Beruflich Dokumente
Kultur Dokumente
© 1996 ElsevierScienceLimited
Printed in Ireland. All rights reserved
0266-1144/96 $15.00
ELSEVIER PII:SO266- 1 144(96)00007-6
A BS TRA C T
1 INTRODUCTION
175
176 R. A. Austin, A. J. T. Gilchrist
This paper discusses some of the early research work carried out on
geogrids together with recent work carried out on pavement geocompo-
sites, in addition to describing an installation case study.
2 INITIAL RESEARCH
the pavement. A slightly less stiff base was used, but the support was
continuous. A saw cut was made in the base of the beam to determine the
position of the onset of fatigue cracking. A vertical cyclic loading was used
and strains were measured at various points over the depth of the beam
and the propagation of cracking through the beam monitored.
Results showed that in general the fatigue life of the pavement was
increased by up to a factor of 10 to a given level of traffic induced strain
within the asphalt, when the geogrid was installed at the base of the layer.
Since the geogrid has a modulus similar to that of the asphalt,
comparative testing of both reinforced and unreinforced pavements
immediately after construction, showed little or no difference in stiffness.
However after an extended period of trafficking it was found that the
stiffness of the unreinforced pavement diminished rapidly, as expected, as
fatigue cracks developed from the bottom of the bituminous layers,
whereas the reinforced pavement maintained its original stiffness over a
significantly longer period.
Investigation showed that the geogrid takes over the tensile load carry-
ing role, once the bitumen has cracked. This validated the original theory
that the reinforcing element should have a stiffness compatible to the
bitumen itself and not be excessively strong to interfere with the elastic
properties of the pavement.
3 F U L L SCALE T R I A L S
Many full scale trials have been carried out in different geographical
locations throughout the world to confirm the results of the laboratory
testing and to develop efficient methods of installing the geogrid (Nunn &
Potter, 1993).
From the results of the laboratory and field trials it was possible to
derive an analytical design method incorporating geogrids which is based
on the strain capacity improvement of the pavement related to the number
of axle passes (Brown, 1985a).
4 DEVELOPMENTS
Although the methods developed for installing the geogrid gained rapid
acceptance, methods to improve the technique were constantly being
investigated. In 1990 Netlon began to examine the benefits of bonding a
geotextile to the asphalt reinforcing geogrid in order to provide a material
which could be installed without the need to fix, tension and dress prior to
paving by machine.
178 R. A. Austin, A. J. T. Gilchrist
5 C U R R E N T RESEARCH
Hydraulic Motor
The pit was permanently filled with approximately 1.1 m of a local Keuper
Marl subgrade made from compacted wet clay bricks and the final level
was controlled to give the required height and CBR by replacing or adding
bricks and controlling the moisture content. A single pressure cell per test
section was pressed into the subgrade clay centrally in the wheel track to
20 m m below the surface, prior to placing of the sub-base layer.
A 15 m m thick regulating course of 6 m m asphalt was spread thinly over
the sub-base on all sections to provide an overall seal and a suitable
surface for tack coating on the composite section. A tack coat of bitumen
emulsion was applied at the rate of 1.5 l/m 2 and the composite brushed
into the tack coat and left to cure. A 40ram layer of 14mm dense bitumen
m a c a d a m (DBM) wearing course was placed and compacted. Following
compaction of the first 40ram layer, the composite in the mid asphalt
position was placed following the same procedure and the second bitumi-
nous layer placed and fully compacted.
5.1.3 Loading
A 300mm wide strip centred on each wheel track was painted white so
that any cracks developed during wheel loading would be visible and
initial surface profiles were taken relative to longitudinal reference beams
on either side of the test pit.
The pavement was tested with the wheel running in single track mode at
a wheel load of 6 k N and contact pressure of approximately 300kPa.
Surface profiles were taken at regular intervals. The single track mode was
chosen because it is a concentrated load leading to a more rapid defor-
mation of the pavement. T h r o u g h o u t the test, subgrade stress readings
were taken from the pressure cells. The test was continued for 25,000
passes o f the wheel load.
5.1.4 Results
30
20
10
i
o . . . . . . . . . . . . . . . I .... +~,,
0 5 10 15 20 25 30
Number of Wheel Passes (x 1000)
Fig. 3. Average surface d e f o r m a t i o n vs n u m b e r of passes.
had been deliberately weakened by using a soft subgrade, failure was defined
as the point at which the wheel track visibly sheared along each side. This
occurred for the control section at 24,000 passes. Figure 4 shows the test
section surface profiles at the end of trafficking.
