Beruflich Dokumente
Kultur Dokumente
4
Particular Technical Specification
6.4.1
Mechanical Equipment
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Table of Contents
6.4.1.1. General 1
6.4.1.1. General
These Particular Technical Specifications are part of the Employer’s
Requirements of this contract. They are based on the design of the project
carried out by the Employer which is represented in the technical drawings
(Part II, Section 6.7 Tender Drawings) and the Design Calculations and
Design Memorandum Reports, November 2019 (Part IV Reports) produced
by the Employer.
· three (3) vertical Pelton turbines with six (6) nozzles, operating at
synchronous speed of 300 rpm
· three (3) digital electronic - hydraulic governors including pressure oil
system
· three (3) main inlet valves (MIVs) of the spherical valve type, including
pressure oil systems
· hydraulic quantities measuring system
· spare parts and special tools
· model testing of Pelton turbine
· shop and field tests
· installation and commissioning.
The scope of supply shall include all components which are required for
performance, durability and satisfactory operation of the turbines, governing
systems and main inlet valves even though not individually or specifically
stated in this specification.
1
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· three (3) vertical shaft Pelton type hydraulic turbines each with six (6)
nozzles and a specified turbine output of not less than 87.4 MW at a rated
net head of 433.42 mWC and a rated discharge of 22.88 m³/s
· turbine model testing
· three (3) dismantling/expansion pipes
· service platforms, runner removal cart and runner removal doors
· dewatering pipes and valves
· measuring pipes and instruments
· oil piping between servomotors and governor oil systems
· brake jet assemblies
· lifting facilities and electric illumination for the turbine shaft pit
· assembly and tests in the workshop
· transportation and delivery to site
· storage at site
· site installation, commissioning and acceptance testing of the turbines
including thermodynamic measurements
· corrosion protection coating
· first lubricant fill plus a 10% extra in barrels
· tools, slings and devices required for assembly and maintenance
· preparation and submission of operation and maintenance manuals and
training of Employers operating and maintenance staff; and
· spare parts required for operation and maintenance.
The turbines’ direction of rotation shall be clockwise when viewed from top
(generator side).
For the unit design the following vertical unit arrangement it is envisioned
that the Pelton turbines are coupled to a generator which is equipped with
combined thrust/guide bearing above and one guide bearing below the rotor
(bearing arrangement according to DIN EN 60034-7, IM 8421).
2
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Reservoir:
· Maximum Operating Level e11352.0 m a.s.l.
· Minimum Operating Level 1339.0 m a.s.l.
The turbines shall be designed and manufactured for daily starts and stops
and continuous operation between minimum and maximum output and
within the head range specified, without exceeding the allowable stresses
and bearing temperatures.
3
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The turbine shall be able to operate safely and satisfactorily under any
conditions of load and the given water level without excessive vibration,
noise, wear (erosion) and tear.
The weighted average efficiencies ηw1, ηw2 and ηw3 of the prototype shall
be calculated according to the following formula. The average efficiency
ηwi shall be calculated according to the following formula:
ηwi = (∑j wi, j ×ηi, j) / (wi1 + wi2 +... + wi5)
where ηi,j is the efficiency in the i,j conditions and wi,j is the relevant
weight according to the following table.
The prototype guaranteed weighted average efficiency ηw2 at rated net head
shall not be lower than 89%.
4
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Max.
net 87.7 88.9 89.9 89.9 89.4 87.4
head
Rated
net 87.4 89.0 89.9 89.9 89.4 87.5
head
Min.
net 85.1 88.9 90.1 90.1 89.5 87.6
head
Values lower than 1.5% (one point five of percent) at any single point will
constitute an efficiency default condition.
W = 0.6 x Z x B2 x t/8000
Where,
W = permissible weight of metal in kilograms
t = hours of operation
Z = number of runner buckets
B = inner width of runner buckets in meters
Should the loss of material in kilograms per ‘t’ hours during the basic
guarantee period exceed the permissible limit as per the aforementioned
formula, the Contractor shall repair and rectify by welding, grinding and
polishing. If after a further period of 8,000 operating hours, the runner again
has suffered loss of material in excess of the limit per ‘t’ hour, the runner
shall be rejected in which case the Contractor shall design, model test,
construct and supply free of charge to the Employer a new runner with
satisfactory cavitation performance.
