Sie sind auf Seite 1von 74

Chevron

Chevron Nigeria Limited

PREPARED BY ENGINEERING & DESIGN OFFICE

Conversion of TANK 200-03 to Wash Tank Service

AFE No: 51232

FINAL REPORT ON THE HAZARD ANALYSIS REVIEW


Conducted 28th to 29th April 2003

DOCUMENT NUMBER

WDFL-0472.RP.70.0001

P2 22/05/03 ISSUED FOR INFORMATION OGUN SFTO SFTO


P1 16/05/03 ISSUED FOR COMMENTS OGUN SFTO SFTO
REV DATE DESCRIPTION BY CHK APP
TABLE OF CONTENTS

1.1 LIST OF ATTENDEES............................................................................................................................................. 3

1.2 SUMMARY ................................................................................................................................................................ 4

1.3 DESIGN REVIEW .................................................................................................................................................... 6

2.0 WHAT IF? ANALYSIS WORKSHEETS ............................................................................................................. 10

3.0 SUMMARY CHECKLIST REVIEW AND ANALYSIS (API RP 14J) ............................................................. 22

5.0 ADDITIONAL CONSIDERATIONS AND ACTION PLAN.............................................................................. 64


5.1 “DESIGN REVIEW RECOMMENFDATIONS................................................................................................... 65
5.2 “WHAT IF” RECOMMENFDATIONS................................................................................................................ 67
5.3 “CHECKLIST ” ADDITIONAL RECOMMENFDATIONS ............................................................................... 70
6.0 REFERENCES ........................................................................................................................................................ 73

7.0 RISK RANKING TABLE....................................................................................................................................... 73

2
1.1 LIST OF ATTENDEES
HAZAN meeting dates
Monday 28th April
Tuesday 29th April

S/N NAME POSITION PHONE - DAYS OF


LOCATION ATTENDANCE
1 Sheyi Tomoye CNL Process Engineer Ext. 1834 – EDO Mon/Tue
(PHA Leader)
2 Comfort Afella CNL Project Engineer Ext. 8341 – Mon/Tue
Lekki
3 Godson Ajaero CNL Process Engineer Ext. 3475 – Mon/Tue
Escravos
4 Tayo Oluyemi CNL Process Engineer Ext. 3475 – Mon/Tue
Escravos
5 Abiola Laditan CNL HES Terminal Ext. 4511– Mon/Tue
Engineer/Specialist Escravos
6 Peter Ugburo- CNL E& I Engineer Ext. 8213 – Mon/Tue
Shanomi Lekki
7 Paul Grundy CNL Snr. Process Ext. 3437 – Mon/Tue
Engineer Escravos
8 John Omabuwa CNL Dehydration Ext. 3171 – Mon/Tue
Supervisor Escravos
9 Roland Onovwie CNL Terminal Operations Ext. 3378 – Mon/Tue
Supervisor Escravos
10 Rizu Nwokoma CNL Terminal Engineer Ext. 8201– Mon
Escravos
11 E. Ehioda DPR Representative DPR Warri Mon/Tue
12 Nick Ndubuizu CNL Terminal Engineer Ext. 8454 – Tue
Escravos
13 Eliot Quinn NALCO Account NALCO – 3891 Tue
Manager Escravos
14 Ememe Ugochukwu CNL Process Engineer Ext. 3827– Tue
Escravos
15 Nav Kandola ABB Lead Process Ext. 1852 – EDO Mon/Tue
Engineer
16 Suraj Mohammed NETCO Process Engineer Ext. 1813 – EDO Mon/Tue
17 Yomi Ogunkilede NETCO Instrument Ext. 1855 – EDO Mon/Tue
Engineer.

3
1.2 SUMMARY

A facility Hazards Analysis (HAZAN) review was conducted for the conversion of Tank 200-03 to
Wash Tank service from April 28th to 29th, 2003. The review group included representatives from
Operations, Safety & Environmental, Facilities Engineering and EDO (Design contractor). See the
list of attendees on page 3.

The intent of this project is to convert Tank 200-03 (ABJ 803) to wash Tank service when Tank
200-01 (ABJ 801) is out of service. The two tanks will also be available for use either as Wash
Tank or as Storage Tank. A tank selection button will be used to select which one of the two tanks
is used as a Wash tank at a particular time.

Tank 200-03 is a fixed roof tank (conical shaped) with storage capacity of 200,000 bbls and
operates at atmospheric conditions. The design flow capacity/flow rate under wash tank service is
650,000 barrels fluid per day (BFPD)>

Front end and detailed engineering design will cover fabrication and installation of piping,
instrumentation and structural items required to convert Tank 200-03 to Wash Tank service. The
scope of work includes but not limited to the following:

1. Installation of a 24” inlet header to come off existing 30” Tank 3 bi-directional oil pipeline
and tie-in to the existing 24” inlet Wash Tank header.

2. Installation of a 20” dry oil outlet pipeline, fitting and nozzle and tie-in to the existing 20”
Wash Tank dry oil outlet pipeline.

3. Installation of a 30” wet oil outlet pipeline, fitting and nozzle and tie-in in to the existing
30” Wash Tank wet oil outlet pipeline.

4. Installation of a 16” produced water outlet pipeline, fitting and nozzle and tie-in in to the
existing 16” Wash Tank produced water outlet pipeline.

5. Installation of an 8” emulsion pad draw-off (internal collector) pipeline at 5 ft of tank height


and tied into the 8” bottom treaters transfer pumps inlet pipeline.

6. Installation of all necessary piping fittings and valves on the pipelines.

7. Installation of emergency relief valve on the 24” manholes for protection against excess
pressure.

8. Determine the capacity of the bottom treater pumps to handle the emulsion pad whose
viscosity is 110centipoise @ 120 0F versus the adequacy of the number of emulsion pad
pick up points for the pump.

4
9. Fabrication and installation of a new valve access platform with double handrail, in
accordance to Chevron’s SID manual.

10. Fabrication and installation of extension to the gaugers platform in accordance with
Chevron’s Safety in Design manual.

11. Fabrication and installation of walkway with grating on the tank roof to link all roof
nozzles.

12. Fabrication and installation of 6” rain rail around the top of tank with six (6) 6” down
spouts

13. Installation of 3” sch 40 pipes & fitting as bottom water draw off line around perimeter of
tank.

14. Installation of 10” gate valve on the 10” section of the discharge line of the produced water
transfer pumps for future sand jetting operations.

15. Determine the possibility of using the exhaust or waste heat from the turbines to heat the
crude at the inlet of the wash tank. This is to take care of the difficulty encountered in
treating crude oil during rainy season as a result of low temperature.

16. Installation of an inlet spreader box and 6 x 16’ gas vent lines connecting the roof of the
spreader box to the space above the oil so that gas from the crude oil within the spreader
box does not go back into the crude oil. The gas vent lines in Tank 1 (Wash Tank) are not
sufficient for effective gas venting.

17. The dip hatch should be installed away from the sump area.

18. Installation of 16” OD x 100” long dry oil internal collector pipe located at 22.6 ft. of tank
height.

19. Installation of 24” OD x 120” long wet oil internal collector pipe located at 10 ft. of tank
height.

20. Installation of 12” OD x 60” long free water internal collector pipe located at 1.5 ft. of tank
height.

21. Installation of instrumentation and controls for the Wash Tank (as exists in Tank 1) and tie
in to the existing dehydration control room. Determine the capacity of the control
hardware/software to accommodate the added control requirements.

22. All other piping supports and all other civil works necessary to complete the conversion of
Tank 200-03 to a Wash Tank.

5
1.3 DESIGN REVIEW

Section: General
P&ID: All Project P& ID’s
P&ID Title:

Issue Raised By Status By


1. Tank 3 was to be converted to wash Roland Addressed in the front end design. Nav
tank service with flexibility to be used Onovwie Detail design to continue with this Kandola
as storage tank later. Is this concept
considered?
2. Installation of the 8-inch emulsion pad Roland One connection presently now in Nav
take-off should be through an inlet Onovwie tank 1. 4 nos. connection provided Kandola
spreader located between 4 & 5ft in the new design with an internal
height. spreader.
Detailed review to be carried out
later.
3. Why the emergency relief valve Rizu Based on request by Operations. Nav
(PVSV) on the 24 inch manhole? Nwokoma Intent is to relieve pressure when Kandola
tank is operated beyond the
atmospheric pressure. Detail review
to be carried out later.
4. Why steel pads are required (design Roland To be reviewed during detail design Nav
review item 11)? Onovwie phase. Kandola
5. Have we combined tank repair work Tayo Not in full. Review to be carried Nav
with the wash tank conversion project Oluyemi out in detail design to determine Kandola
(item 12, 13 & 14)? what has been covered.
6. Is provision made to determine sand Rizu No provision made. Design team to Nav
build-up in the new wash tank?. Nwokoma consider this. Kandola
7. Is there a way to clean the wash tank Godson No provision made. Design team to Nav
while in service? Ajaero consider this. Kandola
8. Where is waste heat recovery from? Rizu From the turbine. PE to discuss Godson/
Nwokoma this issue with operations. Design Nav
team can look into this if required.
9 For item 19 to 21, internal collector Tayo Yes. To be covered during detail Nav
pipes not stated as to be provided Oluyemi design Kandola
10 Is dry oil internal collector pipe Roland Located at 22ft Nav
located at 10ft? Onovwie Kandola
11. Is control and safety Instrumentation Peter U. Separate document to be produced Nav
system separated? Shanomi by design team to address safety Kandola
system
12. Are there new pumps other than the Peter U. No Nav
pneumatic sump? Shanomi Kandola
13. Is design team considering adding John Design team to consider Nav
sampling points close to the wash Omabuwa Kandola
tank?
14 8-inch emulsion pad draw off from Godson PE to review and advise design Sheyi
tank 1 not provided presently Ajaero team Tomoye

6
15 Can the two tanks be operated Peter U. The two tanks can not be operated Godson
together as Wash tank? Shanomi together as wash tank. Selectors Ajaero/
switch to be provided to select Tayo
which tank to be used as wash at Oluyemi
any particular time.
16 Relief line from main header to tank Roland Yes. Provision already made for Nav
1. Is provision made to tie-in tank 3 to Onovwie this. Kandola
the same relief line?
17 Why is the water line maintained at Sheyi To be noted and considered by Godson
4ft level? Believe water draw-off Tomoye Operations and design team Ajaero
should be designed to operate both at
4ft. and 5ft.?
18 Is it possible to have two points for Godson Nozzle can be provided at two Nav
the Agar probe and be able to switch Ajaero points as desired. Kandola
b/w the two?
19 Why Four (4) different tie-in Roland Design team to review tie-in Nav
points? Onovwie points with Escravos operations Kandola
and Process group
20 Why is the tie in points not Roland See comment under item 19 Nav
between 4 ft and 5ft level? Onovwie Kandola
21` Installation of steel pads 4”x4”x1/4” Godson Design team to confirm with Sheyi
plate beneath the roof support Ajaero Obioma Isiuwa Tomoye?
columns (38) in all. Does roof
support apply to only floating roof
and therefore not required in the
scope of this project.

Design Review

Section: Wash Tank #3 Design Tie-Ins


P&ID: 55-041.TNK.PI.10-3003
P&ID Title: Wash Tank ABJ-803

1. What is the function of AT 803B? Is it Godson Meant to be low level alarm for dry Sheyi
to check oil/water interface? Ajaero oil. Actually a redundant alarm. Tomoye/
Design team to review AT 803B Nav
function with ESC process &
Operations group
2. Pg.8 of Control & Operating Godson See 1. above
Philosophy. Why is AT 803B tied to Ajaero
water transfer pump?
3. Spectacle blind was installed on lines Tayo Dry oil outlets, water outlets have Roland
1455, 1454 to enable use of tanks for Oluyemi need for spec blind (i.e. all lines Onovwie
storage service.The other lines should common to storage and wash tank Tayo
also have spectacle blinds for positive purpose). Spec blind required to be Oluyemi/
isolation as this is a DPR requirement if added on all lines by design team to Sheyi
the tank is to be used for storage. prevent co-mingling. Tomoye
4. Are we having Pressure alarm/monitor Tayo Yes. With remote indication Yomi
on tank top Oluyemi Ogunkile
de
5. LSL 803A not clouded as new Godson Instrument will be clouded Nav
Instrument Ajaero Kandola

7
Design Review

Section: Wash Tank #1 Interface with Wash Tank #3


P&ID: 55-041.DHY.PI.10-2001
55-041.SMP.PI.10-0191
55-041.TNK.PI.10-3003
P&ID Title: Wash Tank ABJ-801
Wash Tank Sump & Sump Pump
Wash Tank ABJ-803

Issue Raised By Answered By


1. Why is 24inch line not tie-in further Peter U. Shut down time required Godson
down the line? Shanomi determined the tie-in point. Ajaero
2. Are we installing corrosion coupon on Tayo No. Design team to explore. Nav
any of the lines? Design team should Oluyemi Kandola
consider this.
3. Lines from sample turndish is a 1” line Peter U. Design team to check and Nav
in the new design whereas it is a 2” in Shanomi consolidate with the existing Kandola
the existing
4. Do we have temperature indicator on Rizu No. Design team to include. Nav
the inlet/outlet lines? Are they Nwokoma Kandola
desirable?
5. Consider notes to indicate valves in the Rizu Design team to include. Nav
bottom lines as NC Nwokoma Kandola
6. Spectacle blind in the inlet line to Tank Peter U. Design team to implement Nav
3 should be clouded Shanomi Kandola
7. Is LTI 803B (Internal Hanging Fisher Peter U. Design team to investigate and Sheyi
Level Gauge) required? Shanomi review with Operations/Process Tomoye
group
8. Is there provision for sampling points Paul Design team to investigate and Sheyi
to monitor SRB growth to check Grundy review with Operations/Process Tomoye
whether growth is from the tank or group
brought in from the field?
9. What type of lightning protection is G. Separate team presently working Peter U.
provided? Ehioda on provision of lightning protective Shanomi
device for all tanks
10. LIT 200B in the existing tank 1 Peter U. Design team to check/review as Nav
compared to corresponding instrument Shanomi required Kandola
in tank 3 is not specific on the
instrument elevation. Also LSL
11. Electrical earthing on tanks to be G. Electrical earthing on tank 3 typical Peter U.
confirmed. Ehioda as for other tanks Shanomi
12. Is there going to be as-built drawings to Rizu As-built drawing to be produced at Nav
show the nozzles? Nwokoma the end of project. Kandola/
Sheyi
Tomoye

8
Design Review

Section: Wash Tank Sump / Sump Pump PBH 803


P&ID: 55-041.SMP.PI.10-0191
55-041.TNK.PI.10-3003
P&ID Title: Wash Tank ABJ-801
Wash Tank ABJ-803

Issue Raised By Answered By


1. No question raised
2.
3.
4.
5.
6.
7.
8.
9.
10.

9
2.0 WHAT IF? ANALYSIS WORKSHEETS

( Risk Ranking Table in Appendix 5.0)

10
Clarification Notes

The project P & ID’s were divided into 16 sections for the purpose of the “What If” analysis.
11 Nos. P&ID’s were fully analyzed and risk ranking assigned to possible hazardous occurrences.

