INTEGRATED MANAGEMENT SYSTEM No.

Dokumen

PT.PJB UBJ O&M LJ-1 PLTU TIDORE Tanggal

RAB MATERIAL OVERHAUL MEAN INSPECTION UNIT #2 Lampiran

TAHUN 2020 Revisi

KEBUTUHAN MATERIAL DAN JASA


NO DISKRIPSI PEKERJAAN HARGA SATUAN JUMLAH HARGA LEVERING KET
No Spesifikasi Jumlah Satuan

A. MEKANIK

Material Plat Besi


Penggantian & Upgrade Material Water Jet
1 1 Material : SUS316 6 Sheet Rp 17,750,000 Rp 106,500,000 14 Hari PIC PROJECT
Tank
Size : 1200 x 2400 x 2 mm

2 Jasa Pemasangan 1 Lot Rp - Rp - PIC PROJECT

2 Perbaikan Refractory boiler area 1 Ramming Type Refractory with Spec Up to 1700 C (prefer Bluram HS Plastic) 14000 Ea Rp 61,000 Rp 854,000,000 PIC PROJECT

Anchor : Stainless Y 10 x 370 SUS 309


2 237.5 Ea Rp 196,000 Rp 46,550,000
Welding Rod SUS 309

3 Jasa Perbaikan Refractory 1 Lot Rp 403,562,500 Rp 403,562,500 PIC PROJECT

3 Penggantian Tube condensor 1 Tube Titanium 100 EA Rp 3,550,000 Rp 355,000,000 45 Hari PIC PROJECT

Standar GB/T3625 – 2007


- Grade : TA2
- Outside diameter : 20 mm
- Thickness : 0.5 mm
- Length : 4562 mm

2 Jasa Penggantian & Pemasangan Tube 100 Ea Rp 1,750,000 Rp 175,000,000 PIC UJLJ-2

4 Penggantian Tube secondary superheater 1 Tube Secondary Superheater 1 Ea Rp 17,000,000 Rp 17,000,000 14 Hari

- Material : A213 T22


- Design Pressure : 62.77 Bar
- Design Temperature : 520 ˚C
- Outside Diameter : 44.5 mm
- Thickness : 4.5 mm
- minimum thickness required : 3,8 mm

2 U-Bend Tube Sec Superheater 2 Ea Rp 9,000,000 Rp 18,000,000 14 Hari

- Material : A213 T22


- Design Pressure : 62.77 Bar
- Design Temperature : 520 ˚C
- Outside Diameter : 44.5 mm
- Thickness : 4.5 mm
- minimum thickness required : 3,8 mm

3 Jasa Pemasangan 1 Lot Rp - Rp - PIC PROJECT


5 Penggantian Valve drain debris filter 1 Knife Gate Valve : 1 EA Rp 94,800,000 Rp 94,800,000 14 Hari

- Type : Gate Valve TV - E


- Size : DN100 / 4 Inch
- Body Material : EN.14408
- Gate material : SS 316 L
- Seat Material : PTFE , EPDM , Nitrile , Viton
- Flange Drilling : EN 1092 PN10 , ANSI Class 150
- Actuator (Manual) : Ratchet Wrench

2 Jasa Pemasangan 1 Lot Rp - Rp - PIC UNIT

Pipa :
- Size : 2.5 Inch, SCH : 5 mm
1 - Material : SS 316 5 Length Rp 15,600,000 Rp 78,000,000

Elbow :
- Radial : 2.5 Inch
2 - Material : SS 316 , Welding 8 EA Rp 825,000 Rp 6,600,000

Flange :
- OD : 180 mm / 2.5 Inch, Class : 150
3 - Lubang Baut : 4, Material SS 316 , Welding 32 EA Rp 5,050,000 Rp 161,600,000

Pipa :
- Size : 6 Inch
4 - Material : SS 316, SCH : 5 mm 1 Length Rp 20,400,000 Rp 20,400,000