-20
r
J
-40
-60 J
v t
I
- -
j I
j J
i
-80 i
I
J
l I
Control Section 41.)AR-G at Mid LDcpth -/~ AR-G at Base of Asphalt I
-I00
-300 -200 - 100 0 100 200 300
Fig. 4. R u t profiles after 25,000 wheel passes.
182 R. A. Austin, A. J. T. Gilehrist
TABLE 1
Summary of Average Rut Depths for Weak Foundation Test
Test seetion Rut depth (rnm) Rut depth~control rut
depth
Control 60 1.0
Composite in middle of asphalt layer 48 0-80
Composite at base of asphalt layer 20 0.33
60
40
i
20
0 t t ~ , i t i t t ! : t i i i ] t i ,
0 10 15 20 25 30
Number o f Wheel Passes (x 1000)
Fig. 5. Subgrade stress vs number of wheel passes.
Enhanced per.[brmance of asphalt pavements 183
Plywood base
20mm Thick Sandsheet
10mm Gap Rul
Fig. 6. Slab construction.
184 R. A. Austin, A. J. T. Gilchrist
3.7m I
Motor I
f ~ Load cell
t ~. 1.22m _
The results of the slab testing are summarized in Table 2. The control slab
became severely cracked at an early stage in the testing, with cracks
propagating across the sandsheet/DBM interface by 1700 passes. Crack
growth continued rapidly until the slab was completely cracked through
by 3300 passes.
For the geogrid reinforced slab the crack propagated through the
sandsheet at 4500 passes. The crack then travelled to 5ram above the
geogrid level and stopped at this position until 7600 passes. After 13,000
passes the slab became cracked through due to the crack propagating
from the base of the slab joining the surface crack. The surface crack had
been caused by a rocking movement of the slab as the wheel moved on
and off the slab at the end of its travel.
For the composite reinforced slab, the sandsheet cracked through at
4600 passes. This crack widened, but did not transfer into the DBM until
12,700 passes had been completed. At 18,900 passes a surface crack
TABLE 2
Summary of Slab Test Results
Number of wheel passes
Slab type Crack through sandsheet Crack through slab
Control 1700 3300
Geogrid 4500 13,000
Composite 4600 25,000
Enhanced performance of asphalt pavements 185
developed which eventually met the base crack at 25,000 passes. Traffick-
ing continued to 30,000 passes, with still only a very fine crack visible in
the DBM layer and a value of 2500 microstrain recorded.
The installation of the geogrid into the slab improved the crack resistance
of the slab under a moving wheel load with reference to the control slab,
which became severely cracked. This had been observed before by Brown
(1985b), as well as the fact that even when a crack propagates through a
geogrid reinforced beam it still retains its structural integrity. The addition
of the geotextile to the geogrid to form the composite further improved
reflective crack resistance.
At the end of the test it was observed that the composite debonded from
the sandsheet for about 150mm either side of the gap. It is thought that
the composite may control cracking through this mechanism, rather than
strengthening the interface.
6 CASE STUDY
The B3004 road in Hampshire, England, carries heavy local traffic over
soft saturated ground on low embankments. Failure of the existing surfa-
cing had been caused by geotechnical failure of the subgrade leading to the
formation of a longitudinal crack along the centre of the lane with
evidence of both lateral and vertical deformation. In 1991, a hot rolled
asphalt overlay was laid on the road in three sections, two of which were
reinforced using proprietary systems and one of which was left as an
unreinforced control section.
The existing road surface was first regulated with fine asphalt to a
thickness of 30mm. Bitumen emulsion was then sprayed at a rate of 1.5 1/
m ~ and Tensar AR-G composite immediately rolled out as the emulsion
cured. To ensure full curing of the emulsion, vigorous brushing of the
composite into the emulsion was then carried out.
The other proprietary system involved the use of a self-adhesive woven
geogrid which was installed directly onto the regulated surface.
When the bitumen had fully cured, 40mm of hot rolled asphalt was
overlaid by a conventional paver at a maximum temperature of 165~C. No
evidence of movement of the composite was detected during paving.
The site has now been open to traffic for over three years and although
the control and the section containing the self-adhesive woven geogrid are
186 R. A. Austin, A. J. T. Gilchrist
7 CONCLUSIONS
REFERENCES