 2 7.300 - 3.800 55.480
Wall-456 SM 2 7.300 - 3.800 55.480
Wall-457 SM 2 2.500 - 3.800 19.000
Wall-467 SM 2 4.500 - 3.800 34.200
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-469 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-472 SM 2 1.450 - 3.800 11.020
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-498 SM 2 2.650 - 3.800 20.140
Wall-517 SM 2 3.110 - 3.800 23.636
Wall-519 SM 2 7.089 - 3.800 53.876
Wall-520 SM 2 3.110 - 3.800 23.636
Wall-532 SM 2 7.080 - 3.800 53.808
D-10A SM -2 1.000 - 2.150 -4.300
Wall-545 SM 2 7.189 - 3.800 54.636
D/d of Drop Panel SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
43 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-552 SM 2 7.090 - 3.800 53.884


Wall-559 SM 2 2.550 - 3.800 19.380
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-564 SM 2 3.800 - 3.800 28.880
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-565 SM 2 1.450 - 3.800 11.020
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-567 SM 2 0.900 - 3.800 6.840
Wall-568 SM 2 2.799 - 3.800 21.272
Wall-569 SM 2 7.800 - 3.800 59.280
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-570 SM 2 8.459 - 3.800 64.288
D-9B SM -2 0.900 - 2.150 -3.870
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-571 SM 2 7.755 - 3.800 58.938
Wall-583 SM 2 6.350 - 3.800 48.260
D/d of Drop Panel SM
Wall-585 SM 2 5.500 - 3.800 41.800
D/d of Window SM -2 1.700 - 1.000 -3.400
Wall-586 SM 2 7.700 - 3.800 58.520
RFD-12 SM -2 1.200 - 2.150 -5.160
Wall-589 SM 2 5.900 - 3.800 44.840
RFD-12 SM -2 1.200 - 2.150 -5.160
Wall-600 SM 2 2.335 - 3.800 17.746
Wall-601 SM 2 0.365 - 3.800 2.774
Wall-603 SM 2 2.680 - 3.800 20.368
Wall-608 SM 2 7.617 - 3.800 57.889
Wall-612 SM 2 2.205 - 3.800 16.758
Wall-614 SM 2 1.231 - 3.800 9.356
FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
44 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-615 SM 2 2.250 - 3.800 17.100


D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-616 SM 2 4.450 - 3.800 33.820
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-626 SM 2 5.375 - 3.800 40.850
Wall-627 SM 2 5.375 - 3.800 40.850
D/d of Window SM -2 1.700 - 1.000 -3.400
Wall-674 SM 2 7.370 - 3.800 56.012
Wall-675 SM 2 3.100 - 3.800 23.560
Wall-678 SM 2 3.100 - 3.800 23.560
Wall-705 SM 2 7.080 - 3.800 53.808
D/d of Window SM -6 1.300 - 2.150 -16.770
Wall-711 SM 2 1.500 - 3.800 11.400
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-713 SM 2 3.827 - 3.800 29.085
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-718 SM 2 5.150 - 3.800 39.140
D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-720 SM 2 8.700 - 3.800 66.120
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-747 SM 2 1.680 - 3.800 12.768
Wall-748 SM 2 1.442 - 3.800 10.959
Wall-749 SM 2 1.360 - 3.800 10.336
Wall-750 SM 2 2.510 - 3.800 19.076
Wall-751 SM 2 15.090 - 3.800 114.684
Wall-752 SM 2 1.442 - 3.800 10.959
Wall-753 SM 2 1.680 - 3.800 12.768
D/d for Window SM -8 0.635 - 1.000 -5.080
Wall-761 SM 2 1.500 - 3.800 11.400
FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
45 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-762 SM 2 2.550 - 3.800 19.380


D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-777 SM 2 4.450 - 3.800 33.820
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-764 SM 2 1.020 - 3.800 7.752
D/d of Window SM -2 1.020 - 1.000 -2.040
Wall-765 SM 2 0.165 - 3.800 1.254
Wall-766 SM 2 3.770 - 3.800 28.652
Wall-767 SM 2 0.165 - 3.800 1.254

Qty Ground Floor= (Sub total b) 4,845.009


First Floor
H = 9.825-6.225-0.225 = 2.6
Wall-1 SM 2 6.434 - 2.600 33.457
Wall-2 SM 2 8.250 - 2.600 42.900
d/d for Door SM -2 1.200 - 2.150 -5.160
Wall-6 SM 2 7.100 - 2.600 36.920
Wall-8 SM 2 7.300 - 2.600 37.960
Wall-14 SM 2 3.588 - 2.600 18.658
Wall-16 SM 2 7.624 - 2.600 39.645
Wall-17 SM 2 7.691 - 2.600 39.993
Wall-20 SM 2 4.829 - 2.600 25.111
Wall-34 SM 2 7.464 - 2.600 38.813
Wall-36 SM 2 7.517 - 2.600 39.088
Wall-40 SM 2 0.600 - 2.600 3.120
Wall-41 SM 2 0.600 - 2.600 3.120
Wall-42 SM 2 7.056 - 2.600 36.691
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-48 SM 2 0.600 - 2.600 3.120
Wall-49 SM 2 6.217 - 2.600 32.328

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
46 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Window SM -2 1.350 - 2.000 -5.400


Wall-50 SM 2 0.600 - 2.600 3.120
Wall-54 SM 2 0.600 - 2.600 3.120
Wall-55 SM 2 0.600 - 2.600 3.120
Wall-56 SM 2 7.299 - 2.600 37.955
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-57 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-58 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-59 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-60 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-61 SM 2 5.450 - 2.600 28.340
D/d for Opening SM -4 1.200 - 2.150 -10.320
Wall-63 SM 2 24.600 - 2.600 127.920
Wall-68 SM 2 0.600 - 2.600 3.120
Wall-69 SM 2 7.300 - 2.600 37.960
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-70 SM 2 0.600 - 2.600 3.120
Wall-78 SM 2 0.800 - 2.600 4.160
Wall-79 SM 2 2.500 - 2.600 13.000
Wall-80 SM 2 0.800 - 2.600 4.160
Wall-82 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-84 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-85 SM 2 4.150 - 2.600 21.580
FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
47 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-90 SM 2 2.100 - 2.600 10.920


Wall-93 SM 2 7.200 - 2.600 37.440
Wall-95 SM 2 0.800 - 2.600 4.160
Wall-96 SM 2 7.300 - 2.600 37.960
Wall-97 SM 2 7.300 - 2.600 37.960
Wall-102 SM 2 6.350 - 2.600 33.020
D/d of Window SM 2 1.350 - 2.000 5.400
Wall-103 SM 2 0.600 - 2.600 3.120
Wall-104 SM 2 0.600 - 2.600 3.120
Wall-106 SM 2 1.605 - 2.600 8.346
Wall-114 SM 2 0.600 - 2.600 3.120
Wall-116 SM 2 7.300 - 2.600 37.960
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-117 SM 2 0.600 - 2.600 3.120
Wall-123 SM 2 0.600 - 2.600 3.120
Wall-124 SM 2 7.300 - 2.600 37.960
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-126 SM 2 0.600 - 2.600 3.120
Wall-132 SM 2 0.600 - 2.600 3.120
Wall-133 SM 2 0.600 - 2.600 3.120
Wall-134 SM 2 7.300 - 2.600 37.960
D/d of Window SM -2 1.350 - 2.000 -5.400
Wall-146 SM 2 7.300 - 2.600 37.960
Wall-151 SM 2 7.300 - 2.600 37.960
Wall-156 SM 2 2.500 - 2.600 13.000
Wall-158 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-159 SM 2 4.500 - 2.600 23.400
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-161 SM 2 2.650 - 2.600 13.780

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
48 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-162 SM 2 7.090 - 2.600 36.868


Wall-163 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-165 SM 2 7.080 - 2.600 36.816
Wall-166 SM 2 2.240 - 2.600 11.648
Wall-167 SM 2 4.690 - 2.600 24.388
Wall-209 SM 2 3.000 - 2.600 15.600
Wall-210 SM 2 1.150 - 2.600 5.980
Wall-212 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-213 SM 2 3.550 - 2.600 18.460
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-220 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-237 SM 2 7.080 - 2.600 36.816
Wall-238 SM 2 7.080 - 2.600 36.816
Wall-239 SM 2 6.916 - 2.600 35.963
Wall-240 SM 2 7.080 - 2.600 36.816
Wall-241 SM 2 6.916 - 2.600 35.963
Wall-243 SM 2 7.080 - 2.600 36.816
Wall-244 SM 2 1.290 - 2.600 6.708
Wall-245 SM 2 2.250 - 2.600 11.700
Wall-246 SM 2 6.990 - 2.600 36.348
Wall-249 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-250 SM 2 4.450 - 2.600 23.140
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-270 SM 2 3.770 - 2.600 19.604
Wall-291 SM 2 1.120 - 2.600 5.824
Wall-292 SM 2 6.980 - 0.200 2.792

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
49 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-322 SM 2 11.200 - 2.600 58.240


Wall-349 SM 2 8.700 - 2.600 45.240
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-350 SM 2 5.150 - 2.600 26.780
D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-353 SM 2 7.800 - 2.600 40.560
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-356 SM 2 3.827 - 2.600 19.900
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-377 SM 2 7.689 - 2.600 39.983
Wall-378 SM 2 2.205 - 2.600 11.466
Wall-380 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-381 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-382 SM 2 4.450 - 2.600 23.140
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-384 SM 2 3.000 - 2.600 15.600
DD-88B SM -2 1.600 - 2.150 -6.880
Wall-386 SM 2 0.610 - 2.625 3.203
Wall-419 SM 4 6.400 - 2.600 66.560

Qty First Floor= (Sub total c) 1,928.733

Second Floor
H = 13.425-9.828-0.225 = 2.6
Wall-58 SM 2 4.150 - 2.600 21.580
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-59 SM 2 2.550 - 2.600 13.260

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
50 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Opening SM -2 1.300 - 2.150 -5.590


Wall-61 SM 2 1.450 - 2.600 7.540
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-63 SM 2 0.800 - 2.600 4.160
Wall-64 SM 2 2.100 - 2.600 10.920
Wall-87 SM 2 2.205 - 2.600 11.466
Wall-89 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-90 SM 2 4.433 - 2.600 23.052
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-91 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.600 -6.760
Wall-95 SM 2 6.990 - 0.200 2.796
Wall-98 SM 2 0.610 - 2.600 3.172
Wall-101 SM 2 6.750 - 0.200 2.700
Wall-102 SM 2 6.750 - 0.200 2.700
Wall-105 SM 2 2.875 - 2.600 14.950
Wall-108 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-109 SM 2 3.833 - 2.000 15.332
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-110 SM 2 8.700 - 2.600 45.240
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-144 SM 2 6.700 - 0.200 2.680
Wall-144a SM 2 1.120 - 2.600 5.824
Wall-145 SM 2 6.750 - 0.200 2.700
Wall-145a SM 2 1.120 - 2.600 5.824
Wall-146 SM 2 6.750 - 0.200 2.700
Wall-148 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
51 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-149 SM 2 4.450 - 2.600 23.140


FD-12 SM -2 1.200 - 2.150 -5.160
Wall-150 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-154 SM 2 2.250 - 2.600 11.700
Wall-183 SM 2 3.900 - 2.600 20.280
Wall-187 SM 2 3.900 - 2.600 20.280
Wall-192 SM 2 6.750 - 0.200 2.700
Wall-200 SM 2 2.250 - 2.600 11.700
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-201 SM 2 2.550 - 2.600 13.260
D/d of Opening SM -2 1.300 - 2.150 -5.590
Wall-202 SM 2 2.250 - 2.600 11.700
Wall-203 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-291 SM 2 7.800 - 2.600 40.560
D/d of Opening SM -6 1.300 - 2.150 -16.770
Wall-301 SM 2 5.150 - 2.600 26.780
D/d of Opening SM -4 1.300 - 2.150 -11.180
Wall-339 SM 2 7.080 - 0.200 2.832
Wall-352 SM 2 7.080 - 0.200 2.832
Wall-362 SM 2 7.080 - 0.200 2.832
Wall-367 SM 2 7.080 - 0.200 2.832
Wall-368 SM 2 7.080 - 0.200 2.832
Wall-369 SM 2 7.080 - 0.200 2.832

Qty Second Floor= (Sub total d) 333.148


3rd Floor
Wall-5 SM 2 2.250 - 2.600 11.700
Wall-8 SM 2 1.450 - 2.600 7.540

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
52 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 (5.160)


Wall-9 SM 2 2.550 - 2.600 13.260
D/d of opening SM -2 1.300 - 2.150 (5.590)
Wall-11 SM 2 2.100 - 2.600 10.920
Wall-12 SM 2 4.100 - 2.600 21.320
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-13 SM 2 2.500 - 2.600 13.000
Wall-14 SM 2 4.399 - 2.600 22.875
DD-88 SM -2 1.600 - 2.150 (6.880)
Wall-15 SM 2 2.351 - 2.600 12.225
Wall-16 SM 2 7.200 - 2.600 37.440
Wall-17 SM 2 7.300 - 2.600 37.960
D/d window SM -2 1.350 - 2.050 -5.535
Wall-18 SM 2 7.300 - 2.600 37.960
D/d window SM -4 1.350 - 2.050 -11.070
Wall-19 SM 2 7.300 - 2.600 37.960
D/d window SM -4 1.350 - 2.050 -11.070
Wall-20 SM 2 7.300 - 2.600 37.960
D/d window SM -4 1.350 - 2.050 -11.070
Wall-21 SM 2 7.300 - 2.600 37.960
D/d window SM -4 1.350 - 2.050 -11.070
Wall-22 SM 2 7.300 - 2.600 37.960
D/d window SM -4 1.350 - 2.050 -11.070
Wall-23 SM 2 2.500 - 2.600 13.000
D/d window SM -2 1.350 - 2.050 -5.535
Wall-24 SM 46 0.600 - 2.600 71.760
Wall-25 SM 2 4.700 - 2.600 24.440
D/d of Drop Panel SM
Wall-26 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
53 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-27 SM 2 7.200 - 2.600 37.440


D/d of Drop Panel SM
Wall-28 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM
Wall-29 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM
Wall-30 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM
Wall-31 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM
Wall-32 SM 2 2.790 - 2.600 14.508
DD-88A SM -2 1.600 - 2.150 (6.880)
D/d of Drop Panel SM
Wall-33 SM 2 2.500 - 2.600 13.000
Wall-34 SM 2 4.500 - 2.600 23.400
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-35 SM 2 2.550 - 2.600 13.260
D/d opening SM -2 1.300 - 2.150 (5.590)
Wall-36 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-40 SM 2 2.650 - 2.600 13.780
Wall-41 SM 2 62.000 - 2.600 322.400
D/d for Door SM -8 1.600 - 2.150 -27.520
Wall-45 SM 2 6.923 - 2.600 36.000
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-46 SM 2 7.300 - 2.600 37.960
Wall-47 SM 2 3.000 - 2.600 15.600
Wall-76 SM 2 2.008 - 2.600 10.442
Wall-77 SM 2 0.950 - 2.600 4.940
D/d of Drop Panel SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
54 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10 SM -2 1.000 - 2.150 (4.300)


Wall-78 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM
Wall-79 SM 2 7.300 - 2.600 37.960
D/d Drop Panel 0.950+0.800 SM
Wall-80 SM 2 7.300 - 2.600 37.960
Wall-101 SM 2 24.455 - 2.600 127.166
D-10A SM -6 1.000 - 2.150 (12.900)
D-9A SM -6 0.900 - 2.150 (11.610)
Wall-102 SM 2 7.300 - 2.600 37.960
D/d drop Panel SM
Wall-103 SM 2 7.300 - 2.600 37.960
D/d for Door SM -2 1.000 - 2.150 -4.300
D/d Drop Panel SM
Wall-105 SM 4 0.860 - 2.600 8.944
Wall-107 SM 2 8.110 - 2.600 42.172
Wall-109 SM 2 2.500 - 2.600 13.000
Wall-111 SM 2 4.700 - 2.600 24.440
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-118 SM 2 2.550 - 2.600 13.260
Wall-119 SM 2 1.450 - 2.600 7.540
D/d opening SM -2 1.300 - 2.150 (5.590)
Wall-126 SM 2 2.205 - 2.600 11.466
Wall-128 SM 2 1.500 - 2.600 7.800
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-129 SM 2 4.463 - 2.600 23.208
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-130 SM 2 2.550 - 2.600 13.260
D/d opening SM -2 1.300 - 2.150 (5.590)
Wall-148 SM 2 1.300 - 2.600 6.760

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
55 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 (5.160)


Wall-150 SM 2 3.827 - 2.600 19.900
DD-88 SM -2 1.600 - 2.150 (6.880)
Wall-156 SM 2 7.180 - 2.600 37.336
D-9A SM -4 0.900 - 2.150 (7.740)
Wall-158 SM 2 5.300 - 2.600 27.560
Wall-159 SM 2 4.544 - 2.600 23.629
Wall-160 SM 2 7.140 - 2.600 37.128
D-9A SM -2 0.900 - 2.150 -3.870
Wall-161 SM 2 7.800 - 2.600 40.560
D/d opening SM -6 1.300 - 2.150 (16.770)
Wall-167 SM 2 8.700 - 2.600 45.240
D/d opening SM -6 1.300 - 2.150 (16.770)
Wall-168 SM 2 5.150 - 2.600 26.780
D/d opening SM -4 1.300 - 2.150 (11.180)
Wall-170 SM 2 4.850 - 2.600 25.220
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-171 SM 2 6.900 - 2.600 35.880
D-10A SM -2 1.000 - 2.150 (4.300)
D/d of Drop Panel SM
Wall-172 SM 2 3.399 - 2.600 17.675
Wall-173 SM 2 16.100 - 2.600 83.720
DD-88A SM -6 1.600 - 2.150 (20.640)
Wall-175 SM 2 3.700 - 2.600 19.240
Wall-176 SM 2 15.750 - 2.600 81.900
DD-88A SM -4 1.600 - 2.150 (13.760)
Wall-177 SM 2 1.999 - 2.600 10.395
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-178 SM 2 7.001 - 2.600 36.405
D/d Drop Panel SM

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
56 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-179 SM 2 2.199 - 2.600 11.435


D/d Drop Panel SM
Wall-180 SM 2 12.350 - 2.600 64.220
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-181 SM 2 12.350 - 2.600 64.220
DD-88A SM -2 1.600 - 2.150 (6.880)
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-182 SM 2 2.401 - 2.600 12.485
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-183 SM 2 7.000 - 2.600 36.400
D/d Drop Panel SM
Wall-184 SM 2 2.100 - 2.600 10.920
D/d Drop Panel SM
Wall-185 SM 2 3.400 - 2.600 17.680
D/d Drop Panel SM
Wall-193 SM 2 4.450 - 2.600 23.140
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-208 SM 2 2.550 - 2.600 13.260
D/d opening SM -2 1.300 - 2.150 (5.590)
Wall-210 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-212 SM 2 2.250 - 2.600 11.700

Qty Third Floor= (Sub total e) 2,190.274


Total Qty of Plaster work on 200mm thick wall 9,676.559
Plaster on 150mm hollow block work
Wall 01 sq.m 2 13.750 3.800 104.500
Door Deduction D10C sq.m -2 1.000 2.150 -4.300
Wall 02 sq.m 2 5.650 3.800 42.940
Wall 03 sq.m 2 21.350 3.800 162.260

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
57 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Columns Deduction sq.m -4 0.900 2.150 -7.740


Wall 08 sq.m 2 1.950 3.800 14.820
Door Deduction DD88D sq.m -2 1.600 2.150 -6.880
Wall 11 sq.m 2 0.800 3.800 6.080
Wall 13 sq.m 2 7.300 3.800 55.480
Wall 14 sq.m 2 7.300 3.800 55.480
Wall 15 sq.m 2 3.150 3.800 23.940
Wall 16 sq.m 2 4.650 3.800 35.340
Wall 17 sq.m 2 7.300 3.800 55.480
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 18 sq.m 2 5.150 3.800 39.140
Wall 19 sq.m 2 7.300 3.800 55.480
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 20 sq.m 2 5.150 3.800 39.140
Wall 21 sq.m 2 24.950 3.800 189.620
Wall 22 sq.m 2 2.425 3.800 18.430
Door Deduction D75 sq.m -2 0.750 2.150 -3.225
Wall 24 sq.m 2 1.950 3.800 14.820
Wall 25 sq.m 2 1.501 3.800 11.408
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Wall 26 sq.m 2 4.352 3.800 33.075
D/d for Door sq.m 2 -1.000 2.150 -4.300
Wall 30 sq.m 2 2.949 3.800 22.412
Wall 31 sq.m 2 4.850 3.800 36.860
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 32 sq.m 2 4.200 3.800 31.920
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 33 sq.m 2 8.750 3.800 66.500
D/d for Door sq.m -2 1.000 2.150 -4.300
Wall 34 sq.m 2 5.400 3.800 41.040

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
58 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Deduction Column sq.m -2 0.800 2.150 -3.440


Wall 35 sq.m 2 5.400 3.800 41.040
Door Deduction D10C sq.m -2 1.000 2.150 -4.300
Wall 36 sq.m 2 3.600 3.800 27.360
Wall 41 sq.m 2 5.749 3.800 43.692
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Wall 42 sq.m 2 2.500 3.800 19.000
D/d for Door sq.m 2 1.600 2.150 6.880
Wall 45 sq.m 2 2.650 3.800 20.140
Door Deduction D88D sq.m -2 1.600 2.150 -6.880
Wall 46 sq.m 2 21.175 3.800 160.930
D/d for Door sq.m -2 1.800 2.150 -7.740
Wall 47 sq.m 2 17.841 3.800 135.592
Deduction of Coulmn sq.m -4 0.800 2.150 -6.880
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
D/d for Opening sq.m -2 7.471 3.800 -56.780
Wall 48 sq.m 2 3.000 3.800 22.800
Wall 49 sq.m 2 1.650 3.800 12.540
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Wall 50 sq.m 2 5.800 3.800 44.080
Wall 51 sq.m 2 5.150 3.800 39.140
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Wall 63 sq.m 2 5.400 3.800 41.040
Wall 64 sq.m 2 2.490 3.800 18.924
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Wall 70 sq.m 2 14.950 3.800 113.620
Deduction Coulmns sq.m -4 2.000 2.150 -17.200
Wall 86 sq.m 2 2.500 3.800 19.000
Door Deduction D-88D sq.m -2 1.600 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
59 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 87 sq.m 2 7.826 3.800 59.478


Door Deduction D-88A sq.m -2 1.600 2.150 -6.880
Wall 88 sq.m 2 2.858 3.800 21.721
Door Deduction D-9A sq.m -2 0.900 2.150 -3.870
Wall 89 sq.m 2 2.858 3.800 21.721
Wall 90 sq.m 2 11.175 3.800 84.930
Column Deduction sq.m -2 0.800 3.800 -6.080
Wall 91 sq.m 2 8.900 3.800 67.640
D/d for Opening sq.m -2 3.000 3.800 -22.800
Wall 92 sq.m 2 0.750 3.800 5.700
Wall 93 sq.m 2 2.500 3.800 19.000
Wall 94 sq.m 2 7.300 3.800 55.480
Door Deduction D-9D sq.m -2 0.900 2.150 -3.870
Wall 96 sq.m 2 2.400 3.800 18.240
Wall 97 sq.m 2 2.400 3.800 18.240
Wall 98 sq.m 2 2.250 3.800 17.100
Door Deduction DD88A sq.m -2 1.600 2.150 -6.880
Wall 136 sq.m 2 3.250 3.800 24.700
Wall 137 sq.m 2 2.350 3.800 17.860
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Wall 141 sq.m 2 2.700 3.800 20.520
Wall 143 sq.m 2 3.200 3.800 24.320
Wall 144 sq.m 2 7.300 3.800 55.480
Door Deduction D9A sq.m -6 0.900 2.150 -11.610
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 145 sq.m 2 8.112 3.800 61.651
Door Deduction D9A sq.m -4 0.900 2.150 -7.740
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 145 A sq.m 2 3.100 3.800 23.560
Wall 146 sq.m 2 3.100 3.800 23.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
60 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 146 A sq.m 2 4.450 3.800 33.820


Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 152 sq.m 2 1.860 3.800 14.136
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 156 sq.m 2 6.351 3.800 48.268
Wall 157 sq.m 2 7.300 3.800 55.480
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 163 sq.m 2 4.525 3.800 34.390
Deduction Oppening sq.m -2 1.735 2.150 -7.461
Wall 164 sq.m 2 21.325 3.800 162.070
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Door Deduction DD-88A sq.m -2 2.318 2.150 -9.967
Wall 165 sq.m 2 2.750 3.800 20.900
Wall 166 sq.m 2 1.900 3.800 14.440
Door Deduction D-12B sq.m -2 1.200 2.150 -5.160
Wall 167 sq.m 2 0.450 3.800 3.420
Wall 168 sq.m 2 20.875 3.800 158.650
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Door Deduction D-09A sq.m -4 0.900 2.150 -7.740
Wall 169 sq.m 2 2.858 3.800 21.721
Wall 170 sq.m 2 2.858 3.800 21.721
Wall 171 sq.m 2 2.858 3.800 21.721
Wall 172 sq.m 2 12.950 3.800 98.420
Wall 214 sq.m 2 2.500 3.800 19.000
Door Deduction D88A A sq.m -2 1.600 2.150 -6.880
Wall 216 sq.m 2 32.727 3.800 248.725
Door Deduction D-88D sq.m -2 1.600 2.150 -6.880
Wall 217 sq.m 2 0.352 3.800 2.675
Wall 218 sq.m 2 5.150 3.800 39.140
Wall 219 sq.m 2 1.693 3.800 12.867

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
61 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 220 sq.m 2 2.457 3.800 18.673


Wall 222 sq.m 2 2.800 3.800 21.280
Wall 223 sq.m 2 4.225 3.800 32.110
Door Deduction D-09 A sq.m -2 0.900 2.150 -3.870
Wall 224 sq.m 2 5.586 3.800 42.454
Wall 225 sq.m 2 5.200 3.800 39.520
Wall 226 sq.m 2 1.500 3.800 11.400
Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590
Wall 227 sq.m 2 3.262 3.800 24.791
Wall 228 sq.m 2 1.188 3.800 9.029
Wall 230 sq.m 2 1.499 3.800 11.392
Wall 231 sq.m 2 1.527 3.800 11.605
Wall 232 sq.m 2 0.630 3.800 4.788
Wall 233 sq.m 2 8.650 3.800 65.740
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Wall 234 sq.m 2 6.400 3.800 48.640
Door Deduction DD-88A sq.m -4 1.600 2.150 -13.760
Wall 235 sq.m 2 2.222 3.800 16.887
Door Deduction DD-10A sq.m -2 1.000 2.150 -4.300
Wall 236 sq.m 2 2.137 3.800 16.241
Wall 237 sq.m 2 7.600 3.800 57.760
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 238 sq.m 2 3.780 3.800 28.728
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 239 sq.m 2 1.379 3.800 10.480
Wall 240 sq.m 2 3.100 3.800 23.560
Wall 241 sq.m 2 37.676 3.800 286.338
Door Deduction DD-88A sq.m -4 1.600 2.150 -13.760
Door Deduction D-9A sq.m -2 0.900 2.150 -3.870
Wall 242 sq.m 2 2.499 3.800 18.992

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
62 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 243 sq.m 2 19.051 3.800 144.788


Wall 244 sq.m 2 14.050 3.800 106.780
Door Deduction D-10A sq.m -6 1.000 2.150 -12.900
Wall 245 sq.m 2 4.150 3.800 31.540
Wall 246 sq.m 2 2.350 3.800 17.860
Wall 247 sq.m 2 10.550 3.800 80.180
Door Deduction D-10A sq.m -2 1.000 2.150 -4.300
Wall 248 sq.m 2 4.000 3.800 30.400
Wall 249 sq.m 2 4.000 3.800 30.400
Wall 250 sq.m 2 6.200 3.800 47.120
Wall 251 sq.m 2 17.200 3.800 130.720
Door Deduction D-10C sq.m -10 1.000 2.150 -21.500
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Wall 252 sq.m 2 3.100 3.800 23.560
Wall 253 sq.m 2 3.100 3.800 23.560
Wall 254 sq.m 2 2.042 3.800 15.519
Wall 255 sq.m 2 0.226 3.800 1.718
Wall 256 sq.m 2 25.526 3.800 193.998
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 257 sq.m 2 3.100 3.800 23.560
Wall 260 sq.m 2 3.100 3.800 23.560
Wall 261 sq.m 2 4.450 3.800 33.820
Wall 262 sq.m 2 10.550 3.800 80.180
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 263 sq.m 2 8.950 3.800 68.020
Door Deduction D-10A sq.m -6 1.000 2.150 -12.900
Wall 264 sq.m 2 13.750 3.800 104.500
Door Deduction D-10A sq.m -6 1.000 2.150 -12.900
D/d for Window sq.m -2 4.000 2.500 -20.000

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
63 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 265 sq.m 2 1.200 3.800 9.120


Wall 266 sq.m 2 1.850 3.800 14.060
Wall 267 sq.m 2 3.500 3.800 26.600
Wall 268 sq.m 2 22.000 3.800 167.200
Wall 269 sq.m 2 2.400 3.800 18.240
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 274 sq.m 2 19.814 3.800 150.586
Door Deduction DD-88A sq.m -4 1.600 2.150 -13.760
Wall 276 sq.m 2 2.957 3.800 22.473
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 277 sq.m 2 6.675 3.800 50.730
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Door Deduction GD-01 sq.m -2 1.100 2.150 -4.730
Wall 279 sq.m 2 2.800 3.800 21.280
Wall 280 sq.m 2 2.150 3.800 16.340
Wall 281 sq.m 2 4.500 3.800 34.200
Wall 282 sq.m 2 4.500 3.800 34.200
Wall 283 sq.m 2 7.300 3.800 55.480
Wall 284 sq.m 2 2.800 3.800 21.280
Wall 286 sq.m 2 2.800 3.800 21.280
D/d for D-75 sq.m -4 0.900 2.150 -7.740
Wall 287 sq.m 2 2.150 3.800 16.340
Wall 288 sq.m 2 6.675 3.800 50.730
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Door Deduction GD-01 sq.m -2 1.100 2.150 -4.730
Wall 289 sq.m 2 1.186 3.800 9.014
Wall 290 sq.m 2 2.150 3.800 16.340
Wall 291 sq.m 2 2.150 3.800 16.340
Wall 292 sq.m 2 1.186 3.800 9.014
Wall 293 sq.m 2 3.300 3.800 25.080

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
64 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 294 sq.m 2 3.300 3.800 25.080


Wall 299 sq.m 2 5.027 3.800 38.205
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Wall 300 sq.m 2 5.025 3.800 38.190
Door Deduction DD-99 sq.m -2 1.300 2.150 -5.590
Wall 301 sq.m 2 14.898 3.800 113.225
Door Deduction DD-99 sq.m -2 1.600 2.150 -6.880
D/d for Column sq.m -4 0.800 3.800 -12.160
Wall 302 sq.m 2 4.786 3.800 36.374
Wall 302 a sq.m 2 0.875 3.800 6.650
Wall 303 sq.m 2 3.308 3.800 25.141
Wall 304 sq.m 2 0.516 3.800 3.922
Wall 305 sq.m 2 2.137 3.800 16.241
Wall 306 sq.m 2 2.231 3.800 16.956
Wall 307 sq.m 2 2.225 3.800 16.910
Wall 308 sq.m 2 7.800 3.800 59.280
D/d for Door sq.m -6 1.300 2.150 -16.770
Wall 309 sq.m 2 16.898 3.800 128.425
Door Deduction DD-88 sq.m -2 1.600 2.150 -6.880
Wall 310 sq.m 2 1.750 3.800 13.300
Wall 311 sq.m 2 15.000 3.800 114.000
Deduction Column sq.m -2 0.800 2.150 -3.440
Wall 312 sq.m 2 3.085 3.800 23.446
Wall 313 sq.m 2 4.774 3.800 36.282
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Wall 314 sq.m 2 2.035 3.800 15.466
Wall 315 sq.m 2 1.350 3.800 10.260
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Wall 316 sq.m 2 4.585 3.800 34.846
Wall 317 sq.m 2 4.450 3.800 33.820

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
65 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 318 sq.m 2 3.215 3.800 24.434