Flange :
- OD : 206 mm / 6 Inch, Class : 150
5 - Lubang Baut : 8, Material SS 316 , Welding 8 EA Rp 10,700,000 Rp 85,600,000
6 Penggantian Part Cooler Generator Korosif 14 hari

Valve :
- Type : Gate Valve, Class : 300
6 - Size : 2.5 Inch 8 EA Rp 16,750,000 Rp 134,000,000
- Material : SS 316, Connection : Flange (4 baut)

Mur + Baut + Ring Plat + Ring Pir :


- Size : M18 x 100 mm
7 - Material : Carbon Steel 8.0 (Full Drat) 16 EA Rp 292,000 Rp 4,672,000

Mur + Baut + Ring Plat + Ring Pir :


- Size : M16 x 70 mm
8 - Material : Carbon Steel 8.0 (Full Drat) 100 EA Rp 237,500 Rp 23,750,000

Plate Besi :
9 - Size : 3 x 1200 x 2400 mm 1 Sheet Rp 26,545,000 Rp 26,545,000
- Material : SS 316

10 Jasa Pemasangan 1 Lot Rp - Rp - PIC PROJECT

Penggantian Shutt Off Valve Drain Sootblower


7 1 Control Valve 1 Set Rp 101,574,000 Rp 101,574,000 60 Hari
Macet

Pneumatic Control Valve :


APP No: AM100388, Series: 101-P1, Body Material : A 216 WCB, Characteristic :
Linier, Actuator : UIII-30V, Supply Pressure : 4.0 Bar, Control Range : 1.2-2.0 Bar
OA No.411 400 0652, DN: 50, ANSI: 600, Type : SS, Kv-Value : 43, Function : Open,
Seat Diameter : 48 mm, Connection with Flange. REFF : FORBES MARSHALL

2 Jasa Penggantian Control Valve 1 Lot Rp - PIC PROJECT


8 Penggantian modul MOV Boiler 1 Modul MOV Boiler 2 EA Rp - Rp -

Part Number : D33652, 10 38, RU Δ E231017 , 0L-D 94V-0, Model / Type MOV : RM
2500 Series
REFF : RIME Control, MASIER CONTROL

9 Penggantian sensor LVDT pada governor 1 LINIER DIFFERENTIAL TRANSFORMER (LVDT) 2 EA Rp 15,000,000 Rp 30,000,000 7 Hari

QBJ-TD1, NO: 0910072, Range Stroke: 0-100mm. 3 Wire. Compatible with TSI QBJ-
3800. REFF: Jiangyin No.3 Electronic Factory

Control Valve : OA Number : 411401179, Tag Number : LAB50AA101, APP


10 Penggantian Control Valve Feedwater Passing 1 1 Set Rp 235,200,000 Rp 235,200,000 119 Hari
Number : A1000884
- Actuator :
Model : SSP2-30R, Action : Air to Open, Spring Range : 1.2 to 2.0 BarG ,
Handwhell : Top Mounted
- Positioner :
Model : SIPART PS2, Action : Direct, GG : With, AFR (Total Qnty): 1, Range : 4.0 to
20 mA VDC

- Valve :
Size : 80, Type : Control Valve, Ansi Class : 900, Body Material : A 216 WCB, No Of
Flange : 4, IBR/NonIBR: Non-IBR, Bonnet : Standar, Trim Material : SS410 NITR

- Limit Switch :
Jai Balaji 110 VA Mechanical, Valve Mounted

- Accessories :
Tubing in SS316, COnnection With Line : Flange to Flange
Reff : FORBES MARSHALL

2 Jasa Penggantian Control Valve 1 Lot Rp - PIC PROJECT

11 Penggantian Sealing Ring Cover HPH 1 Sealing Ring HPH 1 EA Rp 13,085,900 Rp 13,085,900 30 Hari

Size : Sesuai Drawing


Material : ST52

2 Jasa Penggantian Sealing Ring 1 Lot Rp - PIC PROJECT

12 Penggantian TI Winding Generator 1 Temperatur Gauge 2 EA Rp 6,210,000 Rp 12,420,000 90 Hari

Diameter : 4 Inch
Range : 0 - 200 C
Connection Process : 3/4 Inch
Material : Full Stainless Steel
Model : Payung
Panjang Stik : 300 mm
Diameter Stik : 3/8 Inch
Existing : WIKA

