Beruflich Dokumente
Kultur Dokumente
ON-Z-1301 A/B/C/D/E/F/G
PROJECT-0846
VA&S1 ONSHORE DEVLOPMENT TERMINAL
ONGC- ODALAREVU
INTRODUCTION
(3)16.25 & (2) 10.5 & 10.0 X 6HOS6-3 @1000
COMPRESSOR TYPE :-
STAGES OF INSTALLATIONS:-
➢ Foundation inspection.
➢ Materials Verification& Inspection.
➢ Compressor skid Installation.
➢ Engine erection.
➢ Cylinders Installations & Levelling.
➢ Pistons Installations & clearances inspection.
➢ Lube oil Flushing.
➢ Engine Jacket water filling and Oil filling and Alignments.
➢ Air cooler Heat Exchanger (ACHE) Erection
➢ Tube Bundles & Platform Erection.
➢ Torqueing of Stud bolts.
➢ Alignment, coupling installation.
➢ Reports.
➢ Preservations of units.