The remaining P&IDs were not reviewed because they did not impact the project scope of work.
They were included as part of the project P& ID to provide complete view of the facilities
associated with the Wash Tank service.

The section descriptions of the P& ID’s fully reviewed during the “What If” analysis are:

Description P&ID No.

• Wash Tank ABJ-803 55-041.TNK,PI.10-3003


• Wash Tank ABJ-801Instrument and Utility Air Header 55-041.DHY,PI.10-2001
• Wash Tank Sump (ABH-803)/Sump Pump (PBH 803) 55-041.SMP.PI.10-0191
• Dehydration- Wash Tank Dry Oil Pumps 55-041.DHY.PI.10-2002
• KTI Charge Pumps 55-041.DHY.PI.10-2102
• Incoming Pipelines & Receivers/Pipeline Receivers 55-041.PPL.PI.10-1003
From Offshore 55-041.PPL.PI.10-1003
• Export Area Instrument Air System/ Instrument Air
Distribution System 55-041.IAS.P1.10-9604
• Tank Bottoms Transfer Pumps 55-041.TNK.PI.10-3011
• Coalescer #1 & #2 Wet Oil Charge Pumps 55-041.DHY.PI.10-2003
• Coalescer #3&#4 Wet Oil Charge Pumps 55-041.TNK,PI.10-2010

11
Location: Escravos Study Date:
P&ID No.: P&ID Title: P&ID Revision Date:
55-041.TNK.PI.10-3003 Wash Tank ABJ-803 03/02/03

Section Description: Wash Tank Designs Tie-Ins


Design Intention: Wash Tank ABJ-803 Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

1. LSL 803C Fails • Pumps may deliver • Pressure monitoring 3 4 5


gas with oil (Pressure transmitter)
• Pumps may run dry to open recycle valve
• Damage to pump • Operating procedure /
Operations
surveillance
• High Pressure alarm

2. VG-60 on line 1455 left • Treated Oil deliver to • Operating procedure 4 2 5 • Spectacle blind to be
open Wash Tank from any • Operators Surveillance provided
of the storage tanks • LOTO provision
• False production
figures
• Upset in Wash Tank
operation

3. VG-60 on line 1042 fail • Pressure build up in • HC Drain vessel has 3 4 5 • Consider installing a RO
close (Internal the line PSH-352 (production or a globe valve
mechanism drop to close • Platform shutdown shut-in), PAH-352, downstream of the ball
valve) • Back pressure PSV-352, TSE valves – Project Team
offshore • Operating procedures
• Possibility of line LOTO procedures
rupture
• Spill / Pollution

12
4. Offshore sends excess • Wash Tank upset • 12 nos. vent & flame 3 3 4 • Convert PSVs to PVSVs
gas • Breaking of other arrestors • Communication between
storage tanks seals • PSVs Platform and Offshore
• Damage to inlet • 2 nos. relief hatches
spreader box on 24” Manways
• Excess gas release • Operating Procedure
to atmosphere
5. Isolation valve on all • Tank out of service • Preventive 4 4 5 • Maintenance access will
outlet lines faulty Maintenance be provided by design
(Maintenance) team (Detail design)
6. AT 803 (Agar Probe) • High water level in • LSL/LAL 803A 3 3 4
faulty the tank] • SOP (Sampling
• Oil to water intervals)
treatment facilities

7. Internal gas vent • Wash Tank profile • 6 nos. vent 4 4 5


collapses upset
8. Excess crude into Wash • Inefficient treating 4 4 5
Tank
9. Failure of one or more of • None • Preventive 4 4 5
PSVs Maintenance checks
• 12 nos, PSVs provided

10. Leakage in the tank or • Spill / Pollution • Bund wall 2 4 5


pipeline • Fire • Tanks coated
• Fire fighting
equipment

11. Fire on tank 3 or adjacent • Production • Tanks spacing 1 3 2 • Operating procedure


tank shutdown • Bund wall should address.
• Equipment damage • Fire fighting
Impact on crude equipment
storage • SOP
• Injuries to personnel

12. Tanks sump filled up with • Upset in Wash Tank • Preventive 4 2 5


sand maintenance
• SOP

13
13. Presence of H2S in the • Injuries to personnel • SOP 2 3 3 • Use of monitoring
tank • Tank damage due to • Biocide Instrument
corrosion • Monitoring • On-line monitors to be
• No well test provided

14. LTI 803A fails • Design team to review


LSL 8093/803B Control Philosophy
LIT /LIC 803
15. PSVs have no upstream
valve for annual
calibration purpose
16. LSH 803 fails • Liquid overflow • LIC 803, LAH 803, etc 3 4 5 • Design team to review
• Pollution • SOP Control Philosophy

17. PAH/L 803 fails to alarm • Gas release to • SOP 2 4 5


atmosphere
• Tank collapse
18. Inlet spreader box gives • Wash Tank upset • None 3 4 5
way • Excess gas release
to atmosphere Off
Spec Oil

19. Oil carry over (from draw • Not applicable N/A


off line) into the trench
20. LIT 803 gives false • Design team to review
reading Control philosophy
• Need to develop SAFE
chart
• Design team to review
Instrument function with
Escravos Operation &
Process group
21. LAH 803 fails to alarm • Design team to review
Control philosophy
• Need to develop SAFE
chart
• Design team to review
Instrument function with
Escravos Operation &
Process group

14
22. Tanks hit by lightning • Vent fire • Flame arrestors 3 3 4 • DPR Regulation
• Fire fighting • PE to check DPR
equipment requirement and
• SOP recommend

23. One or more sample • No sample at • None 4 2 5 • Design team to provide


points blocked blocked points ladder rung as access for
sampling
24. No water wash from tank • Wash Tank upset None 3 4 5
• Excess gas release
to atmosphere Off
Spec Oil

25. One or more flame • None • Preventive 4 4 5


arrestors blocked Maintenance checks
• 12 nos, arrestors
provided

26. No maintenance access • Tank out of service • Preventive 4 4 5 • Maintenance access will
for PSVs, flame arrestors Maintenance be provided by design
on tank top team (Detail design)
27. Hazardous gas release • Injuries to personnel • SOP 2 3 3 • Use of monitoring
to atmosphere (i.e. H2S) • Tank damage due to • Biocide Instrument
corrosion • Monitoring • On-line monitors to be
• No well test provided
28. High pressure or leak on • Spill / Pollution • Bund wall 2 4 5 • Spill / Pollution
the inlet/outlet lines • Fire • Tanks coated • Fire
• Fire fighting
equipment

S = Severity L = Likelihood R = Risk

15
Location: Escravos Study Date:
P&ID No.: P&ID Title: P&ID Revision Date:
55-041.DHY.PI.10-2001 Wash Tank ABJ-801 03/02/03
55-041.SMP.PI.10-0191 Wash Tank Sump (ABH 803)/Sump Pump (PBH 803)
55-041.TNK.PI.10-3003 Wash Tank ABJ-8003

Section Description: Wash Tank #1 Interface Tie-In


with Wash Tank #3
Design Intention: Wash Tank #1 Interface with Wash Tank #3 Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

29 FT 200A does not work • No flow reading • Ultrasonic flow meter 4 4 5


• Tank gauging reading

30. VG-60 on line 1405 left • Crude flow to both • Spectacle blind 4 4 5
open tanks • SOP
• Shipping off spec oil
plus unaccounted oil
to storage tanks

31. High pressure from relief • High level in Wash SOP 4 2 5 • Integrate rupture disc
line (AT 1461) – Rupture Tank monitoring to EDMAC
disc or line open • Incorporate CSO/CSC
when switching between
two wash tanks to SOP
32 Relief line opens to both • Shipping off spec oil • None 4 4 5 • Provide spectacle blind
tanks plus unaccounted oil on CSC/CSO
to storage tanks • Revise SOP

33 Back flow on line 1456 • Not applicable

34. Line 1456 leakage due to • Not applicable


rupture

S = Severity L = Likelihood R = Risk

16
Location: Escravos Study Date:
P&ID No.: P&ID Title: P&ID Revision Date:
55-041.SMP.10-0191 Wash Tank ABJ-801 03/02/03
55-041.TNK.PI.10-3003 Wash Tank aABJ-803

Section Description: Wash Tank Sump/ Sump Pump


(PBH 803)
Design Intention: Wash Tank Water Transfer Pump Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

35 LSH 803 fails • Liquid overflow • SOP 4 3 5 • Design team to automate


• Pollution • Bund wall pit sump & pump
• Fire • Revise existing P&ID to
reflect automated sump
pit & pump
36 LSL 803G fails • Pump sucks air • LAL 803G 4 3 5

37 Pump PBH 803 fails to • Liquid overflow • SOP 4 3 5


start • Pollution • Bund wall
• Fire

38 Instrument air not • Liquid overflow • SOP 4 3 5


available • Pollution • Bund wall
• Fire

39. Sample point left open in • Liquid overflow • SOP 4 3 5 • Design team to automate
error • Pollution • Bund wall pit sump & pump
• Fire • Revise existing P&ID to
reflect automated sump
pit & pump
40. VG-60 on line 1462 left • Line over pressure • SOP 4 3 5
closed • Pump Diaphragm • Bund wall
rupture
• Liquid overflow
• Pollution

17
41 Fire around the sump • Not applicable • Wellhead PSH (dual if 4 3 5
SITP>MAWP)
• Operating procedures
• TSEs & SDVs on
wellhead
• PAH/PSH 212, PSV 212

42 Flame arrestor blocked • Not applicable 4 4 5 • Design team to tag flame


arrestor.

S = Severity L = Likelihood R = Risk

Location: Escravos Study Date:


P&ID No.: P&ID Title: P&ID Revision Date:
55-041.DHY.PI.10-2021 Wash Tank ABJ-801 03/02/03
55-041.TNK.PI.10-3003 Wash Tank ABJ-8003

Section Description: Produced water Transfer


System
Design Intention: Produced Water Transfer System Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

43 VG-60 (2 nos.) are left • None • None


open in error
44 LSL 803/B fails • Pump continues to LSL 803A 3 4 5 • Design team to check
run instrument tags
• Oil to water • Check Control Philosophy
treatment facilities for the existing tank
• Pollution

45 PBA 567 A/b fails to start • High water level • SOP 4 4 5


• Oil to water • Preventive
treatment facilities maintenance check
• Pollution • 100% Redundancy

18
46 PBA 567 A/b fails to stop • Low water level • LAH 2 4 5
• Oil to water • SOP
treatment facilities • Preventive
• Damage to pump maintenance check

S = Severity L = Likelihood R = Risk

Location: Escravos Study Date:


P&ID No.: P&ID Title: P&ID Revision Date:
55-041.DHY.PI.10-0102 Dehydration – wash tank Dry Oil Pumps 03/02/03
55-041.TNK.PI.10-3003 Wash Tank ABJ-803

Section Description: Dry Oil Transfer System


Design Intention: Dry Oil Transfer System Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

47 Isolation valve on line • None


1408 (VG-60) not closed
48 FCV 800 fails open • Design team to confirm
failure mode
49 FT 800 reading not correct • Incorrect • Design team to review
production figure Control philosophy with
Escravos Operations &
process group
50 LCV 800 fails to close • Off spec oil • Operations 3 3 4 • Operating procedure
Surveillance should address new
• Preventive pump system -
maintenance Operations
check • Review pump logic –
Project team

51 LSL 803C fails • • 3 4 5 • See comment in item 1

S = Severity L = Likelihood R = Risk

19
Location: Escravos Study Date:
P&ID No.: P&ID Title: P&ID Revision Date:
55-041.DHY.PI.10-2102 KTI Charge Pumps 03/02/03
55-041.TNK.PI.10-3003 Wash Tank ABJ-803
55-041.DHY.PI.10-2003 Coalescer#1 &2 Wet Oil Charge Pumps
55-041.TNK.PI.10-2010 Coalescer#1 &2 Wet Oil Charge Pumps

Section Description: Wet Oil Transfer System


Design Intention: Wet Oil Transfer System Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

52 8” valve connecting line • Emulsion pad flows • SOP 4 1 4


1453 and 1454 open to wet oil • Operations
Surveillance
S = Severity L = Likelihood R = Risk

Location: Escravos Study Date:


P&ID No.: P&ID Title: P&ID Revision Date:
55-041.DHY.PI.10-1003 Incoming Pipelines and Receivers/Pipeline Receivers from 03/02/03
55-041.TNK.PI.10-0191 Offshore

Section Description: 16” Relief Line to Wash Tank


Inlet
Design Intention: 16” Relief line Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

53 Same as items 29-42

S = Severity L = Likelihood R = Risk

20
Location: Escravos Study Date:
P&ID No.: P&ID Title: P&ID Revision Date:
55-041.IAS.PI.10-9604 Export Area Instrument Air system / Instrument Air 03/02/03
55-041.TNK.PI.10-3003 Distribution
Wash Tank ABJ-803

Section Description: Instrument Air


Design Intention: Instrument Air Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)

54 No Issue raised

S = Severity L = Likelihood R = Risk

Location: Escravos Study Date:


P&ID No.: P&ID Title: P&ID Revision Date:
55-041.TNK.PI.10-3003 Wash Tank ABJ-803 03/02/03
55-041.TNK.PI.10-3011 Tank Bottoms Transfer Pumps

Section Description: Bottoms Tank Transfer


Design Intention: Oil Manifold /Tank Bottoms Transfer Pumps Piping & Instrumentation
POTENTIAL EXISTING SYSTEMS & PROCEDURES S L R ADDITIONAL CONSIDERATIONS
WHAT IF ..... ? CONSEQUENCES (SAFEGUARDS)
.

55 No Issue raised

S = Severity L = Likelihood R = Risk

21
3.0 SUMMARY CHECKLIST REVIEW AND ANALYSIS
(API RP 14J)

22
Process Hazards Research and
Analysis Checklist: Plant Layout/Siting Technology

Checklist Type: General Review Date:


FILENAME: SITEUNIT.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Unit/Project:
Company

MOC#:
Checklist Questions Y/N/NA Reference/Comments
Do plant setbacks and equipment spacing comply with company, industry, or N/A
insurance requirements?
Can equipment be accessed for maintenance without the need for conducting N Should be addressed at detail
heavy crane lifts over pipeways or other in-service equipment? design
Is the secondary containment or drainage for storage vessels containing N/A
incompatible materials segregated to prevent adverse reactions if spills occur?
Is the unit sufficiently isolated from adjacent unit(s) (e.g., by berms, drainage Y
channels, etc.) to minimize impact if a loss of containment occurs in the
adjacent unit?
Have site-specific hazards such as earthquake, hurricane, lightning, and flood Y
been evaluated?
Are horizontal LPG storage vessels oriented with their ends directed away N/A
from occupied buildings and critical equipment?
Is rotating machinery (i.e., pumps and compressors) located such that a seal N/A
fire will have minimal impact on adjacent or overhead equipment?
Is equipment that is located adjacent to roads or other access ways adequately Y
protected from damage due to vehicle impact?
Are the egress routes (number and path) adequate to safely evacuate the unit in N Should be addressed at detail
the event of emergency? Has the potential for simultaneously blocking all design
egress routes been evaluated (e.g., train crossing, main access road closed due
to maintenance, etc.)?
Is emergency vehicle access to the unit adequate? Y
Is motor vehicle access to the unit adequately controlled [review installation of Y
signs and road barriers]?
Is site security sufficient to prevent unauthorized access to the unit? N Site security team to address
If applicable, are tall structures equipped with aircraft warning lights? N/A
Are electrical power supply lines for the unit routed to minimize the potential N/A
for power loss to the unit due to a fire at other units?
Are redundant instrument or power cables adequately separated to prevent a N/A
single incident (e.g., fire, supporting pole failure, etc.) from resulting in failure
of both cables (i.e., common cause failures)?