13 Penggantian U-Bend Tube Economizer 1 U-Bend Tube Economizer 6 EA Rp 8,000,000 Rp 48,000,000 14 Hari

- Material : A192
- Design Pressure : 64,75 Bar
- Design Temperature : 279 ˚C
- Outside Diameter : 50,8 mm
- Thickness : 4,06 mm
- MWT : 3,58 mm
2 Jasa Penggantian U-Bend Tube 1 Lot Rp - PIC PROJECT

14 Penggantian Bearing Gearbox Ash Cooler 1 Gearbox Ash Cooler 1 Set Rp 9,750,000 Rp 9,750,000

Model : TR58
Input Rpm : 1420
Output Rpm : 65
Input kW : 2.2
Ratio : 21 : 93
S. No : 297427 14 Hari
Existing : Moller Helical geared Motor

2 Oil Seal

- Oil Seal : 45 - 80 - 10 2 ea Rp 300,000 Rp 600,000

- Oil Seal : 45 - 75 - 8 2 ea Rp 350,000 Rp 700,000

15 Perbaikan Isolasi Boiler dan Turbin Area 1 Jasa Perbaikan Isolasi Boiler Area 1 Lot Rp 87,840,000 Rp 87,840,000

2 Jasa Perbaikan Isolasi Turbin Area 1 Lot Rp 159,655,065 Rp 159,655,065

16 Penggantian Pompa CWP (AI 2020) 1 Pompa CWP 1 Ea Rp 827,000,000 Rp 827,000,000 150 Hari

Type & Size : CDM 450 LN


Total Head : 19.5 M
Capacity : 1512 m3/h
Speed : 980 rpm
Driver : 110 kW
Existing : Torishima

2 Jasa Pemasangan Pompa 1 Lot Rp - Rp -

17 Penggantian Part Travelling Grate 1 Rack Clip (Sesuai List) 1 Set Rp 1,801,578,750 Rp 1,801,578,750 45 hari PIC UJLJ-2

2 Driving Grate (Sesuai List) 1 Set Rp 479,182,000 Rp 479,182,000 150 Hari PIC UJLJ-2

3 Bearing Travelling Grate (Sesuai List) 1 Set Rp 159,312,000 Rp 159,312,000 30 Hari PIC UJLJ-2

4 Shaft travelling Grate (Sesuai List) 1 Set Rp 76,096,000 Rp 76,096,000 45 Hari PIC UJLJ-2

5 Sprocket Travelling Grate (Sesuai List) 1 Set Rp 64,680,000 Rp 64,680,000 120 Hari PIC UJLJ-2

6 Sprocket Travelling Grate (Sesuai List) 1 Set Rp 240,616,800 Rp 240,616,800 120 Hari PIC UJLJ-2

7 Jasa Penggantian Part Travelling Grate 1 Lot Rp - PIC PROJECT

18 Penggantian Impeller FD Fan 1 Impeller FD Fan 1 Ea Rp 90,000,000 Rp 90,000,000 90 Hari


Model Fan : Centrifugal Fan
Type : 84-73 11D

2 Jasa Penggantian Impeller FD Fan 1 Lot Rp - Rp - PIC PROJECT

19 Sight Glass Steam Drum 1 Sight Glass : Include 1 set Rp 120,000,000 Rp 120,000,000 14 Hari

KTA 180-DVK2 (Size 6xl)


Type : Bicolor (with valve, for right and left side of drum) 1 set
End Connection to Line : Flange
Dimension Center to Center : 1068 mm

Flange : NPS 3/4 inch, A 105 N , Class 900, B16 4 Pair

Pipe : NPS 3/4 Inch x 6000 mm , A 105, SCH 80 1 Length

SWG : SWG According to Flange (NPS 3/4 inch, A 105 N, class 900, B16) with outer 4 EA
ring and outer ring