Door Deduction D-75 sq.m -4 0.750 2.150 -6.450
Wall 319 sq.m 2 2.015 3.800 15.310
Wall 320 sq.m 2 3.564 3.800 27.086
Wall 321 sq.m 2 1.164 3.800 8.846
Wall 322 sq.m 2 1.164 3.800 8.846
Wall 323 sq.m 2 3.301 3.800 25.088
Wall 324 sq.m 2 4.151 3.800 31.548
Wall 325 sq.m 2 3.415 3.800 25.954
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Wall 326 sq.m 2 5.049 3.800 38.372
Wall 327 sq.m 2 7.000 3.800 53.200
Wall 328 sq.m 2 4.600 3.800 34.960
Door Deduction DD-88 sq.m -8 1.600 2.150 -27.520
Wall 330 sq.m 2 10.565 3.800 80.294
Door Deduction D-09A sq.m -2 0.900 2.150 -3.870
Door Deduction D-09B sq.m -4 0.900 2.150 -7.740
Wall 331 sq.m 2 2.885 3.800 21.926
Wall 333 sq.m 2 2.250 3.800 17.100
Wall 334 sq.m 2 1.885 3.800 14.326
Wall 335 sq.m 2 3.219 3.800 24.464
Door Deduction D-75 sq.m -4 0.750 2.150 -6.450
Wall 337 sq.m 2 8.951 3.800 68.028
Door Deduction D-9B sq.m -2 0.900 2.150 -3.870
Wall 339 sq.m 2 5.300 3.800 40.280
Door Deduction D-9A sq.m -4 0.900 2.150 -7.740
Wall 340 sq.m 2 2.350 3.800 17.860
Wall 341 sq.m 2 2.350 3.800 17.860
Wall 342 sq.m 2 2.550 3.800 19.380
Wall 343 sq.m 2 4.400 3.800 33.440

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
66 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Door Deduction FD-12 sq.m -2 1.300 2.150 -5.590


Wall 347 sq.m 2 2.100 3.800 15.960
Wall 348 sq.m 2 3.850 3.800 29.260
Wall 349 sq.m 2 2.100 3.800 15.960
Wall 350 sq.m 2 7.050 3.800 53.580
Door Deduction D-09A sq.m -4 0.900 2.150 -7.740
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Wall 351 sq.m 2 15.330 3.800 116.508
Door Deduction DD-88D sq.m -2 2.200 2.150 -9.460
Wall 356 sq.m 2 0.690 3.800 5.244
Wall 367 sq.m 2 3.000 3.800 22.800
Wall 368 sq.m 2 0.900 3.800 6.840
Wall 369 sq.m 2 3.750 3.800 28.500
Wall 370 sq.m 2 2.100 3.800 15.960
Wall 371 sq.m 2 0.900 3.800 6.840
Wall 372 sq.m 2 1.050 3.800 7.980
Wall 373 sq.m 2 1.041 3.800 7.912
Wall 374 sq.m 2 7.080 3.800 53.808
Wall 375 sq.m 2 7.080 3.800 53.808
Wall 380 sq.m 2 1.890 3.800 14.364
Wall 399 sq.m 1 2.628 3.800 9.986
Window Deduction W-23 sq.m -2 1.000 2.000 -4.000

Plaster Qty on L.G.F at 150mm thick hollow block work= 7,572.933

Ground Floor
Wall-62 SM 2 2.911 - 3.800 22.124
Wall-63 SM 2 2.358 - 3.800 17.921
D-10A SM -2 1.000 - 2.150 -4.300
Wall-74 SM 2 3.437 - 3.800 26.121
Wall-75 SM 2 6.919 - 3.800 52.584

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
67 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-76 SM 2 0.150 - 3.800 1.140


Wall-77 SM 2 4.683 - 3.800 35.591
Wall-77a SM 2 1.200 - 3.800 9.120
D-10A SM -2 1.000 - 2.150 -4.300
Wall-80 SM 2 5.383 - 3.800 40.911
Wall-82 SM 2 1.200 - 3.800 9.120
D-10A SM -2 1.000 - 2.150 -4.300
Wall-83 SM 2 10.600 - 3.800 80.560
Wall-115 SM 2 2.125 - 3.800 16.150
Wall-117 SM 2 8.635 - 3.800 65.626
D-9A SM -2 0.900 - 2.150 -3.870
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-118 SM 2 2.400 - 3.800 18.240
Wall-119 SM 2 2.400 - 3.800 18.240
Wall-120 SM 2 8.350 - 3.800 63.460
D-9B SM -2 0.900 - 2.150 -3.870
Wall-121 SM 2 5.125 - 3.800 38.950
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-123 SM 2 3.551 - 3.800 26.988
Wall-124 SM 2 2.527 - 3.800 19.205
Wall-125 SM 2 2.500 - 3.800 19.000
Wall-132 SM 2 7.950 - 3.800 60.420
D/d of Opening SM -2 2.100 - 3.800 -15.960
D-9A SM -2 0.900 - 2.150 -3.870
Wall-133 SM 2 4.425 - 3.800 33.630
D-75 SM -2 0.750 - 2.150 -3.225
Wall-139 SM 2 2.997 - 3.800 22.777
DD-88A SM 2 1.600 - 2.150 6.880
Wall-140 SM 2 6.919 - 3.800 52.584
Wall-150 SM 2 2.750 - 3.800 20.900

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
68 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-152 SM 2 6.851 - 3.800 52.068


Wall-155 SM 2 7.166 - 3.800 54.462
D/d of Drop Panel SM -2 2.700 - 0.150 -0.810
Wall-156 SM 2 9.650 - 3.800 73.340
D-10A SM -2 1.000 - 2.150 -4.300
DD-88A SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 2.700 - 0.150 -0.810
Wall-157 SM 2 4.250 - 3.800 32.300
Wall-160 SM 2 1.200 - 3.800 9.120
Wall-162 SM 2 1.800 - 3.800 13.680
D-10 SM -2 1.000 - 2.150 -4.300
Wall-163 SM 2 1.350 - 3.800 10.260
Wall-164 SM 2 2.750 - 3.800 20.900
Wall-168 SM 2 5.475 - 3.800 41.610
D/d of Drop Panel SM -2 1.050 - 0.150 -0.315
Wall-169 SM 2 27.224 - 3.800 206.902
DD-88A SM -2 1.600 - 2.150 -6.880
D-10A SM -2 1.000 2.150 -4.300
Wall-170 SM 2 5.250 3.800 39.900
Wall-175 SM 2 5.277 - 3.800 40.105
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-179 SM 2 2.679 - 3.800 20.360
Wall-180 SM 2 1.700 - 3.800 12.920
Wall-195 SM 2 24.599 - 3.800 186.952
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-196 SM 2 9.650 - 3.800 73.340
Wall-197 SM 2 4.700 - 3.800 35.720
Wall-198 SM 2 4.550 - 3.800 34.580
Wall-199 SM 2 5.350 - 3.800 40.660
D/d of Drop Panel SM -2 1.300 - 0.150 -0.390

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
69 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-200 SM 2 2.400 - 3.800 18.240


Wall-201 SM 2 2.700 - 3.800 20.520
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-202 SM 2 1.050 - 3.800 7.980
Wall-203 SM 2 3.817 - 3.800 29.009
D/d of Drop Panel SM -2 0.767 - 0.150 -0.230
Wall-204 SM 2 16.750 - 3.800 127.300
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-205 SM 2 4.817 - 3.800 36.609
D-9A SM -2 0.900 - 2.150 -3.870
Wall-225 SM 2 4.850 - 3.800 36.860
Wall-240 SM 2 4.650 - 3.800 35.340
Wall-241 SM 2 7.300 - 3.800 55.480
Wall-242 SM 2 21.801 - 3.800 165.688
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-243 SM 2 7.219 - 3.800 54.864
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-244 SM 2 1.950 - 3.800 14.820
Wall-247 SM 2 0.200 - 3.800 1.520
Wall-252 SM 2 2.100 - 3.800 15.960
Wall-253 SM 2 4.550 - 3.800 34.580
Wall-255 SM 2 1.100 - 3.800 8.360
Wall-256 SM 2 7.150 - 3.800 54.340
D-10A SM -2 1.000 - 2.150 -4.300
Wall-257 SM 2 2.000 - 3.800 15.200
D-10A SM -2 1.000 - 2.150 -4.300
Wall-258 SM 2 2.000 - 3.800 15.200
Wall-259 SM 2 2.700 - 3.800 20.520
Wall-260 SM 2 8.600 - 3.800 65.360
D/d of Window SM -2 0.900 - 1.000 -1.800

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
70 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


Wall-261 SM 2 2.750 - 3.800 20.900
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-261A SM 2 7.300 - 3.800 55.480
Wall-262 SM 2 3.075 - 3.800 23.370
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-263 SM 2 2.750 - 3.800 20.900
Wall-264 SM 2 3.000 - 3.800 22.800
Wall-265 SM 2 2.750 - 3.800 20.900
Wall-266 SM 2 7.300 - 3.800 55.480
Wall-267 SM 2 0.800 - 3.800 6.080
Wall-277 SM 2 4.174 - 3.800 31.722
Wall-278 SM 2 4.129 - 3.800 31.380
Wall-280 SM 2 3.587 - 3.800 27.261
D-9B SM -2 0.900 - 2.150 -3.870
Wall-281 SM 2 7.749 - 3.800 58.892
D-9B SM -2 0.900 - 2.150 -3.870
Wall-282 SM 2 1.150 - 3.800 8.740
Wall-283 SM 2 1.252 - 3.800 9.515
Wall-284 SM 2 1.723 - 3.800 13.095
Wall-285 SM 2 1.433 - 3.800 10.891
Wall-286 SM 2 24.600 - 3.800 186.960
DD-88A SM -2 1.600 - 2.150 -6.880
GD-1 SM -2 2.200 - 2.150 -9.460
Wall-287 SM 2 2.975 - 3.800 22.610
Wall-288 SM 2 2.950 - 3.800 22.420
D-9A SM -2 0.900 - 2.150 -3.870
Wall-289 SM 2 4.675 - 3.800 35.530
Wall-290 SM 2 5.075 - 3.800 38.570
Wall-291 SM 2 7.500 - 3.800 57.000

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
71 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 -6.880


Wall-292 SM 2 6.919 - 3.800 52.584
D-9A SM -2 0.900 - 2.150 -3.870
D-9 SM -2 0.900 - 2.150 -3.870
Wall-293 SM 2 13.952 - 3.800 106.035
DD-88A SM -2 1.600 - 2.150 -6.880
D-9 SM -2 0.900 - 2.150 -3.870
Wall-294 SM 2 2.675 - 3.800 20.330
Wall-295 SM 2 8.150 - 3.800 61.940
Wall-298 SM 2 5.125 - 3.800 38.950
Wall-301 SM 2 3.850 - 3.800 29.260
Wall-305 SM 2 7.875 - 3.800 59.850
Wall-306 SM 2 7.450 - 3.800 56.620
Wall-307 SM 2 13.952 - 3.800 106.035
D-9 SM -2 0.900 - 2.150 -3.870
GD-4 SM -2 0.900 - 2.150 -3.870
Wall-308 SM 2 3.110 - 3.800 23.636
D-9A SM -2 0.900 - 2.150 -3.870
Wall-309 SM 2 5.475 - 3.800 41.610
Wall-310 Missing
Wall-313 SM 2 5.475 - 3.800 41.610
D-9B SM -2 0.900 - 2.150 -3.870
Wall-314 SM 2 4.340 - 3.800 32.984
D-9B SM -2 0.900 - 2.150 -3.870
Wall-317 SM 2 4.875 - 3.800 37.050
D-9A SM -2 0.900 - 2.150 -3.870
Wall-318 SM 2 7.500 - 3.800 57.000
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-322 SM 2 6.000 - 3.800 45.600
Wall-323 SM 2 5.400 - 3.800 41.040

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
72 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-324 SM 2 1.000 - 3.800 7.600


Wall-325 SM 2 7.300 - 3.800 55.480
D-9A SM -2 0.900 - 2.150 -3.870
Wall-326 SM 2 5.400 - 3.800 41.040
Wall-327 SM 2 4.900 - 3.800 37.240
Wall-328 SM 2 5.075 - 3.800 38.570
D-9A SM -2 0.900 - 2.150 -3.870
D-10A SM -2 1.000 - 2.150 -4.300
Wall-329 Missing
Wall-330 SM 2 5.250 - 3.800 39.900
Wall-331 SM 2 3.600 - 3.800 27.360
Wall-332 SM 2 2.500 - 3.800 19.000
Wall-333 SM 2 5.250 - 3.800 39.900
Wall-334 SM 2 2.200 - 3.800 16.720
Wall-335 SM 2 5.150 - 3.800 39.140
D-10A SM -2 1.000 - 2.150 -4.300
Wall-336 SM 2 2.200 - 3.800 16.720
Wall-339 SM 2 5.400 - 3.800 41.040
Wall-340 SM 2 8.600 - 3.800 65.360
D-9A SM -2 0.900 - 2.150 -3.870
Wall-341 SM 2 4.900 - 3.800 37.240
Wall-342 SM 2 24.800 - 3.800 188.480
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-344 SM 2 2.560 - 3.800 19.456
D-10A SM -2 1.000 - 2.150 -4.300
Wall-345 SM 2 0.800 - 3.800 6.080
Wall-346 SM 2 11.360 - 3.800 86.336
Wall-352 SM 2 2.400 - 4.650 22.320
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-354 SM 2 1.900 - 3.800 14.440

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
73 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


Wall-357 SM 2 11.510 - 3.800 87.476
DD-88A SM -2 1.600 - 2.150 -6.880
D-9A SM -2 0.900 - 2.150 -3.870
Wall-358 SM 2 2.365 - 3.800 17.974
Wall-359 SM 2 5.150 - 3.800 39.140
Wall-360 SM 2 3.015 - 3.800 22.914
Wall-362 SM 2 2.600 - 3.800 19.760
Wall-363 SM 2 3.000 - 3.800 22.800
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-370 SM 2 3.000 - 3.800 22.800
D-9A SM -2 0.900 - 2.150 -3.870
Wall-371 SM 2 0.900 - 3.800 6.840
Wall-372 SM 2 2.549 - 3.800 19.372
D/d of Drop Panel SM -2 0.950 - 3.800 -7.220
Wall-373 SM 2 1.400 - 3.800 10.640
D-9A SM -2 0.900 - 2.150 -3.870
Wall-374 SM 2 1.550 - 3.800 11.780
D-9A SM -2 0.900 - 2.150 -3.870
Wall-375 SM 2 24.449 - 3.800 185.812
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-376 SM 2 2.250 - 3.800 17.100
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-377 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-378 SM 2 3.000 - 3.800 22.800
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-379 SM 2 3.000 - 3.800 22.800
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
74 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-380 SM 2 2.500 - 3.800 19.000


DD-99B SM -2 1.800 - 2.150 -7.740
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-381 SM 2 4.650 - 3.800 35.340
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-383 SM 2 7.377 - 3.800 56.065
DD-88B SM -2 1.600 - 2.150 -6.880
D-9B SM -2 0.900 - 2.150 -3.870
Wall-384 SM 2 2.500 - 3.800 19.000
D-9B SM -2 0.900 - 2.150 -3.870
Wall-385 SM 2 4.650 - 3.800 35.340
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-386 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-387 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-388 SM 2 7.302 - 3.800 55.495
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-389 SM 2 4.650 - 3.800 35.340
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-390 SM 2 2.825 - 3.800 21.470
DD-88B SM -2 1.600 - 2.150 -6.880
Wall-391 SM 2 5.251 - 3.800 39.908
Wall-392 SM 2 1.200 - 3.800 9.120
Wall-397 SM 2 1.479 - 3.800 11.240
Wall-398 SM 2 1.479 - 3.800 11.240
Wall-401 SM 2 3.751 - 3.800 28.508
Wall-402 SM 2 2.149 - 3.800 16.332

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
75 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.600 - 0.150 -0.180


Wall-405 SM 2 1.000 - 3.800 7.600
Wall-406 SM 2 29.425 - 3.800 223.630
D/d of Opening SM -2 2.475 - 3.800 -18.810
D/d of Opening SM -2 1.200 - 3.800 -9.120
D/d of Opening SM -2 1.000 - 3.800 -7.600
D/d of Opening SM -2 2.750 - 3.800 -20.900
DD-99B SM -2 1.800 - 2.150 -7.740
Wall-407 SM 2 5.251 - 3.800 39.908
Wall-411 SM 2 4.650 - 3.800 35.340
Wall-414 SM 2 4.649 - 3.800 35.332
Wall-415 SM 2 2.825 - 3.800 21.470
DD099B SM -2 1.800 - 2.150 -7.740
Wall-416 SM 2 7.299 - 3.800 55.472
Wall-417 SM 2 7.300 - 3.800 55.480
DD-99B SM -2 1.800 - 2.150 -7.740
D/d of Drop Panel SM 1350.000
Wall-418 SM 2 7.300 - 3.800 55.480
DD-99B SM -2 1.800 - 2.150 -7.740
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-419 SM 2 6.300 - 3.800 47.880
D-9A SM -2 0.900 - 2.150 -3.870
Wall-420 SM 2 2.155 - 3.800 16.378
Wall-421 SM 2 2.480 - 3.800 18.848
Wall-422 SM 2 5.350 - 3.800 40.660
Wall-423 SM 2 2.075 - 3.800 15.770
Wall-424 SM 2 2.400 - 3.800 18.240
Wall-425 SM 2 6.300 - 3.800 47.880
D-9A SM -2 0.900 - 2.150 -3.870
D-10A SM -2 1.000 - 2.150 -4.300

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
76 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-426 SM 2 2.400 - 3.800 18.240


Wall-427 SM 2 5.030 - 3.800 38.228
Wall-428 SM 2 29.275 - 3.800 222.490
DD-88A SM -2 1.600 - 2.150 -6.880
D/d of Opening SM -2 2.750 - 3.800 -20.900
D/d of Opening SM -2 2.550 - 3.800 -19.380
Wall-429 SM 2 4.649 - 3.800 35.332
Wall-430 SM 2 7.299 - 3.800 55.472
Wall-431 SM 2 4.650 - 3.800 35.340
Wall-432 SM 2 4.000 - 3.800 30.400
Missing 1350.000

Wall-434 SM 2 0.975 - 3.800 7.410


Wall-435 SM 2 0.975 - 3.800 7.410
Wall-436 SM 2 4.650 - 3.800 35.340
Wall-437 SM 2 0.975 - 3.800 7.410
Wall-438 SM 2 0.975 - 3.800 7.410
Wall-439 SM 2 15.401 - 3.800 117.048
DD-99C SM -2 1.800 - 2.150 -7.740
LD-93A SM -2 1.200 - 2.150 -5.160
D/d of Drop Panel SM -2 2.700 - 0.150 -0.810
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
D/d of Column SM -2 0.800 - 3.800 -6.080
Wall-440 SM 2 13.699 - 3.800 104.112
LD-93A SM -2 1.200 - 2.150 -5.160
LD-93 SM -2 1.200 - 2.150 -5.160
Wall-441 SM 2 4.725 - 3.800 35.910
D-9 SM -2 0.900 - 2.150 -3.870
Wall-442 SM 2 4.875 - 3.800 37.050
Wall-443 SM 2 2.650 - 3.800 20.140
Wall-444 SM 2 4.225 - 3.800 32.110

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
77 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285


Wall-445 SM 2 0.900 - 3.800 6.840
Wall-446 SM 2 0.900 - 3.800 6.840
Wall-447 SM 2 3.975 - 3.800 30.210
Wall-448 SM 2 4.075 - 3.800 30.970
Wall-449 SM 2 0.600 - 3.800 4.560
Wall-450 SM 2 2.550 - 3.800 19.380
Wall-451 SM 2 2.401 - 3.800 18.248
Wall-452 SM 2 1.225 - 3.800 9.310
Wall-453 SM 2 0.453 - 3.800 3.443
Wall-454 SM 2 1.074 - 3.800 8.162
Wall-466 SM 2 1.050 - 3.800 7.980
Wall-473 SM 2 2.500 - 4.650 23.250
DD-88D SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-474 SM 2 2.750 - 3.800 20.900
D-9A SM -2 0.900 - 2.150 -3.870
Wall-475 SM 2 2.750 - 3.800 20.900
D-10 SM -2 1.000 - 2.150 -4.300
Wall-476 SM 2 7.950 - 3.800 60.420
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-477 SM 2 3.225 - 3.800 24.510
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
DD-88C SM -2 1.600 - 2.150 -6.880
Wall-478 SM 2 27.701 - 3.800 210.528
LD-93A SM -2 1.200 - 2.150 -5.160
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-479 SM 2 5.801 - 3.800 44.088
Wall-480 SM 2 5.801 - 3.800 44.088
Wall-481 SM 2 5.151 - 3.800 39.148

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
78 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285


Wall-482 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-483 SM 2 9.825 - 3.800 74.670
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-484 SM 2 0.925 - 3.800 7.030
D/d of Drop Panel SM -2 0.925 - 0.150 -0.278
Wall-485 SM 2 8.575 - 3.800 65.170
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-486 SM 2 0.925 - 3.800 7.030
D/d of Drop Panel SM -2 0.925 - 0.150 -0.278
Wall-487 SM 2 9.675 - 3.800 73.530
D/d for Wall Portion SM -2 0.150 - 3.800 -1.140
Wall-488 SM 2 8.275 - 3.800 62.890
Wall-489 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-490 SM 2 9.675 - 3.800 73.530
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-491 SM 2 5.649 - 3.800 42.932
Wall-492 SM 2 0.925 - 3.800 7.030
D/d of Drop Panel SM -2 0.925 - 0.150 -0.278
Wall-493 SM 2 7.300 - 0.150 2.190
D/d of Drop Panel SM -2 0.925 - 0.150 -0.278
Wall-494 SM 2 5.349 - 3.800 40.652
Wall-495 SM 2 5.499 - 3.800 41.792
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-496 SM 2 40.409 - 3.800 307.108
D/d for Wall Portion SM -2 7.950 - 3.800 -60.420
DD-88A SM -2 1.600 - 2.150 -6.880
DD-88B SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
79 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


D-9A SM -2 0.900 - 2.150 -3.870
Wall-497 SM 2 7.300 - 3.800 55.480
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-499 SM 2 3.010 - 3.800 22.876
D-9A SM -2 0.900 - 2.150 -3.870
Wall-500 SM 2 3.825 - 3.800 29.070
D-9A SM -2 0.900 - 2.150 -3.870
Wall-504 SM 2 5.760 - 3.800 43.776
Wall-505 SM 2 5.750 - 3.800 43.700
Wall-509 SM 2 4.950 - 3.800 37.620
Wall-514 SM 2 4.940 - 3.800 37.544
Wall-515 SM 2 7.950 - 3.800 60.420
D/d for Wall Portion SM -2 2.500 - 3.800 -19.000
Wall-524 SM 2 1.400 - 3.800 10.640
D-9A SM -2 0.900 - 2.150 -3.870
Wall-525 SM 2 1.400 - 3.800 10.640
D-9A SM -2 0.900 - 2.150 -3.870
Wall-526 SM 2 4.940 - 3.800 37.544
Wall-527 SM 2 2.950 - 3.800 22.420
Wall-528 SM 2 3.000 - 3.800 22.800
D-9 SM -2 0.900 - 2.150 -3.870
Wall-537 SM 2 5.266 - 3.800 40.022
Wall-538 SM 2 5.936 - 3.800 45.114
Wall-541 SM 2 5.116 - 3.800 38.882
Wall-542 SM 2 16.025 - 3.800 121.790
LD-93A SM -8 1.200 - 2.150 -20.640
Wall-543 SM 2 5.936 - 3.800 45.114
Wall-546 SM 2 3.251 - 3.800 24.708

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
80 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-547 SM 2 2.188 - 3.800 16.629


D-9 SM -2 0.900 - 2.150 -3.870
Wall-548 SM 2 2.650 - 3.800 20.140
DD-99C SM -2 1.800 - 2.150 -7.740
Wall-549 SM 2 4.975 - 3.800 37.810
Wall-551 SM 2 5.234 - 3.800 39.778
D-9B SM -2 0.900 - 2.150 -3.870
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-553 SM 2 1.173 - 3.800 8.915
Wall-554 SM 2 1.008 - 3.800 7.661
Wall-556 SM 2 1.058 - 3.800 8.041
Wall-557 SM 2 1.008 - 3.800 7.661
Wall-560 SM 2 2.499 - 3.800 18.992
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-561 SM 2 3.150 - 3.800 23.940
Wall-562 SM 2 2.500 - 3.800 19.000
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
DD-88C SM -2 1.600 - 2.150 -6.880
Wall-563 SM 2 5.500 - 3.800 41.800
D-9A SM -2 0.900 - 2.150 -3.870
Wall-573 SM 2 7.080 - 3.800 53.808
Wall-581 SM 2 16.374 - 3.800 124.442
SD-16 SM -2 1.600 - 2.150 -6.880
Wall-584 SM 2 1.990 - 3.800 15.124
D-9A SM -2 0.900 - 2.150 -3.870
Wall-586A SM 2 1.350 - 3.800 10.260
Wall-587 SM 2 1.950 - 3.800 14.820
SD-12 SM -2 0.900 - 2.150 -3.870
Wall-588 SM 2 1.250 - 3.800 9.500
Wall-590 SM 2 2.305 - 3.800 17.518

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
81 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 -3.870


Wall-591 SM 2 3.050 - 3.800 23.180
D-9A SM -2 0.900 - 2.150 -3.870
Wall-592 SM 2 1.350 - 3.800 10.260
Wall-593 SM 2 1.600 - 3.800 12.160
Wall-594 SM 2 1.800 - 3.800 13.680
Wall-595 SM 2 1.800 - 3.800 13.680
Wall-596 SM 2 17.429 - 3.800 132.460
D-9A SM -2 0.900 - 2.150 -3.870
Wall-597 SM 2 3.800 - 3.800 28.880
Wall-598 SM 2 2.675 - 3.800 20.330
D-9A SM -2 0.900 - 2.150 -3.870
Wall-599 SM 2 0.430 - 3.800 3.268
Wall-602 SM 2 3.000 - 3.800 22.800
Wall-604 SM 2 7.967 - 3.800 60.549
D-9A SM -6 0.900 - 2.150 -11.610
Wall-605 SM 2 1.110 - 3.800 8.436
Wall-606 SM 2 1.569 - 3.800 11.924
Wall-607 SM 2 5.500 - 3.800 41.800
Wall-609 SM 2 0.914 3.800 6.946
Wall-610 SM 2 4.700 3.800 35.720
D/d of Drop Panel SM -2 0.950 0.150 -0.285
Wall-611 SM 2 7.350 3.800 55.860
DD-88A SM -2 1.600 2.150 -6.880
D/d of Drop Panel SM -2 0.950 0.150 -0.285
Wall-618 SM 2 2.350 - 3.800 17.860
Wall-619 1238.000
Wall-620 SM 2 4.450 - 3.800 33.820
D-9 SM -2 0.900 - 2.150 -3.870
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
82 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-621 SM 2 4.450 - 3.800 33.820


Wall-622 SM 2 10.711 - 3.800 81.404
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-623 SM 2 0.566 - 3.800 4.302
D/d of Drop Panel SM -2 0.566 - 0.150 -0.170
Wall-624 SM 2 4.400 - 3.800 33.440
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-625 SM 2 4.650 - 3.800 35.340
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-628 SM 2 2.290 - 3.800 17.404
D-9A SM -2 0.900 - 2.150 -3.870
Wall-629 SM 2 4.490 - 3.800 34.124
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-630 SM 2 2.335 - 3.800 17.746
Wall-631 SM 2 5.735 - 3.800 43.586
LD-93 SM -2 1.200 - 2.150 -5.160
Wall-632 SM 2 0.260 - 3.800 1.976
Wall-633 SM 2 2.400 - 3.800 18.240
Wall-634 SM 2 3.150 - 3.800 23.940
D/d of Window SM -2 1.350 - 1.000 -2.700
Wall-635 SM 2 1.117 - 3.800 8.489
Wall-636 SM 2 2.281 - 3.800 17.336
Wall-637 SM 2 1.781 - 3.800 13.536
Wall-638 SM 2 3.485 - 3.800 26.486
D-9 SM -2 0.900 - 2.150 -3.870
Wall-639 SM 2 6.250 - 3.800 47.500
D-9 SM -2 0.900 - 2.150 -3.870
Wall-640 SM 2 1.916 - 3.800 14.562
D-9 SM -2 0.900 - 2.150 -3.870
Wall-641 SM 2 1.045 - 3.800 7.942

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
83 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-642 SM 2 1.045 - 3.800 7.942


Wall-643 SM 2 2.258 - 3.800 17.161
Wall-644 SM 2 2.267 - 3.800 17.229
Wall-645 SM 2 7.000 - 3.800 53.200
Wall-646 SM 2 2.879 - 3.800 21.880
D-9 SM -2 0.900 - 2.150 -3.870
Wall-647 SM 2 4.450 - 3.800 33.820
D-9 SM -2 0.900 - 2.150 -3.870
Wall-648 SM 2 3.218 - 3.800 24.457
D-9 SM -2 0.900 - 2.150 -3.870
Wall-649 SM 2 1.875 - 3.800 14.250
D-9 SM -2 0.900 - 2.150 -3.870
Wall-650 SM 2 2.267 - 3.800 17.229
Wall-651 SM 2 5.787 - 3.800 43.981
Wall-655 SM 2 4.951 - 3.800 37.628
Wall-656 SM 2 5.750 - 3.800 43.700
DD-88B SM -2 1.600 - 2.150 -6.880
Wall-657 SM 2 24.120 - 3.800 183.312
D-9A SM -2 0.900 - 2.150 -3.870
D-9 SM -2 0.900 - 2.150 -3.870
GD-3 SM -2 1.000 - 2.150 -4.300
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-658 SM 2 7.100 - 3.800 53.960
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-659 SM 2 2.850 - 3.800 21.660
Wall-660 SM 2 2.369 - 3.800 18.004
D-9 SM -2 0.900 - 2.150 -3.870
Wall-661 SM 2 2.250 - 3.800 17.100
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-662 SM 2 4.660 - 3.800 35.416

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
84 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9 SM -2 0.900 - 2.150 -3.870


Wall-663 SM 2 5.290 - 3.800 40.204
LD-93 SM -2 1.200 - 2.150 -5.160
Wall-664 SM 2 1.582 - 3.800 12.023
D/d of Drop Panel SM -2 1.200 - 0.150 -0.360
Wall-665 SM 2 3.341 - 3.800 25.392
DD-99B SM -2 1.800 - 2.150 -7.740
D/d of Drop Panel SM -2 0.460 - 0.150 -0.138
Wall-666 SM 2 1.377 - 3.800 10.465
D/d of Drop Panel SM -2 1.377 - 0.150 -0.413
Wall-667 SM 2 4.583 - 3.800 34.831
DD-88 SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.890 - 0.150 -0.267
Wall-668 SM 2 1.091 - 3.800 8.292
Wall-669 SM 2 5.140 - 3.800 39.064
LD-93 SM -2 1.200 - 2.150 -5.160
Wall-670 SM 2 3.012 - 3.800 22.891
D/d of Window SM -2 1.350 - 1.000 -2.700
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-671 SM 2 7.100 - 3.800 53.960
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-677 SM 2 2.550 - 3.800 19.380
Wall-682 SM 2 3.145 - 3.800 23.902
Wall-683 SM 2 5.875 - 3.800 44.650
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-684 SM 2 2.464 - 3.800 18.726
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-685 SM 2 2.823 - 3.800 21.455
D-9A SM -2 0.900 - 2.150 -3.870
Wall-686 SM 2 5.907 - 3.800 44.893

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
85 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 1.060 - 0.150 -0.318


Wall-687 SM 2 6.261 - 3.800 47.584
Wall-688 SM 2 2.474 - 3.800 18.802
D/d of Drop Panel SM 2 1.130 - 3.800 8.588
Wall-689 SM 2 1.315 - 3.800 9.994
Wall-690 SM 2 1.200 - 3.800 9.120
Wall-691 SM 2 1.050 - 3.800 7.980
Wall-692 SM 2 3.150 - 3.800 23.940
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-693 SM 2 1.511 - 3.800 11.484
D/d of Drop Panel SM -2 1.511 - 0.150 -0.453
Wall-694 SM 2 0.735 - 3.800 5.586
D/d of Drop Panel SM -2 0.735 - 0.150 -0.221
Wall-695 SM 2 1.000 - 3.800 7.600
D-9A SM -2 0.900 - 2.150 -3.870
Wall-696 SM 2 1.000 - 3.800 7.600
D-9A SM -2 0.900 - 2.150 -3.870
Wall-697 SM 2 3.847 - 3.800 29.237
D/d of Opening SM -2 1.200 - 3.800 -9.120
Wall-698 SM 2 5.950 - 3.800 45.220
Wall-699 SM 2 2.500 - 3.800 19.000
Wall-704 SM 2 7.994 - 3.800 60.754
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-707 SM 2 4.849 - 3.800 36.852
Wall-723 SM 2 8.810 - 3.800 66.956
Wall-724 SM 2 0.165 - 3.800 1.254
Wall-725 SM 2 7.850 - 0.200 3.140
Wall-726 SM 2 0.165 - 3.800 1.254
Wall-727 SM 2 0.165 - 3.800 1.254
Wall-728 SM 2 13.230 - 3.800 100.548