23
Has all buried equipment (e.g., process lines, fire water lines, electrical N To be addressed at detail
conduit, and sewers) been identified on drawings and by aboveground markers design
as appropriate?
Are atmospheric vents for flammable or toxic material routed to a safe location Y
(i.e., away from personnel and ignition sources)?
Does all equipment and instrumentation comply with the electrical area Y
classification?
Has equipment that is routinely operated been placed for ready access by the N To be addressed at detail
average size operator? design
Has equipment that must be operated in short time sequence (such as valve N/A
switching) been located to facilitate operator actions [i.e., minimum
separation]?
Is plant surface drainage sufficient to handle maximum expected runoff, Y
including fire water runoff?
Have the possible explosion, fire, and toxic material impacts to nearby Y
occupied or critical buildings been evaluated?

24
Process Hazards
Analysis Checklist: Storage Tanks Research and Technology

Checklist Type: Process Equipment Review Date:


FILENAME: TANKS.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Is the storage tank material appropriate for the fluid properties, including maximum Y
contaminant concentration?
Is the storage tank secondary containment area of adequate size and design to hold Y
the contents of the largest tank in the event of a tank leak or failure?
Is the area around the storage tank graded to prevent pooling of product [concern N To be addressed by separate
for fire] or water [concern for external corrosion] at the base of the tank? project group, HES to follow
up
Is the storage tank equipped with an appropriate water draw system capable of Y
removing expected quantities of water, both during normal operation and when
placing the tank into service? [Note: Some facilities must put the tank roof on-
float with water before introducing hydrocarbon.] Are water draw systems
adequately protected against freezing?
Is the storage tank adequately grounded? Y
Has the interaction between cathodic protection systems for the tank and connected Y
pipelines been evaluated?
TANK APPURTENANCES:
Is the storage tank roof (including roof seal design) compatible with the materials Y
to be stored?
If the storage tank gagewell is to be used for tank sampling, is the gagewell Y
slotted?
Does storage tank gaging/sampling equipment provide protection against vapor N SOP to address
release/personnel exposure [concern is for personnel exposure to H2S or inert
blanketing or release of flammable vapors]?
For storage tanks with floating roofs, are vacuum breakers installed to prevent roof N/A
or tank damage when emptying the tank (with the roof on set on its supports)?
Are the storage tank overpressure vents/vacuum breakers sized for maximum Y
fill/emptying rates?
Are floating swing lines properly ballasted for the density of the material to be N/A
stored in the tank?
Are mechanical seals on tank mixers compatible with the material stored in the NA
tank?

25
Does the tank mixer motor meet the electrical classification requirements of the N/A
storage tank area?
PROCESS UPSETS:
Has a stock leak through the tank floor been evaluated [consider the requirements Y
for internal coating of tank floor or secondary containment with external drains
under the tank floor]?
Has a failure of the storage tank roof drain (i.e., leak in internal swing line or roof N/A
drain hose) been evaluated ?
If the storage tank is equipped with a steam heater or bottom coils, has a heater or N/A
coil failure been evaluated [consider potential for tank damage due to possible
boilover or rapid expansion in the tank]?
Has loss of steam (or other heating medium) to the storage tank been evaluated? N/A
Has increased temperature (may be due to loss of product cooling or process upset) N/A
of the stock to the storage tank been evaluated [determine if upset may result in
exceeding flash point of stock]?
Has high vapor pressure stock to the storage tank been evaluated [may occur N/A
during startup or shutdown or be caused by upset at the upstream unit(s)]?
Has loss of level in an upstream pressure vessel been evaluated? Y
Has water carryover or contamination from the storage tank to downstream process Y
units or outside customers been evaluated? [Note: Leaking swing line joints are a
common cause for water carryover from tankage.]
Has a hazardous material entering a tank that normally contains a benign material N/A
been evaluated (e.g., hydrocarbon into a water tank or sour stock into a sweet
tank)?
FACILITY SITING:
Is adequate fire water coverage available at or near the storage tank? Is there Y
sufficient access and an adequate staging area for fire-fighting equipment near the
storage tank?
Does the spacing between the storage tank and other tanks or equipment conform Y
with applicable fire codes and local jurisdictional codes, regulations, and practices?
Does the storage tank’s fixed fire protection system provide sufficient water to cool N Other project group
the involved tank and the affected surfaces of surrounding tanks? addressing this
Is the storage tank’s foam system compatible with the tank design and type of stock N/A
or material stored?
For storage tanks containing oxygenate blend stocks or other polar materials, is the N/A
available foam appropriate for use in the event of fire (alcohol-resistant foam
required)?
Are foam injection valves located outside the storage tank secondary containment Y
area? [Note: Foam injection valves located inside the secondary containment area
should be locked open when tank is in-service.]
Does the storage tank’s containment area grading plan consider the need to collect Y
and remove rainwater?
Has site-specific hazards such as earthquake, hurricane, lightning, and floods been Y
evaluated?
HUMAN FACTORS:
Are tank suction and fill lines and valves clearly labeled, including flow direction? N Detail design to address

26
Is the lighting adequate in the unit [consider valve manifold locations and valves Y
requiring operation during emergency conditions, etc.]? Is the emergency lighting
(light fixtures on the emergency power circuit) adequate in the unit?
Are all operating valves accessible during normal or emergency operation? Y
Are manually operated valves positioned to allow proper operation without muscle Y
strain?
Is access adequate at all valve manifolds (including battery or plot limit) for both N Detail design to address
routine and emergency operation and for maintenance? [Review requirements for
changing battery or plot limit blinds.]
Are drain valves located to allow personnel to monitor levels while draining? N/A
Have storage tank valve manifolds been arranged to reduce the likelihood of mis- N Detail design to address
manifolding? Has valve mis-manifolding been evaluated [consider complex
suction, fill, or water draw manifolds]?
PROCEDURES:
Do storage tank startup procedures specify a maximum fill rate until the tank liquid N SOP to address
level covers the fill piping? [Note: possible static electricity concern]
Do procedures specify the safe-fill level of the storage tank? [Note: The tank safe- N SOP to address
fill level may be influenced by site-specific seismic hazards.]
Do procedures specify storage tank minimum level? [Note: possible concern for N SOP to address
floating roof tanks]
Are pressure vents/vacuum breakers routinely inspected? Y
Do procedures specify water removal (water draw) method and frequency? N/A
Is the accuracy of the automatic tank gaging systems checked routinely? N/A
Do procedures specify method and frequency for draining storage tank roofs N/A
(applies to floating roof tanks)?
Do procedures prevent compromising secondary containment areas by leaving N/A
rainwater drain valves open?
Do procedures specify how to either reroute or rerun off-specification product? N/A
Do procedures specify the method and frequency for sampling storage tank N/A
contents?

27
Research and
Technology

Process Hazards
Analysis Checklist: Pumps
Checklist Type: Process Equipment Review Date:
FILENAME: PUMP.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Is the pump casing design pressure greater than the maximum pump suction N/A
pressure plus the pump shutoff pressure [consider largest impeller when
determining maximum pump differential]?
Is the downstream piping or equipment design pressure greater than the maximum N/A
pump discharge pressure [consider largest impeller when determining maximum
pump differential], or is the downstream piping or equipment protected from
overpressure in the event that the pump is blocked in?
If a downstream blockage would raise the pump suction pressure, is the N/A
downstream piping and equipment rated for the maximum suction pressure plus the
pump shutoff pressure?
If a downstream blockage would not raise pump suction pressure, is the N/A
downstream piping and equipment rated for the greater of (1) normal suction
pressure plus the pump shutoff pressure or (2) maximum suction pressure plus
normal pump differential pressure?
Has a discharge relief valve been provided for positive displacement pumps? N/A
Is the pump adequately protected from damage when operating at low flow rates
[determine if minimum flow protection is required]?
Is the pump design temperature greater than the maximum operating temperature? N/A
Is the pump material selection appropriate for the expected fluid properties, N/A
including maximum contaminant concentration?
PUMP AUXILIARIES, INCLUDING MECHANICAL SEAL OR PACKING:
Is the selected mechanical seal or packing appropriate for the intended service, N/A
including maximum contaminant concentration?
Has mechanical seal or packing failure been evaluated? N/A

28
Has failure of pump heat removal equipment (e.g., lube oil coolers, gland oil N/A
coolers, stuffing box coolers, seal flush coolers, and seal flush) been evaluated
[consider loss of circulation or supply and plugging of coolers]?
Are pump "run" indicators (running lights or other process indicators) provided at a N/A
continuously staffed location for critical service pumps?
PROCESS UPSETS:
Has the pump stopping been evaluated? N/A
Has blocking in the pump been evaluated? N/A
Has loss of suction to the pump been evaluated? N/A
Has reverse flow through the pump, when it shuts down, been evaluated [assume N/A
the discharge check valve sticks open]?
If the pump is provided with minimum flow protection, have failures of the N/A
minimum flow system been evaluated [consider minimum flow valve (control or
manual) closed and wide open]?
Has the pump stopping and the minimum flow recycle control valve open (trying to N/A
maintain minimum flow) been evaluated?
For manual minimum flow recycle systems (manual valve or restriction orifice), N/A
has the pump stopping been evaluated?
For parallel pump arrangements (one pump operating and an idle spare pump on N/A
standby), has leakage through the spare pump's discharge check valve been
evaluated [concern is for overpressuring the spare pump suction valve and
piping]?
Has operation with higher specific gravity fluid, due to process upset or N/A
startup/shutdown, been evaluated [consider whether or not the pump driver is
adequately sized for water if the pump will be required to transfer or circulate
water during startup or shutdown]?
FACILITY SITING:
Is adequate fire water coverage available for the pump area? N/A
Is there adequate emergency access to the pump? N/A
Can the pump be safely isolated in an emergency? N/A
If emergency isolation valves (either manual, automatic, or remotely operated) are N/A
provided to isolate the pump, are these valves appropriate for the process service
and valve location [review requirements for fire-rating of isolation valves; fail-safe
position of isolation valves; and fireproofing of valve actuator, power cables, and
instrument cables of the isolation valves]?
If emergency isolation valves are provided, has failure of the isolation valves been N/A
evaluated [consider valves closing and valves failing to close when demanded]?
For installations where critical service equipment (e.g., air-cooled heat exchangers N/A
or power/instrument cables) is located above a pump handling flammable material,
is the critical equipment adequately protected in the event of fire at the pump
[review requirements for fireproofing and installation of fixed water or fixed steam
deluge]?
If fixed water or fixed steam deluge is provided, can the valve or station that N/A
actuates the system be operated safely in the event of fire at or near the pump
[consider location of valve/station or the ability to operate valve/station remotely]?

29
Have flexible piping components (e.g., hoses, expansion joints, and tubing) been N/A
reduced or eliminated where possible? If flexible piping components are installed,
are they designed for maximum operating pressure and temperature? Are flexible
connections adequately protected against possible rupture due to mechanical
impact and fire?
Have leaks (at mechanical seal, flanges, etc.) to the atmosphere been evaluated for N/A
pumps located in buildings or shelters [concern is for buildup of explosive
atmosphere with possible fire or explosion]?
For pump installations using an engine driver (gas or diesel driven) are the air N/A
intake and exhaust lines vented to a safe location?
Can critical service pumps be quickly shut down from a safe location? N/A
PROCEDURES:
If emergency isolation valves (either manual, automatic, or remotely operated) are N/A
provided, are procedures in place for the routine testing of these valves?
For critical service pumps, are preventative maintenance procedures in place to N/A
reduce the likelihood of equipment failures that could result in hydrocarbon or
toxic material releases?
For pump installations with auxiliary systems (e.g., lube oil, seal oil, vibration, N/A
etc.), are alarms and shutdowns routinely tested?

30
Research and
Technology

Process Hazards
Analysis Checklist: Instrumentation
Checklist Type: Process Equipment Review Date:
FILENAME: INSTRUMT.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Is the instrument specification suitable for the expected fluid properties, including Y
maximum contaminant concentration?
Is the instrument design pressure greater than the maximum operating pressure of Y
the process system to which it is connected?
Is the instrument design temperature greater than the maximum operating Y
temperature of the process system to which it is connected?
Is the instrument installation designed to allow on-line testing and calibration of the Y
instrument?
Are critical safety shutdown systems designed and installed to ensure reliability of N Detail design to address
the shutdown system [consider requirements for redundancy of components,
independence from process control system, and ability to test system to ensure
reliability]?
Are critical safety shutdown systems designed to fail-safe? Does the design Y
require operator action to reset the shutdown system (e.g., manual reset of isolation
valves) after the shutdown system is actuated to prevent unsafe conditions due to
system response when the shutdown trip condition clears?
Are instrument installations that result in moment arm arrangements (multiple or N/A
heavy valves branching from the pipe) adequately designed (e.g., supported or
reinforced, such as bridge welding) to prevent failure of welded connections due to
vibration or mechanical impact?
Are emergency shutdown switches guarded against inadvertent operation [consider N/A
location, switch operation, and guards or covers]?
Are all critical service alarms routed to a continuously staffed location? Y

31
Are redundant instrument or power cables physically separated [i.e., separated to N/A
prevent a single incident, such as fire or mechanical impact, from resulting in
failure of both cables]?
Are instrument sensing lines adequately purged or heat traced to prevent plugging? Y
For plugging services, does the design allow for safely unplugging the instrument
on-line?
Are utility instruments adequately heat traced and insulated or designed to prevent N/A
cold weather freezing and plugging?
Are control valves or emergency isolation valves designed to close under N/A
maximum differential pressure process conditions?
For services where the piping specification changes to a lower design rating after N/A
the control valve, is the downstream piping specification suitable for upset
situations with the control valve wide open?
Are the instruments suitable for the electrical area classification? Y
PROCESS UPSETS:
Has the control valve failing wide open been evaluated? N/A
Has the control valve failing closed been evaluated? N/A
Has the control valve leaking been evaluated? N/A
Has the control valve bypass left open or leaking been evaluated? N/A
For plugging or fouling services, has plugging of the flow orifice or other primary N/A
flow element been evaluated?
Has operation with higher or lower specific gravity fluid (may be due to process Y
upset or startup/shutdown) been evaluated?
Has loss of power to the process unit been evaluated [determine if the process unit Y
is designed fail-safe]?
Has loss of power, including partial loss of power and total loss of power, to the Y
process control system been evaluated?
Has loss of instrument air to the process unit been evaluated [determine if the Y
process unit is designed fail-safe]?
Has inadvertent operation of the safety shutdown system been evaluated? Y
FACILITY SITING:
If emergency isolation valves (either manual, automatic, or remotely operated) are N/A
provided, are these valves appropriate for the process service and valve location
[review requirements for fire-rating of isolation valves; fail-safe position of
isolation valves; and fireproofing of valve actuator, power cables, and instrument
cables of the isolation valves]?
If emergency isolation valves are provided, has failure of the isolation valves been N/A
evaluated [consider valves closing and valves failing to close when demanded]?
Are critical safety shutdown systems adequately protected in the event of fire? N/A
[Determine if the safety shutdown system’s primary elements or sensors, the power
and instrument cables, and the final elements such as emergency isolation block
valves or equipment shutdown interlocks are adequately fireproofed, fail-safe,
and/or located in a nonhazardous area.]
Are the control building air conditioning and pressurization adequate to protect the N/A
electronic instrumentation? Are they adequate to prevent intrusion of toxics,
flammables, or corrosive contaminants (if applicable)?