Penggantian Terminasi Control Breaker 6.3 kV


20 1 Terminal Block : 10 PACK Rp 1,460,000 Rp 14,600,000
GCB
PHOENIX , Type : UK6N (30 04 52 4)
800V/41A/2.5SQMM

2 Din Rail : 5 EA Rp 54,500 Rp 272,500

Size : 35 mm

Penggantian Isolator Busbar sering terjadi


21 1 Monoblock : 2 Set Rp - Rp -
Korona

Lower dan Upper Monoblock untuk VCB VD4 24.06.25 p210

2 Vacuum Circuit Breaker : 1 EA Rp 388,800,000 Rp 388,800,000 PIC UJLJ-2

VD4 24.06.25 p210

22 Pemindahan Transmitter Vacuum Condensor 1 Tubing 1/2 Inchi, Schedule : 20 mm, ss316 4 Length Rp 2,400,000 Rp 9,600,000

2 Needle Valve : Size : 1/2 Inch 4 EA Rp 2,080,000 Rp 8,320,000


45 Hari
3 Tee Connector : Size 1/2 Inch 2 EA Rp 560,000 Rp 1,120,000

4 Conduit : Metal Flexible Conduit Size : 3/4 Inch @50 Meter 1 Roll Rp 1,200,000 Rp 1,200,000

23 Penggantian Kabel Control Turbin Area Kabel Control RTD Rp - 84 Hari

Type RTD kabel, size 1T+SHIELD x 1,5mm


1 Conductor type : Singgle Stranded Plain Annealed Copper 100 Meter Rp 35,000 Rp 3,500,000

Type RTD kabel, size 12T+SHIELD x 1,5mm


2 Conductor type : Singgle Stranded Plain Annealed Copper
50 Meter Rp 175,000 Rp 8,750,000

24 Penggantian TSI Turbin 1 TSI Turbin 1 Set Rp 514,552,500 Rp 514,552,500 60 Hari


QBJ – 3800 C Monitoring Protection Equipment (Intelligent), POWER SUPPLY type:
3800C/001, COMUNICATION & PRINT MOULD type: QBJ – 3800 C, VIBRATION
MONITOR (VIBRATION AMPLITUDE) DOUBLE CHANNEL type: 3800 C/012 2
SET, THERMAL EXPANSION MONITOR SINGLE CHANNEL type: 3800 C/05, OIL
ENGINE MONITOR SINGLE CHANNEL type: 3800 C/061, OIL BOX LEVEL
MONITOR SINGLE CHANNEL type: 3800 C/063, AXIAL DISPLACEMENT
MONITOR SINGLE CHANNEL type: 3800 C/021, TACHOMETER SINGLE
CHANNEL type: 3800 C/041.
REFF: JIANG YING No.3 ELECTRONIC FACTORY

25 Penggantian Level Switch Steam Drum 1 LEVEL SWITCH LOW LOW 1 Set Rp 75,200,000 Rp 75,200,000 84 Hari

MODEL 103W1-K212-N4-C14-X2, 7~100 IN WCD (ADJUSTABLE RANGE), 1500


PSI (OVERANGE), 1500 PSI (PROOF). REFF SOR Inc. Knurled cap over Set Point
adjustment
- Hi side gaseous process connection 1/4” NPT(F)
- Hi side liquid process connection 1/4” NPT(F)
- Hermetically sealed switching element capsule (18”, 18-AWG wire leads)
- 1/2” NPT(M) electrical conduit connection
- 3/4” NPT(F) electrical conduit connection
- Weathertight switching element housing (terminal block under cover), REFF: SOR