5
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The Contractor shall verify and adjust his design to meet the limitations of
the speed and pressure transients and to comply with stability and regulation
requirements of the grid.
The reference diameter of the runner shall be at least 250 mm, the bucket
width shall not be smaller than 80 mm respectively.
Piezometer taps locations on the model should reflect and resemble the
prototype locations. The number and locations shall be established by the
Contractor in accordance with the IEC requirements and shall be to the
acceptance of the Employer.
6
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The Employer shall be notified 30 days in advance of the final tests and may
witness final tests to verify the model performance.
7
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Final scale model acceptance tests report shall be submitted to the Employer
upon completion of the tests. It shall include, in particular, all the prototype
hill curves within the installation operating range, as well as all results of
the tests, calculations, measurements and observations performed.
6.4.1.2.2.7 Vibrations
The unit vibrations shall be assessed according to the following standards:
Non-rotating parts:
· ISO 10816-1 (1995), Mechanical vibration, Evaluation of machine
vibration by measurements on non-rotating parts, Part 1: General
guidelines
· ISO 10816-5 (2000), Mechanical vibration, Evaluation of machine
vibration by measurements on non-rotating parts, Part 5: Machine sets in
hydraulic power generating and pumping plants.
The Contractor shall guarantee that the vibration level of the unit, when new
and running under normal operating conditions shall not exceed values
defined by:
8
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Investigation Criteria
Water passage water hammer Compare with natural frequencies of
pressure wave: the turbine and generator components
F = V/4L (separately for the entire and unit rotating element.
length of the water passage and for
the intake up to the nozzles).
Dynamic unbalance of rotating parts: Compare with natural frequencies of
F = N/60 the turbine and generator components
and unit rotating element.
Runner bucket passing frequency: Compare with natural frequencies of
F = N*B/60 the turbine and generator components
and unit rotating element.
Runner bucket and nozzle passing Compare with natural frequencies of
frequency: the turbine and generator components
F = N*B*B’/60 and unit rotating element.
Nomenclature:
F= Frequency, Hz
N= Speed, rpm
B= Number of runner buckets
B’ = Number of nozzles
V= Velocity of pressure waves in water passages, m/s
L= Length of respective water passage section, m
6.4.1.2.2.10.1 Distributor
A distributor shall be furnished extending from the downstream side of the
spherical valve dismantling joint to the nozzles. The distributor shall be
fabricated from welded carbon steel plates, in the minimum number of
sections dictated by shipping/transport clearance requirements. Bolting
flanges shall be provided on the branches to connect the nozzles to the
distributor.
A connection pipe with one expansion joint, as part of the spherical valve
supply shall be provided between the distributor and the spherical valve on
the dismantling pipe. The spherical valve shall be located upstream of the
longitudinal central line of the units. The connection pipe and the expansion
joints shall be made of high strength fine grain steel.
9
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The distributor shall be furnace stress relieved after welding and before
machining. The welds shall be 100% tested by the ultrasonic method.
Adequate carbon steel plates shall be used for the distributor and all welding
edges shall be properly prepared.
The lower side of the distributor shall be provided with pads for levelling
during the erection. Jacks and tie down rods and turnbuckles for aligning,
levelling and holding the distributor in place while embedding in concrete
shall be supplied. The Contractor shall provide enough lifting provisions for
handling.
A set of four stainless steel piezometer taps at a point where flow conditions
will be most favourable for accurate measurement of pressure head shall be
provided. The piezometer taps shall be equally spaced around the
circumference of the inlet section and shall be located 45 degrees from the
vertical centreline. All necessary tubing, fittings, valves and air vents shall
be supplied.
The distributor shall have a drain outlet for water removal after the turbine
shut off and by-pass valves are closed. A manually operated plug or gate
valve shall be provided which shall be arranged at an accessible location.
The valve, drain line and fittings shall be adequate to fully discharge all
leakage water under maximum hydrostatic pressure.