32
Are control valves and associated instrumentation accessible for maintenance? N/A
HUMAN FACTORS:
Can critical valves or equipment be closed or shut off from a safe location? Y
Is the lighting adequate in the unit [consider local instrument panels, battery or Y
plot limit valve manifold locations, equipment and valves requiring operation
during emergency conditions, etc.]? Is the emergency lighting (light fixtures on
the emergency power circuit) adequate in the unit?
Are all instrument labels easy to read (clear and in good condition)? N Detail design to address
Are all instrument labels correct and unambiguous? N Detail design to address
Are all instrument labels located close to the items that they identify? N Detail design to address
Do all instrument labels use standard terminology (e.g., acronyms, abbreviations, N Detail design to address
equipment tags, etc.)? Are the instrument labels consistent with nomenclature used
in procedures?
Are all components that are mentioned in procedures (e.g., valves) labeled or N Detail design to address
otherwise identified?
Do switch labels identify discrete positions (e.g., ON or OFF, OPEN or CLOSE)? N Detail design to address
Are the field instruments that are routinely monitored by operations personnel N Detail design to address
easily accessible to ensure information is read in accordance with recommended
frequency [consider instruments or areas that are difficult to reach, such as
climbing 40 feet of ladder or squeezing into close quarters]?
Are the engineering units of similar instruments consistent [e.g., do the pump seal Y
flush rotameters all display flow in either gpm or gph]?
Are field instrument indicators routinely checked for accuracy? N SOP to include
Are field instrument ranges appropriate for the service [e.g., avoid using a 0-2500 N Detail design to address
psig pressure gage on a 100 psig system]?
Are operating ranges for process variables specified in the same engineering units N/A
as the instrument read-out or indicator (i.e., mental conversion of units is avoided)?
Are calculations performed by operations personnel documented in a consistent N/A
manner and periodically checked for correctness?
Does the process control system console layout allow for rapid response to upset Y
situations? If required, does the process control system console layout allow for
response by multiple personnel?
Do the process control system displays adequately present the process information Y
[consider the logical layout of process or equipment configuration information,
consistent presentation of information, visibility of information from various work
positions, and the logical linking of information between displays]?
Do the process control system displays for similar equipment (e.g., parallel trains Y
or similar equipment in series) present the information in a unique manner to avoid
confusion?
Do the process control system displays provide feedback to operations personnel to N Detail design to address
confirm operator actions? Does the feedback provide operators with logical
information (e.g., is 100% valve output equivalent to valve wide open)?
Are critical alarms prioritized to alert operations personnel to upset situations that Y
require immediate response?
Is the cause of "nuisance" alarms (repetitive alarms that operations personnel Y
ignore or acknowledge without investigating) investigated and repaired in a timely
manner?

33
Are equipment "run" indicators (running lights or other process indicators) and Y
valve position indicators provided at a continuously staffed location for critical
equipment, valves, and instruments?
Are the communications facilities between process units adequate for clear and Y
uninterrupted communications during both normal and emergency situations [e.g.,
telephone land lines, radio, computer network, and E-mail, and are systems
redundant and/or secure]?
Is the control room lighting adequate [review direct and indirect lighting]? Is the Y
control room emergency lighting (light fixtures on the emergency power circuit)
adequate?
PROCEDURES:
Do procedures prevent changing alarm set points without proper review and Y
authorization? Are alarm changes (set point or priority) communicated to all
affected employees?
Do procedures prevent changing process control system or safety shutdown system Y
control or logic (software) without proper review and authorization? Are process
control system or safety shutdown system changes communicated to all affected
employees?
Do operating procedures document the alarm set points? Do the procedures Y
specify the expected operator response to the alarm? Do the procedures specify the
potential consequences if the alarm set points are exceeded (i.e., consequences of
deviation)?
Do operating crews communicate unusual instrument status (bypassed or out of Y
service) in writing? Are operating crews provided with written temporary
operating procedures when instruments are bypassed or out of service?
Do procedures require verification that instruments that are deliberately disabled Y
during operation (e.g., shutdown interlocks bypassed to allow testing) are placed
back in service?
Do procedures require control valve bypasses to remain closed during normal N/A
operation [possible concern for loss of level during upset conditions if the bypass
around an LCV is open]?
Do procedures specify proper response to alarm indicators (e.g., lights, horns, or Y
whistles) during emergency situations? Are hypothetical emergency situation drills
periodically performed? Are the alarm indicators routinely tested?
Do procedures require routine testing of critical alarms and safety shutdown Y
systems, including primary elements or sensors, shutdown system control and
logic, and final elements such as emergency isolation valves or equipment
shutdown interlocks [determine the need for on-line testing of safety shutdown
systems]?
Do procedures specify response to potential process control system failures Y
[consider loss of input or output signal(s), loss of display screens (loss of view),
loss of memory devices, loss of equipment or system interfaces (gateways), loss of
power, loss of backup power, loss of control program, etc.]?
Do procedures require physical isolation of power source(s) prior to release of Y
equipment for maintenance work (i.e., lockout/tagout)?

34
Research and
Technology

Process Hazards
Analysis Checklist: Piping and Valves
Checklist Type: Process Equipment Review Date:
FILENAME: PIPING.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Is the piping specification suitable for the fluid properties, including maximum Detail design to address all
contaminant concentration? Is the piping specification suitable for potential stress- piping and valves items
corrosion cracking, hydrogen blistering, or other metallurgical concerns, as
applicable?
Are the piping system fabrication requirements [e.g., post weld heat treatment
(PWHT), stress relieving, and nondestructive examination (NDE)] appropriate for
the intended service [consider process upsets including contaminant carryover]?
Is the piping design pressure greater than the maximum operating pressure
[consider maximum pump or compressor discharge pressure]?
Is the piping design temperature greater than the maximum operating temperature
[consider loss of cooling, cooler bypassed, exothermic reaction, etc.]?
Is the piping system adequately designed for thermal growth at maximum
temperature [consider superheated steam, loss of cooling, cooler bypassed, steam-
out, etc.]?
For flashing liquids, is the piping specification suitable to prevent brittle fracture
[consider large pressure drop situations such as venting or draining, etc]?
Is the piping system adequately guided and supported?
Is the piping system adequately designed for cyclical conditions (e.g., pressure,
temperature, and vibration)?

35
Are valve installations that result in moment arm arrangements (multiple or heavy
valves branching from the pipe) adequately designed (e.g., supported or reinforced,
such as bridge welding) to prevent failure of welded connections due to vibration
or mechanical impact?
Are piping dead legs eliminated?
Is the piping system adequately designed to minimize the effects of internal
corrosion or erosion [consider carryover or increased concentration of corrosive
material due to process upset, accumulation of corrosive material in valve seats or
drains, increased erosion or corrosion due to velocity, injection of chemicals such
as anti-foulants]?
Is the piping system adequately designed to minimize the effects of external
corrosion [consider underground installations, insulation on cold piping, exposure
to corrosive atmosphere such as salt water or cooling tower drift, upsets resulting
in release of corrosive materials, etc.]?
Is the piping system adequately designed for cold weather conditions? Where
applicable, are freeze protection and/or heat tracing design adequate?
Is the piping system adequately designed for hot weather conditions?
Does the piping system allow for flushing and/or purging of lines and equipment
for startup or shutdown?
Are process piping connections to utility systems adequately designed and installed
to prevent contamination of the utility system [review requirements for check
valves, double block and bleeds, removable spools, flexible connections, and
blinds]?
Is the piping system adequately designed for thermal expansion of trapped process
material? Is the discharge of the thermal relief device routed to a safe location?
Do the repairs to the piping (materials and methods) comply with the applicable
industry codes and company guidelines?
PROCESS UPSETS:
Have cold weather conditions been evaluated [consider water freezing in low Y
points or in dead-end lines, materials that increase in density, etc.]?
Have hot weather conditions been evaluated [thermal overpressure of blocked-in Y
lines or equipment, etc.]?
Have plugged lines or valves been evaluated? Y
Has rapid closing of automatic valves or check valves been evaluated [determine Y
whether or not hydraulic hammer may occur if a valve closes suddenly; for
example, check valve on the discharge of cooling water supply pump when pump
shuts off]?
Has a valve not opening [may be due to plugging, stem failure, or valve seizing] Y
when demanded been evaluated?
Has a bypass valve (either equipment or control valves) left open or leaking been N/A
evaluated?

FACILITY SITING:
Is adequate fire water coverage available near the piping system (e.g., battery or Y
plot limit manifolds and other valve manifolds)?
Is there adequate access to the piping system in the event of fire or other N Detail design to address all
emergency [consider battery or plot limit manifolds and other valve manifolds that piping and valves items
contain hazardous materials]?

36
If the piping system contains a large inventory of hazardous material (e.g., off-plot
transfer or feed lines), can the piping system be isolated in an emergency?
If emergency isolation valves (either manual, automatic, or remotely operated) are
provided, are these valves appropriate for the process service and valve location
[review requirements for fire-rating of isolation valves; fail-safe position of
isolation valves; and fireproofing of valve actuator, power cables, and instrument
cables of the isolation valves]?
If emergency isolation valves are provided, has failure of the isolation valves been
evaluated [consider valves closing and valves failing to close when demanded]?
Has flange leak been evaluated [consider leaks that may result in flame
impingement on nearby piping or equipment, hydrocarbon release resulting in fire,
and chemical exposure to operators]?
Are the drains and vents located to minimize the potential for damage due to
mechanical impact?
Have flexible piping components (e.g., hoses, expansion joints, and tubing) been
reduced or eliminated where possible? If flexible piping components are installed,
are they designed for maximum operating pressure and temperature? Are flexible
connections adequately protected against possible rupture due to mechanical
impact and fire?
HUMAN FACTORS:
Are battery or plot limit lines/valve labels easy to read (clear and in good Detail design to address all
condition)? piping and valves items
Is the lighting adequate in the unit [consider local instrument panels, battery or
plot limit valve manifold locations, equipment and valves requiring operation
during emergency conditions, etc.]? Is the emergency lighting (light fixtures on
the emergency power circuit) adequate in the unit?
Are all operating valves accessible during normal or emergency operation?
Are manually operated valves positioned to allow proper operation without muscle
strain?
Is access adequate at all valve manifolds (including battery or plot limit) for both
routine and emergency operation and for maintenance? [Review requirements for
changing battery or plot limit blinds.]
Are elevated valves accessible during normal or emergency operation (i.e., access
provided by ladders/platform or chain operator)?
Are valve chain operators properly maintained?
Can critical valves or equipment be closed or shut off from a safe location in a
timely manner?
Has equipment that must be operated in short time sequence (such as valve
switching) been located to facilitate operator actions [i.e., minimum separation]?
Have valve manifolds been arranged to reduce the likelihood of mis-manifolding?
Has valve mis-manifolding been evaluated?
PROCEDURES:
Do procedures require that all drain and vent valves are either plugged, capped, or Detail design to address all
blinded? piping and valves items
Do procedures specify which blinds are to be removed and which spectacle blinds
are to be turned prior to or during startup?

37
Do procedures require routine testing of emergency isolation valves [determine the
need for on-line testing of safety shutdown systems]?
Do procedures control the position of critical valves (e.g., locked or car sealed
open valves beneath relief valves, equipment bypasses or isolation, and area
containment drains)?
Are piping systems inspected at an appropriate interval (depending upon service
and history) to confirm fitness for continued service?
Do procedures require new gaskets (and bolts if needed) to be installed when a
flange closure is opened or broken? Do the procedures provide guidance on the
proper gasket material for the process service?
Do procedures require tightness-testing of all flange bolts prior to startup [concern
is for flanges that were opened during shutdown or flange bolts that may have
loosened due to thermal expansion and contraction]? Do the procedures provide
guidance to prevent over- or under-tightening flange bolts?
Do procedures specify the proper settings for pipe spring hanger supports? Do the
procedures require checking the pipe spring hanger settings prior to each startup
and during normal operation?
Are maintenance personnel trained in the use of piping specifications? Is a process
in place to verify the latest piping specification is used?
For piping modifications and repairs, do procedures require verification that the
repair material to be installed meets the requirements of the piping specification?

Is a program in place for routine testing and inspection of pressure relief devices?
Is documentation maintained regarding the test plan and results for each relief
device [i.e., last test date, results from last test, next test date, etc.]?
Is a program in place for routine testing of flexible piping components (e.g., hoses,
expansion joints, and tubing)?
Are a representative number of new and refurbished valves inspected for the proper
valve packing material upon receipt from the vendor or contract shop?
Do operating crews communicate unusual equipment or instrument status
(bypassed or out of service) in writing? Are operating crews provided with written
temporary operating procedures when equipment or instruments are bypassed or
out of service?
Are the hazards associated with drawing samples communicated to the personnel
responsible for taking the samples and performing the sample analysis? Does the
sampling procedure provide warnings and cautions about the hazards associated
with drawing, transporting, and performing sample analysis? Does the sampling
procedure specify the personnel protective equipment (PPE) to be worn when
drawing or handling the sample?
Is the minimum pressurizing temperature (MPT) of the piping systems documented
and communicated to operations and maintenance personnel?