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
86 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10 SM -2 1.000 - 2.150 -4.300


DD-88 SM -2 1.600 - 2.150 -6.880
Wall-729 SM 2 0.165 - 3.800 1.254
Wall-730 SM 2 0.165 - 3.800 1.254
Wall-731 SM 2 39.150 - 0.200 15.660
D/d for Column SM 4 0.800 - 0.200 0.640
Wall-732 SM 2 0.165 - 0.200 0.066
Wall-733 SM 2 0.165 - 0.200 0.066
Wall-734 SM 2 4.430 - 3.800 33.668
Wall-735 SM 2 5.250 - 3.800 39.900
Wall-736 SM 2 2.050 - 3.800 15.580
Wall-737 SM 2 0.165 - 3.800 1.254
Wall-738 SM 2 0.165 - 3.800 1.254
Wall-739 SM 2 4.760 - 3.800 36.176
Wall-740 SM 2 2.050 - 3.800 15.580
Wall-741 SM 2 0.165 - 3.800 1.254
Wall-742 SM 2 0.165 - 3.800 1.254
Wall-743 SM 2 6.750 - 0.200 2.700
Wall-744 SM 2 0.165 - 3.800 1.254
Wall-745 SM 2 2.500 - 3.800 19.000
D-10 SM 2 1.000 - 2.150 4.300
Wall-746 SM 2 4.390 - 3.800 33.364
Wall-768 SM 2 1.450 - 3.800 11.020
Wall-769 SM 2 1.750 - 3.800 13.300
Wall-776 SM 2 3.250 - 3.800 24.700
D-9A SM -2 0.900 - 2.150 -3.870
Wall-778 SM 2 2.390 - 3.800 18.164
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
DD-88 SM -2 1.600 - 2.150 -6.880
Wall-785 SM 2 17.020 - 3.800 129.352

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
87 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 -6.880


D-9A SM -2 0.900 - 2.150 -3.870
D-10 SM -2 1.000 - 2.150 -4.300
Wall-796 SM 2 2.510 - 3.800 19.076
DD-88B SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-798 SM 2 4.000 - 3.800 30.400
Wall-802 SM 2 4.930 - 3.800 37.468
D-9A SM -2 0.900 - 2.150 -3.870
Wall-803 SM 2 1.780 - 3.800 13.528
Wall-808 SM 2 4.930 - 3.800 37.468
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-809 SM 2 7.091 - 3.800 53.892
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-812 SM 2 3.610 - 3.800 27.436
Wall-813 SM 2 8.001 - 3.800 60.808
D-9A SM -2 0.900 - 2.150 -3.870
Wall-814 SM 2 1.250 - 3.800 9.500
D-75 SM -2 0.750 - 2.150 -3.225
Wall-816 Missing 1632.000
Wall-818 SM 2 1.250 - 3.800 9.500
D-75 SM -2 0.750 - 2.150 -3.225
Wall-819 SM 2 2.750 - 3.800 20.900
D/d of Opening SM -2 1.450 - 3.800 -11.022
Wall-820 SM 2 2.205 - 3.800 16.758
GD-2 SM -2 1.200 - 2.150 -5.160
Wall-821 SM 2 0.461 - 3.800 3.504
Wall-822 SM 2 0.267 - 3.800 2.029
Wall-824 SM 2 0.175 - 3.800 1.330

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
88 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Qty Ground Floor= 18,479.674

First Floor
H = 9.825-6.225-0.225 = 3.375
Wall-3 SM 2 1.449 - 2.600 7.535
Wall-4 SM 2 4.550 - 2.600 23.660
Wall-5 SM 2 3.800 - 2.600 19.760
Wall-7 SM 2 4.395 - 2.600 22.854
Wall-9 SM 2 3.801 - 2.600 19.765
Wall-10 SM 2 17.500 - 2.600 91.000
G-D3 SM -8 1.090 - 2.150 -18.748
Wall-11 SM 2 0.577 - 2.600 3.000
Wall-12 SM 2 0.625 - 2.600 3.250
Wall-15 SM 2 1.396 - 2.600 7.259
Wall-15B SM 2 0.750 - 2.600 3.900
Wall-18 SM 2 11.685 - 2.600 60.762
D-9A SM -2 0.900 - 2.150 -3.870
D-10 SM -2 1.000 - 2.150 -4.300
Wall-19 SM 2 4.399 - 2.600 22.875
Wall-21 SM 2 1.625 - 2.600 8.450
Wall-22 SM 2 1.475 - 2.600 7.670
Wall-23 SM 2 4.525 - 2.600 23.530
D-75 SM -3 0.750 - 2.150 -4.838
Wall-24 SM 2 1.475 - 2.600 7.670
Wall-25 SM 2 8.875 - 2.600 46.150
Wall-26 SM 2 3.300 - 2.600 17.160
D-10 SM -2 1.000 - 2.150 -4.300
Wall-29 SM 2 1.475 - 2.600 7.670

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
89 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-30 SM 2 1.475 - 2.600 7.670


Wall-31 SM 2 1.475 - 2.600 7.670
Wall-32 SM 2 4.675 - 2.600 24.310
D-75 SM -3 0.750 - 2.150 -4.838
Wall-33 SM 2 8.600 - 2.600 44.720
Wall-35 SM 2 3.300 - 2.600 17.160
D-10 SM -2 1.000 - 2.150 -4.300
Wall-37 SM 2 4.916 - 2.600 25.563
G-D3 SM -2 1.090 - 2.150 -4.687
D/d of Opening SM -2 2.827 - 2.600 -14.700
Wall-38 SM 2 11.700 - 2.600 60.840
D-10 SM -2 1.000 - 2.150 -4.300
Wall-43 SM 2 3.150 - 2.600 16.380
Wall-45 SM 2 0.562 - 2.600 2.922
Wall-46 SM 2 1.600 - 2.600 8.320
G-D3 SM -2 1.090 - 2.150 -4.687
Wall-51 SM 2 4.400 - 2.600 22.880
Wall-53 SM 2 1.861 - 2.600 9.677
Wall-62 SM 2 3.750 - 2.600 19.500
Wall-64 SM 2 2.500 - 2.600 13.000
Wall-65 SM 2 1.565 - 2.600 8.138
Wall-66 SM 2 5.450 - 2.600 28.340
Wall-67 SM 2 4.550 - 2.600 23.660
Wall-72 SM 2 2.700 - 2.600 14.040
Wall-73 SM 2 3.050 - 2.600 15.860
Wall-74 SM 2 3.050 - 2.600 15.860
Wall-75 SM 2 2.700 - 2.600 14.040
Wall-76 SM 2 7.300 - 2.600 37.960
D/d of Opening SM -2 3.858 - 2.600 -20.062
Wall-86 SM 2 2.025 - 2.600 10.530

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
90 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-87 SM 2 6.050 - 2.600 31.460


D-9A SM -2 0.900 - 2.150 -3.870
Wall-89 SM 2 4.625 - 2.600 24.050
Wall-91 SM 2 6.850 - 2.600 35.620
DD-88A SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-92 SM 2 3.000 - 2.600 15.600
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-98 SM 2 3.000 - 2.600 15.600
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-99 SM 2 4.625 - 2.600 24.050
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-100 SM 2 3.000 - 2.600 15.600
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-101 SM 2 4.625 - 2.600 24.050
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-105 SM 2 3.000 - 2.600 15.600
Wall-107 SM 2 2.652 - 2.600 13.790
Wall-111 SM 2 34.900 - 2.600 181.480
DD-88A SM -2 1.600 - 2.150 -6.880
DD-88C SM -2 1.600 - 2.150 -6.880
Wall-115 SM 2 4.500 - 2.600 23.400
Wall-118 SM 2 7.300 - 2.600 37.960
Wall-125 SM 2 4.500 - 2.600 23.400
Wall-127 SM 2 4.500 - 2.600 23.400
Wall-135 SM 2 5.250 - 2.600 27.300
Wall-137 SM 2 4.650 - 2.600 24.180
Wall-143 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-147 SM 2 5.250 - 2.600 27.300

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
91 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-150 SM 2 7.300 - 2.600 37.960


D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-152 SM 2 8.550 - 2.600 44.460
Wall-153 SM 2 7.300 - 2.600 37.960
G-D1 SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.950 - 0.150 -0.285
Wall-154 SM 2 3.000 - 2.600 15.600
D-9A SM -2 0.900 - 2.150 -3.870
Wall-155 SM 2 4.400 - 2.600 22.880
D-9A SM -2 0.900 - 2.150 -3.870
Wall-157 SM 2 2.650 - 2.600 13.780
Wall-168 SM 2 5.510 - 2.600 28.652
Wall-169 SM 2 18.550 - 2.600 96.460
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-171 SM 2 2.630 - 2.600 13.676
Wall-174 SM 2 2.330 - 2.600 12.116
Wall-176 SM 2 0.300 - 2.600 1.560
Wall-177 SM 2 0.300 - 2.600 1.560
Wall-180 SM 2 0.300 - 2.600 1.560
Wall-181 SM 2 0.300 - 2.600 1.560
Wall-182 SM 2 0.300 - 2.600 1.560
Wall-183 SM 2 0.300 - 2.600 1.560
Wall-185 SM 2 2.330 - 2.600 12.116
Wall-187 SM 2 2.330 - 2.600 12.116
Wall-188 SM 2 0.450 - 2.600 2.340
Wall-189 SM 2 0.450 - 2.600 2.340
Wall-192 SM 2 0.300 - 2.600 1.560
Wall-193 SM 2 0.300 - 2.600 1.560
Wall-194 SM 2 0.300 - 2.600 1.560
Wall-195 SM 2 0.300 - 2.600 1.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
92 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-196 SM 2 2.630 - 2.600 13.676


Wall-197 SM 2 2.630 - 2.600 13.676
Wall-198 SM 2 2.630 - 2.600 13.676
Wall-199 SM 2 0.300 - 2.600 1.560
Wall-200 SM 2 0.300 - 2.600 1.560
Wall-201 SM 2 0.300 - 2.600 1.560
Wall-204 SM 2 0.300 - 2.600 1.560
Wall-205 SM 2 0.300 - 2.600 1.560
Wall-206 SM 2 2.630 - 2.600 13.676
Wall-207 SM 2 0.300 - 2.600 1.560
Wall-208 SM 2 2.630 - 2.600 13.676
Wall-252 SM 2 7.190 - 2.600 37.388
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-253 SM 2 2.110 - 2.600 10.972
Wall-254 SM 2 3.250 - 2.600 16.900
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-258 SM 2 3.250 - 2.600 16.900
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-259 SM 2 2.110 - 2.600 10.972
Wall-260 SM 2 4.900 - 2.600 25.480
Wall-262 SM 2 0.685 - 2.600 3.562
Wall-263 SM 2 8.720 - 2.600 45.344
D-9A SM -2 0.900 - 2.150 (3.870)
D-10A SM -2 1.000 - 2.150 (4.300)
Wall-264 SM 2 4.801 - 2.600 24.965
D-12 SM -2 1.200 - 2.150 (5.160)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-265 SM 2 7.100 - 2.600 36.920
D-12 SM -2 1.200 - 2.150 (5.160)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
93 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-266 SM 2 3.100 - 2.600 16.120


D-12 SM -2 1.200 - 2.150 (5.160)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-267 SM 2 1.350 - 2.600 7.020
D/d of Window SM -2 1.020 - 1.000 (2.040)
Wall-268 SM 2 1.600 - 2.600 8.320
Wall-269 SM 2 1.450 - 2.600 7.540
Wall-272 SM 2 4.150 - 2.600 21.580
Wall-273 SM 2 5.850 - 2.600 30.420
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-274 SM 2 2.450 - 2.600 12.740
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-275 SM 2 3.300 - 2.600 17.160
Wall-276 SM 2 2.450 - 2.600 12.740
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-277 SM 2 3.300 - 2.600 17.160
Wall-278 SM 2 1.300 - 2.600 6.760
D-10 SM -2 1.000 - 2.150 (4.300)
Wall-280 SM 2 16.851 - 2.600 87.625
SD-11 SM -4 1.100 - 2.150 (9.460)
Wall-281 SM 2 16.851 - 2.600 87.625
SD-10 SM -2 1.000 - 2.150 (4.300)
SD-11 SM -2 1.100 - 2.150 (4.730)
Wall-282 SM 2 3.050 - 2.600 15.860
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-283 SM 2 3.475 - 2.600 18.070
Wall-284 SM 2 3.050 - 2.600 15.860
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-285 SM 2 3.475 - 2.600 18.070
Wall-286 SM 2 4.801 - 2.600 24.965

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
94 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-12 SM -2 1.200 - 2.150 (5.160)


D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-287 SM 2 17.001 - 2.600 88.405
D-12 SM -4 1.200 - 2.150 (10.320)
Wall-288 SM 2 7.000 - 2.600 36.400
D-12 SM -2 1.200 - 2.150 (5.160)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-289 SM 2 3.099 - 2.600 16.115
D-12 SM -2 1.200 - 2.150 (5.160)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-290 SM 2 9.000 - 2.600 46.800
Wall-293 SM 2 1.449 - 2.600 7.535
Wall-294 SM 2 1.500 - 2.600 7.800
Wall-295 SM 2 1.449 - 2.600 7.535
Wall-296 SM 2 1.500 - 2.600 7.800
Wall-297 SM 2 29.950 - 2.600 155.740
D-9A SM -3 0.900 - 2.150 (5.805)
D-10A SM -2 1.000 - 2.150 (4.300)
D-9 SM -3 0.900 - 2.150 (5.805)
Wall-298 SM 2 3.000 - 2.600 15.600
Wall-299 SM 2 3.000 - 2.600 15.600
Wall-300 SM 2 3.000 - 2.600 15.600
Wall-301 SM 2 3.000 - 2.600 15.600
Wall-304 SM 2 1.300 - 2.600 6.760
D-10 SM -2 1.000 - 2.150 (4.300)
Wall-305 SM 2 15.951 - 2.600 82.945
SD-11 SM -3 1.100 - 2.150 (7.095)
Wall-306 SM 2 17.151 - 2.600 89.185
SD-11 SM -4 1.100 - 2.150 (9.460)
Wall-308 SM 2 3.550 - 2.600 18.460

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
95 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 (3.870)


Wall-309 SM 2 0.850 - 2.600 4.420
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-310 SM 2 1.700 - 2.600 8.840
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-311 SM 2 3.550 - 2.600 18.460
Wall-312 SM 2 0.850 - 2.600 4.420
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-313 SM 2 1.650 - 2.600 8.580
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-314 SM 2 3.550 - 2.600 18.460
Wall-316 SM 2 15.951 - 2.600 82.945
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-317 SM 2 15.951 - 2.600 82.945
D-12 SM -6 1.200 - 2.150 (15.480)
Wall-318 SM 2 2.650 - 2.600 13.780
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-320 SM 2 1.400 - 2.600 7.280
Wall-324 SM 2 4.050 - 2.600 21.060
Wall-325 SM 2 2.650 - 2.600 13.780
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-326 SM 2 1.450 - 2.600 7.540
Wall-327 SM 2 1.500 - 2.600 7.800
Wall-328 SM 2 1.800 - 2.600 9.360
D-10 SM -2 1.000 - 2.150 (4.300)
Wall-329 SM 2 4.300 - 2.600 22.360
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-330 SM 2 3.300 - 2.600 17.160
D/d of Drop Panel SM -2 0.950 - 0.150 (0.285)
Wall-331 SM 2 4.150 - 2.600 21.580

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
96 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-332 SM 2 1.950 - 2.600 10.140


Wall-333 SM 2 1.500 - 2.600 7.800
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-334 SM 2 2.250 - 2.600 11.700
Wall-334A SM 2 1.900 - 2.600 9.880
Wall-335 SM 2 13.350 - 2.600 69.420
D/d for Column SM -2 1.000 - 2.600 (5.200)
D-10 SM -2 1.000 - 2.150 (4.300)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
D/d of Drop Panel SM -2 0.750 - 0.150 (0.225)
Wall-336 SM 2 7.100 - 2.600 36.920
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
D/d of Drop Panel SM -2 0.800 - 0.150 (0.240)
Wall-340 SM 2 6.900 - 2.600 35.880
D/d for Door SM -2 1.600 - 2.150 (6.880)
Wall-341 SM 2 7.091 - 2.600 36.873
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
DD-88B SM -2 1.600 - 2.150 (6.880)
Wall-342 SM 2 2.300 - 2.600 11.960
DD-88 SM -2 1.600 - 2.150 (6.880)
Wall-343 SM 2 4.200 - 2.600 21.840
Wall-344 SM 2 4.200 - 2.600 21.840
Wall-345 SM 2 2.300 - 2.600 11.960
D-10A SM -2 1.000 - 2.150 (4.300)
Wall-359 SM 2 5.875 - 2.600 30.550
DD-99 SM -2 1.800 - 2.150 (7.740)
Wall-360 SM 2 3.830 - 2.600 19.916
Wall-361 SM 2 7.374 - 2.600 38.345
DD-99B SM -2 1.800 - 2.150 (7.740)
Wall-362 SM 2 14.653 - 2.600 76.196

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
97 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 2.750 - 0.150 (0.825)


Wall-363 SM 2 1.239 - 2.600 6.443
D/d of Drop Panel SM -2 1.239 - 0.150 (0.372)
D/d for Column SM -2 0.600 - 2.600 (3.120)
Wall-364 SM 2 1.714 - 2.600 8.913
D/d of Drop Panel SM 2 1.714 - 0.150 0.514
Wall-365 SM 2 1.239 - 2.600 6.443
D/d of Drop Panel SM -2 1.239 - 0.150 (0.372)
Wall-366 SM 2 3.688 - 2.600 19.178
D-9A SM -2 0.900 - 2.150 (3.870)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-367 SM 2 12.021 - 2.600 62.509
Wall-370 SM 2 7.301 - 2.600 37.965
Wall-371 SM 2 5.246 - 2.600 27.279
Wall-372 SM 2 7.000 - 2.600 36.400
D-9A SM -2 0.900 - 2.150 (3.870)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-374 SM 2 7.605 - 2.600 39.546
Wall-375 SM 2 4.700 - 2.600 24.440
Wall-376 SM 2 0.928 - 2.600 4.826
Wall-383 SM 2 7.363 - 2.600 38.288
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-387 SM 2 5.835 - 2.600 30.342
Wall-392 SM 2 5.835 - 2.600 30.342
DD-88B SM -2 1.600 - 2.150 (6.880)
Wall-393 SM 2 17.875 - 2.600 92.950
D-10 SM -2 1.000 - 2.150 (4.300)
DD-88A SM -2 1.600 - 2.150 (6.880)
G-D3 SM -2 1.100 - 2.150 (4.730)
Wall-395 SM 2 3.300 - 2.600 17.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
98 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-75 SM -2 0.750 - 2.150 (3.225)


Wall-397 SM 2 1.951 - 2.600 10.145
Wall-398 SM 2 2.250 - 2.600 11.700
Wall-399 SM 2 1.426 - 2.600 7.415
Wall-400 SM 2 1.426 - 2.600 7.415
Wall-401 SM 2 1.426 - 2.600 7.415
Wall-402 SM 2 6.400 - 2.600 33.280
Wall-403 SM 2 1.951 - 2.600 10.145
Wall-404 SM 2 1.576 - 2.600 8.195
Wall-405 SM 2 1.426 - 2.600 7.415
Wall-406 SM 2 1.426 - 2.600 7.415
Wall-407 SM 2 7.000 - 2.600 36.400
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
D/d of Drop Panel SM -2 0.750 - 0.150 (0.225)
Wall-408 SM 2 3.300 - 2.600 17.160
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-409 SM 2 7.100 - 2.600 36.920
D-9A SM -2 0.900 - 2.150 (3.870)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-410 SM 2 4.850 - 2.600 25.220
Wall-411 SM 2 5.835 - 2.600 30.342
Wall-412 SM 2 4.000 - 2.600 20.800
D-10 SM -2 1.000 - 2.150 (4.300)
Wall-413 SM 2 7.100 - 2.600 36.920
D-9A SM -2 0.900 - 2.150 (3.870)
D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-414 SM 2 3.300 - 2.600 17.160
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-415 SM 2 2.205 - 2.600 11.466
Wall-416 SM 2 1.575 - 2.600 8.190

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
99 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-417 SM 2 1.425 - 2.600 7.410


Wall-418 SM 2 1.425 - 2.600 7.410
Wall-420 SM 2 5.763 - 2.600 29.968
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-421 SM 2 1.578 - 2.600 8.206
Wall-422 SM 2 1.426 - 2.600 7.415
Wall-423 SM 2 1.426 - 2.600 7.415
Wall-424 SM 2 1.725 - 2.600 8.970

Qty First Floor= 4,503.555

Second Floor
H = 13.425-9.828-0.225 = 3.375
Wall-96 SM 2 5.787 - 2.600 30.092
Wall-97 SM 2 5.386 - 2.600 28.007
DD-88A SM -2 1.600 - 2.150 -6.880
D/d of Wndow SM -2 3.000 - 1.500 -9.000
Wall-99 SM 2 6.408 - 2.600 33.322
D/d of Wndow SM -2 4.000 - 1.500 -12.000
D-10 SM -2 1.000 - 2.150 -4.300
Wall-100 SM 2 3.436 - 2.600 17.867
D-10 SM -2 1.000 - 2.150 -4.300
Wall-103 SM 2 4.000 - 2.600 20.800
D/d of Wndow SM -2 4.000 - 1.500 -12.000
Wall-104 SM 2 2.638 - 2.600 13.718
D-10 SM -2 1.000 - 2.150 -4.300
Wall-117 SM 2 3.650 - 2.600 18.980

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
100 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

ID-21 SM -2 2.100 - 2.100 -8.820


Wall-118 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-119 SM -2 4.613 - 2.600 -23.988
Wall-120 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-121 SM 2 6.600 - 2.600 34.320
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-123 SM 2 0.850 - 2.600 4.420
Wall-124 SM 2 1.400 - 2.600 7.280
Wall-127 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-128 SM 2 4.613 - 2.600 23.988
Wall-129 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-130 SM 2 6.600 - 2.600 34.320
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-132 SM 2 0.850 - 2.600 4.420
Wall-133 SM 2 1.400 - 2.600 7.280
Wall-136 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-137 SM 2 4.613 - 2.600 23.988
Wall-138 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-139 SM 2 6.200 - 2.600 32.240
ID-21 SM -2 2.100 - 2.100 -8.820
D-9A SM -2 0.900 - 2.150 -3.870
Wall-141 SM 2 1.400 - 2.600 7.280
Wall-143 SM 2 2.850 - 2.600 14.820
Wall-156 SM 2 3.135 - 2.600 16.302

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
101 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-158 SM 2 4.623 - 2.600 24.040


Wall-159 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-160 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-161 SM 2 2.640 - 2.600 13.728
Wall-163 SM 2 6.600 - 2.600 34.320
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-166 SM 2 4.623 - 2.600 24.040
Wall-167 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-168 SM 2 1.042 - 2.600 5.418
D/d of Wndow SM -2 0.725 - 1.100 -1.595
Wall-170 SM 2 2.390 - 2.600 12.428
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-173 SM 2 4.540 - 2.600 23.608
Wall-175 SM 2 5.360 - 2.600 27.872
Wall-176 SM 2 5.360 - 2.600 27.872
Wall-177 SM 2 19.575 - 2.600 101.790
D-9A SM -2 0.900 - 2.150 -3.870
ID-21 SM -2 2.100 - 2.150 -9.030
D/d of Wall SM -2 2.700 - 2.600 -14.040
Wall-179 SM 2 1.155 - 2.600 6.006
D-9B SM -2 0.900 - 2.150 -3.870
Wall-184 SM 2 3.000 - 2.600 15.600
Wall-185 SM 2 1.160 - 2.600 6.032
Wall-191 SM 2 4.540 - 2.600 23.608
Wall-196 SM 2 2.500 - 2.600 13.000
Wall-197 SM 2 3.149 - 2.600 16.375
Wall-198 SM 2 5.650 - 2.600 29.380

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
102 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-199 SM 2 3.149 - 2.600 16.375


Wall-209 SM 2 1.033 - 2.600 5.372
Wall-214 SM 2 5.749 - 2.600 29.895
D-10A SM -2 1.000 - 2.150 -4.300
Wall-215 SM 2 1.616 - 2.625 8.484
D-10 SM -2 1.000 - 2.150 -4.300
Wall-218 SM 2 5.149 - 2.625 27.032
Wall-219 SM 2 16.385 - 2.600 85.202
Wall-224 SM 2 7.300 - 2.600 37.960
Wall-225 SM 2 7.190 - 2.600 37.388
D/d of Drop Panel SM -2 0.950 - 0.200 -0.380
Wall-227 SM 2 1.350 - 2.600 7.020
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-228 SM 2 1.185 - 2.600 6.162
D-10A SM -2 1.000 - 2.150 -4.300
Wall-229 SM 2 1.635 - 2.600 8.502
D-10A SM -2 1.000 - 2.150 -4.300
Wall-230 SM 2 0.520 - 2.600 2.704
D/d of Drop Panel SM -2 0.520 - 0.200 -0.208
Wall-231 SM 2 3.322 - 2.600 17.274
D/d of Drop Panel SM -2 1.187 - 0.200 -0.475
Wall-232 SM 2 8.818 - 2.600 45.854
D-10 SM -2 1.000 - 2.150 -4.300
Wall-233 SM 2 4.025 - 2.600 20.930
Wall-234 SM 2 2.336 - 2.600 12.147
D-10A SM -2 1.000 - 2.150 -4.300
Wall-235 SM 2 4.680 - 2.600 24.336
Wall-236 SM 2 4.025 - 2.600 20.930
Wall-237 SM 2 4.275 - 2.600 22.230
Wall-238 SM 2 3.950 - 2.600 20.540

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
103 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


Wall-239 SM 2 8.275 - 2.600 43.030
D/d for Beam Portion SM -2 1.414 - 0.525 -1.485
Wall-240 SM 2 7.983 - 2.600 41.512
D-10 SM -2 1.000 - 2.150 -4.300
D/d of Window SM -2 0.900 - 1.500 -2.700
DD-99 SM -2 1.800 - 2.150 -7.740
D/d of Drop Panel SM -2 0.950 - 0.200 -0.380
Wall-241 SM 2 2.679 - 2.600 13.931
D/d for Beam Portion SM -2 1.414 - 0.525 -1.485
Wall-242 SM 2 8.275 - 2.600 43.030
D-10 SM -2 1.000 - 2.150 -4.300
D/d for Beam Portion SM -2 1.414 - 0.525 -1.485
Wall-243 SM 2 8.400 - 2.625 44.100
D/d of Column SM -2 1.000 - 2.625 -5.250
Wall-244 SM 2 7.363 - 2.600 38.288
DD-88A SM -2 1.600 - 2.150 -6.880
Wall-245 SM 2 3.000 - 2.600 15.600
DD-88B SM -2 1.600 - 2.150 -6.880
Wall-246 SM 2 6.800 - 2.625 35.700
Wall-247 SM 2 8.900 - 2.850 50.730
Wall-248 SM 2 0.600 - 2.600 3.120
Wall-249 SM 2 0.600 - 2.600 3.120
Wall-250 SM 2 0.650 - 2.600 3.380
Wall-251 SM 2 0.650 - 2.600 3.380
Wall-252 SM 2 3.382 - 2.600 17.586
D-75 SM -2 0.750 - 2.150 -3.225
Wall-253 SM 2 2.178 - 2.600 11.326
Wall-254 SM 2 3.904 - 2.600 20.301
Wall-255 SM 2 1.426 - 2.600 7.415

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
104 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-256 SM 2 1.426 - 2.600 7.415


Wall-257 SM 2 1.426 - 2.600 7.415
Wall-258 SM 2 6.459 - 2.600 33.587
Wall-259 SM 2 1.426 - 2.600 7.415
Wall-260 SM 2 1.426 - 2.600 7.415
Wall-261 SM 2 6.459 - 2.600 33.587
Wall-262 SM 2 1.426 - 2.600 7.415
Wall-263 SM 2 1.426 - 2.600 7.415
Wall-264 SM 2 20.850 - 2.600 108.420
D/d of Column SM -2 1.000 - 2.600 -5.200
D-10A SM -3 1.000 - 2.150 -6.450
D9A SM -2 0.900 - 2.150 -3.870
D/d of Drop Panel SM -2 2.700 - 0.200 -1.080
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-265 SM 2 3.382 - 2.600 17.586
Wall-266 SM 2 7.000 - 2.600 36.400
D/d of Drop Panel SM -2 0.750 - 0.200 -0.300
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-267 SM 2 11.935 - 2.600 62.062
D-10A SM -3 1.000 - 2.150 -6.450
D/d of Drop Panel SM -2 2.700 - 0.200 -1.080
D/d of Column SM -2 1.000 - 2.600 -5.200
Wall-268 SM 2 3.382 - 2.600 17.586
D-75 SM -2 0.750 - 2.150 -3.225
Wall-269 SM 2 2.178 - 2.600 11.326
Wall-270 SM 2 1.301 - 2.600 6.765
Wall-271 SM 2 1.301 - 2.600 6.765
Wall-272 SM 2 6.459 - 2.600 33.587
Wall-273 SM 2 1.301 - 2.600 6.765
Wall-274 SM 2 5.960 - 2.600 30.992

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
105 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300


Wall-275 SM 2 1.576 - 2.600 8.195
Wall-276 SM 2 1.576 - 2.600 8.195
Wall-277 SM 2 6.459 - 2.600 33.587
Wall-278 SM 2 1.426 - 2.600 7.415
Wall-279 SM 2 1.725 - 2.600 8.970
D-75 SM -2 0.750 - 2.150 -3.225
Wall-280 SM 2 3.872 - 2.600 20.134
D/d of Drop Panel SM -2 0.800 - 0.200 -0.320
Wall-281 SM 2 1.805 - 2.600 9.386
D/d of Drop Panel SM -2 1.805 - 0.200 -0.722
Wall-282 SM 2 0.478 - 2.600 2.486
D/d of Drop Panel SM -2 0.478 - 0.200 -0.191
Wall-283 SM 2 0.403 - 2.600 2.096
D/d of Drop Panel SM -2 0.403 - 0.200 -0.161
Wall-284 SM 2 1.030 - 2.600 5.356
D/d of Drop Panel SM -2 1.030 - 0.200 -0.412
Wall-285 SM 2 2.500 - 2.600 13.000
D/d of Drop Panel SM -2 0.550 - 0.200 -0.220
Wall-286 SM 2 2.450 - 2.600 12.740
Wall-287 +3.592+1.677 SM 2 5.269 - 2.600 27.399
D-10A SM -2 1.000 - 2.150 -4.300
D/d of Drop Panel SM -2 2.780 - 0.200 -1.112
Wall-288 SM 2 6.054 - 2.600 31.481
D-10A SM -2 1.000 - 2.150 -4.300
Wall-289 SM 2 9.004 - 2.600 46.821
Wall-290 SM 2 7.665 - 2.600 39.858
DD-99 SM -2 1.800 - 2.150 -7.740
D/d for Beam Portion SM -2 0.424 - 0.175 -0.148
Wall-292 SM 2 3.999 - 2.600 20.795

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
106 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255


Wall-294A SM 2 7.374 - 2.600 38.345
DD-88B SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-296 SM 2 5.878 - 2.600 30.566
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-297 SM 2 6.277 - 2.600 32.640
D/d for Beam Portion SM -2 0.400 - 0.375 -0.300
D-9A SM -2 0.900 - 2.150 -3.870
Wall-298 SM 2 0.560 - 2.600 2.912
Wall-302 SM 2 6.900 - 2.600 35.880
D-9A SM -2 0.900 - 2.150 -3.870
Wall-303 SM 2 2.250 - 2.600 11.700
Wall-307 SM 2 3.100 - 2.600 16.120
D-9 SM -2 0.900 - 2.150 -3.870
Wall-308 SM 2 3.350 - 2.600 17.420
Wall-309 SM 2 1.950 - 2.600 10.140
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-310 SM 2 1.500 - 2.600 7.800
Wall-311 SM 2 1.500 - 2.600 7.800
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-312 SM 2 3.350 - 2.600 17.420
Wall-313 SM 2 7.091 - 2.600 36.873
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-314 SM 2 1.250 - 2.600 6.500
D-9A SM -2 0.900 - 2.150 -3.870
Wall-315 SM 2 1.250 - 2.600 6.500
D-9A SM -2 0.900 - 2.150 -3.870
Wall-316 SM 2 4.200 - 2.600 21.840
D/d for Opening SM -2 1.200 - 2.600 -6.240

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
107 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-317 SM 2 6.900 - 2.600 35.880