Penggantian Valve Drain Lower Continues


26 1 Manual Valve : 1 ea Rp 18,500,000 Rp 18,500,000
Blowdown Passing

Type : Globe Valve


NPS : 1,5 Inchi
Body : A 105 N
Class : 1500
Trim : 5
End : Socked Weld
14 Hari

2 Pipe : 1 Length Rp 4,785,000 Rp 4,785,000

material : A105 NPS 1,5 Inch


Schdule 80 x 6000

3 Jasa Penggantian Valve 1 Lot Rp - Rp - PIC PROJECT

Penggantian Valve venting steam drum indikasi


27 1 Manual Valve : 1 ea Rp 18,000,000 Rp 18,000,000
passing

Type : Globe Valve


NPS : 1 Inchi
Body : A 105 N
Class : 1500
Trim : 5
End : Socked Weld
14 Hari

2 Pipe : 1 Length Rp 4,500,000 Rp 4,500,000


Pipa :
material : A105 NPS 1 Inch
Schdule 80 x 6000

3 Jasa Penggantian Valve 1 Lot Rp - Rp - PIC PROJECT

Penggantian Control Valve Start Up Venting


28 1 Control Valve 1 Set Rp 80,700,000 Rp 80,700,000 180 Hari
passing
Exisiting : FORBES MARSHALL LB30AA101
App No = A1000889 , OA No : 411401179
Series : 113 - L3 , DN = 50
ANSI = 900 , Body Material : A 217 WC9
Type : SS , Characteristic = Linier
kV Value = 12.10 , Actuator = UIII = 30 V
Supply Pr = 4 Bar , Seat = 48 mm diameter
Control Range : 1.2 - 2.0 Bar

2 Jasa Penggantian Valve 1 Lot Rp - Rp - PIC PROJECT

29 Penggantian U-shape Manhole Atas Bag Filter 1 U-shape Manhole 100 M Rp 400,000 Rp 40,000,000 21 Hari

Material : EPDM
Size : 23 mm x 13 mm x 7 mm x
5 mm (Sesuai Contoh)

Penggantian Valve Discharge & Check Valve


30 1 Manual Valve 2 ea Rp 9,450,000 Rp 18,900,000
Cooling Booster Pump C

Type : Butterfly Valve


Body : Cl
Class : 150
Disc : CF8M
Seat : EPDM
Stem : SS410
14 Hari
Connection : Universal Flange
Size : 6 Inchi

2 Bolt Long Drat + Nut + Ring 32 ea Rp 850,000 Rp 27,200,000

Size : M18 x 22 cm
Material : SS316

Penggantian Valve Discharge & Check Valve


31 1 Manual Valve 2 ea Rp 9,450,000 Rp 18,900,000 14 Hari
Cooling Booster Pump D

Type : Butterfly Valve


Body : Cl
Class : 150
Disc : CF8M
Seat : EPDM
Stem : SS410
Connection : Universal Flange
Size : 6 Inchi

32 Penggantian Valve Inlet dan Outlet Oil Cooler C 1 Manual Valve 2 ea Rp 7,850,000 Rp 15,700,000

Type : Butterfly Valve


Body : Cl
Class : 150
Disc : CF8
Seat : EPDM
Stem : SS410 14 Hari
Connection : Universal Flange
Size : 3 Inchi
2 Bolt Long Drat + Nut + Ring 32 ea Rp 775,000 Rp 24,800,000

Size : M16 x 18 cm
Material : SS316

33 Penggantian Valve Inlet dan Outlet Oil Cooler D 1 Manual Valve 2 ea Rp 7,850,000 Rp 15,700,000

Type : Butterfly Valve


Body : Cl
Class : 150
Disc : CF8
Seat : EPDM
Stem : SS410
14 Hari
Connection : Universal Flange
Size : 3 Inchi