38
Research and
Technology

Process Hazards
Analysis Checklist: Static Electricity
Checklist Type: Facility Review Date:
FILENAME: Static.DOC PHA Leader:
Chklist/Rev. Date: August 21, 1998 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
TRAINING & COMMUNICATION
Have personnel been alerted to the static hazards associated with the use of plastic Y
buckets and other insulated containers?
Have personnel involved with vacuum truck operations been trained in static Y
electricity hazards and prevention methods?
Have personnel involved in tank and vessel cleaning activities been trained in static Y
hazards and prevention methods?
Have personnel involved in the loading/offloading of static accumulating liquids Y
been trained in how to recognize static electricity hazards and precautions?
TANK TRUCK & RAIL CAR LOADING OF STATIC ACCUMULATORS
For products handled at temperatures < (flash point - 15°F) N/A
Diesel, lube oils and similar high flash products are often static
accumulators, but do not present a high risk of static ignition unless
there is a flammable mixture of air/vapor present. “Switch loading” is
when a high flash product is loaded into a rail car or tank truck after a
previous load of an intermediate or high vapor pressure product. In
this case, there can be a flammable mixture of vapor and air present
and hence static ignition is a concern.
Do procedures include precautions to prevent switch loading? (e.g.
checking the tank truck or rail car for HC gas prior to loading)
If switch loading and/or splash loading may occur, the following questions “for
products handled at temperatures >flash point” apply.
For products handled at temperatures > (flash point - 15°F)

39
1. Are tank trucks and rail cars routinely inspected for internal spark promoters? N/A
(chains, markers and probes that do not extend to the bottom of the
compartment)
2. Is the loading rack designed and operated to ensure a relaxation time of at least N/A
30 seconds downstream of the filter?
3. Are flow rates limited to the velocity recommended in API RP 2003? N/A
1 m/sec until the outlet is submerged, then the velocity (m/sec) is limited to .5/d
where d is the inside diameter of the downspout (m)
4. Is flow indication available so operators can check initial flow rates? N/A
5. Do procedures require waiting at least 1 minute before the loaded tank is gauged N/A
or sampled?
6. Are bottom loaded cars & trucks routinely inspected for splash deflectors? N/A
7. Are top-loading fill pipes fitted with telescoping downspouts? N/A
8. For top loading, is the rack equipped with appropriate bonding or grounding N/A
cables? (Bottom loading is inherently bonded)
9. Do top loading procedures require use of a bonding cable and extending the N/A
downspout to the bottom of the car or truck?
MARINE LOADING OF STATIC ACCUMULATORS
Do the procedures require inerting cargo tanks before and during loading of static N/A
accumulating products? (when an inert system exists)
For loading into a non-inerted barge or ship - (if receiving tanks are inerted, the
following precautions are not required)
1. Have appropriate initial flow rates been established for loading products per N/A
ISGOTT Chapter 7? Initial linear velocity of flow in each tank branch pipe must
not exceed 1m/sec, until the bottom structure is covered and all splashing has
ceased
2. Is flow indication available so operators can check initial flow rates? N/A
3. Do the procedures consider initial flow rates into multiple compartments N/A
simultaneously vs. flow rate at dock valve?
4. Where a filter is installed in the shore pipeline, do the procedures require that the N/A
loading rate be adjusted to ensure at least 30 seconds relaxation time between the
filter and the time it enters any cargo tank?
5. Do the procedures require waiting 30 minutes after loading before dipping, N/A
ullaging or gauging? (unless a sounding pipe is used)
6. Do the procedures prohibit the use of synthetic tapes or ropes in non-inerted N/A
barge or ship tanks?
7. Do the procedures include bonding all metal tapes/gaging devices before N/A
introduction into the barge or ship tank?
FIXED ROOF TANKS
FILLING & GAUGING PROCEDURES FOR STATIC ACCUMULATORS
For liquids handled at temperatures > (flash point - 15°F):
1. Do tank filling procedures specify a maximum fill rate until the tank liquid level N SOP to address
covers the fill piping?
2. Is inlet piping designed to prevent splash filling? Y

40
3. Are gage wells installed in the tank? If no gage well is installed, do the Y
procedures require waiting 30 minutes after filling before gauging or sampling
the tank?
4. Do the procedures prohibit the use of synthetic tapes or ropes in tank gauging? Y
5. Do the procedures include bonding all metal tapes/gaging devices before N/A
introduction into the tank?
HYDROCARBON TANK & VESSEL CLEANING
Do the procedures discuss the potential for static hazards during cleaning operations? Y
Do the procedures require continuous HC gas monitoring? Y
Do the procedures require bonding the wash or steaming hoses to the wall or N
manway?
Do the procedures require that all hoses are checked to ensure that insulated metal Y
fittings are eliminated or bonded and grounded?
Do the procedures require that all ungrounded conductors be removed from the tank Y
or vessel during cleaning?
VACUUM TRUCKS
Do the procedures caution against vacuuming hydrocarbons from plastic containers? N/A
Do the procedures include a discussion of the potential for static ignition due to N/A
vacuum and discharge operations?
Do the procedures recommend gravity discharge whenever possible? N/A
Are the truck hoses in good condition, with no broken sections or broken grounding N/A
wires?
Are all exposed metal hose fittings bonded to the truck through a bonding wire? N/A
Are hoses conductive (<1 megohm resistance)? N/A
Is the testing and inspection program for hoses adequate? Are hoses routinely N/A
inspected (externally) for scrapes, kinks, or other damage?

41
Research and
Technology

Process Hazards
Analysis Checklist: Materials
Checklist Type: General Review Date:
FILENAME: MATERIAL.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Have carbon and alloy steel materials in sour water service been reviewed for N/A Detail design to address all
hardness and their susceptibility to wet H2S cracking? [Note: NACE Standard materials, piping and valves
MR-01-75 provides guidelines on material selection for sour services, including items
maximum hardness limits to prevent sour water cracking.]
Have materials for piping and equipment in hydrogen service been selected or N/A
reviewed for adequate resistance to hydrogen attack in accordance with American
Petroleum Institute (API) Publication 941 (i.e., reviewed using API Publication
941 "Nelson Curves")? [Note: Low molybdenum content carbon-moly alloy
materials are susceptible to hydrogen attack.]
Have all carbon steel vessels, other major equipment, and piping, in amine or
caustic service operating above ambient temperature, been stress-relieved? [Note:
Typical operating temperatures where stress-relieving is required are: 100 °F for
amine equipment, 120 °F for caustic equipment, and 140 °F for steel piping in
amine or caustic service.] Have these equipment and piping services been
inspected for amine or caustic stress-corrosion cracking?
Is the heat tracing for carbon steel piping in amine or caustic service designed to
prevent overheating and stress-corrosion cracking?

42
Have equipment and piping in locations subject to cold weather (i.e., 20 °F or less)
been reviewed per API RP-920 for resistance to cold temperature brittle fracture?
Have storage tanks been similarly reviewed per API RP-650? Have critical
equipment items (e.g., thick-walled vessels and piping) been assigned a Minimum
Pressurization Temperature (MPT) or Minimum Design Metal Temperature
(MDMT), and have these limits been incorporated into the operating and
maintenance procedures?
Has the possibility of auto-refrigeration been evaluated for LPG and other low
boiling point liquid services [concern is for cold temperature brittle fracture], and
the material selection of piping and relief devices specified accordingly?
Are carbon steel air coolers and air cooler outlet piping in hydrotreater reactor
effluent service designed for fluid velocities of 20 feet/second or less to prevent
erosion/corrosion from ammonium sulfides?
Has increased metal temperature in heat exchangers and downstream piping, due to
heat exchanger fouling, been considered in material selection of the exchanger and
piping? Has increased temperature of downstream piping and equipment, due to
bypassing heat exchangers, been considered in material selection? Has increased
temperature of downstream piping and equipment, due to loss of cooling in heat
exchangers (e.g., loss of cooling water, loss of air cooler fans, etc.), been
considered in material selection?
Is the maximum fluid velocity of rich and lean MEA or DEA, and concentrated
sulfuric acid, limited in carbon steel service? [Concern is for excessive
corrosion/erosion due to high fluid velocities; MEA/DEA is typically limited to 6
feet/second, and concentrated sulfuric acid is typically limited to 3 feet/second.]
Has all carbon steel or monel piping and equipment in HF acid service been stress-
relieved after welding?
Have high-pressure hydrotreater reactors and other heavy-wall vessels and piping
constructed of 2-1/4 chrome material and operating between 700 °F and 1050 °F
been reviewed for potential temper embrittlement failure? If such failure is
possible, do the operating and maintenance procedures explain the design
limitation of the material [e.g., do not fully pressure the system when the metal
temperature is below the alloy's maximum possible ductile-to-brittle transition
temperature range, such as 300 °F]?
Has the material selection for auxiliary lube oil and seal oil systems considered the
effects of ambient moisture intrusion, during normal and shutdown operation?
[Concern is for corrosion due to water, with possible damage to mechanical seals,
etc. due to corrosion products.]
PROCESS UPSETS:
For heaters, furnaces or boilers, designed to burn fuel containing sulfur Detail design to address all
compounds, has the possibility of acid condensation during low temperature flue materials, piping and valves
gas operation been evaluated? [Concern is for corrosion of heater ducts, stacks, items
fans, and waste heat recovery heat exchangers due to condensed combustion
products.]
Has chloride stress-corrosion cracking of austenitic stainless steel piping and
equipment been evaluated? [Concern is for exposure to high chloride content
water, e.g., brackish fire water, water-soaked insulation containing chlorides,
coastal hurricane tides, etc.]
Has ammonia stress-corrosion cracking of copper-based alloys been evaluated?

43
HUMAN FACTORS:
Are special materials of construction identified on process flow diagrams (PFD),
piping and instrument diagrams (P&IDs), operating procedures, or other PSI
documentation? Is this information kept current via the MOC process?
PROCEDURES:
Do procedures specify hydrotesting austenitic stainless steel equipment and piping Detail design to address all
systems with water containing less than 50 ppm chloride? [Concern is for chloride materials, piping and valves
stress corrosion cracking.] items
Do procedures require that austenitic stainless steel equipment and piping in sour
or H2S services (i.e., exposed to sulfides) be blanketed with dry inert gas when
shut down, or flushed with soda ash, KOH, or ammonia neutralizing solution,
before opening for inspection and maintenance? [Concern is for ambient moisture
contacting sulfide scale on the surface of austenitic stainless steel, with the
potential for polythionic acid stress corrosion cracking of the stainless materials.]
Do procedures specify thorough water flushing of carbon steel equipment and
piping in amine or caustic service before steaming out to prevent amine or caustic
stress-corrosion cracking?
Do inspection procedures for 1 chrome and 1-1/4 chrome equipment and piping
operating above 800 °F include monitoring for creep embrittlement cracking (i.e.,
hydrogen service, high-pressure steam, etc.)?
Do warehouse procedures require testing of alloy materials for proper alloy content
when received at the facility site (i.e., positive materials identification [PMI]
program)? Are received materials accompanied by proper documentation (i.e., mill
certificates, chemical test reports, ANSI or ASME specification, etc.)?
Are materials segregated and clearly identified when stored, to reduce the
possibility of incorrect material installation?
Are materials stored such that they are protected from ambient conditions as
necessary [i.e., austenitic stainless steel materials protected from chloride salts at
seacoast locations, etc.]?
Are there procedures to order, receive, document, and issue materials for ASME
Code vessel or piping repairs or modifications? Do procedures specify ASME
Code welder qualifications and testing?
Do construction procedures specify that all equipment, piping, instruments, and
structural steel are painted (or otherwise protected) to prevent external corrosion?
Are the painted surfaces inspected and maintained [especially under insulation
when process temperatures are below 180 - 200 °F]?

Are a representative number of new and refurbished valves inspected for the proper
valve packing material upon receipt from the vendor or contract shop?

44
Process Hazards
Research and
Analysis Checklist: Maintenance Technology

Checklist Type: General Review Date:


FILENAME: MAINT.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Has piping and equipment been designed and installed to allow depressurization, Y
draining, and isolation prior to maintenance work?
Has access to equipment for maintenance been evaluated [review crane position Y
and lifts; removal of heat exchanger tube bundles, vessel internals, and rotating
equipment elements; location of monitoring equipment; laydown of tools and
materials; etc.]?
If required, are connections for in-place chemical cleaning or neutralization of N/A
equipment or piping provided?
Does the piping design prevent connection of air tools to other process gas systems N
(e.g., nitrogen or natural gas), such as special connections to the utility air header?
Are equipment and piping that are not designed for field hydrotesting clearly N/A
identified (e.g., relief headers, large overhead vapor lines, refractory lined
equipment and piping, expansion bellows, etc.)?
Are analyzer buildings or enclosures properly ventilated to prevent buildup of N/A
flammable or toxic materials? Alternatively, are flammable or toxic material
detectors provided inside the building to alert personnel of possible danger prior to
entering? Do the detectors alarm to a continuously staffed location as well as
locally, outside the building?
PROCEDURES and TRAINING:
Are there written maintenance procedures for all routine or contemplated N
maintenance activities? Are the procedures appropriate for the complexity of the
job task [i.e., are generic procedures used for routine or simple tasks and job
specific procedures used for nonroutine or complex tasks]?
Are written maintenance procedures developed for nonroutine maintenance Y
activities prior to commencing the work?
Have all personnel involved in maintaining the integrity of process equipment Y
(including contract personnel) received appropriate training? Does the training
include an overview of the process, the hazards associated with the process, and
review of all generic or specific procedures applicable to the employee's job tasks?

45
Is the work permit system understood by all affected employees, maintenance Y
(including contractors), operations, and engineering? Does the work permit clearly
explain the approvals and communication required prior to commencing a
maintenance activity? Does the work permit system require physical inspection of
the job site by maintenance and operations personnel prior to commencing work
[concern is for working on the wrong line or equipment, opening equipment that is
still under pressure or contains toxic material, verification of the correct personnel
protective equipment (PPE) required for the job task, etc.]?
Do procedures require physical isolation of power source(s) prior to release of Y
equipment for maintenance work (i.e., lockout/tagout)?
Do the repairs to the piping or equipment (materials and methods) comply with the
applicable industry codes and company guidelines?
Do field hydrotest procedures include guidance regarding special requirements Y
[e.g., minimum pressurizing temperature for heavy-wall vessels and piping, low-
chloride test water for 18-8 stainless steel, adequate vents for large-diameter or
thin-wall equipment to prevent collapse from external pressure, etc.]?
For maintenance activities where pressure relief devices are isolated or removed, is
backup relief protection provided?
Do procedures require physical inspection of completed maintenance work by Y
operations personnel before "sign-off" of the work or job order?
Do procedures require new gaskets (and bolts if needed) to be installed when a Y
flange closure is opened or broken? Do the procedures provide guidance on the
proper gasket material for the process service?
Do procedures require tightness-testing of all flange bolts prior to startup [concern Y
is for flanges that were opened during shutdown or flange bolts that may have
loosened due to thermal expansion and contraction]? Do the procedures provide
guidance to prevent over- or under-tightening flange bolts?
Do procedures specify the proper settings for pipe spring hanger supports? Do the N/A
procedures require checking the pipe spring hanger settings prior to each startup
and during normal operation?
Are maintenance personnel trained in the use of piping specifications? Is a process Y
in place to verify the latest piping specification is used?
For piping modifications and repairs, do procedures require verification that the Y
repair material to be installed meets the requirements of the piping specification?
Is the piping system's minimum pressurizing temperature (MPT) documented and N/A
communicated to?
Do procedures require that 18-8 stainless steel equipment and piping in sour or N/A
H2S services (i.e., exposed to sulfides) be blanketed with dry inert gas when shut
down, or flushed with soda ash, KOH, or ammonia neutralizing solution, before
opening for inspection and maintenance? [Concern is for ambient moisture
contacting sulfide scale on the surface of 18-8 stainless steel, with the potential for
polythionic acid stress corrosion cracking of the stainless.]
Do procedures for loading and unloading catalyst (i.e., reactors, driers, columns, Y
etc.) include information regarding the hazards of the catalyst and identify the PPE
required when handling either fresh or spent catalyst?
Have all maintenance personnel (including contractors) been trained in the purpose Y
and use of the facility management of change (MOC) procedure? Do all
maintenance personnel understand the MOC definition of "replacement-in-kind"?