D-9A SM -2 0.900 - 2.150 -3.870
Wall-318 SM 2 4.150 - 2.600 21.580
Wall-322 SM 2 2.300 - 2.600 11.960
D/d of Drop Panel SM -2 1.700 - 0.200 -0.680
Wall-323 SM 2 7.050 - 2.600 36.660
D/d of Drop Panel SM -2 0.750 - 0.200 -0.300
DD-88B SM -2 1.600 - 2.150 -6.880
Wall-324 SM 2 7.090 - 2.600 36.868
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-327 SM 2 4.423 - 2.600 23.000
Wall-328 SM 2 1.042 - 2.600 5.418
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-329 SM 2 3.650 - 2.600 18.980
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-330 SM 2 2.600 - 2.600 13.520
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-331 SM 2 2.550 - 2.600 13.260
D/d of Drop Panel SM -2 0.800 - 0.200 -0.320
Wall-332 SM 2 5.000 - 2.600 26.000
Wall-333 SM 2 3.540 - 2.600 18.408
Wall-336 SM 2 5.000 - 2.600 26.000
Wall-337 SM 2 1.923 - 2.600 10.000
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-338 SM 2 7.650 - 2.600 39.780
ID-21 SM -2 2.100 - 2.150 -9.030
Wall-340 SM 2 1.042 - 2.600 5.418
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-343 SM 2 2.440 - 2.600 12.688
Wall-345 SM 2 6.600 - 2.600 34.320

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
108 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

ID-21 SM -2 2.100 - 2.100 -8.820


Wall-346 SM 2 1.700 - 2.600 8.840
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-347 SM 2 1.349 - 2.600 7.015
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-348 SM 2 4.050 - 2.600 21.060
Wall-349 SM 2 4.050 - 2.600 21.060
Wall-350 SM 2 6.100 - 2.600 31.720
Wall-351 SM 2 6.100 - 2.600 31.720
Wall-353 SM 2 0.949 - 2.600 4.935
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-354 SM 2 1.042 - 2.600 5.418
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-355 SM 2 4.423 - 2.600 23.000
Wall-358 SM 2 6.600 - 2.600 34.320
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-360 SM 2 2.440 - 2.600 12.688
Wall-361 SM 2 4.413 - 2.600 22.948
Wall-363 SM 2 0.949 - 2.600 4.935
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-364 SM 2 1.042 - 2.600 5.418
D/d of Window SM -2 0.900 - 1.000 -1.800
Wall-365 SM 2 3.662 - 2.600 19.042
ID-21 SM -2 2.100 - 2.100 -8.820
Wall-366 SM 2 4.490 - 2.600 23.348
Wall-370 SM 2 3.600 - 2.600 18.720
D-10 SM -2 1.000 - 2.150 -4.300
Wall-371 SM 2 5.700 - 2.600 29.640
D-10A SM -2 1.000 - 2.150 -4.300
Wall-372 SM 2 17.200 - 2.600 89.440

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
109 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10 SM -2 1.000 - 2.150 -4.300


Wall-373 SM 2 5.150 - 2.600 26.780
D/d of Drop Panel SM -2 0.750 - 0.200 -0.300
Wall-374 SM 2 6.100 - 2.600 31.720
Wall-375 SM 2 6.100 - 2.600 31.720
Wall-376 SM 2 1.701 - 2.600 8.845
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-377 SM 2 1.349 - 2.600 7.015
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-378 SM 2 2.520 - 2.600 13.104
Wall-379 SM 2 1.530 - 2.600 7.956
D-9A SM -2 0.900 - 2.150 -3.870
Wall-380 SM 2 17.200 - 2.600 89.440
D-10 SM -2 1.000 - 2.150 -4.300
D-9A SM -2 0.900 - 2.150 -3.870
D/d of Opening SM -2 1.200 - 2.600 -6.240
Wall-381 SM 2 1.200 - 2.600 6.240
Wall-382 SM 2 2.520 - 2.600 13.104
Wall-383 SM 2 1.530 - 2.600 7.956
D-9A SM -2 0.900 - 2.150 -3.870
Wall-384 SM 2 4.050 - 2.600 21.060
Wall-384A SM 2 4.050 - 2.600 21.060
Wall-385 SM 2 1.700 - 2.600 8.840
D-9A SM -2 0.900 - 2.150 -3.870
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340
Wall-386 SM 2 1.349 - 2.600 7.015
D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Qty Second Floor= 3,356.777

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
110 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor
H = 17.025-13.425-0.300 = 3.300
Wall-8 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-9 SM 2 2.550 - 2.600 13.260
D/d Opening SM -2 1.300 - 2.150 (5.590)
Wall-11 SM 2 2.100 - 2.600 10.920
Wall-12 SM 2 4.100 - 2.600 21.320
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-34 SM 2 4.500 - 2.600 23.400
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-35 SM 2 2.550 - 2.600 13.260
D/d Opening SM -2 1.300 - 2.150 (5.590)
Wall-36 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 (5.160)
Wall-40 SM 2 2.650 - 2.600 13.780
Wall-42 SM 2 4.501 - 2.600 23.405
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-43 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-44 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-50 SM 2 3.110 - 2.600 16.172
Wall-59 SM 2 2.634 - 2.600 13.697
Wall-60 SM 2 2.470 - 2.600 12.844
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-61 SM 2 12.930 - 2.600 67.236

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
111 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 (3.870)


Wall-62 SM 2 1.800 - 2.600 9.360
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-63 SM 2 2.449 - 2.600 12.735
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-64 SM 2 7.298 - 2.600 37.950
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-65 SM 2 7.300 - 2.600 37.960
D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-67 SM 2 5.602 - 2.600 29.130
Wall-68 SM 2 4.951 - 2.600 25.745
D-9A SM -2 0.900 - 2.150 (3.870)
D/d Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-73 SM 2 3.300 - 2.600 17.160
D-75 SM -2 0.750 - 2.150 (3.225)
Wall-106 SM 2 8.009 - 2.600 41.647
D-10A SM -2 1.000 - 2.150 (4.300)
D/d of Window SM -2 1.500 - 1.500 (4.500)
Wall-112 SM 2 2.199 - 2.600 11.435
D-9B SM -2 0.900 - 2.150 (3.870)
Wall-121 SM 2 1.179 - 2.600 6.131
Wall-122 SM 2 1.008 - 2.600 5.242
Wall-123 SM 2 1.008 - 2.600 5.242
Wall-124 SM 2 1.173 - 2.600 6.100
Wall-125 SM 2 6.750 - 0.200 2.700
Wall-139 SM 2 5.800 - 2.600 30.160
D/d of opening SM -2 2.600 - 2.150 (11.180)
D-9A Wall-139 SM -2 0.900 - 2.150 (3.870)
Wall-139A SM 2 3.000 - 2.600 15.600

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
112 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-140 SM 2 1.350 - 2.600 7.020


D-9A SM -2 0.850 - 0.150 (0.255)
Wall-151 SM 2 3.765 - 2.600 19.578
Wall-152 SM 2 6.423 - 2.600 33.400
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-153 SM 2 2.425 - 2.600 12.610
Wall-154 SM 2 2.425 - 2.600 12.610
Wall-155 SM 2 0.504 - 2.600 2.621
Wall-157 SM 2 7.374 - 2.600 38.345
DD-88A SM -2 1.600 - 2.150 -6.880
D/d for Opening SM -2 0.850 - 0.150 -0.255
Wall-187 SM 2 3.243 - 2.600 16.864
Wall-188 SM 2 3.243 - 2.600 16.864
Wall-189 SM 2 3.243 - 2.600 16.864
Wall-190 SM 2 5.950 - 2.600 30.940
Wall-192 SM 2 5.473 - 2.600 28.460
D/d SM -2 1.200 - 2.150 (5.160)
Wall-194 SM 2 1.000 - 2.600 5.200
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-195 SM 2 1.000 - 2.600 5.200
D-9A SM -2 0.900 - 2.150 (3.870)
Wall-195a SM 2 2.500 - 2.600 13.000
Wall-224 SM 2 5.400 - 2.600 28.080
New Added Qty deduct from other block and add here as per drawing
Ground floor
Wall-770 SM 2 1.150 - 3.800 8.740
D-9A SM -2 0.900 - 2.150 -3.870
Wall-771 SM 2 2.000 - 3.800 15.200
Wall-773 SM 2 1.150 - 3.800 8.740
D-9A SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
113 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-774 SM 2 2.650 - 3.800 20.140


Wall-775 SM 2 2.150 - 3.800 16.340

Qty Third Floor= 848.332


Total Qty of Plaster work on 150mm Holow block 34,761.271
4.2 Plaster work on 200mm thick hollow block work
Lower Ground floor
Wall 12 sq.m 2 4.650 3.800 35.340
Wall 23 sq.m 2 1.450 3.800 11.020
Wall 27 sq.m 2 1.450 3.800 11.020
Wall 51 (Duplicate) sq.m
Wall 57 sq.m 2 27.575 3.800 209.570
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Door Deduction D88A sq.m -2 1.600 2.150 -6.880
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 59 sq.m 2 5.100 3.800 38.760
Wall 60 sq.m 2 7.300 3.800 55.480
Wall 61 sq.m 2 5.100 3.800 38.760
Wall 62 sq.m 2 2.900 3.800 22.040
Door Deduction D9A sq.m -2 0.900 2.150 -3.870
Wall 69 sq.m 2 13.900 3.800 105.640
Wall 71 sq.m 2 5.000 3.800 38.000
Wall 78 sq.m 2 4.400 3.800 33.440
Wall 79 sq.m 2 8.200 3.800 62.320
Door Deduction DD-88C sq.m -2 1.600 2.150 -6.880
Wall 81 sq.m 2 2.450 3.800 18.620
Wall 83 sq.m 2 3.200 3.800 24.320
Wall 84 sq.m 2 2.250 3.800 17.100
Wall 85 sq.m 2 6.850 3.800 52.060
Door Deduction D-9A sq.m -4 0.900 2.150 -7.740

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
114 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Door Deduction D-88A sq.m -2 1.600 2.150 -6.880


Wall 99 sq.m 2 7.300 3.800 55.480
Wall 109 sq.m 2 5.500 3.800 41.800
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 114 sq.m 2 3.200 3.800 24.320
Door Deduction D10A sq.m -2 1.000 2.150 -4.300
Wall 115 sq.m 2 5.300 3.800 40.280
Deduction Oppening sq.m -4 0.900 2.150 -7.740
Wall 116 sq.m 2 1.789 3.800 13.596
Wall 117 sq.m 2 2.226 3.800 16.918
Wall 118 sq.m 2 6.915 3.800 52.554
Deduction Oppening sq.m -2 0.800 2.150 -3.440
Wall 119 sq.m 2 2.226 3.800 16.918
Wall 138 sq.m 2 3.200 3.800 24.320
Wall 140 sq.m 2 3.802 3.800 28.895
Wall 153 sq.m 2 0.765 3.800 5.814
Wall 154 sq.m 2 4.525 3.800 34.390
Wall 158 sq.m 2 7.300 3.800 55.480
Wall 160 sq.m 2 8.100 3.800 61.560
Wall 173 sq.m 2 22.551 3.800 171.388
Deduction Column sq.m -4 0.800 2.150 -6.880
Wall 174 sq.m 2 2.400 3.800 18.240
Wall 175 sq.m 2 5.200 3.800 39.520
Deduction Column sq.m -2 0.800 2.150 -3.440
Wall 176 sq.m 2 13.200 3.800 100.320
Door Deduction D-10B sq.m -6 1.000 2.150 -12.900
Deduction Column sq.m -2 0.800 2.150 -3.440
Wall 177 sq.m 2 5.900 3.800 44.840
Door Deduction D-10 sq.m -2 1.000 2.150 -4.300
Wall 178 sq.m 2 5.000 3.800 38.000

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
115 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 179 sq.m 2 5.100 3.800 38.760


Wall 180 sq.m 2 3.000 3.800 22.800
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 181 sq.m 2 5.700 3.800 43.320
Wall 182 sq.m 2 2.400 3.800 18.240
Wall 183 sq.m 2 20.251 3.800 153.908
Door Deduction D-10 sq.m -2 1.000 2.150 -4.300
Door Deduction D-10 C sq.m -4 1.000 2.150 -8.600
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 186 sq.m
Wall 187 sq.m 2 5.700 3.800 43.320
Wall 188 sq.m 2 5.100 3.800 38.760
Wall 189 sq.m 2 28.551 3.800 216.988
Door Deduction DD-88D sq.m -2 1.600 2.150 -6.880
Wall 190 sq.m 2 5.500 3.800 41.800
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 191 sq.m 2 5.100 3.800 38.760
Wall 192 sq.m 2 8.498 3.800 64.585
Wall 193 sq.m 2 2.412 3.800 18.331
Wall 194 sq.m 2 2.088 3.800 15.869
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 195 sq.m 2 4.600 3.800 34.960
Door Deduction D-10 C sq.m -2 1.000 2.150 -4.300
Wall 196 sq.m 2 7.300 3.800 55.480
Wall 197 sq.m 2 2.812 3.800 21.371
Wall 198 sq.m 2 1.200 3.800 9.120
Wall 199 sq.m 2 3.753 3.800 28.523
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 200 sq.m 2 2.211 3.800 16.804

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
116 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 201 sq.m 2 5.028 3.800 38.213


Door Deduction D-10 A sq.m -4 1.000 2.150 -8.600
Wall 202 sq.m 2 1.603 3.800 12.183
Wall 203 sq.m 2 2.389 3.800 18.156
Wall 204 sq.m 2 4.700 3.800 35.720
Deduction Oppening sq.m -4 1.000 2.150 -8.600
Wall 205 sq.m 2 2.628 3.800 19.973
Wall 206 sq.m 2 5.700 3.800 43.320
Wall 207 sq.m 2 15.839 3.800 120.376
Wall 208 sq.m 2 2.534 3.800 19.258
Wall 209 sq.m 2 3.465 3.800 26.334
Wall 210 sq.m 2 1.293 3.800 9.827
Wall 211 sq.m 2 0.493 3.800 3.747
Wall 212 sq.m 2 1.266 3.800 9.622
Wall 213 sq.m 2 0.802 3.800 6.095
Wall 215 sq.m 2 11.657 3.800 88.593
Door Deduction D-10 A sq.m -2 1.000 2.150 -4.300
Wall 221 (Doubling) sq.m
Wall 258 sq.m 2 2.800 3.800 21.280
Wall 270 sq.m 2 29.480 3.800 224.048
Deduction of Columns sq.m -4 0.800 2.150 -6.880
Wall 271 sq.m 2 4.650 3.800 35.340
Wall 272 sq.m 2 7.300 3.800 55.480
Wall 273 sq.m 2 6.498 3.800 49.385
Door Deduction MD-99 sq.m -2 1.900 2.150 -8.170
Wall 275 sq.m 2 2.800 3.800 21.280
Wall 336 sq.m 2 1.150 3.800 8.740
Wall 338 sq.m 2 16.100 3.800 122.360
Door Deduction D-9B sq.m -2 0.900 2.150 -3.870
Deduction w-22 sq.m -2 2.000 2.000 -8.000

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
117 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 343 sq.m 2 4.400 3.800 33.440


Door Deduction FD-12 sq.m -2 1.200 2.150 -5.160
Wall 344 sq.m 2 2.550 3.800 19.380
Wall 354 sq.m 4 3.100 3.800 47.120
Wall 357 sq.m 2 5.340 3.800 40.584
Wall 358 sq.m 2 1.999 3.800 15.192
Door Deduction DD-88C sq.m -2 1.600 2.150 -6.880
Wall 359 sq.m 2 7.000 3.800 53.200
Door Deduction D-09A sq.m -4 1.000 2.150 -8.600
Wall 360 sq.m 2 8.810 3.800 66.956
Wall 361 sq.m 2 7.000 3.800 53.200
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 362 sq.m 2 0.804 3.800 6.110
Wall 363 sq.m 2 2.400 3.800 18.240
Wall 364 sq.m 2 2.103 3.800 15.983
Door Deduction DD-88C sq.m -2 1.600 2.150 -6.880
Wall 365 sq.m 2 3.585 3.800 27.246
Wall 366 sq.m 2 2.456 3.800 18.666
Wall 381 sq.m 2 3.000 3.800 22.800
Wall 392 sq.m 2 5.115 3.800 38.874
Door Deduction D-10A sq.m -4 1.000 2.150 -8.600
Wall 401 sq.m 2 2.489 3.800 18.916
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880
Wall 404 sq.m 2 2.070 3.800 15.732
Wall 405 sq.m 2 2.045 3.800 15.542
Wall 412 sq.m 2 5.307 3.800 40.333
Wall 413 sq.m 2 5.508 3.800 41.861
Wall 415 sq.m 2 5.310 3.800 40.356
Wall 420 sq.m 2 4.791 3.800 36.412
Door Deduction DD-88A sq.m -2 1.600 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
118 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall 421 sq.m 2 10.995 3.800 83.562


Wall 422 sq.m 2 7.080 3.800 53.808
Wall 427 sq.m 2 4.682 3.800 35.583
Deduction Oppening sq.m -4 1.000 2.150 -8.600
Qty of Plaster on 200mm Hollow block masonry 4,170.846

Ground Floor
Wall-126 SM 2 2.500 - 3.800 19.000
Wall-158 SM 2 7.300 - 3.800 55.480
Wall-186 SM 2 0.229 - 3.800 1.740
Wall-550 SM 2 7.475 - 3.800 56.810
LD-93A SM -2 1.200 - 2.150 -5.160
Wall-706 SM 2 5.100 - 3.800 38.760
Wall-754 SM 2 5.210 - 3.800 39.596
D-10 SM -2 1.000 - 2.150 -4.300
Wall-772 SM 2 1.700 - 3.800 12.920
Wall-779 SM 2 1.700 - 3.800 12.920
Wall-780 SM 2 4.890 - 3.800 37.164
Wall-781 SM 2 5.690 - 3.800 43.244
Wall-782 SM 2 15.200 - 3.800 115.520
LD-93 SM -6 1.200 - 2.150 -15.480
D/d of Drop Panel SM -8 0.850 - 0.150 -1.020
D/d for Column SM -2 1.000 - 3.800 -7.600
Wall-783 SM 2 15.910 - 3.800 120.916
LD-93 SM -2 1.200 - 2.150 -5.160
LD-10 SM -2 1.000 - 2.150 -4.300
Wall-784 SM 2 5.690 - 2.150 24.467
Wall-786 SM 2 16.040 - 3.800 121.904
D/d of Opening SM -2 2.000 - 3.800 -15.200
DD-88 SM -2 1.600 - 2.150 -6.880
D/d of Drop Panel SM -6 0.850 - 0.150 -0.765

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
119 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-787 SM 2 5.591 - 3.800 42.492


LD-10 SM -2 1.000 - 2.150 -4.300
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-788 SM 2 17.018 - 3.800 129.337
LD-10 SM -6 1.000 - 2.150 -12.900
Wall-789 SM 2 5.600 - 3.800 42.560
LD-10 SM -2 1.000 - 2.150 -4.300
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-790 SM 2 2.010 - 3.800 15.276
DD-88B SM -2 1.600 - 2.150 -6.880
Dld of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-791 SM 2 1.350 - 3.800 10.260
Wall-792 SM 2 1.350 - 3.800 10.260
Wall-793 SM 2 4.590 - 3.800 34.884
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-797 SM 2 5.190 - 3.800 39.444
Wall-799 SM 2 5.200 - 3.800 39.520
D/d for Window SM -2 1.510 - 1.510 -4.560
Wall-804 (6.200+6.211) SM 2 12.041 - 3.800 91.512
LD-93 SM -2 1.200 - 2.150 -5.160
Wall-805 SM 2 13.030 - 3.800 99.028
LD-93 SM -2 1.200 - 2.150 -5.160
D-9A SM -2 0.900 - 2.150 -3.870
D/d of Drop Panel SM -6 0.850 - 0.150 -0.765
Wall-806 SM 2 7.080 - 3.800 53.808
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
D-10 SM -2 1.000 - 2.150 -4.300
Wall-807 SM 2 5.365 - 3.800 40.774
Wall-810 SM 2 8.375 - 3.800 63.650
Wall-811 SM 2 7.000 - 3.800 53.200

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
120 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255


Wall-815 SM 2 3.401 - 0.150 1.020
D/d of Drop Panel SM -2 0.850 - 0.150 -0.255
Wall-823 SM 2 1.700 - 3.800 12.920

Qty Ground Floor= 1,360.541


First Floor
H = 9.825-6.225-0.225 = 3.375
Wall-27 SM 2 8.600 - 2.600 44.720
Wall-28 SM 2 7.500 - 2.600 39.000
Wall-44 SM 2 5.363 - 2.600 27.888
Wall-51 SM 2 4.400 - 2.600 22.880
Wall-67 SM 2 4.550 - 2.625 23.888
Wall-242 SM 2 5.375 - 2.600 27.950
Wall-251 SM 2 4.540 - 2.600 23.608
Wall-257 SM 2 3.050 - 2.600 15.860
Wall-261 SM 2 0.670 - 2.600 3.484
Wall-321 SM 2 2.500 - 2.600 13.000
Wall-373 SM 2 0.801 - 2.600 4.165
Wall-389 SM 2 8.700 - 2.600 45.240
Wall-390 SM 2 7.000 - 2.600 36.400
Wall-391 SM 2 4.650 - 2.600 24.180
Wall-396 SM 2 0.600 - 2.600 3.120
Qty First Floor= 355.383

Second Floor
H = 13.425-9.825-0.225 = 3.375
Wall-3 SM 2 1.450 - 2.600 7.540
FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
121 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-4 SM 2 2.550 - 2.600 13.260


D/d Opening SM -2 1.300 - 2.150 -5.590
Wall-5 SM 2 2.600 - 2.600 13.520
Wall-6 SM 2 4.600 - 2.600 23.920
FD-12 SM -2 1.200 - 2.150 -5.160
Wall-7 SM 2 0.500 - 2.600 2.600
Wall-8 SM 2 0.600 - 2.600 3.120
Wall-9 SM 2 2.500 - 2.600 13.000
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-12 SM 2 0.600 - 2.600 3.120
Wall-13 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.325 - 1.500 -3.975
Wall-14 SM 2 4.050 - 2.600 21.060
Wall-15 SM 2 0.500 - 2.600 2.600
Wall-17 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-19 SM 2 0.600 - 2.600 3.120
Wall-20 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-21 SM 2 4.050 - 2.600 21.060
Wall-22 SM 2 0.600 - 2.600 3.120
Wall-23 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-25 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-27 SM 2 0.600 - 2.600 3.120
Wall-28 SM 2 4.050 - 2.600 21.060
Wall-29 SM 2 0.600 - 2.600 3.120
Wall-30 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
122 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-33 SM 2 1.625 - 2.600 8.450


D/d Window SM -2 1.350 - 1.500 -4.050
Wall-34 SM 2 0.600 - 2.600 3.120
Wall-35 SM 2 4.050 - 2.600 21.060
Wall-36 SM 2 0.600 - 2.600 3.120
Wall-37 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-40 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-41 SM 2 0.600 - 2.600 3.120
Wall-42 SM 2 4.050 - 2.600 21.060
Wall-43 SM 2 0.600 - 2.600 3.120
Wall-44 SM 2 1.625 - 2.600 8.450
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-47 SM 2 2.000 - 2.600 10.400
D/d Window SM -2 1.350 - 1.500 -4.050
Wall-48 SM 2 0.600 - 2.600 3.120
Wall-49 SM 2 5.300 - 2.600 27.560
Wall-50 SM 2 7.200 - 2.600 37.440
Wall-51 SM 2 10.550 - 2.600 54.860
D/d of Column. SM -2 1.000 - 2.600 -5.200
Wall-52 SM 2 10.550 - 2.600 54.860
D/d of Column. SM -2 1.000 - 2.600 -5.200
Wall-53 SM 2 7.250 - 2.600 37.700
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-54 SM 2 7.250 - 2.600 37.700
DD-99 SM -2 1.800 - 2.150 -7.740
Wall-55 SM 2 5.200 - 2.600 27.040
Wall-56 SM 2 5.200 - 2.600 27.040
Wall-57 SM 2 7.000 - 2.600 36.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
123 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-65 SM 2 2.500 - 2.600 13.000


Wall-66 SM 2 0.600 - 2.600 3.120
Wall-67 SM 2 2.100 - 2.600 10.920
D/d of window SM -2 1.350 - 1.500 -4.050
Wall-68 SM 2 0.600 - 2.600 3.120
Wall-69 SM 2 2.600 - 2.625 13.650
Wall-70 SM 2 2.600 - 2.625 13.650
Wall-71 SM 2 0.600 - 2.600 3.120
Wall-72 SM 2 2.100 - 2.600 10.920
D/d of window SM -2 1.350 - 1.500 -4.050
Wall-73 SM 2 0.600 - 2.600 3.120
Wall-74 SM 2 2.600 - 2.600 13.520
Wall-75 SM 2 2.600 - 2.600 13.520
Wall-76 SM 2 0.600 - 2.600 3.120
Wall-77 SM 2 2.100 - 2.600 10.920
D/d of window SM -2 1.350 - 1.500 -4.050
Wall-78 SM 2 0.600 - 2.600 3.120
Wall-79 SM 2 2.600 - 2.600 13.520
Wall-80 SM 2 2.600 - 2.600 13.520
Wall-81 SM 2 0.600 - 2.600 3.120
Wall-82 SM 2 2.100 - 2.600 10.920
D/d of window SM -2 1.350 - 1.500 -4.050
Wall-83 SM 2 0.600 - 2.600 3.120
Wall-84 SM 2 1.650 - 2.600 8.580
Wall-85 SM 2 1.580 - 2.600 8.216
Wall-86 SM 2 7.689 - 2.600 39.983
Wall-147 SM 2 3.722 - 2.600 19.354
Wall-155 SM 2 6.990 - 2.600 36.348
Wall-172 SM 2 7.080 - 2.600 36.816
Wall-174 SM 2 7.080 - 2.600 36.816

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
124 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-178 SM 2 7.080 - 2.600 36.816


Wall-193 SM 2 7.080 - 2.600 36.816
D/d for Door SM -2 1.600 - 2.150 -6.880
Wall-194 SM 2 31.380 - 2.600 163.176
D/d of Column. SM -3 1.000 - 2.600 -7.800
Wall-195 SM 2 23.290 - 2.600 121.108
D/d of Column. SM -2 1.000 - 2.600 -5.200
Wall-205 SM 2 3.000 - 2.600 15.600
Wall-210 SM 2 4.810 - 2.600 25.012
Wall-220 SM 2 5.259 - 0.100 1.052
Wall-223 SM 2 7.190 - 2.600 37.388
Qty Second Floor= 1,311.266

3rd Floor
H = 17.025-13.425-0.300 = 3.300
Wall-1 SM 2 7.200 - 2.600 37.440
Wall-2 SM 2 7.300 - 2.600 37.960
Wall-3 SM 2 7.300 - 2.600 37.960
Wall-4 SM 2 6.350 - 2.600 33.020
Wall-6 SM 16 0.600 - 2.600 24.960
Wall-81 SM 2 7.300 - 2.600 37.960
DD-88A SM -2 1.600 - 2.150 -6.880
D/d Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-82 SM 2 7.300 - 2.600 37.960
D/d Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-83 SM 2 4.499 - 2.600 23.395
D/d Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-84 SM 2 7.300 - 2.600 37.960
D/d Drop Panel SM -2 0.950 - 0.200 (0.380)
Wall-85 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
125 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)


Wall-86 SM 2 2.600 - 2.600 13.520
Wall-87 SM 2 6.750 - 0.200 2.700
Wall-88 SM 2 0.165 - 2.600 0.858
Wall-89 SM 2 0.165 - 2.600 0.858
Wall-90 SM 2 6.738 - 0.200 2.695
Wall-91 SM 2 0.165 - 2.600 0.858
Wall-92 SM 2 0.165 - 2.600 0.858
Wall-93 SM 2 6.744 - 0.200 2.698
Wall-94 SM 2 0.171 - 2.600 0.889
Wall-95 SM 2 0.177 - 2.600 0.920
Wall-96 SM 2 6.732 - 0.200 2.693
Wall-96a SM 2 0.171 - 2.600 0.889
Wall-97 SM 2 7.080 - 2.600 36.816
DD-88A SM -2 1.600 - 2.150 (6.880)
Wall-97a SM 2 0.165 - 2.600 0.858
Wall-98 SM 2 6.750 - 0.200 2.700
Wall-99 SM 2 6.750 - 0.200 2.700
Wall-100 SM 2 6.750 - 0.200 2.700
Wall-104 SM 2 7.300 - 2.600 37.960
Wall-131 SM 2 7.600 - 2.600 39.520
Wall-134 SM 2 8.650 - 2.600 44.980
DD88A SM -2 1.600 - 2.150 (6.880)
Wall-135 SM 2 7.650 - 2.600 39.780
DD88A SM -2 1.600 - 2.150 (6.880)
D/d Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-136 SM 2 4.800 - 2.600 24.960
Wall-137 SM 2 8.900 - 2.600 46.280
Wall-138 SM 2 8.749 - 2.600 45.495
D/d opening SM -2 1.700 - 0.150 (0.510)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
126 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH
CENTER (TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.1Ordinary Plaster
(Refer Specs. Section #. 9200)
Item Descriptions:-Providing and laying 12 mm thick smooth Cement Sand plaster (1:4) to Internal Block /
Concrete Walls / Columns / Beams including forming key, casing, corner and stop beads metal lathing at any
height complete with leveling, finishing, curing, etc. complete as per Drawings, Specifications, Room Finishes
Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-144 SM 2 15.470 - 0.200 6.188


Wall-145 SM 2 7.000 - 2.600 36.400
D/d Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-174 SM 2 12.625 - 2.600 65.650
Wall-199 SM 2 1.800 - 2.600 9.360
Wall-202 SM 2 7.100 - 2.600 36.920
D/d Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-207 SM 2 2.399 - 2.600 12.475
DD-88A SM -2 1.600 - 2.150 (6.880)
D/d Drop Panel SM -2 0.850 - 0.150 (0.255)
Wall-213 SM 2 6.990 - 2.600 36.348
Wall-214 SM 2 1.290 - 2.000 5.160
Wall-215 SM 2 4.740 - 2.600 24.648
Wall-216 SM 2 0.165 - 2.600 0.858
Wall-218 SM 2 0.165 - 2.600 0.858
Wall-219 SM 2 0.165 - 2.600 0.858

Qty Third Floor= 899.653

Total Qty of Plaster on 200mm thick Hollow block work 8,097.689

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
127 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

ii- Paint on 150mm thick Block Masnory

Ground Floor

Wall-30 SM 2 4.150 - 0.200 1.660

Wall-32 SM 2 4.050 - 0.200 1.620

Wall-38 SM 2 3.600 - 0.200 1.440

Wall-46 SM 2 3.600 - 0.200 1.440

Wall-48 SM 2 4.100 - 0.200 1.640

Wall-50 SM 2 4.100 - 0.200 1.640

Wall-55 SM 2 7.400 - 0.200 2.960

Wall-59 SM 2 7.300 - 0.200 2.920

Wall-85 SM 2 2.800 - 0.200 1.120

Wall-90 SM 2 3.600 - 0.200 1.440

Wall-92 SM 2 3.050 - 0.200 1.220

Wall-98 SM 2 3.700 - 0.200 1.480

Wall-101 SM 2 3.700 - 0.200 1.480

Wall-102 SM 2 4.150 - 0.200 1.660

Wall-105 SM 2 3.150 - 0.200 1.260

Wall-110 SM 2 4.250 - 0.200 1.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
128 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-134 SM 2 5.075 - 0.200 2.030

Wall-148 SM 2 7.850 - 0.200 3.140

Wall-174 SM 2 5.250 - 0.200 2.100

Wall-176 SM 2 3.230 - 0.200 1.292

Wall-185 SM 2 3.620 - 0.200 1.448

Wall-187 SM 2 3.617 - 0.200 1.447

Wall-190 SM 2 3.230 - 0.200 1.292

Wall-191 SM 2 3.217 - 0.200 1.287

Wall-194 SM 2 3.712 - 0.200 1.485

Wall-207 SM 2 10.061 - 0.200 4.024

Wall-210 SM 2 6.651 - 0.200 2.660

Wall-222 SM 2 6.570 - 0.200 2.628

Wall-234 SM 2 4.650 - 3.800 35.340

Wall-236 SM 2 4.650 - 3.800 35.340

Wall-467 SM 2 4.500 - 3.800 34.200

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-498 SM 2 2.650 - 3.800 20.140

Wall-501 SM 2 0.175 - 3.800 1.330

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
129 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-502 SM 2 6.700 - 0.200 2.680

