I. PURPOSE
The purpose of the method statement is to provide step by step
guidelines for erection of the following Equipments.
ELE. ABOVE
DESCRIPTION SIZE OF EMPTY WEIGHT
GROUND ACTIVITY TO BE
SL OF EQUIPMENT OF EQUIPMENT
LEVEL CARRIEDOUT
No EQUIPMENTS (Meter) (MT)
(Meter)
MP CONSENSER
1 12.0 1.258 X 8.166 10.0 Replacement
21 E-07
80.5+.98+1.05
2 UREA STRIPPER 11E-1 11.5 Reversal
2.9 X 12.104 = 82.08
AMM. RECEIVER 11V-01
3 & RECOVERY TOWER11C- 5.0 3.326 X 10.27 / Replacement
42.0
05 0.813 X 4.0
DISTILLATION TOWER
4 Removal, Retubing &
OVERHEAD CONDENSER 0.905 X 12.414 11.0
Reinstallation
E-17
C. ASSEMBLY OF CRANE.
Assembly for the main crane would be done at the Road No-3 i.e co-ordinate (y-1504.920). The
minimum time required for assembly of crane will be 5-6 days. The same as been enclosed.
D. LOAD TESTING
Load test will be done by lifting crane self counter weight for a minimum height of 1.5 to 2
mtr ,at the assembly point.
V ERECTION METHODOLOGY
Step by step 0method is depicted below for erection of the CCR equipments. The Plan and
Elevation drawings for various stages are indicated in the enclosed erection scheme drawings.
A ERECTION OF EQUIPMENTS
1. After checking the level of the foundation with reference to Reference Bench mark ,
necessary chipping, cleaning would be done in order to maintain
2. General orientation of Nozzle would be ascertained to confirm the general plot plan. Elevation
of the equipment should be checked from plot plan and nozzle co-ordination from the
equipment drawings
3. Ear marked area for positioned of the crane shall be prepared for required levelness & uniform
compaction.
4. With required boom length, crane shall be marched and placed on the top of the hard stand,
final location for carrying out the entire erection.
5. First lift the equipment with the main crane and trailing crane.
6. Initially lift the equipment to a height of 1mtr.
7. Check once again the path of equipment movement and then swing the crane boom towards
the actual position.
8. Place the equipment over the structural foundation provide as per drawing and bolts shall be
fixed on all the bolt holes in legs.
9. After completion of erection, carryout inspection for proper positioning and vertical alignment.
10. The shim plates if required shall be placed in between frames and legs.
11. Tighten all the bolts completely for all the four legs and carryout final inspection for
alignment.
12. Detach the crane sling with the equipment after completion swing the crane towards
the path for preparing itself for erection.
13. The points 1 to 10 shall be repeated for erection of all remaining equipments (enclosed with
erection drawing).
1. Scaffolding
2. Crane deployment and load test
3. Dismounting of all piping connection by debolting and cutting and removal of same.
4. Removal of all instruments and valves.
5. Removal of fire hydrant point.
6. Removal of structure of all levels i.e. level and wherever required.
7.