46
Do procedures require appropriate approval and supervision of crane use [concern N/A
is for lifts over equipment that contain toxic or hazardous materials, over power
lines, over critical equipment, etc.]? Are lifts reviewed by a rigging specialist
before they are performed?
Do procedures require appropriate inspections and approvals prior to performing Y
hot taps?
Do procedures specify appropriate methods for temporary leak repair (e.g., type of Y
clamp, material, etc.)? Do the procedures include administrative controls that
require a permanent repair be made at the earliest opportunity (i.e., next
shutdown)?
Do procedures prevent changing alarm set points without proper review and Y
authorization? Are alarm changes (set point or priority) communicated to all
affected employees?
Do procedures prevent changing process control system or safety shutdown system Y
control or logic (software) without proper review and authorization? Are process
control system or safety shutdown system changes communicated to all affected
employees?
Do procedures require routine testing of critical alarms and safety shutdown Y
systems, including primary elements or sensors, shutdown system control and
logic, and final elements such as emergency isolation valves or equipment
shutdown interlocks [determine the need for on-line testing of safety shutdown
systems]?
Do procedures require verification that instruments that are deliberately disabled Y
during operation (e.g., shutdown interlocks bypassed to allow testing) are placed
back in service?
Do procedures prohibit the use of pipe wrench extensions ("persuaders") on small N
or special valves in hazardous service [e.g., small piping valves, screwed bonnet
valves, orbit valves, twin-seal valves, etc.]?
QUALITY ASSURANCE:
Do warehouse procedures include verification that materials received are in Y
accordance with the purchase specification?
Are special materials of construction identified on process flow diagrams (PFD), Y
piping and instrument diagrams (P&IDs), operating procedures, or other PSI
documentation? Is this information kept current via the MOC process?
Do procedures require testing of alloy materials for proper alloy content when N/A
received at the facility site (i.e., positive materials identification [PMI] program)?
Are received materials accompanied by proper documentation (i.e., mill
certificates, chemical test reports, ANSI or ASME specification, etc.)?
Are materials segregated and clearly identified when stored, to reduce the Y
possibility of incorrect material installation?
Are alloy materials stored such that they are protected from ambient conditions as N/A
necessary [i.e., 18-8 stainless steel materials protected from chloride salts at
seacoast locations, etc.]?
Are there procedures to order, receive, document, and issue materials for ASME N
Code vessel or piping repairs or modifications? Do procedures specify ASME
Code welder qualifications and testing?
Are a representative number of new and refurbished valves inspected for the proper Y
valve packing material upon receipt from the vendor or contract shop?
Is a program in place for routine monitoring of critical rotating equipment for N/A
excessive vibration?

47
Is a program in place for routine monitoring of lube or seal oil quality at critical N/A
rotating equipment [e.g., monitor for metal fragments, oil degradation,
contaminants, etc.]?
Is a program in place for routine testing of critical turbine overspeed trip devices? N/A
Is a program in place for routine testing and inspection of pressure relief devices? Y
Is documentation maintained regarding the test plan and results for each relief
device [i.e., last test date, results from last test, next test date, etc.]?
Is a program in place for routine testing of flexible piping components (e.g., hoses, N
expansion joints, and tubing)?
Is sufficient PPE available at all times [review the needs for normal operating, Y
shutdown operation, and emergency response situations]?
Is a cleaning and testing program in place to ensure PPE is fit for use? Are Y
locations where clean and used PPE properly segregated and labeled?
Is a program in place to periodically inspect and test cranes and equipment (i.e., Y
lifting slings) used for lifts?
Is a program in place to ensure routine testing and maintenance of critical steam N/A
traps?
HUMAN FACTORS:
Is all equipment labeled and clearly identified (e.g., tag number, unit number, Y
module number, etc.)?
For equipment that must be maintained while the process unit is "on-line," is safe Y
access and egress provided for maintenance personnel (e.g., access platforms, heat
shielding for elevated air coolers, furnace draft fans and soot blowers, furnace
stack sampling systems and analyzers, etc.)?
For maintenance activities where bulky PPE is required, has emergency access and Y
egress been evaluated?

48
Process Hazards
Research and
Analysis Checklist: Relief Systems Technology

Checklist Type: General Review Date:


FILENAME: RELIEF.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
If applicable, are relief systems, relieving devices, and flares designed in Y
accordance with the latest versions of American Petroleum Institute (API)
Recommended Practices (RP) 520 and 521? [Note: API RP-520 was revised in
1990, changing the relief valve sizing equations.]
Has the relief system design capacity been verified, if necessary, for all unit N/A
modifications, expansions, and debottlenecking projects? Are relief system
calculations current and available for review?
If rupture disks are installed under relief valves, does the relief valve sizing N/A
consider flow restriction (i.e., derate) caused by the rupture disk?
Have the relief valve inlet and outlet branch connections been properly reinforced N/A
to prevent vibration failure due to the relief valve opening [severe vibration may
occur when relieving from a high pressure system, or in high- capacity relief
valves]?
Are the inlets and outlets of all relief valves free-draining to prevent trapping N/A
liquid? Are all relief headers free-draining to the relief collection or knock out
(KO) drum?
Are relief header block valves installed to prevent blockage in case of an internal N/A
valve component failure [e.g., are gate valves in relief headers installed with the
stem in the horizontal plane to prevent dropping the gate if the valve stem fails by
cracking or corrosion]?
Are drains from flare stack molecular or other vapor-phase gas seals left open and N/A
designed to be free-draining to prevent accumulation of liquids that could plug the
seal and flare stack? Are the drain lines from vapor or liquid seals winterized to
prevent freezing? Does the sizing of the drain line consider the possibility of
plugging due to corrosion products?
Is each ASME Pressure Vessel or Boiler Code vessel protected by a Code- N/A
approved relief device?
Are the relief headers designed to accommodate the maximum piping expansion N/A
anticipated for the highest temperature relief condition?
Are the relief headers provided with continuous fuel gas or natural gas purge to N/A
ensure that oxygen cannot accumulate or be drawn into the system? [Concern is
for an explosive mixture forming in the relief system.]

49
Is the relief system adequately designed to minimize the effects of internal N/A
corrosion or erosion [consider venting or relief of sulfur compounds, chloride or
fluoride compounds, caustic, amine, etc., with the potential for corrosion, stress-
corrosion cracking, and other materials problems]?
If the relief system handles heavy oils (residuum, vacuum bottoms, etc.), are N/A
branches and headers designed to prevent plugging [e.g., heat tracing, heated "gut"
line, flush oil, heating coils at the KO drum, etc.]?
Have flexible piping components (e.g., expansion joints and bellows) been reduced N/A
or eliminated where possible? If flexible piping components are installed, are they
designed for maximum relief pressure and temperature? Are flexible connections
located to minimize damage and possible rupture due to mechanical impact or fire?
Are flexible connections designed to minimize collection of liquids and corrosion
products in the bellows or piping run?
Is relief header sizing based on the maximum relieving capacity of each relief N/A
valve? [Selecting the next largest orifice size may significantly increase the relief
valve capacity over the minimum required by the process, possibly impacting the
relief system design capacity.]
Has the possibility of auto-refrigeration been evaluated for LPG and other low N/A
boiling point liquid services [concern is for cold temperature brittle fracture], and
the material selection of piping and relief devices specified accordingly?
PROCESS UPSETS:
Have cold weather conditions been evaluated [consider water freezing in relief N/A
header low points or in dead-end lines, materials that increase in density, etc.]?
Are flare combustion controls, including pilot burner flame front generators, N/A
provided with a reliable, uninterruptable source of electric power? [In a general
power failure, the flare may be required to remain in operation to safely dispose of
flammable materials.]
Has rapid closing of relief valves been evaluated [determine whether or not Y
hydraulic hammer may occur if a relief valve closes suddenly, for example, if a
high-pressure liquid relief valve on the discharge of a pump slams shut after
opening]?
Has rapid closing of automatic valves or check valves been evaluated [determine N/A
whether or not hydraulic hammer may occur if a valve closes suddenly; for
example, check valve on the discharge of cooling water supply pump when pump
shuts off]?
Has the need for redundant relief valves been evaluated [e.g., dirty or fouling Y
services requiring frequent testing and inspection of relief valves, critical services
where failure of relief valves to reseat may result in significant production loss,
etc.]?
FACILITY SITING:
Have credible worst-case releases of hazardous materials from extinguished flares, Y
atmospheric process or tank vents, or from relief valves that exhaust to the
atmosphere been evaluated [concern is for ground-level concentrations of toxic or
flammable materials]?

50
Has the maximum heat release from the flare during credible worst-case relief N/A
scenarios been evaluated with respect to ground-level personnel, nearby tankage
and equipment, and traffic on adjacent roads? [Depending upon the location and
height of the flare stack, concern is for significant flare tip heat releases that may
endanger operating or maintenance personnel in the area, or that may cause
overheating of flammable materials stored nearby. When maximum relief cases
are redefined during the lifetime of the facility, the potential risk to nearby
personnel and equipment should be evaluated based on the maximum heat that
may be released from the flare stack.]
Is there adequate emergency access to the flare stack and adjacent equipment in the N/A
event of fire [consider burning liquids from flare tip, igniting grass around base of
stack]?
HUMAN FACTORS:
Are relief system and flare alarms and instrument readings displayed at a N/A
continuously staffed location?
Is lighting at the relief drum and flare stack control stations adequate? N/A
Are all flare and relief system operating valves and controls accessible during N/A
normal or emergency operation?
Are relief system controls and instruments identified with permanent signs or tags? N/A
Are flare seal drain valves located to allow monitoring the filling and draining of N/A
the flare seal and ensure the safety of personnel [consider potential exposure to
sour gas, sour water, LPG, benzene, etc.]?
PROCEDURES:
Is a program in place for routine testing and inspection of pressure relief devices? Y
Is documentation maintained regarding the test plan and results for each relief
device [i.e., last test date, results from last test, next test date, etc.]?
Is a program in place for the routine replacement of rupture disks at the end of their N/A
useful lives, as recommended by the rupture disk manufacturer? Is documentation
maintained regarding the replacement plan?
Are procedures in place to document critical process safety information for each Y
relief valve and rupture disk: sizing criteria (vapor, liquid, and mixed phase);
maximum relieving material flow rate; fluid properties (molecular weight, density,
viscosity, temperature, etc.); set pressure; equipment protected; design relief case
(blocked discharge, fire, utility failure, etc.); flange size and rating (inlet and
outlet); orifice size; and relief valve or rupture disk manufacturer and model
number?
Do procedures require that changes to relief valve set pressures are reviewed Y
through the Management of Change process?
Do procedures prevent unintentional closure of block valves upstream or Y
downstream of relief valves [e.g., chain-locked or car-sealed open valves, operator
checklists, three-way/non-closing valves, etc.]?
Do procedures require all relief valve bypasses to be closed during startup? N/A
Do maintenance procedures specify proper rupture disk installation, including bolt N/A
tightening and disk orientation with respect to flow?
Do procedures prevent the accidental filling of relief headers with liquid if they are N/A
not designed to support the weight of a liquid-filled line?

51
Do operating crews communicate unusual equipment status (bypassed or out of Y
service) in writing (e.g., relief bypass valves that are open during normal
operation)? Are operating crews provided with written temporary operating
procedures when equipment is bypassed or out of service?
Are the hazards associated with atmospheric relief valve, tank, or process vents Y
documented and communicated to personnel whose duties take them into the
vicinity of these vents [e.g., high noise levels from high-pressure boiler safety
valves, toxic or flammable vapors from tank or process vents, etc.]?

52
Process Hazards
Analysis Checklist: Emergency Response
Checklist Type: General Review Date:
FILENAME: ER.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/N Reference/Comments
A
Is there a written emergency response plan for this unit that addresses credible Y
emergency scenarios (e.g., toxic material releases, fire, explosions, sabotage, bomb
threat, etc.)? Are copies of the written plan readily available to all affected personnel?
Does the emergency response plan include an incident command structure (or other Y
authority and communication structure) that outlines personnel responsibilities during
emergency situations?
Does the emergency response plan specify evacuation routes and personnel assembly or Y
refuge areas?
Does the emergency response plan contain emergency notification requirements, Y
including a list of contact names and phone numbers, for both company and outside
responders? Is this list up-to-date?
Does the emergency response plan identify essential personnel who must remain on-site Y
during an emergency [confirm that a sufficient number of trained people who are
knowledgeable in the hazards of the process and emergency response are available at
all times, either on-site or via rapid call-out]?
Does the emergency response plan identify the resources (personnel and equipment) Y
available from outside sources (i.e., community fire departments, mutual-aid partners,
etc.)?
Does the emergency response plan include procedures to account for all personnel Y
following an incident, including employees, contractors, and visitors?
Do procedures specify proper response to warning sirens, whistles, or horns? Are these Y
warning devices routinely tested?
Does the emergency response plan specify which communication channels are Y
restricted for use by emergency responders during an incident?
Does the emergency response plan include provisions for off-site traffic control and Y
access for off-site responders?
Does the emergency response plan specify the reporting requirements for the various Y
incidents that may occur at the facility, including reporting to facility and company
management as well as to outside agencies?
Has an incident command center, stocked with necessary reference information (e.g., Y
emergency response plan, site and community maps, call-out lists, etc.) and
communication systems been established? For large facilities, is this information
available at multiple locations?

53
Are hypothetical emergency drills routinely conducted? Do outside sources (i.e., Y
community fire departments, mutual-aid partners, etc.) participate in the hypothetical
drills? Are procedures in place to critique the response to hypothetical drills and
resolve the recommendations from these reviews?
Is a program in place to verify all affected personnel receive initial and refresher Y
training in the emergency response plan? Is the refresher training provided on an
annual basis and whenever updates to the plan are made?
Has the adequacy of the outside agency response program been evaluated [consider Y
familiarity with the hazards of the process, knowledge on how to respond to emergency
situations, physical condition of outside agency members, etc.]? Has the adequacy of
the outside agency equipment been evaluated [consider availability and adequacy of
fire-fighting equipment, including foam, adequacy and integrity of personnel protective
equipment, and amount of equipment available]?
Do procedures specify the method and frequency for inspection, maintenance, service, Y
and testing of emergency response equipment (i.e., fire suppression and extinguishing
systems, personnel protective equipment, etc.)?

54
Process Hazards
Research and
Analysis Checklist: Utilities Technology
Checklist Type: General Review Date:
FILENAME: UTILITY.DOC PHA Leader:
Chklist/Rev. Date: January 1, 1996 Location:
Prepared by: Chevron Research and Technology Company Unit/Project:
MOC#:
Checklist Questions Y/N/NA Reference/Comments
DESIGN:
Is there a design standard for safe connection (both permanent and temporary) of N/A
utilities to process streams, including safeguards to prevent backflow into the
utility system, and proper isolation of the utility from the process when it is not in
use?
Are lower-pressure steam systems, which are supplied with steam by let-down N/A
stations from higher-pressure systems, provided with suitable over-pressure
protection [i.e., is the pressure safety valve (PSV) on the lower pressure line sized
for the let-down control valve in the full open position]?
Have steam traps been designed for all credible operating scenarios [e.g., startup, N/A
extreme cold weather, upset conditions, etc.]? Have existing steam traps that
frequently fail been evaluated for proper sizing or application?
If utility system PSVs relieve to the atmosphere, is it possible for heat exchanger N/A
tube leaks (or other process leaks into the utility system) to create a hazard at the
utility relief valve vent outlet (concern is for hydrocarbon or toxic material release
to atmosphere, may want to consider routing PSV discharge to closed relief system
or safe location)?
Are all steam-generating heat exchangers designed and/or operated with routine N/A
manual or continuous blowdown to prevent sludge from accumulating in the shell
[concern is for sludge buildup resulting in tube or tubesheet failure]?
Have high-pressure steam system PSV installations been designed to adequately N/A
resist the thrust moment imposed on the piping when the PSV opens? Is the PSV
vent pipe located to exhaust steam away from platforms and other occupied areas?
Is the PSV vent pipe drained to remove accumulated rainwater, which could be
heated by the exhaust and expose personnel when it falls? Has personnel exposure
to the noise of an atmospheric relief been evaluated?
Are all critical utility service indicators and alarms routed to a continuously staffed
location?
Are redundant main power lines or cables physically separated [i.e., separated to N/A
prevent a single incident, such as fire or mechanical impact, from causing the
failure of redundant lines or cables]?
Are utility instruments adequately heat traced and insulated or designed to prevent N/A
cold weather freezing and plugging?