Wall-503 SM 2 0.165 - 3.800 1.254

Wall-506 SM 2 0.165 - 3.800 1.254

Wall-507 SM 2 6.700 - 0.200 2.680

Wall-508 SM 2 0.165 - 3.800 1.254

Wall-510 SM 2 0.165 - 3.800 1.254

Wall-511 SM 2 6.700 - 0.200 2.680

Wall-512 SM 2 0.165 - 3.800 1.254

Wall-529 SM 2 0.165 - 3.800 1.254

Wall-530 SM 2 6.750 - 0.200 2.700

Wall-531 SM 2 0.165 - 3.800 1.254

Wall-533 SM 2 0.165 - 3.800 1.254

Wall-534 SM 2 6.915 - 0.200 2.766

Wall-535 SM 2 0.175 - 3.800 1.330

Wall-536 SM 2 0.165 - 3.800 1.254

Wall-539 SM 2 0.165 - 3.800 1.254

Wall-540 SM 2 0.165 - 3.800 1.254

Wall-544 SM 2 0.165 - 3.800 1.254

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
130 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-555 SM 2 6.870 - 0.200 2.748

Wall-559 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-564 SM 2 3.800 - 3.800 28.880

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-565 SM 2 1.450 - 3.800 11.020

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-572 SM 2 0.165 - 3.800 1.254

Wall-574 SM 2 0.165 - 3.800 1.254

Wall-575 SM 2 6.750 - 0.200 2.700

Wall-576 SM 2 7.080 - 0.200 2.832

Wall-577 SM 2 0.165 - 3.800 1.254

Wall-578 SM 2 0.165 - 3.800 1.254

Wall-579 SM 2 0.165 - 3.800 1.254

Wall-580 SM 2 6.915 - 0.200 2.766

Wall-582 SM 2 0.165 - 3.800 1.254

Wall-612 SM 2 2.205 - 3.800 16.758

Wall-614 SM 2 1.231 - 3.800 9.356

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
131 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-615 SM 2 2.250 - 3.800 17.100

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-616 SM 2 4.450 - 3.800 33.820

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-652 SM 2 0.125 - 3.800 0.950

Wall-653 SM 2 0.125 - 3.800 0.950

Wall-654 SM 2 0.125 - 3.800 0.950

Wall-705 SM 2 7.080 - 3.800 53.808

D/d of Window SM -6 1.300 - 2.150 -16.770

Wall-708 SM 2 5.174 - 3.800 39.322

Wall-709 SM 2 2.425 - 3.800 18.430

Wall-710 SM 2 6.273 - 3.800 47.675

D-9A SM -4 0.900 - 2.150 -7.740

Wall-711 SM 2 1.500 - 3.800 11.400

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-713 SM 2 3.827 - 3.800 29.085

DD-88 SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
132 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-714 SM 2 3.765 - 3.800 28.614

Wall-715 SM 2 2.231 - 3.800 16.956

Wall-716 SM 2 2.231 - 3.800 16.956

Wall-717 SM 2 2.231 - 3.800 16.956

Wall-718 SM 2 5.150 - 3.800 39.140

D/d of Opening SM -4 1.300 - 2.150 -11.180

Wall-719 SM 2 4.000 - 3.800 30.400

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-720 SM 2 8.700 - 3.800 66.120

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-721 SM 2 3.300 - 3.800 25.080

Wall-722 SM 2 3.300 - 3.800 25.080

Wall-761 SM 2 1.500 - 3.800 11.400

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-762 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-777 SM 2 4.450 - 3.800 33.820

FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
133 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Qty Ground Floor= 769.973

First Floor

H = 9.825-6.225-0.225 = 3.375

Wall-13 SM 2 3.840 - 0.200 1.536

Wall-15A SM 2 3.699 - 0.200 1.480

Wall-39 SM 2 2.827 - 0.200 1.131

Wall-47 SM 2 1.805 - 0.200 0.722

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
134 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-52 SM 2 3.110 - 0.200 1.244

Wall-57 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-58 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-59 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-60 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-61 SM 2 5.450 - 2.600 28.340

Wall-77 SM 2 3.358 - 2.600 17.462

Wall-82 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-84 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-85 SM 2 4.150 - 2.600 21.580

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-88 SM 2 7.250 - 0.200 2.900

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
135 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-90 SM 2 2.100 - 2.600 10.920

Wall-95 SM 2 0.800 - 2.600 4.160

Wall-108 SM 2 6.350 - 0.200 2.540

Wall-109 SM 2 7.300 - 0.200 2.920

Wall-110 SM 2 7.300 - 0.200 2.920

Wall-112 SM 2 1.829 - 0.200 0.732

Wall-113 SM 2 4.540 - 0.200 1.816

Wall-119 SM 2 3.410 - 0.200 1.364

Wall-120 SM 2 1.210 - 0.200 0.484

Wall-121 SM 2 1.829 - 0.200 0.732

Wall-122 SM 2 4.540 - 0.200 1.816

Wall-128 SM 2 3.410 - 0.200 1.364

Wall-129 SM 2 1.260 - 0.200 0.504

Wall-130 SM 2 1.829 - 0.200 0.732

Wall-131 SM 2 4.540 - 0.200 1.816

Wall-138 SM 2 3.360 - 0.200 1.344

Wall-139 SM 2 1.260 - 0.200 0.504

Wall-140 SM 2 1.225 - 0.200 0.490

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
136 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-141 SM 2 7.300 - 0.200 2.920

Wall-142 SM 2 1.225 - 0.200 0.490

Wall-144 SM 2 1.829 - 0.200 0.732

Wall-145 SM 2 4.490 - 0.200 1.796

Wall-148 SM 2 3.910 - 0.200 1.564

Wall-149 SM 2 1.260 - 0.200 0.504

Wall-158 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-159 SM 2 4.500 - 2.600 23.400

Wall-161 SM 2 2.650 - 2.600 13.780

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-163 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-170 SM 2 2.335 - 0.200 0.934

Wall-172 SM 2 2.335 - 0.200 0.934

Wall-173 SM 2 2.335 - 0.200 0.934

Wall-175 SM 2 2.335 - 0.200 0.934

Wall-178 SM 2 2.838 - 0.200 1.135

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
137 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-179 SM 2 2.838 - 0.200 1.135

Wall-184 SM 2 2.335 - 0.200 0.934

Wall-186 SM 2 2.335 - 0.200 0.934

Wall-187A SM 12 2.335 - 0.200 5.604

Wall-190 SM 2 2.838 - 0.200 1.135

Wall-191 SM 2 2.838 - 0.200 1.135

Wall-198A SM 12 2.335 - 0.200 5.604

Wall-202 SM 2 2.838 - 0.200 1.135

Wall-203 SM 2 2.838 - 0.200 1.135

Wall-210 SM 2 1.150 - 2.600 5.980

Wall-212 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-213 SM 2 3.550 - 2.600 18.460

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-215 SM 2 1.008 - 2.600 5.242

Wall-216 SM 2 1.058 - 2.600 5.502

Wall-217 SM 2 7.200 - 0.200 2.880

Wall-218 SM 2 6.750 - 0.200 2.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
138 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-219 SM 2 6.985 - 0.200 2.794

Wall-220 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-221 SM 2 3.150 - 2.600 16.380

Wall-222 SM 2 5.500 - 2.600 28.600

D-9A SM -2 0.900 - 2.150 -3.870

Wall-223 SM 2 2.500 - 2.600 13.000

Wall-224 SM 2 1.080 - 2.600 5.616

Wall-225 SM 2 1.058 - 2.600 5.502

Wall-226 SM 2 6.750 - 0.200 2.700

Wall-227 SM 2 0.165 - 2.600 0.858

Wall-228 SM 2 0.165 - 2.600 0.858

Wall-229 SM 2 0.165 - 2.600 0.858

Wall-230 SM 2 0.165 - 2.600 0.858

Wall-231 SM 2 0.165 - 2.600 0.858

Wall-232 SM 2 0.165 - 2.600 0.858

Wall-233 SM 2 6.750 - 0.200 2.700

Wall-234 SM 2 6.700 - 0.200 2.680

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
139 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-235 SM 2 6.725 - 0.200 2.690

Wall-236 SM 2 0.165 - 2.600 0.858

Wall-244 SM 2 1.290 - 2.600 6.708

Wall-245 SM 2 2.250 - 2.600 11.700

Wall-271 SM 2 6.650 - 0.200 2.660

Wall-278 SM 2 6.750 - 0.200 2.700

Wall-303 SM 2 6.750 - 0.200 2.700

Wall-315 SM 2 6.750 - 0.200 2.700

Wall-337 SM 2 6.750 - 0.200 2.700

Wall-338 SM 2 6.650 - 0.200 2.660

Wall-339 SM 2 6.650 - 0.200 2.660

Wall-346 SM 2 3.300 - 2.600 17.160

Wall-347 SM 2 3.300 - 2.600 17.160

Wall-348 SM 2 3.932 - 2.600 20.446

Wall-349 SM 2 8.700 - 2.600 45.240

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-350 SM 2 5.150 - 2.600 26.780

D/d of Opening SM -4 1.300 - 2.150 -11.180

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
140 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-351 SM 2 2.219 - 2.600 11.539

Wall-352 SM 2 2.225 - 2.600 11.570

Wall-353 SM 2 7.800 - 2.600 40.560

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-354 SM 2 2.231 - 2.600 11.601

Wall-355 SM 2 3.765 - 2.600 19.578

Wall-356 SM 2 3.827 - 2.600 19.900

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-357 SM 2 6.273 - 2.600 32.620

D-9A SM -4 0.900 - 2.150 -7.740

Wall-357A SM 2 2.425 - 2.600 12.610

Wall-368 SM 2 7.190 - 0.200 2.876

Wall-369 SM 2 7.300 - 0.200 2.920

Wall-378 SM 2 2.205 - 2.600 11.466

Wall-380 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-381 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
141 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-382 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 -5.160

Qty first Floor= 663.437

Second Floor

H = 13.425-9.825-0.225 = 3.375

Wall-3 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-5 SM 2 2.600 - 2.600 13.520

Wall-6 SM 2 4.600 - 2.600 23.920

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-58 SM 2 4.150 - 2.600 21.580

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-59 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
142 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-61 SM 2 1.450 - 2.600 7.540

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-63 SM 2 0.800 - 2.600 4.160

Wall-64 SM 2 2.100 - 2.600 10.920

Wall-87 SM 2 2.205 - 2.600 11.466

Wall-89 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-90 SM 2 4.433 - 2.600 23.052

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-91 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.600 -6.760

Wall-108 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-109 SM 2 3.833 - 2.600 19.932

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-110 SM 2 8.700 - 2.600 45.240

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-111 SM 2 3.300 - 2.600 17.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
143 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-112 SM 2 3.300 - 2.600 17.160

Wall-113 SM 2 8.060 - 2.600 41.912

D/d of Opening SM -2 2.300 - 2.600 -11.960

Wall-114 SM 2 7.576 - 2.600 39.395

DD-99 SM -2 1.800 - 2.150 -7.740

D/d for Column SM -2 1.000 - 2.600 -5.200

Wall-148 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-149 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-150 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-154 SM 2 2.250 - 2.600 11.700

Wall-200 SM 2 2.250 - 2.600 11.700

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-201 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-202 SM 2 2.250 - 2.600 11.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
144 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-203 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-206 SM 2 6.865 - 0.200 2.746

Wall-212 SM 2 6.915 - 0.200 2.766

Wall-213 SM 2 7.080 - 0.200 2.832

Wall-291 SM 2 7.800 - 2.600 40.560

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-293 SM 2 2.225 - 2.600 11.570

Wall-294 SM 2 2.225 - 2.600 11.570

Wall-295 SM 2 2.425 - 2.600 12.610

Wall-299 SM 2 3.765 - 2.600 19.578

Wall-300 SM 2 2.225 - 2.600 11.570

Wall-301 SM 2 5.150 - 2.600 26.780

D/d of Opening SM -4 1.300 - 2.150 -11.180

Qty Second Floor= 443.259

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
145 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor

H = 17.025-13.425-0.300 = 3.300

Wall-5 SM 2 2.250 - 2.600 11.700

Wall-51 SM 2 2.430 - 2.600 12.636

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-52 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM -4 0.950 - 0.200 (0.760)

Wall-53 SM 2 8.599 - 2.600 44.715

D-9A SM -6 0.900 - 2.150 (11.610)

Wall-54 SM 2 3.596 - 2.600 18.699

Wall-55 SM 2 3.595 - 2.600 18.694

Wall-56 SM 2 3.595 - 2.600 18.694

Wall-57 SM 2 4.951 - 2.600 25.745

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-58 SM 2 5.601 - 2.600 29.125

Wall-66 SM 2 7.300 - 2.600 37.960

D-10 SM -4 1.000 - 2.150 (8.600)

D/d of Drop Panel SM -4 0.950 - 0.200 (0.760)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
146 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-69 SM 2 7.625 - 2.600 39.650

D-9A SM -4 0.900 - 2.150 (7.740)

Wall-74 SM 2 7.300 - 2.600 37.960

D-9A SM -2 0.900 - 2.150 (3.870)

DD-88 SM -2 1.600 - 2.150 (6.880)

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-75 SM 2 8.225 - 2.600 42.770

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-108 SM 2 3.600 - 2.600 18.720

D-10A SM -2 1.000 - 2.150 (4.300)

Wall-110 SM 2 3.000 - 2.600 15.600

Wall-111 SM 2 4.700 - 2.600 24.440

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-113 SM 2 7.300 - 2.600 37.960

FD-12 SM -2 1.200 - 2.150 (5.160)

D-9B SM -4 0.900 - 2.150 (7.740)

D/d of drop Panel SM -4 0.950 - 0.200 (0.760)

Wall-114 SM 2 3.149 - 2.600 16.375

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
147 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-115 SM 2 3.149 - 2.600 16.375

Wall-116 SM 2 2.500 - 2.600 13.000

D/d of drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-118 SM 2 2.550 - 2.600 13.260

D/d of opening SM -2 1.300 - 2.150 (5.590)

Wall-119 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-126 SM 2 2.205 - 2.600 11.466

Wall-128 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-129 SM 2 4.463 - 2.600 23.208

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-130 SM 2 2.550 - 2.600 13.260

D/d of opening SM -2 1.300 - 2.150 (5.590)

Wall-141 SM 2 4.400 - 0.200 1.760

Wall-142 SM 2 7.000 - 0.200 2.800

Wall-143 SM 2 7.000 - 0.200 2.800

Wall-143A SM 2 8.329 - 0.200 3.332

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
148 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-146 SM 2 5.025 - 0.200 2.010

D-10 SM -2 1.000 - 2.150 (4.300)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-148 SM 2 1.300 - 2.600 6.760

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-150 SM 2 3.827 - 2.600 19.900

DD-88 SM -2 1.600 - 2.150 (6.880)

Wall-161 SM 2 7.800 - 2.600 40.560

D/d of opening SM -6 1.300 - 2.150 (16.770)

Wall-162 SM 2 2.231 - 2.600 11.601

Wall-163 SM 2 2.231 - 2.600 11.601

Wall-164 SM 2 2.231 - 2.600 11.601

Wall-165 SM 2 3.300 - 2.600 17.160

Wall-166 SM 2 3.300 - 2.600 17.160

Wall-167 SM 2 8.700 - 2.600 45.240

D/d of Opening SM -6 1.300 - 2.150 (16.770)

Wall-168 SM 2 5.150 - 2.600 26.780

D/d of opening SM -4 1.300 - 2.150 (11.180)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
149 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-169 SM 2 2.000 - 2.600 10.400

DD-99 SM -2 1.800 - 2.150 (7.740)

Wall-169A SM 2 2.000 - 2.600 10.400

Wall-186 SM 2 3.094 - 0.200 1.238

Wall-191 SM 2 10.827 - 0.200 4.331

Wall-193 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-208 SM 2 2.550 - 2.600 13.260

D/d of opening SM -2 1.300 - 2.150 (5.590)

Wall-210 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-212 SM 2 2.250 - 2.600 11.700

Wall-214 SM 2 1.290 - 2.600 6.708

Wall-221 SM 2 0.820 - 2.600 4.264

Wall-222 SM 2 0.690 - 2.600 3.588

Wall-223 SM 2 0.820 - 2.600 4.264

Wall-225 SM 2 13.447 - 0.200 5.379

Qty Third Floor = 739.224

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
150 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Qty of Lower Ground floor Sheets attached 703.856

Total Qty of Paint on 150mm thick solid block work 3,319.749

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
151 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

ii- Internal Paint

Ground Floor

Wall-1 SM 2 0.284 - 2.6.8 0.570

Wall-2 SM 2 2.742.6 - 2.6.8 2.000

Wall-2.6 SM 2 7.695 - 2.6.8 15.390

D/d of Window SM -2 1.2.65 - 1.000 -2.000

Wall-4 SM 2 0.685 - 2.6.8 1.370

Wall-5 SM 2 0.42.64 - 2.6.8 2.000

Wall-6 SM 2 7.691 - 2.6.8 15.380

D/d of Window SM -2 1.2.65 - 1.000 -2.000

Wall-7 SM 2 0.685 - 2.6.8 1.370

Wall-8 SM 2 0.62.64 - 2.6.8 2.000

Wall-9 SM 2 7.699 - 2.6.8 15.400

D/d of Window SM -2 1.2.65 - 1.000 -2.000

Wall-10 SM 2 0.685 - 2.6.8 1.370

Wall-11 SM 2 0.62.64 - 2.6.8 2.000

Wall-12 SM 2 7.695 - 3.800 58.482

D/d of Window SM -2 1.350 - 1.000 -2.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
152 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-13 SM 2 0.685 - 3.800 5.206

Wall-14 SM 2 0.634 - 3.800 4.818

Wall-15 SM 2 7.695 - 3.800 58.482

D/d of Window SM -2 1.350 - 1.000 -2.700

Wall-16 SM 2 0.685 - 3.800 5.206

Wall-17 SM 2 0.634 - 3.800 4.818

Wall-19 SM 2 7.695 - 3.800 58.482

D/d of Window SM -2 1.350 - 1.000 -2.700

Wall-20 SM 2 0.634 - 3.800 4.818

Wall-21 Missing

Wall-22 Missing

Wall-23 SM 2 3.552 - 3.800 26.995

Wall-24 SM 2 4.769 - 3.800 36.244

Wall-25 SM 2 0.364 - 3.800 2.766

Wall-26 SM 2 4.375 - 3.800 33.250

D/d of Window SM -2 1.800 - 1.500 -5.400

Wall-27 SM 2 1.258 - 3.800 9.561

D-9B SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
153 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-42 SM 2 0.685 - 3.800 5.206

Wall-64 SM 2 0.203 - 3.800 1.543

Wall-65 SM 2 2.804 - 3.800 21.310

Wall-66 SM 2 4.054 - 3.800 30.810

Wall-67 SM 2 1.863 - 3.800 14.159

Wall-68 SM 2 3.230 - 3.800 24.548

D/d of Window SM -2 2.700 - 1.500 -8.100

Wall-69 SM 2 0.700 - 3.800 5.320

Wall-70 SM 2 5.502 - 3.800 41.815

Wall-71 SM 2 1.317 - 3.800 10.009

Wall-72 SM 2 0.447 - 3.800 3.397

Wall-73 SM 2 3.430 - 3.800 26.068

D/d of Window SM -2 2.700 - 1.500 -8.100

Wall-79 SM 2 10.300 - 3.800 78.280

Wall-94 SM 2 11.304 - 3.800 85.910

Wall-114 SM 2 9.007 - 3.800 68.453

Wall-116 SM 2 6.434 - 3.800 48.898

Wall-122 SM 2 8.100 - 3.800 61.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
154 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-127 SM 2 0.332 - 3.800 2.523

Wall-128 SM 2 4.551 - 3.800 34.588

Wall-129 SM 2 1.416 - 3.800 10.762

Wall-130 SM 2 0.453 - 3.800 3.443

Wall-131 SM 2 3.430 - 3.800 26.068

D/d of Window SM -2 2.700 - 1.500 -8.100

Wall-141 SM 2 0.351 - 3.800 2.668

Wall-142 SM 2 4.555 - 3.800 34.618

Wall-143 SM 2 1.621 - 3.800 12.320

Wall-144 SM 2 3.230 - 3.800 24.548

D/d of Window SM -2 2.700 - 1.500 -8.100

Wall-145 SM 2 0.459 - 3.800 3.488

Wall-146 SM 2 5.236 - 3.800 39.794

Wall-147 SM 2 5.933 - 3.800 45.091

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-154 SM 2 3.700 - 3.800 28.120

Wall-177 SM 2 0.465 - 3.800 3.534

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
155 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-178 SM 2 5.236 - 3.800 39.794

Wall-188 SM 2 4.635 - 3.800 35.226

Wall-189 SM 2 0.432 - 3.800 3.283

Wall-192 SM 2 0.903 - 3.800 6.863

Wall-208 SM 2 0.949 - 3.800 7.212

Wall-209 SM 2 1.125 - 3.800 8.550

Wall-212 SM 2 0.467 - 3.800 3.549

Wall-213 SM 2 1.569 - 3.800 11.924

Wall-214 SM 2 1.069 - 3.800 8.124

Wall-215 SM 2 1.680 - 3.800 12.768

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-216 SM 2 0.407 - 3.800 3.093

Wall-217 SM 2 4.654 - 3.800 35.370

Wall-218 SM 2 0.505 - 3.800 3.838

D-9B SM -2 0.900 - 2.150 -3.870

Wall-219 SM 2 0.505 - 3.800 3.838

Wall-220 SM 2 4.749 - 3.800 36.092

D/d of Window SM -2 1.350 - 1.500 -4.050

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
156 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-221 SM 2 7.900 - 3.800 60.040

D-9B SM -2 0.900 - 2.150 -3.870

Wall-226 SM 2 0.600 - 3.800 4.560

Wall-227 SM 2 1.715 - 3.800 13.034

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-228 SM 2 0.600 - 3.800 4.560

Wall-229 SM 2 7.500 - 3.800 57.000

D/d of Wall SM -2 1.715 - 3.800 -13.034

Wall-230 SM 2 0.600 - 3.800 4.560

Wall-231 SM 2 1.715 - 3.800 13.034

Wall-232 SM 2 6.500 - 3.800 49.400

D/d of Wall SM -2 1.715 - 3.800 -13.034

Wall-233 SM 2 0.600 - 3.800 4.560

Wall-235 SM 2 7.300 - 3.800 55.480

Wall-237 SM 2 7.299 - 3.800 55.472

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-238 SM 2 0.600 - 3.800 4.560

Wall-239 SM 2 0.600 - 3.800 4.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
157 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-245 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-246 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-248 SM 2 2.550 - 3.800 19.380

Wall-249 SM 2 2.550 - 3.800 19.380

Wall-250 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-251 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-254 SM 2 24.700 3.800 187.720

DD-88A SM -2 1.600 2.150 -6.880

Wall-268 SM 2 4.540 3.800 34.504

Wall-269 SM 2 7.300 3.800 55.480

Wall-270 SM 2 7.300 3.800 55.480

Wall-271 SM 2 7.491 3.800 56.932

Wall-272 SM 2 7.500 3.800 57.000

D-9B SM -2 0.900 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
158 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-273 SM 2 1.564 3.800 11.886

Wall-274 SM 2 0.443 3.800 3.367

Wall-275 SM 2 6.017 3.800 45.729

D/d of Window SM -2 1.800 1.500 -5.400

Wall-276 SM 2 2.045 3.800 15.542

Wall-279 SM 2 15.900 3.800 120.840

Wall-296 SM 2 2.900 - 3.800 22.040

Wall-303 SM 2 2.900 - 3.800 22.040

Wall-311 SM 2 0.600 3.800 4.560

Wall-312 SM 2 0.600 3.800 4.560

Wall-315 SM 2 0.600 3.800 4.560

Wall-316 SM 2 0.600 3.800 4.560

Wall-319 SM 2 0.600 - 3.800 4.560

Wall-320 SM 2 0.600 - 3.800 4.560

Wall-321 SM 2 46.833 - 3.800 355.931

D/d of Window SM -10 1.350 - 1.500 -20.250

D/d of Column SM -6 0.800 - 3.800 -18.240

Wall-337 SM 2 0.600 - 3.800 4.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
159 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-338 SM 2 0.600 - 3.800 4.560

Wall-343 SM 2 0.600 - 3.800 4.560

Wall-347 SM 2 2.250 - 3.800 17.100

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-349 SM 2 1.450 - 3.800 11.020

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-350 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-353 SM 2 4.150 - 3.800 31.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-355 SM 2 2.100 - 3.800 15.960

Wall-356 Missing -

Wall-361 SM 2 18.550 - 3.800 140.980

D/d for Column SM -4 0.800 - 3.800 -12.160

Wall-365 & 365A SM 4 2.800 - 3.800 42.560

Wall-382 SM 2 2.550 - 3.800 19.380

D/d of Drop Panel SM

Wall-393 SM 2 0.600 - 3.800 4.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
160 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-394 SM 2 0.600 - 3.800 4.560

Wall-395 SM 2 4.651 - 3.800 35.348

D-75 SM -4 0.750 - 2.150 -6.450

D-10A SM -2 1.000 - 2.150 -4.300

Wall-399 SM 2 7.306 - 3.800 55.526

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-403 SM 2 7.306 - 3.800 55.526

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-404 SM 2 2.225 - 3.800 16.910

D-75 SM -2 0.750 - 2.150 -3.225

Wall-408 SM 2 0.600 - 3.800 4.560

Wall-409 SM 2 0.600 - 3.800 4.560

Wall-410 SM 2 7.306 - 3.800 55.526

D/d of Window SM -2 1.350 - 1.500 -4.050

Wall-412 SM 2 0.600 - 3.800 4.560

Wall-413 SM 2 0.600 - 3.800 4.560

Wall-455 SM 2 7.300 - 3.800 55.480

Wall-456 SM 2 7.300 - 3.800 55.480

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
161 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-457 SM 2 2.500 - 3.800 19.000

Wall-467 SM 2 4.500 - 3.800 34.200

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-469 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-472 SM 2 1.450 - 3.800 11.020

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-498 SM 2 2.650 - 3.800 20.140

Wall-517 SM 2 3.110 - 3.800 23.636

Wall-519 SM 2 7.089 - 3.800 53.876

Wall-520 SM 2 3.110 - 3.800 23.636

Wall-532 SM 2 7.080 - 3.800 53.808

D-10A SM -2 1.000 - 2.150 -4.300

Wall-545 SM 2 7.189 - 3.800 54.636

D/d of Drop Panel SM

Wall-552 SM 2 7.090 - 3.800 53.884

Wall-559 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
162 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-564 SM 2 3.800 - 3.800 28.880

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-565 SM 2 1.450 - 3.800 11.020

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-567 SM 2 0.900 - 3.800 6.840

Wall-568 SM 2 2.799 - 3.800 21.272

Wall-569 SM 2 7.800 - 3.800 59.280

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-570 SM 2 8.459 - 3.800 64.288

D-9B SM -2 0.900 - 2.150 -3.870

D/d of Window SM -2 1.350 - 1.000 -2.700

Wall-571 SM 2 7.755 - 3.800 58.938

Wall-583 SM 2 6.350 - 3.800 48.260

D/d of Drop Panel SM

Wall-585 SM 2 5.500 - 3.800 41.800

D/d of Window SM -2 1.700 - 1.000 -3.400

Wall-586 SM 2 7.700 - 3.800 58.520

RFD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
163 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-589 SM 2 5.900 - 3.800 44.840

RFD-12 SM -2 1.200 - 2.150 -5.160

Wall-600 SM 2 2.335 - 3.800 17.746

Wall-601 SM 2 0.365 - 3.800 2.774

Wall-603 SM 2 2.680 - 3.800 20.368

Wall-608 SM 2 7.617 - 3.800 57.889

Wall-612 SM 2 2.205 - 3.800 16.758

Wall-614 SM 2 1.231 - 3.800 9.356

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-615 SM 2 2.250 - 3.800 17.100

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-616 SM 2 4.450 - 3.800 33.820

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-626 SM 2 5.375 - 3.800 40.850

Wall-627 SM 2 5.375 - 3.800 40.850

D/d of Window SM -2 1.700 - 1.000 -3.400

Wall-674 SM 2 7.370 - 3.800 56.012

Wall-675 SM 2 3.100 - 3.800 23.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
164 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-678 SM 2 3.100 - 3.800 23.560

Wall-705 SM 2 7.080 - 3.800 53.808

D/d of Window SM -6 1.300 - 2.150 -16.770

Wall-711 SM 2 1.500 - 3.800 11.400

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-713 SM 2 3.827 - 3.800 29.085

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-718 SM 2 5.150 - 3.800 39.140

D/d of Opening SM -4 1.300 - 2.150 -11.180

Wall-720 SM 2 8.700 - 3.800 66.120

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-747 SM 2 1.680 - 3.800 12.768

Wall-748 SM 2 1.442 - 3.800 10.959

Wall-749 SM 2 1.360 - 3.800 10.336

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
165 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-750 SM 2 2.510 - 3.800 19.076

Wall-751 SM 2 15.090 - 3.800 114.684

Wall-752 SM 2 1.442 - 3.800 10.959

Wall-753 SM 2 1.680 - 3.800 12.768

D/d for Window SM -8 0.635 - 1.000 -5.080

Wall-761 SM 2 1.500 - 3.800 11.400

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-762 SM 2 2.550 - 3.800 19.380

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-777 SM 2 4.450 - 3.800 33.820

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-764 SM 2 1.020 - 3.800 7.752

D/d of Window SM -2 1.020 - 1.000 -2.040

Wall-765 SM 2 0.165 - 3.800 1.254

Wall-766 SM 2 3.770 - 3.800 28.652

Wall-767 SM 2 0.165 - 3.800 1.254

Qty Ground Floor= 4,845.009

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
166 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

First Floor

H = 9.825-6.225-0.225 = 2.6

Wall-1 SM 2 6.434 - 2.600 33.457

Wall-2 SM 2 8.250 - 2.600 42.900

d/d for Door SM -2 1.200 - 2.150 -5.160

Wall-6 SM 2 7.100 - 2.600 36.920

Wall-8 SM 2 7.300 - 2.600 37.960

Wall-14 SM 2 3.588 - 2.600 18.658

Wall-16 SM 2 7.624 - 2.600 39.645

Wall-17 SM 2 7.691 - 2.600 39.993

Wall-20 SM 2 4.829 - 2.600 25.111

Wall-34 SM 2 7.464 - 2.600 38.813

Wall-36 SM 2 7.517 - 2.600 39.088

Wall-40 SM 2 0.600 - 2.600 3.120

Wall-41 SM 2 0.600 - 2.600 3.120

Wall-42 SM 2 7.056 - 2.600 36.691

D/d of Window SM -2 1.350 - 2.000 -5.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
167 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-48 SM 2 0.600 - 2.600 3.120

Wall-49 SM 2 6.217 - 2.600 32.328

D/d of Window SM -2 1.350 - 2.000 -5.400

Wall-50 SM 2 0.600 - 2.600 3.120

Wall-54 SM 2 0.600 - 2.600 3.120

Wall-55 SM 2 0.600 - 2.600 3.120

Wall-56 SM 2 7.299 - 2.600 37.955

D/d of Window SM -2 1.350 - 2.000 -5.400

Wall-57 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-58 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-59 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-60 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-61 SM 2 5.450 - 2.600 28.340

D/d for Opening SM -4 1.200 - 2.150 -10.320

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
168 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-63 SM 2 24.600 - 2.600 127.920

Wall-68 SM 2 0.600 - 2.600 3.120

Wall-69 SM 2 7.300 - 2.600 37.960

D/d of Window SM -2 1.350 - 2.000 -5.400

Wall-70 SM 2 0.600 - 2.600 3.120

Wall-78 SM 2 0.800 - 2.600 4.160

Wall-79 SM 2 2.500 - 2.600 13.000

Wall-80 SM 2 0.800 - 2.600 4.160

Wall-82 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-84 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-85 SM 2 4.150 - 2.600 21.580

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-90 SM 2 2.100 - 2.600 10.920

Wall-93 SM 2 7.200 - 2.600 37.440

Wall-95 SM 2 0.800 - 2.600 4.160

Wall-96 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
169 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-97 SM 2 7.300 - 2.600 37.960

Wall-102 SM 2 6.350 - 2.600 33.020

D/d of Window SM 2 1.350 - 2.000 5.400

Wall-103 SM 2 0.600 - 2.600 3.120

Wall-104 SM 2 0.600 - 2.600 3.120

Wall-106 SM 2 1.605 - 2.600 8.346

Wall-114 SM 2 0.600 - 2.600 3.120

Wall-116 SM 2 7.300 - 2.600 37.960

D/d of Window SM -2 1.350 - 2.000 -5.400

Wall-117 SM 2 0.600 - 2.600 3.120

Wall-123 SM 2 0.600 - 2.600 3.120

Wall-124 SM 2 7.300 - 2.600 37.960

D/d of Window SM -2 1.350 - 2.000 -5.400

Wall-126 SM 2 0.600 - 2.600 3.120

Wall-132 SM 2 0.600 - 2.600 3.120

Wall-133 SM 2 0.600 - 2.600 3.120

Wall-134 SM 2 7.300 - 2.600 37.960

D/d of Window SM -2 1.350 - 2.000 -5.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
170 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-146 SM 2 7.300 - 2.600 37.960