2 Bolt Long Drat + Nut + Ring 32 ea Rp 775,000 Rp 24,800,000

Size : M16 x 18 cm
Material : SS316

Penggantian Check Valve Condensate Pump C


34 1 Check Valve 2 ea Rp 14,500,000 Rp 29,000,000
& D Passing

Type : Check Valve


Body : KRCN
Disc : WCB
Size : 3 Inchi
Class : 300 14 Hari

2 Bolt Long Drat + Nut + Ring 16 ea Rp 825,000 Rp 13,200,000

Size : M18 x 14 cm
Material : SS316

35 Penggantian Check Valve Water Jet Pump C 1 Check Valve 2 ea Rp 14,500,000 Rp 29,000,000

Type : Check Valve


Body : WCB
Disc : WCB
Seat : 13 Cr
Size : 3 Inchi
14 Hari
Class : 300

2 Bolt Long Drat + Nut + Ring 16 ea Rp 825,000 Rp 13,200,000

Size : M18 x 14 cm
Material : SS316

Rp -

36 Penambahan Wiremesh Intake Bar Screen 1 Sesuai ECP 1 Set Rp 156,180,000 Rp 156,180,000

2 Jasa Pemasangan Lot Rp - Rp -


37 Pembuatan Jalur Baru Kabel CWP 1 Sesuai ECP 1 Set Rp - Rp -

2 Jasa Pemasangan Lot Rp - Rp -

38 Penggantian Cathodic Condensor 1 Cathodic Condensor 16 ea Rp 3,795,000 Rp 60,720,000 30 hari

Sesuai Drawing

Penggantian Safety Valve Deaerator tidak


39 1 Safety Valve 2 set Rp 132,000,000 Rp 264,000,000 7 hari
sesuai spesifikasi

Type : Relief Valve


Relief Valve Capacity : 141,00 kg/h
Set Pressure : 2 Bar
Nozzle Throat Area : 0.13 in2
Orifice Letter : E
Orifice Area : 0.20 in2
Nozzle Throat Diameter : 12.69 mm
ASME Stamp : UV
Overpressure : 10%
Temperature : 104 C
Lifting Lever : Using Lever

- Inlet :
Suitable to Flange
NPS : 3 Inchi , A 105, Class 150
SCH 40, ASME B16.5
Jumlah Baut : 4

- Outlet :
Suitable to Flange
NPS : 4 Inchi , A105, Class 150
SCH 40, ASME B16.5
Jumlah Baut : 8

40 Penggantian Thermocouple Furnace 1 Thermocouple : 2 ea Rp 5,890,000 Rp 11,780,000 21 Hari

Type K, Range : 0 - 1250 C


Process Connection : 1/2 Inch NPT
Panjang Stick : 600 - 700 mm
Diameter Stick : 8 mm

Penggantian Motor & Gearbox Rotary Valve


41 1 Motor & Gearbox 1 set Rp 17,500,000 Rp 17,500,000
Bag Filter

MOTOR :
Type : TS-71-4 B5
Voltage : 380 V
Ampere : 1.12 A
Power : 0.37 KW
Speed : 1400 RPM
GEARBOX :
Seri : THX05-610-59
Existing : Transcyko

42 Inspeksi CV condensate to LPH Passing 1 Jasa Lapping Control Valve 1 Lot Rp - Rp -


43 Inspeksi BFP C 1 Jasa Inspeksi BFP C 1 Lot Rp - Rp - PIC PROJECT

Penggantian Motor & Gearbox Screw Conveyor


44 1 Motor & Gearbox 1 set Rp 20,000,000 Rp 20,000,000
Bag Filter

Type : THX 1 - 611 - 59


Ratio : 59 / 1.8
Power : 0.75 kW
With Motor
Type : TS - 80 - 4
Existing : Transcyko

45 Penggantian Chute Bottom Ash Cooler 1 Chute Ash Cooler 1 set Rp 121,918,000 Rp 121,918,000

Sesuai ECP

46 Modifikasi Drain & DP Strainer Lube Oil 1 Modifikasi Rp - Rp -

Sesuai ECP

Modifikasi Proteksi Vacuum Condensor Menjadi


47 1 Proteksi Rp - Rp -
2/3 (Pressure Switch)

Sesuai ECP

Modifikasi Proteksi Lube Oil Menjadi 2/3


48 1 Proteksi Rp - Rp -
(Pressure Switch)