55
Is the utility piping system adequately designed for thermal growth considering the N/A
maximum possible temperature [e.g., superheated steam with maximum possible
superheat, or steam made up from desuperheated high-pressure steam through a
let-down station and the desuperheater fails closed]?
For services where the utility piping specification changes to a lower design rating N/A
after a control valve, is the downstream piping specification suitable for upset
situations with the control valve wide open?
Are safety showers and eye wash stations and their water supplies protected from N/A
freezing in cold weather or from overheating the water due to sun radiation?
Are data sheets and other process safety information (PSI) for critical utility N/A
equipment and piping current, complete, and accurate? Are they readily available
to the operators? [Note: Include PSI for vendor-supplied equipment, such as
chemical injection pumps, PSVs, etc.]
PROCESS UPSETS:
Has loss of each pressure level of steam (e.g., low, medium, and high pressure) to N/A
the process or utility unit(s) been evaluated?
Has loss of boiler feedwater to the process or utility unit(s) been evaluated? N/A
Has loss of cooling water to the process unit(s) been evaluated [determine whether N/A
or not the process unit(s) are designed fail-safe]?
Has loss of the main fire water supply to the process or utility unit(s) been N/A
evaluated [determine whether or not there are alternative sources of water to fight
fires--cooling tower basins, nearby waterways or ponds, etc.]?
Has loss of normal plant power, including partial loss of power and total loss of N/A
power, to the process or utility unit(s) been evaluated? [Note: Include evaluation
of power to emergency communications, emergency lighting, control room HVAC,
flare pilot flame front generation panel, field solenoid trip valves, electronic
governors for machinery, security gates, emergency block valve MOVs, etc.]
Has loss of emergency power [from an emergency generator and/or uninteruptable N/A
power supply (UPS)] to the process or utility unit(s) been evaluated [determine
whether or not the process or utility unit(s) are designed to be fail-safe; e.g., has
the distributed control system (DCS) software been configured to open/close
control valves or to leave them in their last positions if total power is lost to the
DCS]?
Has loss of instrument air to the process or utility unit(s) been evaluated N/A
[determine whether or not the process or utility unit(s) are designed to be fail-
safe]?
Has loss of plant or utility air to the process or utility unit(s) been evaluated? N/A
Has loss of natural gas or fuel gas to the process or utility unit(s) been evaluated? N/A
Has a momentary dip in the pressure of the fuel gas supply to fired heaters or N/A
boilers been evaluated [determine if loss of burner(s) flame may occur, followed by
buildup of flammable mixture and possible explosion]?
Has high fuel gas pressure been evaluated [may be caused by fuel gas pressure N/A
regulator failure]?
Has contaminants (e.g., H2S, amine, caustic or solids) or the wrong concentration N/A
(e.g., low or high BTU-content components) in the fuel gas or fuel oil supply to the
fired heaters or boilers been evaluated?
Has liquid hydrocarbon carryover into the fuel gas supply to fired heaters or N/A
boilers been evaluated?

56
Has loss of nitrogen to the process or utility unit(s) been evaluated? N/A
Has a leak in a process unit to a utility stream that returns to the Utilities Area been N/A
evaluated [e.g., cooling water exchanger tube leak to returned water, steam heater
tube leak to condensate, etc.]?
Has excess or loss of chemicals in the utility stream been evaluated, including N/A
evaluation to downstream process units [consider excess or loss of: chlorine or
other biocide, water treating chemicals for boiler feedwater (BFW) and cooling
water, oxygen scavengers and filming amines for steam, etc.]?
FACILITY SITING:
If emergency isolation valves (either manual, automatic, or remotely operated) are N/A
provided to isolate utility supply headers, are these valves appropriate for the
service and valve location [review requirements for fire-rating of isolation valves;
fail-safe position of isolation valves; and fireproofing of valve actuator, power
cables, and instrument cables of the isolation valves]?
If emergency isolation valves are provided, has failure of the isolation valves been N/A
evaluated [consider valves closing and valves failing to close when demanded]?
Has an accidental release of hazardous materials that could result in a hazardous N/A
airborne cloud been evaluated [e.g., chlorine, ammonia, hydrogen sulfide, etc.]?
Are chemical injection facilities that could be hazardous to personnel or the N/A
environment identified (by signs, color coding, pavement striping, etc.)? Are
chemical spills prevented from entering the storm water or oily water drain
systems? Has the need for safety showers and eyewash stations to be situated
nearby been evaluated?
Has the need for alarming the activation of safety showers and eye wash stations N/A
been considered [i.e., are facilities remote from frequented areas, potentially
preventing awareness of an incident and delaying assistance to personnel who
activate emergency stations]?
For process units handling flammable materials, are critical utilities (such as power N/A
and instrument cables, cooling water, instrument air, etc.) adequately protected in
the event of fire? Are they routed away from likely sources of leaks and fires
(such as fired heaters and pump rows), adequately fireproofed, or located in a
nonhazardous area?
Are utility header valves and associated instrumentation accessible for N/A
maintenance?
Are the Utilities Area control building air conditioning and pressurization adequate N/A
to protect the electronic instrumentation? Are they adequate to prevent intrusion
of toxics, flammables, or corrosive contaminants (if applicable)?
Has control building utility supply failure (including HVAC failure), coincidental N/A
with a release of hazardous materials in the process unit or from a nearby process
unit, been evaluated?
HUMAN FACTORS:
Can critical utility valves or equipment be closed or shut off from a safe location? N/A
Is the lighting adequate in the unit [consider local instrument panels, battery or N/A
plot limit valve manifold locations, equipment and valves requiring operation
during emergency conditions, etc.]? Is the emergency lighting (light fixtures on
the emergency power circuit) adequate in the unit?
Are utility lines and valves clearly labeled, including flow direction? N/A

57
Are the utility field instruments that are routinely monitored by operations N/A
personnel easily accessible to ensure information is read in accordance with
recommended frequency [consider instruments or areas that are difficult to reach,
such as climbing 40 feet of ladder or squeezing into close quarters]?
Are the engineering units of similar instruments consistent [e.g., do the steam and N/A
boiler feedwater meters all display flow in gpm or lbs/hr, and the fuel gas and
nitrogen meters in SCFH or SCFD]?
Are field instrument indicators routinely checked for accuracy? N/A
Are field instrument ranges appropriate for the service [e.g., avoid using a 0-500 N/A
psig pressure gage on a 50 psig steam system]?
Are the communications facilities between the Utilities Area and other process N/A
units adequate for clear and uninterrupted communications during both normal and
emergency situations [e.g., telephone land lines, radio, computer network, and E-
mail, and are systems redundant and/or secure]?
Is the control room lighting adequate [review direct and indirect lighting]? Is the N/A
control room emergency lighting (light fixtures on the emergency power circuit)
adequate?
PROCEDURES:
Do procedures prohibit connection of drinking or potable water supply lines to any N/A
process or other utility system, even temporary connections during shutdowns and
maintenance work? [Note: Drinking water should only connect to sinks, drinking
fountains, sanitary facilities, safety showers, and eye wash stations.]
Do procedures control connection of fire water to process systems or to other N/A
utility systems [e.g., to provide water for hydrotesting piping and equipment
systems]?
Do procedures prohibit connecting air tools to any other utility except to a N/A
compressed air system? [Note: Use of nitrogen for air tools in a confined space,
for example, may expose personnel to nitrogen asphyxiation.]
Do procedures prohibit use of hose connections on process systems [e.g., air hose N/A
connection on fuel gas system]?
Do procedures specify that all blinds and drop-out spools in utility connections to N/A
process equipment are turned to their "safe" position before introduction of
hazardous materials at startup of a process or utility unit [e.g., pre-startup
checklist, etc.]?
Do emergency procedures include loss of steam? N/A
Do emergency procedures include loss of normal electric power? N/A
Do emergency procedures include loss of cooling water? N/A
Do emergency procedures include loss of instrument air? N/A
Do emergency procedures include loss of natural gas or fuel gas? N/A
Do emergency procedures include loss of boiler feedwater? N/A
Do procedures specify response to potential process control system failures N/A
[consider loss of input or output signal(s), loss of display screens (loss of view),
loss of memory devices, loss of equipment or system interfaces (gateways), loss of
power, loss of backup power, loss of control program, etc.]?

58
Is there a procedure or program to place winterization measures in service before N/A
cold weather arrives [e.g., steam traps and tracing, electric tracing, insulation,
etc.]?
Are steam traps routinely inspected and repaired or replaced? [Note: Concern is N/A
for flooding equipment or tracers, leading to loss of heating, with potential for
freezing, rupture, and loss of containment.]
Do procedures prevent the use of utility hoses for temporary process piping? N/A
Is there a procedure for routine inspection of utility hoses? N/A

59
Process Hazard Analysis
WRAP-UP DISCUSSION CHECKLIST

A. Safety/fire protection (consider the participation of a specialist from the Safety Department for this discussion)
1. Is the fire water supply adequate? What is the reliability of the fire water supply pumps? Y

2. Review the availability of fixed fire equipment, such as hydrants, monitors and hose reels. Are the
number and location of fixed equipment adequate? Y

3. Are the areas with high risk of fire accessible from portable fire equipment, such as pumper trucks? Y

4. Is training provided? Adequate? Drills conducted with plant equipment? Y

5. Are hazard communications, such as material safety data sheets (MSDS), available to employees? Y

6. Are the emergency shutdown (ESD) systems routinely tested? By whom and how often? Are there
any hazards associated with testing the ESD systems? Y

7. Is the electrical area classification of the process unit appropriate for the materials processed? Is new
equipment reviewed for compliance with the electrical area classification? Y

8. Is self contained breathing apparatus available and is training provided? Y

9. Are showers/eyewashes tested and alarmed? Y

10. Is an Industrial hygiene program in place? What areas are covered? Y

11. How is Asbestos abatement handled in the plant? N/A

12. Are Noise surveys conducted? Are high noise areas identified? Is protection provided? Y

13. Is Lighting adequate for all work areas in the plant? Y

14. Is Ventilation for labs and sample areas adequate? Y

15. Are special safety areas clearly delineated (noise, chemicals, etc.)? Y

B. Emergency response (consider the participation of a Safety Engineer for this discussion)
In-plant Emergency Response Plan
1. Describe your emergency response training program for in-plant personnel.

2. Which in-plant personnel are expected to respond to an accidental release?

3. Describe the PPE (protective clothing) that personnel would wear to respond to an accidental release.
Where is the PPE located and who maintains it?

4. What medical training is provided to in-plant personnel for response to injuries?

5. What evacuation plans are in place?

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 60
Process Hazard Analysis
WRAP-UP DISCUSSION CHECKLIST
6. Are hypothetical drills conducted? Are all employees in area involved?

7. Review injury reports of this unit over the last five years (may be reviewed in conjunction with
discussion regarding previous incidents)

C. Procedures
1. Are the operating procedures for this unit currently up-to-date? Do they cover startup, shutdown,
normal operation and emergency situations? Are they accessible to all employees who are expected to
use them? TO BE REVISED ASAP

2. Are there any procedures of particular concern that were not discussed during the detailed PHA
review? N

3. Are there any procedures that seem to be done incorrectly on a regular basis by less experienced
personnel? N

4. Are maintenance procedures available and up-to-date? Y

5. Are drawings and sketches used to clarify written text? Y

6. Do the procedures include explanation of expected system responses for operator actions? Y

7. Are there incidents that regularly occur on startup or shutdown that are not addressed in the
procedures?

• storage and handling? • reactivity concerns?


• personnel exposure hazards? • regulatory compliance?
8. Are procedures available that cover loading/unloading for:

• static electricity? • control of drivers?


• quality control? • regulations?
• personnel hazards?
D. Loss of Utilities
1. Review and document the global loss of the following utilities that apply to the process unit being analyzed. Note
that local loss of utility, such as loss of power, instrument air, or cooling water, to a single piece of equipment or
control valve is typically covered during line-by-line analysis when reviewing the equipment or controls that
require that utility.

2. The intention of the general discussion is to identify system interactions that may be hazardous, such as requiring
an operator to block in equipment to prevent backflow or remove heat to prevent overpressure.

3. Each utility outage should be documented separately. Where loss of a particular utility has significant
consequences, review and document the reliability of the utility supply system. Where applicable, review loss of:
• Instrument Air•Electricity
• Plant or Utility Air•Steam (150 PSI, 450 PSI, 850 PSI, etc.)
• Cooling Water•Nitrogen or Inerting Gas
• Fuel Gas

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 61
Process Hazard Analysis
WRAP-UP DISCUSSION CHECKLIST
E. Siting/control room location (discussion should be documented to ensure compliance with OSHA Regulation 29 CFR
1910.119)
1. Are there any concerns about control room siting relative to releases in adjacent units? N

2. Is the control room pressurized? Is inlet air filtered and/or treated? Is loss of control room pressurization
monitored by an alarm system?

3. Is the control building capable of withstanding blast overpressure resulting from credible release and
subsequent explosion in the area? Y

4. Do feeders on critical control instruments and power supplies enter the building overhead or underground?

5. Are control room fire suppression systems compatible with both humans and instrumentation? Y

F. Previous Incidents (discussion should be documented to ensure compliance with OSHA Regulation 29 CFR 1910.119;
consider the participation of a specialist from the Safety Department for this discussion)
1. Confirm that the facility has an incident investigation procedure. Y

2. Review incident reports of this or similar units at the facility over the last five years.

3. Review incident reports of this or similar units at other facilities of which team members have knowledge.

4. Discuss the history of near-miss incidents in this or similar units that may not be documented but of which the
team has knowledge.

5. Have recommendations from previous incident s been implemented? Y

6. Are previous incidents with severe consequences likely to occur again, given the current practices and
procedures? N
G. Human Factors (discussion should be documented to ensure compliance with OSHA Regulation 29 CFR 1910.119)
1. Are there any operating or maintenance procedures that may present a specific hazard? N

2. Are there cases where valve arrangements are confusing? N


3. Are there areas where correct procedures (PPE, isolation) are so difficult that a person may attempt to shortcut,
resulting in hazardous material release or personnel injury? Y

4. Are there any areas where routine operator monitoring is so difficult (climbing 40 feet of ladder, squeezing into
close quarters) that an operator may ignore the reading?