Wall-151 SM 2 7.300 - 2.600 37.960

Wall-156 SM 2 2.500 - 2.600 13.000

Wall-158 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-159 SM 2 4.500 - 2.600 23.400

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-161 SM 2 2.650 - 2.600 13.780

Wall-162 SM 2 7.090 - 2.600 36.868

Wall-163 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-165 SM 2 7.080 - 2.600 36.816

Wall-166 SM 2 2.240 - 2.600 11.648

Wall-167 SM 2 4.690 - 2.600 24.388

Wall-209 SM 2 3.000 - 2.600 15.600

Wall-210 SM 2 1.150 - 2.600 5.980

Wall-212 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
171 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-213 SM 2 3.550 - 2.600 18.460

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-220 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-237 SM 2 7.080 - 2.600 36.816

Wall-238 SM 2 7.080 - 2.600 36.816

Wall-239 SM 2 6.916 - 2.600 35.963

Wall-240 SM 2 7.080 - 2.600 36.816

Wall-241 SM 2 6.916 - 2.600 35.963

Wall-243 SM 2 7.080 - 2.600 36.816

Wall-244 SM 2 1.290 - 2.600 6.708

Wall-245 SM 2 2.250 - 2.600 11.700

Wall-246 SM 2 6.990 - 2.600 36.348

Wall-249 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-250 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-270 SM 2 3.770 - 2.600 19.604

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
172 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-291 SM 2 1.120 - 2.600 5.824

Wall-292 SM 2 6.980 - 0.200 2.792

Wall-322 SM 2 11.200 - 2.600 58.240

Wall-349 SM 2 8.700 - 2.600 45.240

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-350 SM 2 5.150 - 2.600 26.780

D/d of Opening SM -4 1.300 - 2.150 -11.180

Wall-353 SM 2 7.800 - 2.600 40.560

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-356 SM 2 3.827 - 2.600 19.900

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-377 SM 2 7.689 - 2.600 39.983

Wall-378 SM 2 2.205 - 2.600 11.466

Wall-380 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-381 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-382 SM 2 4.450 - 2.600 23.140

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
173 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-384 SM 2 3.000 - 2.600 15.600

DD-88B SM -2 1.600 - 2.150 -6.880

Wall-386 SM 2 0.610 - 2.625 3.203

Wall-419 SM 4 6.400 - 2.600 66.560

Qty First Floor= 1,928.733

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
174 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Second Floor

H = 13.425-9.828-0.225 = 2.6

Wall-58 SM 2 4.150 - 2.600 21.580

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-59 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-61 SM 2 1.450 - 2.600 7.540

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-63 SM 2 0.800 - 2.600 4.160

Wall-64 SM 2 2.100 - 2.600 10.920

Wall-87 SM 2 2.205 - 2.600 11.466

Wall-89 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-90 SM 2 4.433 - 2.600 23.052

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-91 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.600 -6.760

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
175 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-95 SM 2 6.990 - 0.200 2.796

Wall-98 SM 2 0.610 - 2.600 3.172

Wall-101 SM 2 6.750 - 0.200 2.700

Wall-102 SM 2 6.750 - 0.200 2.700

Wall-105 SM 2 2.875 - 2.600 14.950

Wall-108 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-109 SM 2 3.833 - 2.000 15.332

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-110 SM 2 8.700 - 2.600 45.240

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-144 SM 2 6.700 - 0.200 2.680

Wall-144a SM 2 1.120 - 2.600 5.824

Wall-145 SM 2 6.750 - 0.200 2.700

Wall-145a SM 2 1.120 - 2.600 5.824

Wall-146 SM 2 6.750 - 0.200 2.700

Wall-148 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
176 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-149 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-150 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-154 SM 2 2.250 - 2.600 11.700

Wall-183 SM 2 3.900 - 2.600 20.280

Wall-187 SM 2 3.900 - 2.600 20.280

Wall-192 SM 2 6.750 - 0.200 2.700

Wall-200 SM 2 2.250 - 2.600 11.700

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-201 SM 2 2.550 - 2.600 13.260

D/d of Opening SM -2 1.300 - 2.150 -5.590

Wall-202 SM 2 2.250 - 2.600 11.700

Wall-203 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-291 SM 2 7.800 - 2.600 40.560

D/d of Opening SM -6 1.300 - 2.150 -16.770

Wall-301 SM 2 5.150 - 2.600 26.780

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
177 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Opening SM -4 1.300 - 2.150 -11.180

Wall-339 SM 2 7.080 - 0.200 2.832

Wall-352 SM 2 7.080 - 0.200 2.832

Wall-362 SM 2 7.080 - 0.200 2.832

Wall-367 SM 2 7.080 - 0.200 2.832

Wall-368 SM 2 7.080 - 0.200 2.832

Wall-369 SM 2 7.080 - 0.200 2.832

Qty Second Floor= 333.148

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
178 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor

Wall-5 SM 2 2.250 - 2.600 11.700

Wall-8 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-9 SM 2 2.550 - 2.600 13.260

D/d of opening SM -2 1.300 - 2.150 (5.590)

Wall-11 SM 2 2.100 - 2.600 10.920

Wall-12 SM 2 4.100 - 2.600 21.320

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-13 SM 2 2.500 - 2.600 13.000

Wall-14 SM 2 4.399 - 2.600 22.875

DD-88 SM -2 1.600 - 2.150 (6.880)

Wall-15 SM 2 2.351 - 2.600 12.225

Wall-16 SM 2 7.200 - 2.600 37.440

Wall-17 SM 2 7.300 - 2.600 37.960

D/d window SM -2 1.350 - 2.050 -5.535

Wall-18 SM 2 7.300 - 2.600 37.960

D/d window SM -4 1.350 - 2.050 -11.070

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
179 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-19 SM 2 7.300 - 2.600 37.960

D/d window SM -4 1.350 - 2.050 -11.070

Wall-20 SM 2 7.300 - 2.600 37.960

D/d window SM -4 1.350 - 2.050 -11.070

Wall-21 SM 2 7.300 - 2.600 37.960

D/d window SM -4 1.350 - 2.050 -11.070

Wall-22 SM 2 7.300 - 2.600 37.960

D/d window SM -4 1.350 - 2.050 -11.070

Wall-23 SM 2 2.500 - 2.600 13.000

D/d window SM -2 1.350 - 2.050 -5.535

Wall-24 SM 46 0.600 - 2.600 71.760

Wall-25 SM 2 4.700 - 2.600 24.440

D/d of Drop Panel SM

Wall-26 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM

Wall-27 SM 2 7.200 - 2.600 37.440

D/d of Drop Panel SM

Wall-28 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
180 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM

Wall-29 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM

Wall-30 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM

Wall-31 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM

Wall-32 SM 2 2.790 - 2.600 14.508

DD-88A SM -2 1.600 - 2.150 (6.880)

D/d of Drop Panel SM

Wall-33 SM 2 2.500 - 2.600 13.000

Wall-34 SM 2 4.500 - 2.600 23.400

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-35 SM 2 2.550 - 2.600 13.260

D/d opening SM -2 1.300 - 2.150 (5.590)

Wall-36 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-40 SM 2 2.650 - 2.600 13.780

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
181 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-41 SM 2 62.000 - 2.600 322.400

D/d for Door SM -8 1.600 - 2.150 -27.520

Wall-45 SM 2 6.923 - 2.600 36.000

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-46 SM 2 7.300 - 2.600 37.960

Wall-47 SM 2 3.000 - 2.600 15.600

Wall-76 SM 2 2.008 - 2.600 10.442

Wall-77 SM 2 0.950 - 2.600 4.940

D/d of Drop Panel SM

D-10 SM -2 1.000 - 2.150 (4.300)

Wall-78 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM

Wall-79 SM 2 7.300 - 2.600 37.960

D/d Drop Panel 0.950+0.800 SM

Wall-80 SM 2 7.300 - 2.600 37.960

Wall-101 SM 2 24.455 - 2.600 127.166

D-10A SM -6 1.000 - 2.150 (12.900)

D-9A SM -6 0.900 - 2.150 (11.610)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
182 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-102 SM 2 7.300 - 2.600 37.960

D/d drop Panel SM

Wall-103 SM 2 7.300 - 2.600 37.960

D/d for Door SM -2 1.000 - 2.150 -4.300

D/d Drop Panel SM

Wall-105 SM 4 0.860 - 2.600 8.944

Wall-107 SM 2 8.110 - 2.600 42.172

Wall-109 SM 2 2.500 - 2.600 13.000

Wall-111 SM 2 4.700 - 2.600 24.440

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-118 SM 2 2.550 - 2.600 13.260

Wall-119 SM 2 1.450 - 2.600 7.540

D/d opening SM -2 1.300 - 2.150 (5.590)

Wall-126 SM 2 2.205 - 2.600 11.466

Wall-128 SM 2 1.500 - 2.600 7.800

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-129 SM 2 4.463 - 2.600 23.208

FD-12 SM -2 1.200 - 2.150 (5.160)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
183 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-130 SM 2 2.550 - 2.600 13.260

D/d opening SM -2 1.300 - 2.150 (5.590)

Wall-148 SM 2 1.300 - 2.600 6.760

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-150 SM 2 3.827 - 2.600 19.900

DD-88 SM -2 1.600 - 2.150 (6.880)

Wall-156 SM 2 7.180 - 2.600 37.336

D-9A SM -4 0.900 - 2.150 (7.740)

Wall-158 SM 2 5.300 - 2.600 27.560

Wall-159 SM 2 4.544 - 2.600 23.629

Wall-160 SM 2 7.140 - 2.600 37.128

D-9A SM -2 0.900 - 2.150 -3.870

Wall-161 SM 2 7.800 - 2.600 40.560

D/d opening SM -6 1.300 - 2.150 (16.770)

Wall-167 SM 2 8.700 - 2.600 45.240

D/d opening SM -6 1.300 - 2.150 (16.770)

Wall-168 SM 2 5.150 - 2.600 26.780

D/d opening SM -4 1.300 - 2.150 (11.180)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
184 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-170 SM 2 4.850 - 2.600 25.220

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-171 SM 2 6.900 - 2.600 35.880

D-10A SM -2 1.000 - 2.150 (4.300)

D/d of Drop Panel SM

Wall-172 SM 2 3.399 - 2.600 17.675

Wall-173 SM 2 16.100 - 2.600 83.720

DD-88A SM -6 1.600 - 2.150 (20.640)

Wall-175 SM 2 3.700 - 2.600 19.240

Wall-176 SM 2 15.750 - 2.600 81.900

DD-88A SM -4 1.600 - 2.150 (13.760)

Wall-177 SM 2 1.999 - 2.600 10.395

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-178 SM 2 7.001 - 2.600 36.405

D/d Drop Panel SM

Wall-179 SM 2 2.199 - 2.600 11.435

D/d Drop Panel SM

Wall-180 SM 2 12.350 - 2.600 64.220

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
185 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-181 SM 2 12.350 - 2.600 64.220

DD-88A SM -2 1.600 - 2.150 (6.880)

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-182 SM 2 2.401 - 2.600 12.485

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-183 SM 2 7.000 - 2.600 36.400

D/d Drop Panel SM

Wall-184 SM 2 2.100 - 2.600 10.920

D/d Drop Panel SM

Wall-185 SM 2 3.400 - 2.600 17.680

D/d Drop Panel SM

Wall-193 SM 2 4.450 - 2.600 23.140

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-208 SM 2 2.550 - 2.600 13.260

D/d opening SM -2 1.300 - 2.150 (5.590)

Wall-210 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
186 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-212 SM 2 2.250 - 2.600 11.700

Qty Third Floor= 2,190.274

Lower Ground Floor Qty Sheets Attached 379.395

Total Qty of Paint work on 200mm thick wall 9,676.56

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
187 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Paint on 150mm hollow block work


ii-

Ground Floor

Wall-62 SM 2 2.911 - 3.800 22.124

Wall-63 SM 2 2.358 - 3.800 17.921

D-10A SM -2 1.000 - 2.150 -4.300

Wall-74 SM 2 3.437 - 3.800 26.121

Wall-75 SM 2 6.919 - 3.800 52.584

Wall-76 SM 2 0.150 - 3.800 1.140

Wall-77 SM 2 4.683 - 3.800 35.591

Wall-77a SM 2 1.200 - 3.800 9.120

D-10A SM -2 1.000 - 2.150 -4.300

Wall-80 SM 2 5.383 - 3.800 40.911

Wall-82 SM 2 1.200 - 3.800 9.120

D-10A SM -2 1.000 - 2.150 -4.300

Wall-83 SM 2 10.600 - 3.800 80.560

Wall-115 SM 2 2.125 - 3.800 16.150

Wall-117 SM 2 8.635 - 3.800 65.626

D-9A SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
188 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-118 SM 2 2.400 - 3.800 18.240

Wall-119 SM 2 2.400 - 3.800 18.240

Wall-120 SM 2 8.350 - 3.800 63.460

D-9B SM -2 0.900 - 2.150 -3.870

Wall-121 SM 2 5.125 - 3.800 38.950

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-123 SM 2 3.551 - 3.800 26.988

Wall-124 SM 2 2.527 - 3.800 19.205

Wall-125 SM 2 2.500 - 3.800 19.000

Wall-132 SM 2 7.950 - 3.800 60.420

D/d of Opening SM -2 2.100 - 3.800 -15.960

D-9A SM -2 0.900 - 2.150 -3.870

Wall-133 SM 2 4.425 - 3.800 33.630

D-75 SM -2 0.750 - 2.150 -3.225

Wall-139 SM 2 2.997 - 3.800 22.777

DD-88A SM 2 1.600 - 2.150 6.880

Wall-140 SM 2 6.919 - 3.800 52.584

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
189 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-150 SM 2 2.750 - 3.800 20.900

Wall-152 SM 2 6.851 - 3.800 52.068

Wall-155 SM 2 7.166 - 3.800 54.462

D/d of Drop Panel SM -2 2.700 - 0.150 -0.810

Wall-156 SM 2 9.650 - 3.800 73.340

D-10A SM -2 1.000 - 2.150 -4.300

DD-88A SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 2.700 - 0.150 -0.810

Wall-157 SM 2 4.250 - 3.800 32.300

Wall-160 SM 2 1.200 - 3.800 9.120

Wall-162 SM 2 1.800 - 3.800 13.680

D-10 SM -2 1.000 - 2.150 -4.300

Wall-163 SM 2 1.350 - 3.800 10.260

Wall-164 SM 2 2.750 - 3.800 20.900

Wall-168 SM 2 5.475 - 3.800 41.610

D/d of Drop Panel SM -2 1.050 - 0.150 -0.315

Wall-169 SM 2 27.224 - 3.800 206.902

DD-88A SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
190 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 2.150 -4.300

Wall-170 SM 2 5.250 3.800 39.900

Wall-175 SM 2 5.277 - 3.800 40.105

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-179 SM 2 2.679 - 3.800 20.360

Wall-180 SM 2 1.700 - 3.800 12.920

Wall-195 SM 2 24.599 - 3.800 186.952

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
191 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-196 SM 2 9.650 - 3.800 73.340

Wall-197 SM 2 4.700 - 3.800 35.720

Wall-198 SM 2 4.550 - 3.800 34.580

Wall-199 SM 2 5.350 - 3.800 40.660

D/d of Drop Panel SM -2 1.300 - 0.150 -0.390

Wall-200 SM 2 2.400 - 3.800 18.240

Wall-201 SM 2 2.700 - 3.800 20.520

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-202 SM 2 1.050 - 3.800 7.980

Wall-203 SM 2 3.817 - 3.800 29.009

D/d of Drop Panel SM -2 0.767 - 0.150 -0.230

Wall-204 SM 2 16.750 - 3.800 127.300

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-205 SM 2 4.817 - 3.800 36.609

D-9A SM -2 0.900 - 2.150 -3.870

Wall-225 SM 2 4.850 - 3.800 36.860

Wall-240 SM 2 4.650 - 3.800 35.340

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
192 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-241 SM 2 7.300 - 3.800 55.480

Wall-242 SM 2 21.801 - 3.800 165.688

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-243 SM 2 7.219 - 3.800 54.864

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-244 SM 2 1.950 - 3.800 14.820

Wall-247 SM 2 0.200 - 3.800 1.520

Wall-252 SM 2 2.100 - 3.800 15.960

Wall-253 SM 2 4.550 - 3.800 34.580

Wall-255 SM 2 1.100 - 3.800 8.360

Wall-256 SM 2 7.150 - 3.800 54.340

D-10A SM -2 1.000 - 2.150 -4.300

Wall-257 SM 2 2.000 - 3.800 15.200

D-10A SM -2 1.000 - 2.150 -4.300

Wall-258 SM 2 2.000 - 3.800 15.200

Wall-259 SM 2 2.700 - 3.800 20.520

Wall-260 SM 2 8.600 - 3.800 65.360

D/d of Window SM -2 0.900 - 1.000 -1.800

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
193 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300

Wall-261 SM 2 2.750 - 3.800 20.900

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-261A SM 2 7.300 - 3.800 55.480

Wall-262 SM 2 3.075 - 3.800 23.370

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-263 SM 2 2.750 - 3.800 20.900

Wall-264 SM 2 3.000 - 3.800 22.800

Wall-265 SM 2 2.750 - 3.800 20.900

Wall-266 SM 2 7.300 - 3.800 55.480

Wall-267 SM 2 0.800 - 3.800 6.080

Wall-277 SM 2 4.174 - 3.800 31.722

Wall-278 SM 2 4.129 - 3.800 31.380

Wall-280 SM 2 3.587 - 3.800 27.261

D-9B SM -2 0.900 - 2.150 -3.870

Wall-281 SM 2 7.749 - 3.800 58.892

D-9B SM -2 0.900 - 2.150 -3.870

Wall-282 SM 2 1.150 - 3.800 8.740

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
194 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-283 SM 2 1.252 - 3.800 9.515

Wall-284 SM 2 1.723 - 3.800 13.095

Wall-285 SM 2 1.433 - 3.800 10.891

Wall-286 SM 2 24.600 - 3.800 186.960

DD-88A SM -2 1.600 - 2.150 -6.880

GD-1 SM -2 2.200 - 2.150 -9.460

Wall-287 SM 2 2.975 - 3.800 22.610

Wall-288 SM 2 2.950 - 3.800 22.420

D-9A SM -2 0.900 - 2.150 -3.870

Wall-289 SM 2 4.675 - 3.800 35.530

Wall-290 SM 2 5.075 - 3.800 38.570

Wall-291 SM 2 7.500 - 3.800 57.000

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-292 SM 2 6.919 - 3.800 52.584

D-9A SM -2 0.900 - 2.150 -3.870

D-9 SM -2 0.900 - 2.150 -3.870

Wall-293 SM 2 13.952 - 3.800 106.035

DD-88A SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
195 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9 SM -2 0.900 - 2.150 -3.870

Wall-294 SM 2 2.675 - 3.800 20.330

Wall-295 SM 2 8.150 - 3.800 61.940

Wall-298 SM 2 5.125 - 3.800 38.950

Wall-301 SM 2 3.850 - 3.800 29.260

Wall-305 SM 2 7.875 - 3.800 59.850

Wall-306 SM 2 7.450 - 3.800 56.620

Wall-307 SM 2 13.952 - 3.800 106.035

D-9 SM -2 0.900 - 2.150 -3.870

GD-4 SM -2 0.900 - 2.150 -3.870

Wall-308 SM 2 3.110 - 3.800 23.636

D-9A SM -2 0.900 - 2.150 -3.870

Wall-309 SM 2 5.475 - 3.800 41.610

Wall-310 Missing

Wall-313 SM 2 5.475 - 3.800 41.610

D-9B SM -2 0.900 - 2.150 -3.870

Wall-314 SM 2 4.340 - 3.800 32.984

D-9B SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
196 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-317 SM 2 4.875 - 3.800 37.050

D-9A SM -2 0.900 - 2.150 -3.870

Wall-318 SM 2 7.500 - 3.800 57.000

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-322 SM 2 6.000 - 3.800 45.600

Wall-323 SM 2 5.400 - 3.800 41.040

Wall-324 SM 2 1.000 - 3.800 7.600

Wall-325 SM 2 7.300 - 3.800 55.480

D-9A SM -2 0.900 - 2.150 -3.870

Wall-326 SM 2 5.400 - 3.800 41.040

Wall-327 SM 2 4.900 - 3.800 37.240

Wall-328 SM 2 5.075 - 3.800 38.570

D-9A SM -2 0.900 - 2.150 -3.870

D-10A SM -2 1.000 - 2.150 -4.300

Wall-329 Missing

Wall-330 SM 2 5.250 - 3.800 39.900

Wall-331 SM 2 3.600 - 3.800 27.360

Wall-332 SM 2 2.500 - 3.800 19.000

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
197 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-333 SM 2 5.250 - 3.800 39.900

Wall-334 SM 2 2.200 - 3.800 16.720

Wall-335 SM 2 5.150 - 3.800 39.140

D-10A SM -2 1.000 - 2.150 -4.300

Wall-336 SM 2 2.200 - 3.800 16.720

Wall-339 SM 2 5.400 - 3.800 41.040

Wall-340 SM 2 8.600 - 3.800 65.360

D-9A SM -2 0.900 - 2.150 -3.870

Wall-341 SM 2 4.900 - 3.800 37.240

Wall-342 SM 2 24.800 - 3.800 188.480

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-344 SM 2 2.560 - 3.800 19.456

D-10A SM -2 1.000 - 2.150 -4.300

Wall-345 SM 2 0.800 - 3.800 6.080

Wall-346 SM 2 11.360 - 3.800 86.336

Wall-352 SM 2 2.400 - 4.650 22.320

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-354 SM 2 1.900 - 3.800 14.440

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
198 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300

Wall-357 SM 2 11.510 - 3.800 87.476

DD-88A SM -2 1.600 - 2.150 -6.880

D-9A SM -2 0.900 - 2.150 -3.870

Wall-358 SM 2 2.365 - 3.800 17.974

Wall-359 SM 2 5.150 - 3.800 39.140

Wall-360 SM 2 3.015 - 3.800 22.914

Wall-362 SM 2 2.600 - 3.800 19.760

Wall-363 SM 2 3.000 - 3.800 22.800

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-370 SM 2 3.000 - 3.800 22.800

D-9A SM -2 0.900 - 2.150 -3.870

Wall-371 SM 2 0.900 - 3.800 6.840

Wall-372 SM 2 2.549 - 3.800 19.372

D/d of Drop Panel SM -2 0.950 - 3.800 -7.220

Wall-373 SM 2 1.400 - 3.800 10.640

D-9A SM -2 0.900 - 2.150 -3.870

Wall-374 SM 2 1.550 - 3.800 11.780

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
199 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 -3.870

Wall-375 SM 2 24.449 - 3.800 185.812

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-376 SM 2 2.250 - 3.800 17.100

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-377 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-378 SM 2 3.000 - 3.800 22.800

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-379 SM 2 3.000 - 3.800 22.800

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-380 SM 2 2.500 - 3.800 19.000

DD-99B SM -2 1.800 - 2.150 -7.740

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-381 SM 2 4.650 - 3.800 35.340

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-383 SM 2 7.377 - 3.800 56.065

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
200 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88B SM -2 1.600 - 2.150 -6.880

D-9B SM -2 0.900 - 2.150 -3.870

Wall-384 SM 2 2.500 - 3.800 19.000

D-9B SM -2 0.900 - 2.150 -3.870

Wall-385 SM 2 4.650 - 3.800 35.340

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-386 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-387 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-388 SM 2 7.302 - 3.800 55.495

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-389 SM 2 4.650 - 3.800 35.340

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-390 SM 2 2.825 - 3.800 21.470

DD-88B SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
201 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-391 SM 2 5.251 - 3.800 39.908

Wall-392 SM 2 1.200 - 3.800 9.120

Wall-397 SM 2 1.479 - 3.800 11.240

Wall-398 SM 2 1.479 - 3.800 11.240

Wall-401 SM 2 3.751 - 3.800 28.508

Wall-402 SM 2 2.149 - 3.800 16.332

D/d of Drop Panel SM -2 0.600 - 0.150 -0.180

Wall-405 SM 2 1.000 - 3.800 7.600

Wall-406 SM 2 29.425 - 3.800 223.630

D/d of Opening SM -2 2.475 - 3.800 -18.810

D/d of Opening SM -2 1.200 - 3.800 -9.120

D/d of Opening SM -2 1.000 - 3.800 -7.600

D/d of Opening SM -2 2.750 - 3.800 -20.900

DD-99B SM -2 1.800 - 2.150 -7.740

Wall-407 SM 2 5.251 - 3.800 39.908

Wall-411 SM 2 4.650 - 3.800 35.340

Wall-414 SM 2 4.649 - 3.800 35.332

Wall-415 SM 2 2.825 - 3.800 21.470

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
202 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD099B SM -2 1.800 - 2.150 -7.740

Wall-416 SM 2 7.299 - 3.800 55.472

Wall-417 SM 2 7.300 - 3.800 55.480

DD-99B SM -2 1.800 - 2.150 -7.740

D/d of Drop Panel SM 1350.000

Wall-418 SM 2 7.300 - 3.800 55.480

DD-99B SM -2 1.800 - 2.150 -7.740

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-419 SM 2 6.300 - 3.800 47.880

D-9A SM -2 0.900 - 2.150 -3.870

Wall-420 SM 2 2.155 - 3.800 16.378

Wall-421 SM 2 2.480 - 3.800 18.848

Wall-422 SM 2 5.350 - 3.800 40.660

Wall-423 SM 2 2.075 - 3.800 15.770

Wall-424 SM 2 2.400 - 3.800 18.240

Wall-425 SM 2 6.300 - 3.800 47.880

D-9A SM -2 0.900 - 2.150 -3.870

D-10A SM -2 1.000 - 2.150 -4.300

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
203 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-426 SM 2 2.400 - 3.800 18.240

Wall-427 SM 2 5.030 - 3.800 38.228

Wall-428 SM 2 29.275 - 3.800 222.490

DD-88A SM -2 1.600 - 2.150 -6.880

D/d of Opening SM -2 2.750 - 3.800 -20.900

D/d of Opening SM -2 2.550 - 3.800 -19.380

Wall-429 SM 2 4.649 - 3.800 35.332

Wall-430 SM 2 7.299 - 3.800 55.472

Wall-431 SM 2 4.650 - 3.800 35.340

Wall-432 SM 2 4.000 - 3.800 30.400

Missing 1350.000

Wall-434 SM 2 0.975 - 3.800 7.410

Wall-435 SM 2 0.975 - 3.800 7.410

Wall-436 SM 2 4.650 - 3.800 35.340

Wall-437 SM 2 0.975 - 3.800 7.410

Wall-438 SM 2 0.975 - 3.800 7.410

Wall-439 SM 2 15.401 - 3.800 117.048

DD-99C SM -2 1.800 - 2.150 -7.740

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
204 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

LD-93A SM -2 1.200 - 2.150 -5.160

D/d of Drop Panel SM -2 2.700 - 0.150 -0.810

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

D/d of Column SM -2 0.800 - 3.800 -6.080

Wall-440 SM 2 13.699 - 3.800 104.112

LD-93A SM -2 1.200 - 2.150 -5.160

LD-93 SM -2 1.200 - 2.150 -5.160

Wall-441 SM 2 4.725 - 3.800 35.910

D-9 SM -2 0.900 - 2.150 -3.870

Wall-442 SM 2 4.875 - 3.800 37.050

Wall-443 SM 2 2.650 - 3.800 20.140

Wall-444 SM 2 4.225 - 3.800 32.110

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-445 SM 2 0.900 - 3.800 6.840

Wall-446 SM 2 0.900 - 3.800 6.840

Wall-447 SM 2 3.975 - 3.800 30.210

Wall-448 SM 2 4.075 - 3.800 30.970

Wall-449 SM 2 0.600 - 3.800 4.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
205 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-450 SM 2 2.550 - 3.800 19.380

Wall-451 SM 2 2.401 - 3.800 18.248

Wall-452 SM 2 1.225 - 3.800 9.310

Wall-453 SM 2 0.453 - 3.800 3.443

Wall-454 SM 2 1.074 - 3.800 8.162

Wall-466 SM 2 1.050 - 3.800 7.980

Wall-473 SM 2 2.500 - 4.650 23.250

DD-88D SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-474 SM 2 2.750 - 3.800 20.900

D-9A SM -2 0.900 - 2.150 -3.870

Wall-475 SM 2 2.750 - 3.800 20.900

D-10 SM -2 1.000 - 2.150 -4.300

Wall-476 SM 2 7.950 - 3.800 60.420

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-477 SM 2 3.225 - 3.800 24.510

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

DD-88C SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
206 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-478 SM 2 27.701 - 3.800 210.528

LD-93A SM -2 1.200 - 2.150 -5.160

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-479 SM 2 5.801 - 3.800 44.088

Wall-480 SM 2 5.801 - 3.800 44.088

Wall-481 SM 2 5.151 - 3.800 39.148

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-482 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-483 SM 2 9.825 - 3.800 74.670

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-484 SM 2 0.925 - 3.800 7.030

D/d of Drop Panel SM -2 0.925 - 0.150 -0.278

Wall-485 SM 2 8.575 - 3.800 65.170

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-486 SM 2 0.925 - 3.800 7.030

D/d of Drop Panel SM -2 0.925 - 0.150 -0.278

Wall-487 SM 2 9.675 - 3.800 73.530

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
207 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d for Wall Portion SM -2 0.150 - 3.800 -1.140

Wall-488 SM 2 8.275 - 3.800 62.890

Wall-489 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-490 SM 2 9.675 - 3.800 73.530

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-491 SM 2 5.649 - 3.800 42.932

Wall-492 SM 2 0.925 - 3.800 7.030

D/d of Drop Panel SM -2 0.925 - 0.150 -0.278

Wall-493 SM 2 7.300 - 0.150 2.190

D/d of Drop Panel SM -2 0.925 - 0.150 -0.278

Wall-494 SM 2 5.349 - 3.800 40.652

Wall-495 SM 2 5.499 - 3.800 41.792

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-496 SM 2 40.409 - 3.800 307.108

D/d for Wall Portion SM -2 7.950 - 3.800 -60.420

DD-88A SM -2 1.600 - 2.150 -6.880

DD-88B SM -2 1.600 - 2.150 -6.880

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
208 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300

D-9A SM -2 0.900 - 2.150 -3.870

Wall-497 SM 2 7.300 - 3.800 55.480

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-499 SM 2 3.010 - 3.800 22.876

D-9A SM -2 0.900 - 2.150 -3.870

Wall-500 SM 2 3.825 - 3.800 29.070

D-9A SM -2 0.900 - 2.150 -3.870

Wall-504 SM 2 5.760 - 3.800 43.776

Wall-505 SM 2 5.750 - 3.800 43.700

Wall-509 SM 2 4.950 - 3.800 37.620

Wall-514 SM 2 4.940 - 3.800 37.544

Wall-515 SM 2 7.950 - 3.800 60.420

D/d for Wall Portion SM -2 2.500 - 3.800 -19.000

Wall-524 SM 2 1.400 - 3.800 10.640

D-9A SM -2 0.900 - 2.150 -3.870

Wall-525 SM 2 1.400 - 3.800 10.640

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
209 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 -3.870

Wall-526 SM 2 4.940 - 3.800 37.544

Wall-527 SM 2 2.950 - 3.800 22.420

Wall-528 SM 2 3.000 - 3.800 22.800

D-9 SM -2 0.900 - 2.150 -3.870

Wall-537 SM 2 5.266 - 3.800 40.022

Wall-538 SM 2 5.936 - 3.800 45.114

Wall-541 SM 2 5.116 - 3.800 38.882

Wall-542 SM 2 16.025 - 3.800 121.790

LD-93A SM -8 1.200 - 2.150 -20.640

Wall-543 SM 2 5.936 - 3.800 45.114

Wall-546 SM 2 3.251 - 3.800 24.708

Wall-547 SM 2 2.188 - 3.800 16.629

D-9 SM -2 0.900 - 2.150 -3.870

Wall-548 SM 2 2.650 - 3.800 20.140

DD-99C SM -2 1.800 - 2.150 -7.740

Wall-549 SM 2 4.975 - 3.800 37.810

Wall-551 SM 2 5.234 - 3.800 39.778

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
210 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9B SM -2 0.900 - 2.150 -3.870