Sesuai ECP

49 Pengecatan Equipment 1 Warna Biru (Kode NP 9118) 23 Liter Rp 200,000 Rp 4,600,000 PIC PROJECT

2 Warna Hijau (Kode NP 9110) 7 Liter Rp 200,000 Rp 1,400,000

3 Thinner Cat 15 Liter Rp 100,000 Rp 1,500,000

50 Vapour Extraction #2 tidak bisa menghisap 1 Vapour Extraction 1 set Rp 28,080,000 Rp 28,080,000 60 Hari

FAN
-Type : Centrifugal Fan
- Mounting : Duct Fan
- Impeller Mat : Cast Alumunium
- Casing Mat : Q235 Carbon Steel
- Diameter : 137 mm
- Air flow rate : 500 m3/h
- Pressure : 590 Pa
- Speed : 2900 rpm

MOTOR :
- Power : 0.37 kW
- Voltage : 380 V
- Current : 0.99 A
- IP : 44
- Speed : 2800 rpm
Perbaikan Kebocoran Oli dan Steam pada MSV
51 1 Gasket Rp - Rp -
Turbin

Packing Graphite 12 mm

D. MATERIAL RUTIN OH

SWG :
Size : 416 x 436 x 459 mm
1 SWG Steam Drum 4 ea Rp 2,250,000 Rp 9,000,000 30 Hari
Material : 316 L
Class : 900

SWG :
Size : 416 x 436 x 459 mm
2 SWG Water Drum Material : 316 L 4 ea Rp 2,250,000 Rp 9,000,000 30 Hari
Class : 900

Packing Moldit :
ID : 234 mm
OD : 267 mm 5 ea Rp 9,563,000 Rp 47,815,000 30 Hari
Tebal 30 mm
3 MOV Turbin
Gasket Graphite :
ID : 50 mm
OD : 71 mm 10 ea Rp 364,000 Rp 3,640,000 30 Hari
Tebal 10 mm

SWG :
Size : 91.2 x 113.5 x 131 mm
Material : SS304 5 ea Rp 942,000 Rp 4,710,000 30 Hari
Class : 900
4 Long Sootblower
Ring Tembaga :
OD Ring : 44 MM
ID Ring : 36 MM 2 ea Rp 588,000 Rp 1,176,000 30 Hari
Tebal : 2 MM
SWG :
Size : 91.2 x 113.5 x 131 mm
Material : SS304 5 ea Rp 942,000 Rp 4,710,000 30 Hari
Class : 900
5 Rotary Sootblower
Ring Tembaga :
OD Ring : 82 MM
ID Ring : 62 MM 5 ea Rp 854,000 Rp 4,270,000 30 Hari
Tebal : 2 MM

Steam Drum Inlet :


52,4X58,4X85X95
Tebal : 4,5 2 ea Rp 713,000 Rp 1,426,000 30 Hari
Material Grafite
6 SWG Safety Valve Steam Drum Steam Drum Outlet :
82X88X114X124
Tebal :4,5 2 ea Rp 765,000 Rp 1,530,000 30 Hari
Material Grafite

Sootblower Inlet :
50X56X85X95 1 ea Rp 713,000 Rp 713,000 30 Hari
Tebal :4,5

7 SWG Safety Valve Sootblower Sootblower Outlet :


81,7X87,7 X114X124
Tebal : 4,5 1 ea Rp 768,000 Rp 768,000 30 Hari
Material Grafite

Main Steam Inlet :


44,5X50,5X89,5X99,5
Tebal :4,5 1 ea Rp 744,000 Rp 744,000 30 Hari
Material Grafite
8 SWG Safety Valve Mainsteam Main Steam Outlet :
78X84 X114X124
Tebal : 4,5 1 ea Rp 750,000 Rp 750,000 30 Hari
Material Grafite

Deaerator Inlet :
100X106X119X129
Tebal :4,5 2 ea Rp 926,000 Rp 1,852,000 30 Hari
Material Grafite
9 SWG Safety Valve Deaerator Deaerator Outlet :
126X132 X154X164
Tebal : 4,5 2 ea Rp 1,054,000 Rp 2,108,000 30 Hari
Material Grafite

Ring Tembaga :
ID : 10 mm
10 Ring Tembaga Temperatur Indicator OD : 22 mm 50 ea Rp 474,000 Rp 23,700,000 30 Hari
Tebal : 2 mm