5. Are there any instances where instruments (board or local) necessary for safe operation of the plant, or routine
adjustments, are poorly placed and difficult to see? N

6. Are there any “nuisance” alarms that the operators either routinely ignore or disable? N

7. Are field manifolds or local panels adequately labeled? Is the lighting in the area sufficient? Y
H. Testing and Inspection (consider the participation of a specialist from the Inspection Department for this discussion)
1. Describe the Critical Equipment Program

2. Describe the Corrosion/Erosion Monitoring Program

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 62
Process Hazard Analysis
WRAP-UP DISCUSSION CHECKLIST
3. Describe the Instrument List and Testing Frequency

4. Describe the PSV Testing Program

5. Describe the Shutdown Schedule

6. Describe NDT Frequency and Tests


7. Describe how Suitability of Materials for Intended Service is Determined
8. Describe the Documentation System
I. Maintenance (consider the participation of a specialist from the Maintenance Department for this discussion)
1. Do written maintenance procedures exist for repair of equipment in this plant? Y

2. Describe procedures used for equipment isolation, lockout/tagout and confined space entry.

3. Describe how maintenance workers are trained on new systems introduced into this plant.
4. Is equipment designed for draining, neutralization, and purging?

5. Describe the vehicle entry system in place for this plant.

6. If there are hazards associated with the unit (such as H2S, NH3, CL2, LPG or H2SO4), how are the hazards of the
unit communicated to the valve repair personnel?
J. External Events
1. Are there any process hazards created by hot weather during the summer (inadequate cooling)?
2. Are there any problems created by freeze-up during the winter?

3. Are there any concerns about flooding?

4. Are there any concerns about earthquakes or other natural disasters?

5. Is seismic activity a concern in this area? For what seismic zone is the plant designed?

6. Are there any concerns about sabotage? Is this plant accessible from the fence line?

7. Any other external events that might have effects on the plant?

K. Previous hazards analysis studies (discussion should be documented to ensure compliance with OSHA Regulation 29
CFR 1910.119)
1. If the present PHA analysis is the initial analysis that is intended to comply with the OSHA Regulation,
document that this is the initial PHA analysis and that no previous PHA analysis has been performed. NO
PREVIOUS PHA

2. Have the hazards identified in previous PHA analyses been adequately addressed in this analysis? N/A

3. Have the recommendations from previous PHA analyses been resolved? N/A

4. When was the previous PHA analysis performed? N/A

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 63
5.0 ADDITIONAL CONSIDERATIONS AND ACTION PLAN

5.1 DESIGN REVIEW ADDITIONAL CONSIDERATIONS

5.2 “WHAT IF” ADDITIONAL CONSIDERATIONS

5.3 “CHECKLIST” ADDITIONAL CONSIDERATIONS


5.1 “DESIGN REVIEW RECOMMENFDATIONS

Section Description: General

Item Issue Raised Additional Considerations Action By P&ID No.


1. Design flexibility to allow use
of Tank 3 for both wash tank
• Detail design to
Design Team
continue with this
and storage service
concept
2. Installation of 8” emulsion pad • Existing provision to Design Team
take off to be through a be reviewed
spreader between 4 & 5ft
height
3. Why are steel pads required ? • To be reviewed at Design Team
( see design review item 11) detail design
4. Have we combined tank repair • Review to be carried Design Team
work with the wash tank out to determine what
conversion project has been covered
5. Is provision made to • To be considered Design Team
determine sand build- up in
the new wash tank
6. Where is waste heat recovery • PE to discuss with Project
from? operations and advise Engineer
design team
7. Is control and safety system • To be addressed by Design Team
separated ensuring separation
8. Is design team considering • To be considered Design Team
adding sampling points close
to the wash tank
9. 8” emulsion pad draw off from • PE to review and Project
Tank 01 not provided advise design team Engineer
presently
10. Why is the water line • PE and Operations to Project
maintained at 4ft level and not evaluate and advise Engineer
increased to 5ft for instance design team
11. Is it possible to have two (2) • Nozzle can be Design team
nozzles for the Agar probe provided at two points
with possibility of alternating if desired installation.
between the two if required.
12 Wash tank Instruments • Instruments function Project Team
function (Control and Operating
philosophy) to be
Chevron Research and Technology Process Hazard Analysis Workshops
Fire and Process Safety Team 2/27/2004
Wrapup.doc 65
reviewed with Process
and Operation group
13 Spectacle blind • Spectacle blind to be Project Team
added to all lines
common to storage
and wash tank service
to prevent co-mingling
14 LSL 803A not clouded as new • New instruments to be Design Team
Instrument clouded
15 Installation of corrosion • Provision to be Design Team
coupon explored
16 Line from turndish is 1” in • To be checked Design Team
new design whereas 2” I the
existing
17 Temperature Indicator on inlet • To be included Design Team
and outlet lines
18 Notes to indicate valves in the • To be implemented Design Team
bottom lines as NC
19 Is LTI 803B (Internal hanging • To be reviewed with Design Team
Fisher LG) required Operation and Process
group
20 Monitoring/Sampling of SRB • To be reviewed with Design Team
growth to determine if growth Operation and Process
from the tank or from the field group
21 As Built drawings • After detail design and Project team
construction

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 66
5.2 “WHAT IF” RECOMMENFDATIONS

Section Description: Wash Tank Designs Tie-Ins


Design Intention: Wash Tank ABJ-803 Piping & Instrumentation

Note: Considerations with a final risk ranking of 1, 2 or 3 are highlighted in green

Item What If……….? Additional Considerations Action By P&ID No.


1. VG-60 0nline 1455 left open • Spectacle blind to be Design Team TNK.PI.10-
provided. 3003
• LOTO provision
2. VG-60 on line 1042 fail close • Consider Installing a Design Team TNK.PI.10-
(Internal mechanism drop to RO or a Globe valve 3003
close valve) downstream of the ball
valves
3. Offshore send excess gas • Convert PSVs to Project Team TNK.PI.10-
PVSVs. 3003
• Communication
between Platform and
Offshore
4. Isolation valves on all outlet • Maintenance Access to Project Team TNK.PI.10-
lines faulty (Maintenance) be provided 3003
5. Presence of H2S • On-line monitors to be Design Team TNK.PI.10-
provided 3003
6. LTI 803A/LSL 803/803B fails • Control & Operating Project Team TNK.PI.10-
philosophy to be 3003
reviewed
7. LSH 803 fails • Ensure clean out Design Team TNK.PI.10-
connection is 3003
accessible
8. LIT 803 gives false reading • Control & Operating Project Team TNK.PI.10-
philosophy to be 3003
reviewed
9. LAH 803 fails to alarm • Control & Operating Project Team TNK.PI.10-
philosophy to be 3003
reviewed
10. Tanks hit by Lightning • DPR to check DPR Project TNK.PI.10-
regulation and advise Engineer 3003
design team
11. One or more sample points • Ladder rung to be Design Team TNK.PI.10-
blocked provided to access 3003
sampling points
Chevron Research and Technology Process Hazard Analysis Workshops
Fire and Process Safety Team 2/27/2004
Wrapup.doc 67
12. No maintenance access for • To provide Design Team TNK.PI.10-
PSVs and flame arrestors on maintenance access 3003
tank top
13. Fire on tank 3 or adjacent tank • SOP to address Process/Operat
ion Group

Section Description: Wash Tank #1 Interface Tie-IN with wash Tank #3


Design Intention: Wash Tank #1 Interface with Wash Tank #3 Piping & Instrumentation
14. High pressure from relief line • Integrate rupture disc Project Team
(AT 1461) – Rupture disc or monitoring to EDMAC
line open • Incorporate CSO/CSC
when switching
between two wash
tanks to SOP
15. Relief line opens to both • To provide spectacle
tanks blind on CSC/CSO
• Revision of SOP

Section Description: Wash Tank Sump/Sump Pump (PBH 803)


Design Intention: Wash Tank Water Transfer Pump Piping & Instrumentation
16. LSH 803 fails • Pit sump & pump to be Design Team TNK.PI.10-
automated. 3003

• Existing P & ID to be SMP.PI.10-


revised to reflect 0191
automated sump &
pump

17. Flame arrestor blocked • Flame arrestor to be Design Team TNK.PI.10-


tagged 3003

SMP.PI.10-
0191

Section Description: Produced Water Transfer System


Design Intention: Produced Water Transfer System Piping & Instrumentation
18. LSL 803/B fails • Instrumentation tags to Design Team DHY.PI.10-
be checked 3003
• Control & Operating
Philosophy to be TNK.PI.10-
reviewed 2021

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 68

Section Description: Dry Oil Transfer System


Design Intention: Dry Oil Transfer System Piping & Instrumentation
19. FCV 800 fails open • Consider installing a Design Team DHY.PI.10-
check valve 0102
downstream PSV
TNK.PI.10-
3003

20. LCV 800 fails to close • SOP to address new Project Team DHY.PI.10-
pump system. 0102
• Pump logic to be
reviewed TNK.PI.10-
3003

Section Description: Instrument Air


Design Intention: Instrument Air Piping & Instrumentation
21. Four (4) different tie-in points • Tie-in points to be Project Team IAS.PI.10-
reviewed with Process 9604
& Operations group
TNK.PI.10-
3003

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 69
5.3 “CHECKLIST ” ADDITIONAL RECOMMENFDATIONS

Section Description: Storage Tanks


Design Intention:

Item Checklist Questions Additional Considerations Action By


1. Is the area around the storage graded to prevent • Separate project group HES
pooling of product (concern for fire) or water to address.
(concern for external corrosion) at the base of
the tank?
• HES to follow up
2. Does storage tank gaging/sampling equipment • SOP to address Operations/
provide protection against vapor Process group
release/personnel exposure [concern is for
personnel exposure to H2S or inert blanketing
or release of flammable vapors]?
3. Are tank suction and fill lines and valves • Detailed design to Design Team
clearly labeled, including flow direction? address
4. Do procedures specify storage tank minimum • Detailed design to Design Team
level? [Note: possible concern for floating address
roof tanks]
5. Have storage tank valve manifolds been • SOP to address Operations/
arranged to reduce the likelihood of mis- Process group
manifolding? Has valve mis-manifolding been
evaluated [consider complex suction, fill, or
water draw manifolds]?
6. Do storage tank startup procedures specify a • SOP to address Operations/
maximum fill rate until the tank liquid level Process
covers the fill piping? [Note: possible static group
electricity concern]
7. Do procedures specify the safe-fill level of the • SOP to address Operations/
storage tank? [Note: The tank safe-fill level Process group
may be influenced by site-specific seismic
hazards.]

Section Description: Instrumentation


Design Intention:

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 70
Item Checklist Questions Additional Considerations Action By
1. Are critical safety shutdown systems designed
and installed to ensure reliability of the
• Detailed design to
address
shutdown system [consider requirements for
redundancy of components, independence from
process control system, and ability to test
system to ensure reliability]?
2. Are all instrument labels easy to read (clear and • Detailed design to
in good condition)? address
3. Are all instrument labels correct and • Detailed design to
unambiguous? address
4. Do switch labels identify discrete positions • Detailed design to
(e.g., ON or OFF, OPEN or CLOSE)? address
5. Do all instrument labels use standard • Detailed design to
terminology (e.g., acronyms, abbreviations, address
equipment tags, etc.)? Are the instrument
labels consistent with nomenclature used in
procedures?
6. Are all components that are mentioned in • Detailed design to
procedures (e.g., valves) labeled or otherwise address
identified?
7. Are all instrument labels located close to the • Detailed design to
items that they identify? address
8 Are the field instruments that are routinely • Detailed design to
monitored by operations personnel easily address
accessible to ensure information is read in
accordance with recommended frequency
[consider instruments or areas that are difficult
to reach, such as climbing 40 feet of ladder or
squeezing into close quarters]?
9 Are field instrument indicators routinely • SOP to address Operations/
checked for accuracy? Process group
10 Are field instrument ranges appropriate for the • Detailed design to
service [e.g., avoid using a 0-2500 psig address
pressure gage on a 100 psig system]?
11 Do the process control system displays provide • Detailed design to
feedback to operations personnel to confirm address
operator actions? Does the feedback provide
operators with logical information (e.g., is
100% valve output equivalent to valve wide
open)?

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 71
Section Description: Piping and Valves
Design Intention:

Item Checklist Questions Additional Considerations Action By


1. Materials, Piping and Valves checklist Design Team
questions to be addressed at detailed design

Section Description: Static Electricity


Design Intention:

Item Checklist Questions Additional Considerations Action By


1. Do tank filling procedures specify a maximum SOP to address Operations/
fill rate until the tank liquid level covers the fill Process
piping? group

Section Description: Emergency Response


Design Intention:

Item Checklist Questions Additional Considerations Action By


1. Are the operating procedures for this unit SOP to address Operations/
currently up-to-date? Do they cover startup, Process
shutdown, normal operation and emergency group
situations? Are they accessible to all
employees who are expected to use them?

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 72
6.0 REFERENCES

• API RP 14 C - Recommended Practice for Analysis, design, Installation, and Testing of Basic Surface
Safety Systems for Offshore Production Platforms.
• API RP 14 E - Recommended Practice for Design and Installation of Offshore Production Platform
Piping Systems.
• API RP 14 J – Recommended Practice for Design and Hazards Analysis for Offshore Production
Facilities.
• API RP 500 - Recommended Practice for Classification of Locations for Electrical Installations at
Petroleum Facilities Classified as Class I, Division 1 and Division 2.

7.0 RISK RANKING TABLE.

Chevron Research and Technology Process Hazard Analysis Workshops


Fire and Process Safety Team 2/27/2004
Wrapup.doc 73
LIKELIHOOD OF FREQUENT OCCASIONAL SELDOM UNLIKELY
OCCURRENCE
WITH 1 2 3 4
SAFEGUARDS
This incident has This incident is This incident has
Given current
occurred at this likely to occur at occurred at a
practices and
facility and/or is this facility within similar facility
procedures, this
reasonably likely the next 15 years. and may
incident is not
SEVERITY OF to occur at any reasonably occur
likely to occur at
CONSEQUENCES time. at this facility
this facility.
WITHOUT SAFEGUARDS within the next
30 years.

MAJOR 1
SAFETY - Fatality or permanently
disabling injury.
OPERABILITY - Major or total
1 1 2 4
destruction to process areas; plant
downtime in excess of 30 days.
ENVIRONMENTAL & COMMUNITY
IMPACT - One or more severe injuries;
significant release with serious long-term
off-site impact.

SERIOUS 2
SAFETY - Severe injury.
OPERABILITY - Major damage to
process areas with up to 30 days plant
1 2 3 5
downtime.
ENVIRONMENTAL & COMMUNITY
IMPACT - One or more injuries or possible
evacuation; significant release with serious
environmental impact.

MINOR 3
SAFETY - Single injury, not severe,
possible lost time.
OPERABILITY - Some equipment
2 3 4 5
damage with possible downtime.
ENVIRONMENTAL & COMMUNITY
IMPACT - Odor or noise complaint from
the public. Release that results in some
Agency notification or violation.

INCIDENTAL 4
SAFETY - Minor injury or no injury.
OPERABILITY - Minimal equipment
damage with negligible plant downtime.
4 5 5 5
ENVIRONMENTAL & COMMUNITY
IMPACT - No impact off site.
Environmental recordable event with no
agency notification.

LEGEND:
1 = Very High Risk; Additional Consideration Required 4 = Possible Risk; Additional Consideration at
2 = High Risk; Additional Consideration Required Discretion of Team
3 = Moderate Risk; Additional Consideration 5 = Negligible Risk; Additional consideration Not
Recommended Require

Das könnte Ihnen auch gefallen