D/d of Window SM -2 1.350 - 1.000 -2.700

Wall-553 SM 2 1.173 - 3.800 8.915

Wall-554 SM 2 1.008 - 3.800 7.661

Wall-556 SM 2 1.058 - 3.800 8.041

Wall-557 SM 2 1.008 - 3.800 7.661

Wall-560 SM 2 2.499 - 3.800 18.992

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-561 SM 2 3.150 - 3.800 23.940

Wall-562 SM 2 2.500 - 3.800 19.000

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

DD-88C SM -2 1.600 - 2.150 -6.880

Wall-563 SM 2 5.500 - 3.800 41.800

D-9A SM -2 0.900 - 2.150 -3.870

Wall-573 SM 2 7.080 - 3.800 53.808

Wall-581 SM 2 16.374 - 3.800 124.442

SD-16 SM -2 1.600 - 2.150 -6.880

Wall-584 SM 2 1.990 - 3.800 15.124

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
211 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 -3.870

Wall-586A SM 2 1.350 - 3.800 10.260

Wall-587 SM 2 1.950 - 3.800 14.820

SD-12 SM -2 0.900 - 2.150 -3.870

Wall-588 SM 2 1.250 - 3.800 9.500

Wall-590 SM 2 2.305 - 3.800 17.518

D-9A SM -2 0.900 - 2.150 -3.870

Wall-591 SM 2 3.050 - 3.800 23.180

D-9A SM -2 0.900 - 2.150 -3.870

Wall-592 SM 2 1.350 - 3.800 10.260

Wall-593 SM 2 1.600 - 3.800 12.160

Wall-594 SM 2 1.800 - 3.800 13.680

Wall-595 SM 2 1.800 - 3.800 13.680

Wall-596 SM 2 17.429 - 3.800 132.460

D-9A SM -2 0.900 - 2.150 -3.870

Wall-597 SM 2 3.800 - 3.800 28.880

Wall-598 SM 2 2.675 - 3.800 20.330

D-9A SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
212 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-599 SM 2 0.430 - 3.800 3.268

Wall-602 SM 2 3.000 - 3.800 22.800

Wall-604 SM 2 7.967 - 3.800 60.549

D-9A SM -6 0.900 - 2.150 -11.610

Wall-605 SM 2 1.110 - 3.800 8.436

Wall-606 SM 2 1.569 - 3.800 11.924

Wall-607 SM 2 5.500 - 3.800 41.800

Wall-609 SM 2 0.914 3.800 6.946

Wall-610 SM 2 4.700 3.800 35.720

D/d of Drop Panel SM -2 0.950 0.150 -0.285

Wall-611 SM 2 7.350 3.800 55.860

DD-88A SM -2 1.600 2.150 -6.880

D/d of Drop Panel SM -2 0.950 0.150 -0.285

Wall-618 SM 2 2.350 - 3.800 17.860

Wall-619 1238.000

Wall-620 SM 2 4.450 - 3.800 33.820

D-9 SM -2 0.900 - 2.150 -3.870

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-621 SM 2 4.450 - 3.800 33.820

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
213 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-622 SM 2 10.711 - 3.800 81.404

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-623 SM 2 0.566 - 3.800 4.302

D/d of Drop Panel SM -2 0.566 - 0.150 -0.170

Wall-624 SM 2 4.400 - 3.800 33.440

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-625 SM 2 4.650 - 3.800 35.340

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-628 SM 2 2.290 - 3.800 17.404

D-9A SM -2 0.900 - 2.150 -3.870

Wall-629 SM 2 4.490 - 3.800 34.124

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-630 SM 2 2.335 - 3.800 17.746

Wall-631 SM 2 5.735 - 3.800 43.586

LD-93 SM -2 1.200 - 2.150 -5.160

Wall-632 SM 2 0.260 - 3.800 1.976

Wall-633 SM 2 2.400 - 3.800 18.240

Wall-634 SM 2 3.150 - 3.800 23.940

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
214 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Window SM -2 1.350 - 1.000 -2.700

Wall-635 SM 2 1.117 - 3.800 8.489

Wall-636 SM 2 2.281 - 3.800 17.336

Wall-637 SM 2 1.781 - 3.800 13.536

Wall-638 SM 2 3.485 - 3.800 26.486

D-9 SM -2 0.900 - 2.150 -3.870

Wall-639 SM 2 6.250 - 3.800 47.500

D-9 SM -2 0.900 - 2.150 -3.870

Wall-640 SM 2 1.916 - 3.800 14.562

D-9 SM -2 0.900 - 2.150 -3.870

Wall-641 SM 2 1.045 - 3.800 7.942

Wall-642 SM 2 1.045 - 3.800 7.942

Wall-643 SM 2 2.258 - 3.800 17.161

Wall-644 SM 2 2.267 - 3.800 17.229

Wall-645 SM 2 7.000 - 3.800 53.200

Wall-646 SM 2 2.879 - 3.800 21.880

D-9 SM -2 0.900 - 2.150 -3.870

Wall-647 SM 2 4.450 - 3.800 33.820

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
215 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9 SM -2 0.900 - 2.150 -3.870

Wall-648 SM 2 3.218 - 3.800 24.457

D-9 SM -2 0.900 - 2.150 -3.870

Wall-649 SM 2 1.875 - 3.800 14.250

D-9 SM -2 0.900 - 2.150 -3.870

Wall-650 SM 2 2.267 - 3.800 17.229

Wall-651 SM 2 5.787 - 3.800 43.981

Wall-655 SM 2 4.951 - 3.800 37.628

Wall-656 SM 2 5.750 - 3.800 43.700

DD-88B SM -2 1.600 - 2.150 -6.880

Wall-657 SM 2 24.120 - 3.800 183.312

D-9A SM -2 0.900 - 2.150 -3.870

D-9 SM -2 0.900 - 2.150 -3.870

GD-3 SM -2 1.000 - 2.150 -4.300

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-658 SM 2 7.100 - 3.800 53.960

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-659 SM 2 2.850 - 3.800 21.660

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
216 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-660 SM 2 2.369 - 3.800 18.004

D-9 SM -2 0.900 - 2.150 -3.870

Wall-661 SM 2 2.250 - 3.800 17.100

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-662 SM 2 4.660 - 3.800 35.416

D-9 SM -2 0.900 - 2.150 -3.870

Wall-663 SM 2 5.290 - 3.800 40.204

LD-93 SM -2 1.200 - 2.150 -5.160

Wall-664 SM 2 1.582 - 3.800 12.023

D/d of Drop Panel SM -2 1.200 - 0.150 -0.360

Wall-665 SM 2 3.341 - 3.800 25.392

DD-99B SM -2 1.800 - 2.150 -7.740

D/d of Drop Panel SM -2 0.460 - 0.150 -0.138

Wall-666 SM 2 1.377 - 3.800 10.465

D/d of Drop Panel SM -2 1.377 - 0.150 -0.413

Wall-667 SM 2 4.583 - 3.800 34.831

DD-88 SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.890 - 0.150 -0.267

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
217 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-668 SM 2 1.091 - 3.800 8.292

Wall-669 SM 2 5.140 - 3.800 39.064

LD-93 SM -2 1.200 - 2.150 -5.160

Wall-670 SM 2 3.012 - 3.800 22.891

D/d of Window SM -2 1.350 - 1.000 -2.700

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-671 SM 2 7.100 - 3.800 53.960

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-677 SM 2 2.550 - 3.800 19.380

Wall-682 SM 2 3.145 - 3.800 23.902

Wall-683 SM 2 5.875 - 3.800 44.650

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-684 SM 2 2.464 - 3.800 18.726

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-685 SM 2 2.823 - 3.800 21.455

D-9A SM -2 0.900 - 2.150 -3.870

Wall-686 SM 2 5.907 - 3.800 44.893

D/d of Drop Panel SM -2 1.060 - 0.150 -0.318

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
218 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-687 SM 2 6.261 - 3.800 47.584

Wall-688 SM 2 2.474 - 3.800 18.802

D/d of Drop Panel SM 2 1.130 - 3.800 8.588

Wall-689 SM 2 1.315 - 3.800 9.994

Wall-690 SM 2 1.200 - 3.800 9.120

Wall-691 SM 2 1.050 - 3.800 7.980

Wall-692 SM 2 3.150 - 3.800 23.940

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-693 SM 2 1.511 - 3.800 11.484

D/d of Drop Panel SM -2 1.511 - 0.150 -0.453

Wall-694 SM 2 0.735 - 3.800 5.586

D/d of Drop Panel SM -2 0.735 - 0.150 -0.221

Wall-695 SM 2 1.000 - 3.800 7.600

D-9A SM -2 0.900 - 2.150 -3.870

Wall-696 SM 2 1.000 - 3.800 7.600

D-9A SM -2 0.900 - 2.150 -3.870

Wall-697 SM 2 3.847 - 3.800 29.237

D/d of Opening SM -2 1.200 - 3.800 -9.120

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
219 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-698 SM 2 5.950 - 3.800 45.220

Wall-699 SM 2 2.500 - 3.800 19.000

Wall-704 SM 2 7.994 - 3.800 60.754

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-707 SM 2 4.849 - 3.800 36.852

Wall-723 SM 2 8.810 - 3.800 66.956

Wall-724 SM 2 0.165 - 3.800 1.254

Wall-725 SM 2 7.850 - 0.200 3.140

Wall-726 SM 2 0.165 - 3.800 1.254

Wall-727 SM 2 0.165 - 3.800 1.254

Wall-728 SM 2 13.230 - 3.800 100.548

D-10 SM -2 1.000 - 2.150 -4.300

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-729 SM 2 0.165 - 3.800 1.254

Wall-730 SM 2 0.165 - 3.800 1.254

Wall-731 SM 2 39.150 - 0.200 15.660

D/d for Column SM 4 0.800 - 0.200 0.640

Wall-732 SM 2 0.165 - 0.200 0.066

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
220 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-733 SM 2 0.165 - 0.200 0.066

Wall-734 SM 2 4.430 - 3.800 33.668

Wall-735 SM 2 5.250 - 3.800 39.900

Wall-736 SM 2 2.050 - 3.800 15.580

Wall-737 SM 2 0.165 - 3.800 1.254

Wall-738 SM 2 0.165 - 3.800 1.254

Wall-739 SM 2 4.760 - 3.800 36.176

Wall-740 SM 2 2.050 - 3.800 15.580

Wall-741 SM 2 0.165 - 3.800 1.254

Wall-742 SM 2 0.165 - 3.800 1.254

Wall-743 SM 2 6.750 - 0.200 2.700

Wall-744 SM 2 0.165 - 3.800 1.254

Wall-745 SM 2 2.500 - 3.800 19.000

D-10 SM 2 1.000 - 2.150 4.300

Wall-746 SM 2 4.390 - 3.800 33.364

Wall-768 SM 2 1.450 - 3.800 11.020

Wall-769 SM 2 1.750 - 3.800 13.300

Wall-776 SM 2 3.250 - 3.800 24.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
221 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-9A SM -2 0.900 - 2.150 -3.870

Wall-778 SM 2 2.390 - 3.800 18.164

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

DD-88 SM -2 1.600 - 2.150 -6.880

Wall-785 SM 2 17.020 - 3.800 129.352

DD-88A SM -2 1.600 - 2.150 -6.880

D-9A SM -2 0.900 - 2.150 -3.870

D-10 SM -2 1.000 - 2.150 -4.300

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
222 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-796 SM 2 2.510 - 3.800 19.076

DD-88B SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-798 SM 2 4.000 - 3.800 30.400

Wall-802 SM 2 4.930 - 3.800 37.468

D-9A SM -2 0.900 - 2.150 -3.870

Wall-803 SM 2 1.780 - 3.800 13.528

Wall-808 SM 2 4.930 - 3.800 37.468

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-809 SM 2 7.091 - 3.800 53.892

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-812 SM 2 3.610 - 3.800 27.436

Wall-813 SM 2 8.001 - 3.800 60.808

D-9A SM -2 0.900 - 2.150 -3.870

Wall-814 SM 2 1.250 - 3.800 9.500

D-75 SM -2 0.750 - 2.150 -3.225

Wall-816 Missing 1632.000

Wall-818 SM 2 1.250 - 3.800 9.500

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
223 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-75 SM -2 0.750 - 2.150 -3.225

Wall-819 SM 2 2.750 - 3.800 20.900

D/d of Opening SM -2 1.450 - 3.800 -11.022

Wall-820 SM 2 2.205 - 3.800 16.758

GD-2 SM -2 1.200 - 2.150 -5.160

Wall-821 SM 2 0.461 - 3.800 3.504

Wall-822 SM 2 0.267 - 3.800 2.029

Wall-824 SM 2 0.175 - 3.800 1.330

Qty Ground Floor= 18,479.674

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
224 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

First Floor

H = 9.825-6.225-0.225 = 3.375

Wall-3 SM 2 1.449 - 2.600 7.535

Wall-4 SM 2 4.550 - 2.600 23.660

Wall-5 SM 2 3.800 - 2.600 19.760

Wall-7 SM 2 4.395 - 2.600 22.854

Wall-9 SM 2 3.801 - 2.600 19.765

Wall-10 SM 2 17.500 - 2.600 91.000

G-D3 SM -8 1.090 - 2.150 -18.748

Wall-11 SM 2 0.577 - 2.600 3.000

Wall-12 SM 2 0.625 - 2.600 3.250

Wall-15 SM 2 1.396 - 2.600 7.259

Wall-15B SM 2 0.750 - 2.600 3.900

Wall-18 SM 2 11.685 - 2.600 60.762

D-9A SM -2 0.900 - 2.150 -3.870

D-10 SM -2 1.000 - 2.150 -4.300

Wall-19 SM 2 4.399 - 2.600 22.875

Wall-21 SM 2 1.625 - 2.600 8.450

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
225 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-22 SM 2 1.475 - 2.600 7.670

Wall-23 SM 2 4.525 - 2.600 23.530

D-75 SM -3 0.750 - 2.150 -4.838

Wall-24 SM 2 1.475 - 2.600 7.670

Wall-25 SM 2 8.875 - 2.600 46.150

Wall-26 SM 2 3.300 - 2.600 17.160

D-10 SM -2 1.000 - 2.150 -4.300

Wall-29 SM 2 1.475 - 2.600 7.670

Wall-30 SM 2 1.475 - 2.600 7.670

Wall-31 SM 2 1.475 - 2.600 7.670

Wall-32 SM 2 4.675 - 2.600 24.310

D-75 SM -3 0.750 - 2.150 -4.838

Wall-33 SM 2 8.600 - 2.600 44.720

Wall-35 SM 2 3.300 - 2.600 17.160

D-10 SM -2 1.000 - 2.150 -4.300

Wall-37 SM 2 4.916 - 2.600 25.563

G-D3 SM -2 1.090 - 2.150 -4.687

D/d of Opening SM -2 2.827 - 2.600 -14.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
226 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-38 SM 2 11.700 - 2.600 60.840

D-10 SM -2 1.000 - 2.150 -4.300

Wall-43 SM 2 3.150 - 2.600 16.380

Wall-45 SM 2 0.562 - 2.600 2.922

Wall-46 SM 2 1.600 - 2.600 8.320

G-D3 SM -2 1.090 - 2.150 -4.687

Wall-51 SM 2 4.400 - 2.600 22.880

Wall-53 SM 2 1.861 - 2.600 9.677

Wall-62 SM 2 3.750 - 2.600 19.500

Wall-64 SM 2 2.500 - 2.600 13.000

Wall-65 SM 2 1.565 - 2.600 8.138

Wall-66 SM 2 5.450 - 2.600 28.340

Wall-67 SM 2 4.550 - 2.600 23.660

Wall-72 SM 2 2.700 - 2.600 14.040

Wall-73 SM 2 3.050 - 2.600 15.860

Wall-74 SM 2 3.050 - 2.600 15.860

Wall-75 SM 2 2.700 - 2.600 14.040

Wall-76 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
227 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Opening SM -2 3.858 - 2.600 -20.062

Wall-86 SM 2 2.025 - 2.600 10.530

Wall-87 SM 2 6.050 - 2.600 31.460

D-9A SM -2 0.900 - 2.150 -3.870

Wall-89 SM 2 4.625 - 2.600 24.050

Wall-91 SM 2 6.850 - 2.600 35.620

DD-88A SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-92 SM 2 3.000 - 2.600 15.600

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-98 SM 2 3.000 - 2.600 15.600

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-99 SM 2 4.625 - 2.600 24.050

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-100 SM 2 3.000 - 2.600 15.600

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-101 SM 2 4.625 - 2.600 24.050

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
228 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-105 SM 2 3.000 - 2.600 15.600

Wall-107 SM 2 2.652 - 2.600 13.790

Wall-111 SM 2 34.900 - 2.600 181.480

DD-88A SM -2 1.600 - 2.150 -6.880

DD-88C SM -2 1.600 - 2.150 -6.880

Wall-115 SM 2 4.500 - 2.600 23.400

Wall-118 SM 2 7.300 - 2.600 37.960

Wall-125 SM 2 4.500 - 2.600 23.400

Wall-127 SM 2 4.500 - 2.600 23.400

Wall-135 SM 2 5.250 - 2.600 27.300

Wall-137 SM 2 4.650 - 2.600 24.180

Wall-143 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-147 SM 2 5.250 - 2.600 27.300

Wall-150 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-152 SM 2 8.550 - 2.600 44.460

Wall-153 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
229 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

G-D1 SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.950 - 0.150 -0.285

Wall-154 SM 2 3.000 - 2.600 15.600

D-9A SM -2 0.900 - 2.150 -3.870

Wall-155 SM 2 4.400 - 2.600 22.880

D-9A SM -2 0.900 - 2.150 -3.870

Wall-157 SM 2 2.650 - 2.600 13.780

Wall-168 SM 2 5.510 - 2.600 28.652

Wall-169 SM 2 18.550 - 2.600 96.460

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-171 SM 2 2.630 - 2.600 13.676

Wall-174 SM 2 2.330 - 2.600 12.116

Wall-176 SM 2 0.300 - 2.600 1.560

Wall-177 SM 2 0.300 - 2.600 1.560

Wall-180 SM 2 0.300 - 2.600 1.560

Wall-181 SM 2 0.300 - 2.600 1.560

Wall-182 SM 2 0.300 - 2.600 1.560

Wall-183 SM 2 0.300 - 2.600 1.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
230 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-185 SM 2 2.330 - 2.600 12.116

Wall-187 SM 2 2.330 - 2.600 12.116

Wall-188 SM 2 0.450 - 2.600 2.340

Wall-189 SM 2 0.450 - 2.600 2.340

Wall-192 SM 2 0.300 - 2.600 1.560

Wall-193 SM 2 0.300 - 2.600 1.560

Wall-194 SM 2 0.300 - 2.600 1.560

Wall-195 SM 2 0.300 - 2.600 1.560

Wall-196 SM 2 2.630 - 2.600 13.676

Wall-197 SM 2 2.630 - 2.600 13.676

Wall-198 SM 2 2.630 - 2.600 13.676

Wall-199 SM 2 0.300 - 2.600 1.560

Wall-200 SM 2 0.300 - 2.600 1.560

Wall-201 SM 2 0.300 - 2.600 1.560

Wall-204 SM 2 0.300 - 2.600 1.560

Wall-205 SM 2 0.300 - 2.600 1.560

Wall-206 SM 2 2.630 - 2.600 13.676

Wall-207 SM 2 0.300 - 2.600 1.560

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
231 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-208 SM 2 2.630 - 2.600 13.676

Wall-252 SM 2 7.190 - 2.600 37.388

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-253 SM 2 2.110 - 2.600 10.972

Wall-254 SM 2 3.250 - 2.600 16.900

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-258 SM 2 3.250 - 2.600 16.900

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-259 SM 2 2.110 - 2.600 10.972

Wall-260 SM 2 4.900 - 2.600 25.480

Wall-262 SM 2 0.685 - 2.600 3.562

Wall-263 SM 2 8.720 - 2.600 45.344

D-9A SM -2 0.900 - 2.150 (3.870)

D-10A SM -2 1.000 - 2.150 (4.300)

Wall-264 SM 2 4.801 - 2.600 24.965

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-265 SM 2 7.100 - 2.600 36.920

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
232 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-266 SM 2 3.100 - 2.600 16.120

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-267 SM 2 1.350 - 2.600 7.020

D/d of Window SM -2 1.020 - 1.000 (2.040)

Wall-268 SM 2 1.600 - 2.600 8.320

Wall-269 SM 2 1.450 - 2.600 7.540

Wall-272 SM 2 4.150 - 2.600 21.580

Wall-273 SM 2 5.850 - 2.600 30.420

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-274 SM 2 2.450 - 2.600 12.740

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-275 SM 2 3.300 - 2.600 17.160

Wall-276 SM 2 2.450 - 2.600 12.740

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-277 SM 2 3.300 - 2.600 17.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
233 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-278 SM 2 1.300 - 2.600 6.760

D-10 SM -2 1.000 - 2.150 (4.300)

Wall-280 SM 2 16.851 - 2.600 87.625

SD-11 SM -4 1.100 - 2.150 (9.460)

Wall-281 SM 2 16.851 - 2.600 87.625

SD-10 SM -2 1.000 - 2.150 (4.300)

SD-11 SM -2 1.100 - 2.150 (4.730)

Wall-282 SM 2 3.050 - 2.600 15.860

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-283 SM 2 3.475 - 2.600 18.070

Wall-284 SM 2 3.050 - 2.600 15.860

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-285 SM 2 3.475 - 2.600 18.070

Wall-286 SM 2 4.801 - 2.600 24.965

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-287 SM 2 17.001 - 2.600 88.405

D-12 SM -4 1.200 - 2.150 (10.320)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
234 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-288 SM 2 7.000 - 2.600 36.400

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-289 SM 2 3.099 - 2.600 16.115

D-12 SM -2 1.200 - 2.150 (5.160)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-290 SM 2 9.000 - 2.600 46.800

Wall-293 SM 2 1.449 - 2.600 7.535

Wall-294 SM 2 1.500 - 2.600 7.800

Wall-295 SM 2 1.449 - 2.600 7.535

Wall-296 SM 2 1.500 - 2.600 7.800

Wall-297 SM 2 29.950 - 2.600 155.740

D-9A SM -3 0.900 - 2.150 (5.805)

D-10A SM -2 1.000 - 2.150 (4.300)

D-9 SM -3 0.900 - 2.150 (5.805)

Wall-298 SM 2 3.000 - 2.600 15.600

Wall-299 SM 2 3.000 - 2.600 15.600

Wall-300 SM 2 3.000 - 2.600 15.600

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
235 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-301 SM 2 3.000 - 2.600 15.600

Wall-304 SM 2 1.300 - 2.600 6.760

D-10 SM -2 1.000 - 2.150 (4.300)

Wall-305 SM 2 15.951 - 2.600 82.945

SD-11 SM -3 1.100 - 2.150 (7.095)

Wall-306 SM 2 17.151 - 2.600 89.185

SD-11 SM -4 1.100 - 2.150 (9.460)

Wall-308 SM 2 3.550 - 2.600 18.460

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-309 SM 2 0.850 - 2.600 4.420

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-310 SM 2 1.700 - 2.600 8.840

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-311 SM 2 3.550 - 2.600 18.460

Wall-312 SM 2 0.850 - 2.600 4.420

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-313 SM 2 1.650 - 2.600 8.580

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
236 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-314 SM 2 3.550 - 2.600 18.460

Wall-316 SM 2 15.951 - 2.600 82.945

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-317 SM 2 15.951 - 2.600 82.945

D-12 SM -6 1.200 - 2.150 (15.480)

Wall-318 SM 2 2.650 - 2.600 13.780

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-320 SM 2 1.400 - 2.600 7.280

Wall-324 SM 2 4.050 - 2.600 21.060

Wall-325 SM 2 2.650 - 2.600 13.780

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-326 SM 2 1.450 - 2.600 7.540

Wall-327 SM 2 1.500 - 2.600 7.800

Wall-328 SM 2 1.800 - 2.600 9.360

D-10 SM -2 1.000 - 2.150 (4.300)

Wall-329 SM 2 4.300 - 2.600 22.360

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-330 SM 2 3.300 - 2.600 17.160

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
237 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.950 - 0.150 (0.285)

Wall-331 SM 2 4.150 - 2.600 21.580

Wall-332 SM 2 1.950 - 2.600 10.140

Wall-333 SM 2 1.500 - 2.600 7.800

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-334 SM 2 2.250 - 2.600 11.700

Wall-334A SM 2 1.900 - 2.600 9.880

Wall-335 SM 2 13.350 - 2.600 69.420

D/d for Column SM -2 1.000 - 2.600 (5.200)

D-10 SM -2 1.000 - 2.150 (4.300)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

D/d of Drop Panel SM -2 0.750 - 0.150 (0.225)

Wall-336 SM 2 7.100 - 2.600 36.920

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

D/d of Drop Panel SM -2 0.800 - 0.150 (0.240)

Wall-340 SM 2 6.900 - 2.600 35.880

D/d for Door SM -2 1.600 - 2.150 (6.880)

Wall-341 SM 2 7.091 - 2.600 36.873

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
238 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

DD-88B SM -2 1.600 - 2.150 (6.880)

Wall-342 SM 2 2.300 - 2.600 11.960

DD-88 SM -2 1.600 - 2.150 (6.880)

Wall-343 SM 2 4.200 - 2.600 21.840

Wall-344 SM 2 4.200 - 2.600 21.840

Wall-345 SM 2 2.300 - 2.600 11.960

D-10A SM -2 1.000 - 2.150 (4.300)

Wall-359 SM 2 5.875 - 2.600 30.550

DD-99 SM -2 1.800 - 2.150 (7.740)

Wall-360 SM 2 3.830 - 2.600 19.916

Wall-361 SM 2 7.374 - 2.600 38.345

DD-99B SM -2 1.800 - 2.150 (7.740)

Wall-362 SM 2 14.653 - 2.600 76.196

D/d of Drop Panel SM -2 2.750 - 0.150 (0.825)

Wall-363 SM 2 1.239 - 2.600 6.443

D/d of Drop Panel SM -2 1.239 - 0.150 (0.372)

D/d for Column SM -2 0.600 - 2.600 (3.120)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
239 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-364 SM 2 1.714 - 2.600 8.913

D/d of Drop Panel SM 2 1.714 - 0.150 0.514

Wall-365 SM 2 1.239 - 2.600 6.443

D/d of Drop Panel SM -2 1.239 - 0.150 (0.372)

Wall-366 SM 2 3.688 - 2.600 19.178

D-9A SM -2 0.900 - 2.150 (3.870)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-367 SM 2 12.021 - 2.600 62.509

Wall-370 SM 2 7.301 - 2.600 37.965

Wall-371 SM 2 5.246 - 2.600 27.279

Wall-372 SM 2 7.000 - 2.600 36.400

D-9A SM -2 0.900 - 2.150 (3.870)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-374 SM 2 7.605 - 2.600 39.546

Wall-375 SM 2 4.700 - 2.600 24.440

Wall-376 SM 2 0.928 - 2.600 4.826

Wall-383 SM 2 7.363 - 2.600 38.288

DD-88A SM -2 1.600 - 2.150 (6.880)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
240 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-387 SM 2 5.835 - 2.600 30.342

Wall-392 SM 2 5.835 - 2.600 30.342

DD-88B SM -2 1.600 - 2.150 (6.880)

Wall-393 SM 2 17.875 - 2.600 92.950

D-10 SM -2 1.000 - 2.150 (4.300)

DD-88A SM -2 1.600 - 2.150 (6.880)

G-D3 SM -2 1.100 - 2.150 (4.730)

Wall-395 SM 2 3.300 - 2.600 17.160

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-397 SM 2 1.951 - 2.600 10.145

Wall-398 SM 2 2.250 - 2.600 11.700

Wall-399 SM 2 1.426 - 2.600 7.415

Wall-400 SM 2 1.426 - 2.600 7.415

Wall-401 SM 2 1.426 - 2.600 7.415

Wall-402 SM 2 6.400 - 2.600 33.280

Wall-403 SM 2 1.951 - 2.600 10.145

Wall-404 SM 2 1.576 - 2.600 8.195

Wall-405 SM 2 1.426 - 2.600 7.415

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
241 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-406 SM 2 1.426 - 2.600 7.415

Wall-407 SM 2 7.000 - 2.600 36.400

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

D/d of Drop Panel SM -2 0.750 - 0.150 (0.225)

Wall-408 SM 2 3.300 - 2.600 17.160

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-409 SM 2 7.100 - 2.600 36.920

D-9A SM -2 0.900 - 2.150 (3.870)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-410 SM 2 4.850 - 2.600 25.220

Wall-411 SM 2 5.835 - 2.600 30.342

Wall-412 SM 2 4.000 - 2.600 20.800

D-10 SM -2 1.000 - 2.150 (4.300)

Wall-413 SM 2 7.100 - 2.600 36.920

D-9A SM -2 0.900 - 2.150 (3.870)

D/d of Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-414 SM 2 3.300 - 2.600 17.160

D-75 SM -2 0.750 - 2.150 (3.225)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
242 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-415 SM 2 2.205 - 2.600 11.466

Wall-416 SM 2 1.575 - 2.600 8.190

Wall-417 SM 2 1.425 - 2.600 7.410

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
243 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-418 SM 2 1.425 - 2.600 7.410

Wall-420 SM 2 5.763 - 2.600 29.968

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-421 SM 2 1.578 - 2.600 8.206

Wall-422 SM 2 1.426 - 2.600 7.415

Wall-423 SM 2 1.426 - 2.600 7.415

Wall-424 SM 2 1.725 - 2.600 8.970

Qty First Floor= 4,503.555

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
244 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Second Floor

H = 13.425-9.828-0.225 = 3.375

Wall-96 SM 2 5.787 - 2.600 30.092

Wall-97 SM 2 5.386 - 2.600 28.007

DD-88A SM -2 1.600 - 2.150 -6.880

D/d of Wndow SM -2 3.000 - 1.500 -9.000

Wall-99 SM 2 6.408 - 2.600 33.322

D/d of Wndow SM -2 4.000 - 1.500 -12.000

D-10 SM -2 1.000 - 2.150 -4.300

Wall-100 SM 2 3.436 - 2.600 17.867

D-10 SM -2 1.000 - 2.150 -4.300

Wall-103 SM 2 4.000 - 2.600 20.800

D/d of Wndow SM -2 4.000 - 1.500 -12.000

Wall-104 SM 2 2.638 - 2.600 13.718

D-10 SM -2 1.000 - 2.150 -4.300

Wall-117 SM 2 3.650 - 2.600 18.980

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-118 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
245 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-119 SM -2 4.613 - 2.600 -23.988

Wall-120 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-121 SM 2 6.600 - 2.600 34.320

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-123 SM 2 0.850 - 2.600 4.420

Wall-124 SM 2 1.400 - 2.600 7.280

Wall-127 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-128 SM 2 4.613 - 2.600 23.988

Wall-129 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-130 SM 2 6.600 - 2.600 34.320

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-132 SM 2 0.850 - 2.600 4.420

Wall-133 SM 2 1.400 - 2.600 7.280

Wall-136 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-137 SM 2 4.613 - 2.600 23.988

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
246 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-138 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-139 SM 2 6.200 - 2.600 32.240

ID-21 SM -2 2.100 - 2.100 -8.820

D-9A SM -2 0.900 - 2.150 -3.870

Wall-141 SM 2 1.400 - 2.600 7.280

Wall-143 SM 2 2.850 - 2.600 14.820

Wall-156 SM 2 3.135 - 2.600 16.302

Wall-158 SM 2 4.623 - 2.600 24.040

Wall-159 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-160 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-161 SM 2 2.640 - 2.600 13.728

Wall-163 SM 2 6.600 - 2.600 34.320

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-166 SM 2 4.623 - 2.600 24.040

Wall-167 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
247 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-168 SM 2 1.042 - 2.600 5.418

D/d of Wndow SM -2 0.725 - 1.100 -1.595

Wall-170 SM 2 2.390 - 2.600 12.428

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-173 SM 2 4.540 - 2.600 23.608

Wall-175 SM 2 5.360 - 2.600 27.872

Wall-176 SM 2 5.360 - 2.600 27.872

Wall-177 SM 2 19.575 - 2.600 101.790

D-9A SM -2 0.900 - 2.150 -3.870

ID-21 SM -2 2.100 - 2.150 -9.030

D/d of Wall SM -2 2.700 - 2.600 -14.040

Wall-179 SM 2 1.155 - 2.600 6.006

D-9B SM -2 0.900 - 2.150 -3.870

Wall-184 SM 2 3.000 - 2.600 15.600

Wall-185 SM 2 1.160 - 2.600 6.032

Wall-191 SM 2 4.540 - 2.600 23.608

Wall-196 SM 2 2.500 - 2.600 13.000

Wall-197 SM 2 3.149 - 2.600 16.375

Wall-198 SM 2 5.650 - 2.600 29.380

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
248 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-199 SM 2 3.149 - 2.600 16.375