Bahan : NBR
11 Rubber Condensor 60 M Rp 560,000 Rp 33,600,000 30 Hari
Size : Sesuai Contoh

12 Rubber Coupling FD Fan & ID Fan 40 ea Rp - Rp -

JUMLAH HARGA Rp 9,430,860,015

PPN 10 % Rp 943,086,002

TOTAL HARGA Rp 10,373,946,017


OVERHAUL MEAN INSPECTION UNIT #1
TAHUN 2020

KEBUTUHAN MATERIAL DAN JASA


NO DISKRIPSI PEKERJAAN KET
No Spesifikasi Jumlah Satuan

1 Regrouting Pondasi CWP B 1 Semen Sikagrout 215 New 15 Sack


Kapasitas : 25 Kg

2 Triplex : Tebal 1 Cm 2 Lembar

Balok Kayu : Tebal 5 x 5 Cm


3 3 Length
Panjang : 3 Meter

4 Paku : 7 Cm dan 5 Cm 2 Kg
Masing-masing 1 Kg

Rubber Lagging : Diamond Profil


2 Pennggantian Rubber Lagging Ash Cooler 1 Lebar : 1 Meter 10 M
Tebal : 15 mm

2 Lem Belt Conveyor : Rema Tip Top SC 2000 6 Ea

3 Penggantian terminal block switch gear 1 PHOENIX disconnect terminal block - URTK/S - 0311087 200 EA

2 Switching Jumper - USB 2 - RTK/S - 0311278 100 EA

3 Switching Jumper - SB4 - RTK/S - 0311265 100 EA

4 Cover - D - URTK - 0310030 50 EA

4 Penggantian temperatur winding generator 1 Temperature Gauge 1 Ea

Diameter : 4 Inch
Range : 0 - 200 C
Connection Process : 3/4 Inch
Material : Full Stainless Steel
Model : Payung
Panjang Stik : 300 mm
Diameter Stik : 3/8 Inch
Existing : WIKA

5 Penggantian level switch low-low steam drum 1 Level Switch 1 Set


MODEL 103W1-K212-N4-C14-X2, 7~100 IN WCD (ADJUSTABLE RANGE), 1500 PSI (OVERANGE),
1500 PSI (PROOF). REFF SOR Inc. Knurled cap over Set Point adjustment
- Hi side gaseous process connection 1/4” NPT(F)
- Hi side liquid process connection 1/4” NPT(F)
- Hermetically sealed switching element capsule (18”, 18-AWG wire leads)
- 1/2” NPT(M) electrical conduit connection
- 3/4” NPT(F) electrical conduit connection
- Weathertight switching element housing (terminal block under cover), REFF: SOR

6 Penggantian Sensor LVDT Governoor 1 Sensor LVDT 1 Set

LINIER DIFFERENTIAL TRANSFORMER, Spesifikasi: QBJ-TD1, NO: 0910072, Range Stroke: 0-


100mm. 3 Wire. Compatible with TSI QBJ-3800. REFF: Jiangyin No.3 Electronic Factory

7 Penggantian Sensor Thrust Bearing Tinggi 1 Sensor Thrust Bearing 10 Ea

RTD PT100, Type : WZPM-001, Range : 0 - 150 DegC, Diameter sensor : 6 mm, Panjang Sensor :
19.5 mm, Jumlah Kabel : 3 Wire, Panjang Kabel : 4 Meter

8 Penggantian Multi Function Meter 20 kV 1 Multi Function Meter 2 Ea

Schneider Electric
Powerlogic PM810MG

Type RTD kabel, size 1T+SHIELD x 1,5mm


9 Penggantian Kabel Control Turbin Area 1 100 M
Conductor type : Singgle Stranded Plain Annealed Copper

Type RTD kabel, size 12T+SHIELD x 1,5mm


2 50 M
Conductor type : Singgle Stranded Plain Annealed Copper

3 Jasa Penggantian Kabel Control 1 Lot