Wall-209 SM 2 1.033 - 2.600 5.372

Wall-214 SM 2 5.749 - 2.600 29.895

D-10A SM -2 1.000 - 2.150 -4.300

Wall-215 SM 2 1.616 - 2.625 8.484

D-10 SM -2 1.000 - 2.150 -4.300

Wall-218 SM 2 5.149 - 2.625 27.032

Wall-219 SM 2 16.385 - 2.600 85.202

Wall-224 SM 2 7.300 - 2.600 37.960

Wall-225 SM 2 7.190 - 2.600 37.388

D/d of Drop Panel SM -2 0.950 - 0.200 -0.380

Wall-227 SM 2 1.350 - 2.600 7.020

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-228 SM 2 1.185 - 2.600 6.162

D-10A SM -2 1.000 - 2.150 -4.300

Wall-229 SM 2 1.635 - 2.600 8.502

D-10A SM -2 1.000 - 2.150 -4.300

Wall-230 SM 2 0.520 - 2.600 2.704

D/d of Drop Panel SM -2 0.520 - 0.200 -0.208

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
249 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-231 SM 2 3.322 - 2.600 17.274

D/d of Drop Panel SM -2 1.187 - 0.200 -0.475

Wall-232 SM 2 8.818 - 2.600 45.854

D-10 SM -2 1.000 - 2.150 -4.300

Wall-233 SM 2 4.025 - 2.600 20.930

Wall-234 SM 2 2.336 - 2.600 12.147

D-10A SM -2 1.000 - 2.150 -4.300

Wall-235 SM 2 4.680 - 2.600 24.336

Wall-236 SM 2 4.025 - 2.600 20.930

Wall-237 SM 2 4.275 - 2.600 22.230

Wall-238 SM 2 3.950 - 2.600 20.540

D-10A SM -2 1.000 - 2.150 -4.300

Wall-239 SM 2 8.275 - 2.600 43.030

D/d for Beam Portion SM -2 1.414 - 0.525 -1.485

Wall-240 SM 2 7.983 - 2.600 41.512

D-10 SM -2 1.000 - 2.150 -4.300

D/d of Window SM -2 0.900 - 1.500 -2.700

DD-99 SM -2 1.800 - 2.150 -7.740

D/d of Drop Panel SM -2 0.950 - 0.200 -0.380

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
250 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-241 SM 2 2.679 - 2.600 13.931

D/d for Beam Portion SM -2 1.414 - 0.525 -1.485

Wall-242 SM 2 8.275 - 2.600 43.030

D-10 SM -2 1.000 - 2.150 -4.300

D/d for Beam Portion SM -2 1.414 - 0.525 -1.485

Wall-243 SM 2 8.400 - 2.625 44.100

D/d of Column SM -2 1.000 - 2.625 -5.250

Wall-244 SM 2 7.363 - 2.600 38.288

DD-88A SM -2 1.600 - 2.150 -6.880

Wall-245 SM 2 3.000 - 2.600 15.600

DD-88B SM -2 1.600 - 2.150 -6.880

Wall-246 SM 2 6.800 - 2.625 35.700

Wall-247 SM 2 8.900 - 2.850 50.730

Wall-248 SM 2 0.600 - 2.600 3.120

Wall-249 SM 2 0.600 - 2.600 3.120

Wall-250 SM 2 0.650 - 2.600 3.380

Wall-251 SM 2 0.650 - 2.600 3.380

Wall-252 SM 2 3.382 - 2.600 17.586

D-75 SM -2 0.750 - 2.150 -3.225

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
251 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-253 SM 2 2.178 - 2.600 11.326

Wall-254 SM 2 3.904 - 2.600 20.301

Wall-255 SM 2 1.426 - 2.600 7.415

Wall-256 SM 2 1.426 - 2.600 7.415

Wall-257 SM 2 1.426 - 2.600 7.415

Wall-258 SM 2 6.459 - 2.600 33.587

Wall-259 SM 2 1.426 - 2.600 7.415

Wall-260 SM 2 1.426 - 2.600 7.415

Wall-261 SM 2 6.459 - 2.600 33.587

Wall-262 SM 2 1.426 - 2.600 7.415

Wall-263 SM 2 1.426 - 2.600 7.415

Wall-264 SM 2 20.850 - 2.600 108.420

D/d of Column SM -2 1.000 - 2.600 -5.200

D-10A SM -3 1.000 - 2.150 -6.450

D9A SM -2 0.900 - 2.150 -3.870

D/d of Drop Panel SM -2 2.700 - 0.200 -1.080

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-265 SM 2 3.382 - 2.600 17.586

Wall-266 SM 2 7.000 - 2.600 36.400

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
252 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.750 - 0.200 -0.300

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-267 SM 2 11.935 - 2.600 62.062

D-10A SM -3 1.000 - 2.150 -6.450

D/d of Drop Panel SM -2 2.700 - 0.200 -1.080

D/d of Column SM -2 1.000 - 2.600 -5.200

Wall-268 SM 2 3.382 - 2.600 17.586

D-75 SM -2 0.750 - 2.150 -3.225

Wall-269 SM 2 2.178 - 2.600 11.326

Wall-270 SM 2 1.301 - 2.600 6.765

Wall-271 SM 2 1.301 - 2.600 6.765

Wall-272 SM 2 6.459 - 2.600 33.587

Wall-273 SM 2 1.301 - 2.600 6.765

Wall-274 SM 2 5.960 - 2.600 30.992

D-10A SM -2 1.000 - 2.150 -4.300

Wall-275 SM 2 1.576 - 2.600 8.195

Wall-276 SM 2 1.576 - 2.600 8.195

Wall-277 SM 2 6.459 - 2.600 33.587

Wall-278 SM 2 1.426 - 2.600 7.415

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
253 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-279 SM 2 1.725 - 2.600 8.970

D-75 SM -2 0.750 - 2.150 -3.225

Wall-280 SM 2 3.872 - 2.600 20.134

D/d of Drop Panel SM -2 0.800 - 0.200 -0.320

Wall-281 SM 2 1.805 - 2.600 9.386

D/d of Drop Panel SM -2 1.805 - 0.200 -0.722

Wall-282 SM 2 0.478 - 2.600 2.486

D/d of Drop Panel SM -2 0.478 - 0.200 -0.191

Wall-283 SM 2 0.403 - 2.600 2.096

D/d of Drop Panel SM -2 0.403 - 0.200 -0.161

Wall-284 SM 2 1.030 - 2.600 5.356

D/d of Drop Panel SM -2 1.030 - 0.200 -0.412

Wall-285 SM 2 2.500 - 2.600 13.000

D/d of Drop Panel SM -2 0.550 - 0.200 -0.220

Wall-286 SM 2 2.450 - 2.600 12.740

Wall-287 +3.592+1.677 SM 2 5.269 - 2.600 27.399

D-10A SM -2 1.000 - 2.150 -4.300

D/d of Drop Panel SM -2 2.780 - 0.200 -1.112

Wall-288 SM 2 6.054 - 2.600 31.481

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
254 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10A SM -2 1.000 - 2.150 -4.300

Wall-289 SM 2 9.004 - 2.600 46.821

Wall-290 SM 2 7.665 - 2.600 39.858

DD-99 SM -2 1.800 - 2.150 -7.740

D/d for Beam Portion SM -2 0.424 - 0.175 -0.148

Wall-292 SM 2 3.999 - 2.600 20.795

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-294A SM 2 7.374 - 2.600 38.345

DD-88B SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-296 SM 2 5.878 - 2.600 30.566

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-297 SM 2 6.277 - 2.600 32.640

D/d for Beam Portion SM -2 0.400 - 0.375 -0.300

D-9A SM -2 0.900 - 2.150 -3.870

Wall-298 SM 2 0.560 - 2.600 2.912

Wall-302 SM 2 6.900 - 2.600 35.880

D-9A SM -2 0.900 - 2.150 -3.870

Wall-303 SM 2 2.250 - 2.600 11.700

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
255 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-307 SM 2 3.100 - 2.600 16.120

D-9 SM -2 0.900 - 2.150 -3.870

Wall-308 SM 2 3.350 - 2.600 17.420

Wall-309 SM 2 1.950 - 2.600 10.140

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-310 SM 2 1.500 - 2.600 7.800

Wall-311 SM 2 1.500 - 2.600 7.800

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-312 SM 2 3.350 - 2.600 17.420

Wall-313 SM 2 7.091 - 2.600 36.873

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-314 SM 2 1.250 - 2.600 6.500

D-9A SM -2 0.900 - 2.150 -3.870

Wall-315 SM 2 1.250 - 2.600 6.500

D-9A SM -2 0.900 - 2.150 -3.870

Wall-316 SM 2 4.200 - 2.600 21.840

D/d for Opening SM -2 1.200 - 2.600 -6.240

Wall-317 SM 2 6.900 - 2.600 35.880

D-9A SM -2 0.900 - 2.150 -3.870

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
256 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-318 SM 2 4.150 - 2.600 21.580

Wall-322 SM 2 2.300 - 2.600 11.960

D/d of Drop Panel SM -2 1.700 - 0.200 -0.680

Wall-323 SM 2 7.050 - 2.600 36.660

D/d of Drop Panel SM -2 0.750 - 0.200 -0.300

DD-88B SM -2 1.600 - 2.150 -6.880

Wall-324 SM 2 7.090 - 2.600 36.868

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-327 SM 2 4.423 - 2.600 23.000

Wall-328 SM 2 1.042 - 2.600 5.418

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-329 SM 2 3.650 - 2.600 18.980

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-330 SM 2 2.600 - 2.600 13.520

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-331 SM 2 2.550 - 2.600 13.260

D/d of Drop Panel SM -2 0.800 - 0.200 -0.320

Wall-332 SM 2 5.000 - 2.600 26.000

Wall-333 SM 2 3.540 - 2.600 18.408

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
257 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-336 SM 2 5.000 - 2.600 26.000

Wall-337 SM 2 1.923 - 2.600 10.000

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-338 SM 2 7.650 - 2.600 39.780

ID-21 SM -2 2.100 - 2.150 -9.030

Wall-340 SM 2 1.042 - 2.600 5.418

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-343 SM 2 2.440 - 2.600 12.688

Wall-345 SM 2 6.600 - 2.600 34.320

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-346 SM 2 1.700 - 2.600 8.840

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-347 SM 2 1.349 - 2.600 7.015

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-348 SM 2 4.050 - 2.600 21.060

Wall-349 SM 2 4.050 - 2.600 21.060

Wall-350 SM 2 6.100 - 2.600 31.720

Wall-351 SM 2 6.100 - 2.600 31.720

Wall-353 SM 2 0.949 - 2.600 4.935

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
258 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-354 SM 2 1.042 - 2.600 5.418

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-355 SM 2 4.423 - 2.600 23.000

Wall-358 SM 2 6.600 - 2.600 34.320

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-360 SM 2 2.440 - 2.600 12.688

Wall-361 SM 2 4.413 - 2.600 22.948

Wall-363 SM 2 0.949 - 2.600 4.935

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-364 SM 2 1.042 - 2.600 5.418

D/d of Window SM -2 0.900 - 1.000 -1.800

Wall-365 SM 2 3.662 - 2.600 19.042

ID-21 SM -2 2.100 - 2.100 -8.820

Wall-366 SM 2 4.490 - 2.600 23.348

Wall-370 SM 2 3.600 - 2.600 18.720

D-10 SM -2 1.000 - 2.150 -4.300

Wall-371 SM 2 5.700 - 2.600 29.640

D-10A SM -2 1.000 - 2.150 -4.300

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
259 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-372 SM 2 17.200 - 2.600 89.440

D-10 SM -2 1.000 - 2.150 -4.300

Wall-373 SM 2 5.150 - 2.600 26.780

D/d of Drop Panel SM -2 0.750 - 0.200 -0.300

Wall-374 SM 2 6.100 - 2.600 31.720

Wall-375 SM 2 6.100 - 2.600 31.720

Wall-376 SM 2 1.701 - 2.600 8.845

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-377 SM 2 1.349 - 2.600 7.015

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-378 SM 2 2.520 - 2.600 13.104

Wall-379 SM 2 1.530 - 2.600 7.956

D-9A SM -2 0.900 - 2.150 -3.870

Wall-380 SM 2 17.200 - 2.600 89.440

D-10 SM -2 1.000 - 2.150 -4.300

D-9A SM -2 0.900 - 2.150 -3.870

D/d of Opening SM -2 1.200 - 2.600 -6.240

Wall-381 SM 2 1.200 - 2.600 6.240

Wall-382 SM 2 2.520 - 2.600 13.104

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
260 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-383 SM 2 1.530 - 2.600 7.956

D-9A SM -2 0.900 - 2.150 -3.870

Wall-384 SM 2 4.050 - 2.600 21.060

Wall-384A SM 2 4.050 - 2.600 21.060

Wall-385 SM 2 1.700 - 2.600 8.840

D-9A SM -2 0.900 - 2.150 -3.870

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Wall-386 SM 2 1.349 - 2.600 7.015

D/d of Drop Panel SM -2 0.850 - 0.200 -0.340

Qty Second Floor= 3,356.777

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
261 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor

H = 17.025-13.425-0.300 = 3.300

Wall-8 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-9 SM 2 2.550 - 2.600 13.260

D/d Opening SM -2 1.300 - 2.150 (5.590)

Wall-11 SM 2 2.100 - 2.600 10.920

Wall-12 SM 2 4.100 - 2.600 21.320

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-34 SM 2 4.500 - 2.600 23.400

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-35 SM 2 2.550 - 2.600 13.260

D/d Opening SM -2 1.300 - 2.150 (5.590)

Wall-36 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 (5.160)

Wall-40 SM 2 2.650 - 2.600 13.780

Wall-42 SM 2 4.501 - 2.600 23.405

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-43 SM 2 7.300 - 2.600 37.960

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
262 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-44 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-50 SM 2 3.110 - 2.600 16.172

Wall-59 SM 2 2.634 - 2.600 13.697

Wall-60 SM 2 2.470 - 2.600 12.844

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-61 SM 2 12.930 - 2.600 67.236

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-62 SM 2 1.800 - 2.600 9.360

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-63 SM 2 2.449 - 2.600 12.735

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-64 SM 2 7.298 - 2.600 37.950

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-65 SM 2 7.300 - 2.600 37.960

D/d of Drop Panel SM -2 0.950 - 0.200 (0.380)

D-9A SM -2 0.900 - 2.150 (3.870)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
263 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-67 SM 2 5.602 - 2.600 29.130

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
264 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-68 SM 2 4.951 - 2.600 25.745

D-9A SM -2 0.900 - 2.150 (3.870)

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-73 SM 2 3.300 - 2.600 17.160

D-75 SM -2 0.750 - 2.150 (3.225)

Wall-106 SM 2 8.009 - 2.600 41.647

D-10A SM -2 1.000 - 2.150 (4.300)

D/d of Window SM -2 1.500 - 1.500 (4.500)

Wall-112 SM 2 2.199 - 2.600 11.435

D-9B SM -2 0.900 - 2.150 (3.870)

Wall-121 SM 2 1.179 - 2.600 6.131

Wall-122 SM 2 1.008 - 2.600 5.242

Wall-123 SM 2 1.008 - 2.600 5.242

Wall-124 SM 2 1.173 - 2.600 6.100

Wall-125 SM 2 6.750 - 0.200 2.700

Wall-139 SM 2 5.800 - 2.600 30.160

D/d of opening SM -2 2.600 - 2.150 (11.180)

D-9A Wall-139 SM -2 0.900 - 2.150 (3.870)

Wall-139A SM 2 3.000 - 2.600 15.600

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
265 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-140 SM 2 1.350 - 2.600 7.020

D-9A SM -2 0.850 - 0.150 (0.255)

Wall-151 SM 2 3.765 - 2.600 19.578

Wall-152 SM 2 6.423 - 2.600 33.400

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-153 SM 2 2.425 - 2.600 12.610

Wall-154 SM 2 2.425 - 2.600 12.610

Wall-155 SM 2 0.504 - 2.600 2.621

Wall-157 SM 2 7.374 - 2.600 38.345

DD-88A SM -2 1.600 - 2.150 -6.880

D/d for Opening SM -2 0.850 - 0.150 -0.255

Wall-187 SM 2 3.243 - 2.600 16.864

Wall-188 SM 2 3.243 - 2.600 16.864

Wall-189 SM 2 3.243 - 2.600 16.864

Wall-190 SM 2 5.950 - 2.600 30.940

Wall-192 SM 2 5.473 - 2.600 28.460

D/d SM -2 1.200 - 2.150 (5.160)

Wall-194 SM 2 1.000 - 2.600 5.200

D-9A SM -2 0.900 - 2.150 (3.870)

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
266 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-195 SM 2 1.000 - 2.600 5.200

D-9A SM -2 0.900 - 2.150 (3.870)

Wall-195a SM 2 2.500 - 2.600 13.000

Wall-224 SM 2 5.400 - 2.600 28.080


New Added Qty deduct from other
block and add here as per drawing

Ground floor

Wall-770 SM 2 1.150 - 3.800 8.740

D-9A SM -2 0.900 - 2.150 -3.870

Wall-771 SM 2 2.000 - 3.800 15.200

Wall-773 SM 2 1.150 - 3.800 8.740

D-9A SM -2 0.900 - 2.150 -3.870

Wall-774 SM 2 2.650 - 3.800 20.140

Wall-775 SM 2 2.150 - 3.800 16.340

Qty Third Floor= 848.332

Qty of Lower Ground floor Sheet attached 7572.933

Total Qty of Paint work on 150mm Holow block 34,761.271

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
267 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Paint on Block Wall 200 mm thick


ii- Hollow

Ground Floor

Wall-126 SM 2 2.500 - 3.800 19.000

Wall-158 SM 2 7.300 - 3.800 55.480

Wall-186 SM 2 0.229 - 3.800 1.740

Wall-550 SM 2 7.475 - 3.800 56.810

LD-93A SM -2 1.200 - 2.150 -5.160

Wall-706 SM 2 5.100 - 3.800 38.760

Wall-754 SM 2 5.210 - 3.800 39.596

D-10 SM -2 1.000 - 2.150 -4.300

Wall-772 SM 2 1.700 - 3.800 12.920

Wall-779 SM 2 1.700 - 3.800 12.920

Wall-780 SM 2 4.890 - 3.800 37.164

Wall-781 SM 2 5.690 - 3.800 43.244

Wall-782 SM 2 15.200 - 3.800 115.520

LD-93 SM -6 1.200 - 2.150 -15.480

D/d of Drop Panel SM -8 0.850 - 0.150 -1.020

D/d for Column SM -2 1.000 - 3.800 -7.600

Wall-783 SM 2 15.910 - 3.800 120.916

LD-93 SM -2 1.200 - 2.150 -5.160

LD-10 SM -2 1.000 - 2.150 -4.300

Wall-784 SM 2 5.690 - 2.150 24.467

Wall-786 SM 2 16.040 - 3.800 121.904

D/d of Opening SM -2 2.000 - 3.800 -15.200

DD-88 SM -2 1.600 - 2.150 -6.880

D/d of Drop Panel SM -6 0.850 - 0.150 -0.765

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
268 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-787 SM 2 5.591 - 3.800 42.492

LD-10 SM -2 1.000 - 2.150 -4.300

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-788 SM 2 17.018 - 3.800 129.337

LD-10 SM -6 1.000 - 2.150 -12.900

Wall-789 SM 2 5.600 - 3.800 42.560

LD-10 SM -2 1.000 - 2.150 -4.300

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-790 SM 2 2.010 - 3.800 15.276

DD-88B SM -2 1.600 - 2.150 -6.880

Dld of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-791 SM 2 1.350 - 3.800 10.260

Wall-792 SM 2 1.350 - 3.800 10.260

Wall-793 SM 2 4.590 - 3.800 34.884

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-797 SM 2 5.190 - 3.800 39.444

Wall-799 SM 2 5.200 - 3.800 39.520

D/d for Window SM -2 1.510 - 1.510 -4.560

Wall-804 (6.200+6.211) SM 2 12.041 - 3.800 91.512

LD-93 SM -2 1.200 - 2.150 -5.160

Wall-805 SM 2 13.030 - 3.800 99.028

LD-93 SM -2 1.200 - 2.150 -5.160

D-9A SM -2 0.900 - 2.150 -3.870

D/d of Drop Panel SM -6 0.850 - 0.150 -0.765

Wall-806 SM 2 7.080 - 3.800 53.808

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
269 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D-10 SM -2 1.000 - 2.150 -4.300

Wall-807 SM 2 5.365 - 3.800 40.774

Wall-810 SM 2 8.375 - 3.800 63.650

Wall-811 SM 2 7.000 - 3.800 53.200

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-815 SM 2 3.401 - 0.150 1.020

D/d of Drop Panel SM -2 0.850 - 0.150 -0.255

Wall-823 SM 2 1.700 - 3.800 12.920

Qty Ground Floor= 1,360.541

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
270 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

First Floor

H = 9.825-6.225-0.225 = 3.375

Wall-27 SM 2 8.600 - 2.600 44.720

Wall-28 SM 2 7.500 - 2.600 39.000

Wall-44 SM 2 5.363 - 2.600 27.888

Wall-51 SM 2 4.400 - 2.600 22.880

Wall-67 SM 2 4.550 - 2.625 23.888

Wall-242 SM 2 5.375 - 2.600 27.950

Wall-251 SM 2 4.540 - 2.600 23.608

Wall-257 SM 2 3.050 - 2.600 15.860

Wall-261 SM 2 0.670 - 2.600 3.484

Wall-321 SM 2 2.500 - 2.600 13.000

Wall-373 SM 2 0.801 - 2.600 4.165

Wall-389 SM 2 8.700 - 2.600 45.240

Wall-390 SM 2 7.000 - 2.600 36.400

Wall-391 SM 2 4.650 - 2.600 24.180

Wall-396 SM 2 0.600 - 2.600 3.120

Qty First Floor= 355.383

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
271 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Second Floor

H = 13.425-9.825-0.225 = 3.375

Wall-3 SM 2 1.450 - 2.600 7.540

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-4 SM 2 2.550 - 2.600 13.260

D/d Opening SM -2 1.300 - 2.150 -5.590

Wall-5 SM 2 2.600 - 2.600 13.520

Wall-6 SM 2 4.600 - 2.600 23.920

FD-12 SM -2 1.200 - 2.150 -5.160

Wall-7 SM 2 0.500 - 2.600 2.600

Wall-8 SM 2 0.600 - 2.600 3.120

Wall-9 SM 2 2.500 - 2.600 13.000

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-12 SM 2 0.600 - 2.600 3.120

Wall-13 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.325 - 1.500 -3.975

Wall-14 SM 2 4.050 - 2.600 21.060

Wall-15 SM 2 0.500 - 2.600 2.600

Wall-17 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-19 SM 2 0.600 - 2.600 3.120

Wall-20 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-21 SM 2 4.050 - 2.600 21.060

Wall-22 SM 2 0.600 - 2.600 3.120

Wall-23 SM 2 1.625 - 2.600 8.450

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
272 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-25 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-27 SM 2 0.600 - 2.600 3.120

Wall-28 SM 2 4.050 - 2.600 21.060

Wall-29 SM 2 0.600 - 2.600 3.120

Wall-30 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-33 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-34 SM 2 0.600 - 2.600 3.120

Wall-35 SM 2 4.050 - 2.600 21.060

Wall-36 SM 2 0.600 - 2.600 3.120

Wall-37 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-40 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-41 SM 2 0.600 - 2.600 3.120

Wall-42 SM 2 4.050 - 2.600 21.060

Wall-43 SM 2 0.600 - 2.600 3.120

Wall-44 SM 2 1.625 - 2.600 8.450

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-47 SM 2 2.000 - 2.600 10.400

D/d Window SM -2 1.350 - 1.500 -4.050

Wall-48 SM 2 0.600 - 2.600 3.120

Wall-49 SM 2 5.300 - 2.600 27.560

Wall-50 SM 2 7.200 - 2.600 37.440

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
273 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-51 SM 2 10.550 - 2.600 54.860

D/d of Column. SM -2 1.000 - 2.600 -5.200

Wall-52 SM 2 10.550 - 2.600 54.860

D/d of Column. SM -2 1.000 - 2.600 -5.200

Wall-53 SM 2 7.250 - 2.600 37.700

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-54 SM 2 7.250 - 2.600 37.700

DD-99 SM -2 1.800 - 2.150 -7.740

Wall-55 SM 2 5.200 - 2.600 27.040

Wall-56 SM 2 5.200 - 2.600 27.040

Wall-57 SM 2 7.000 - 2.600 36.400

Wall-65 SM 2 2.500 - 2.600 13.000

Wall-66 SM 2 0.600 - 2.600 3.120

Wall-67 SM 2 2.100 - 2.600 10.920

D/d of window SM -2 1.350 - 1.500 -4.050

Wall-68 SM 2 0.600 - 2.600 3.120

Wall-69 SM 2 2.600 - 2.625 13.650

Wall-70 SM 2 2.600 - 2.625 13.650

Wall-71 SM 2 0.600 - 2.600 3.120

Wall-72 SM 2 2.100 - 2.600 10.920

D/d of window SM -2 1.350 - 1.500 -4.050

Wall-73 SM 2 0.600 - 2.600 3.120

Wall-74 SM 2 2.600 - 2.600 13.520

Wall-75 SM 2 2.600 - 2.600 13.520

Wall-76 SM 2 0.600 - 2.600 3.120

Wall-77 SM 2 2.100 - 2.600 10.920

D/d of window SM -2 1.350 - 1.500 -4.050

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
274 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-78 SM 2 0.600 - 2.600 3.120

Wall-79 SM 2 2.600 - 2.600 13.520

Wall-80 SM 2 2.600 - 2.600 13.520

Wall-81 SM 2 0.600 - 2.600 3.120

Wall-82 SM 2 2.100 - 2.600 10.920

D/d of window SM -2 1.350 - 1.500 -4.050

Wall-83 SM 2 0.600 - 2.600 3.120

Wall-84 SM 2 1.650 - 2.600 8.580

Wall-85 SM 2 1.580 - 2.600 8.216

Wall-86 SM 2 7.689 - 2.600 39.983

Wall-147 SM 2 3.722 - 2.600 19.354

Wall-155 SM 2 6.990 - 2.600 36.348

Wall-172 SM 2 7.080 - 2.600 36.816

Wall-174 SM 2 7.080 - 2.600 36.816

Wall-178 SM 2 7.080 - 2.600 36.816

Wall-193 SM 2 7.080 - 2.600 36.816

D/d for Door SM -2 1.600 - 2.150 -6.880

Wall-194 SM 2 31.380 - 2.600 163.176

D/d of Column. SM -3 1.000 - 2.600 -7.800

Wall-195 SM 2 23.290 - 2.600 121.108

D/d of Column. SM -2 1.000 - 2.600 -5.200

Wall-205 SM 2 3.000 - 2.600 15.600

Wall-210 SM 2 4.810 - 2.600 25.012

Wall-220 SM 2 5.259 - 0.100 1.052

Wall-223 SM 2 7.190 - 2.600 37.388

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
275 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Qty Second Floor= 1,311.266

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
276 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

3rd Floor

H = 17.025-13.425-0.300 = 3.300

Wall-1 SM 2 7.200 - 2.600 37.440

Wall-2 SM 2 7.300 - 2.600 37.960

Wall-3 SM 2 7.300 - 2.600 37.960

Wall-4 SM 2 6.350 - 2.600 33.020

Wall-6 SM 16 0.600 - 2.600 24.960

Wall-81 SM 2 7.300 - 2.600 37.960

DD-88A SM -2 1.600 - 2.150 -6.880

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-82 SM 2 7.300 - 2.600 37.960

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-83 SM 2 4.499 - 2.600 23.395

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-84 SM 2 7.300 - 2.600 37.960

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-85 SM 2 7.300 - 2.600 37.960

D/d Drop Panel SM -2 0.950 - 0.200 (0.380)

Wall-86 SM 2 2.600 - 2.600 13.520

Wall-87 SM 2 6.750 - 0.200 2.700

Wall-88 SM 2 0.165 - 2.600 0.858

Wall-89 SM 2 0.165 - 2.600 0.858

Wall-90 SM 2 6.738 - 0.200 2.695

Wall-91 SM 2 0.165 - 2.600 0.858

Wall-92 SM 2 0.165 - 2.600 0.858

Wall-93 SM 2 6.744 - 0.200 2.698

Wall-94 SM 2 0.171 - 2.600 0.889

Wall-95 SM 2 0.177 - 2.600 0.920

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
277 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

Wall-96 SM 2 6.732 - 0.200 2.693

Wall-96a SM 2 0.171 - 2.600 0.889

Wall-97 SM 2 7.080 - 2.600 36.816

DD-88A SM -2 1.600 - 2.150 (6.880)

Wall-97a SM 2 0.165 - 2.600 0.858

Wall-98 SM 2 6.750 - 0.200 2.700

Wall-99 SM 2 6.750 - 0.200 2.700

Wall-100 SM 2 6.750 - 0.200 2.700

Wall-104 SM 2 7.300 - 2.600 37.960

Wall-131 SM 2 7.600 - 2.600 39.520

Wall-134 SM 2 8.650 - 2.600 44.980

DD88A SM -2 1.600 - 2.150 (6.880)

Wall-135 SM 2 7.650 - 2.600 39.780

DD88A SM -2 1.600 - 2.150 (6.880)

D/d Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-136 SM 2 4.800 - 2.600 24.960

Wall-137 SM 2 8.900 - 2.600 46.280

Wall-138 SM 2 8.749 - 2.600 45.495

D/d opening SM -2 1.700 - 0.150 (0.510)

Wall-144 SM 2 15.470 - 0.200 6.188

Wall-145 SM 2 7.000 - 2.600 36.400

D/d Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-174 SM 2 12.625 - 2.600 65.650

Wall-199 SM 2 1.800 - 2.600 9.360

Wall-202 SM 2 7.100 - 2.600 36.920

D/d Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-207 SM 2 2.399 - 2.600 12.475

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
278 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER (TRUST)
PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 9, FINISHISH IPC-16
Item # 9.1.2 Matt Enamel Painting
(Refer Specs. Section # 9900)
Item Descriptions:-Providing and applying 3 coats of Matt enamel Paint (ICI/ Berger/ Jotun/ Nippon or approved equivalent
of approved shade ) to internal surface. Including base preparation and applying Primer coat. Complete as per Drawings,
Specifications, Room Finishes Schedule and as directed by the Consultants / Engineers.

Sr.# Location Unit No. Length Width Height Qty Remarks

DD-88A SM -2 1.600 - 2.150 (6.880)

D/d Drop Panel SM -2 0.850 - 0.150 (0.255)

Wall-213 SM 2 6.990 - 2.600 36.348

Wall-214 SM 2 1.290 - 2.000 5.160

Wall-215 SM 2 4.740 - 2.600 24.648

Wall-216 SM 2 0.165 - 2.600 0.858

Wall-218 SM 2 0.165 - 2.600 0.858

Wall-219 SM 2 0.165 - 2.600 0.858

Qty Third Floor= 899.653


Lower Ground Floor Quantities as
per attached sheets 4170.846

Total Qty of Paint on 200mm thick Hollow block work 8,097.689

Submitted By Checked By Qs
Contractor CPG-Arcop (JV)
279 of 279

M/S ZKB Reliable (JV) Engineering Services (Pvt) Ltd, Lahore.


Subject CONSTRUCTION OF PAKISTAN KIDNEY & LIVER INSTITUTE AND RESEARCH CENTER
(TRUST) PACKAGE-B
MEASUREMENT SHEET

Contractor ZKB-Reliable JV Consultant:- CPG-Arcop


DIVISION 3, #REF!
Reinforcement for Block Masonary

Reinforcement for Block work.

Request
Sr.# Location Unit kg/SM Length Width Height Qty Remarks
Nos

Hollow Reinforced Concrete Block


Wall 200 mm thick
1 Item # 4.1 Kg 2.106 17977.397 37860.399

Hollow Non-Reinforced Concrete


2 Block Wall 200 mm thick Kg 2.106

Hollow Non-Reinforced Concrete


Block Wall 150 mm thick
3 Item # 4.2 Kg 2.106 8097.689 17053.734

4 Solid Block Wall 200mm thick Kg 1.247

5 Solid Block Wall 150 mm thick Kg 1.247

Solid Block Masnory 100 mm thick


6 Item # 4.3 Kg 1.247 7198.445 8976.461

Total Qty up to Date 63,890.594 Kg

Already Paid Qty up to last IPC 10,086.938 Kg

Balance Qty This Bill= 53.804 Ton

Submitted By Reviewed By Qs Reviewed By


Contractor CPG-Arcop (JV) PMC

Das könnte Ihnen auch gefallen