A combined air and vacuum relief valve shall be provided at the highest
point of the distributor or inlet section. The air valve shall function as an air
vent when the distributor is filling and shall function as a vacuum breaker
during unwatering of the distributor. The valve body and all interior parts
shall be designed to withstand the turbine design head.
The valves shall be supplied complete with piping, fittings and drain line.
The distributor shall be furnished with a pressure switch and a float-
operated switch for mounting adjacent to the air release valve. The switch
shall be incorporated in the turbine main inlet valve control circuits to
prevent opening of the main inlet valve until the distributor is filled with
water. Each switch shall be equipped with two contacts, which shall act
when the distributor is filled with water.
10
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The turbine cover shall support the combined weight of the runner and
turbine shaft, when disconnected from the generator shaft.
The lower part of the turbine cover shall be provided with stiffeners and
fixed on the runner pit housing.
The upper and lower turbine housing shall facilitate the efficient discharge
of the water from the turbine runner.
The upper and lower turbine housing shall be designed for a suitable
number of sections required and practicable for shipping and transportation
to site. The housing cover shall be supplied in a minimum of two (2) or
more sections. The housing shell joints shall be prepared for field welding.
Pit housing and pit liner shall be assembled on site by welding and
embedded in concrete.
The steel/concrete structure shall support the dead weight of the turbine
shaft and the runner when the shaft is disconnected from the generator
11
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
shaft, the deflector shaft bearings, the needle control restoring and pipe
connection and other components as necessary. The design shall also
consider the lifting of the nozzles and of the runner by using lifting eyes
provided at the housing ceiling.
The housing shall be provided with all necessary eyebolts, etc. to facilitate
attachment of hoisting equipment for the purpose of erection, maintenance
and dismantling of nozzles, deflectors and runner.
The upper turbine housing, together with the pit liner, turbine distributor,
nozzles, etc. shall be completely assembled and match-marked in the shop
and shipped in as few sections as practical.
The pit liner shall be equipped with adequate baffles to dissipate the energy
of maximum continuous discharge of the jets under maximum head.
12
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· A drain connection together with all fittings, gate valve(s) with stem and
stools, piping gaskets, flanges, bolts etc. all way along the length of
powerhouse and up to the discharge level shall be provided.
The platform shall consist of steel beams, floor gratings and steel support in
the runner pit and shall be designed to support the runner handling cart. The
beams have to withstand the impact of the water discharge from the
deflectors and runner without excessive vibration. Special provisions shall
be made for corrosion protection of the beams and other parts of the
platform which are installed permanently in the runner pit. The floor
gratings shall be galvanized.
Suitable rubber seals shall be provided at the bolted joints to avoid water
leakage under the most severe operating conditions.
A small access door with a clear opening of 0.80 m height and 0.80 m width
shall be integrated in the runner removal door. This door shall also be
equipped with door-hinges, rubber seals and bolted joints. The access door
shall be arranged at an elevation convenient to enter the service platform.
13
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The needles shall be balanced by springs and other means to obtain closing
tendency from fully open to fully closed needle position in the event of
failure of governor oil pressure under the applicable operating heads.
The nozzle pipe shall be bolted to the manifold branch pipe. Provisions shall
be made to facilitate alignment, inspection, maintenance and dismantling of
parts (e.g. replacement of seat rings, needle tips, etc.) and for removal of the
complete nozzle without dismantling the runner.
The nozzle body shall be provided with a removable Stellit or HVOF seat
ring at the point of final water discharge. Removal and replacement of the
seat ring shall be possible without dismantling the runner, jet deflector or
nozzle body.
The selection of GX4CrNiMo13-4 or Stellite for the seat ring and needle tip
shall combine the feature of high resistance against abrasion with the
possibility of re-machining of deteriorated surfaces. The needle arrangement
14
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Suitable means shall be provided to prevent water from entering into the oil
system and vice versa.
Care shall be taken to protect the needle guides against erosion and wear,
caused by fine-grain sand.
Pipe sleeves or ducts to route the piping and restoring linkage from the
nozzles to the shaft pit floor shall be of corrosion-resistant material.
The jet deflector shall be able to deflect the jet completely within 1.5
seconds. In order to reduce the loss of energy and wear of the deflector, for
small load changes the jet shall be controlled only by the needle.
The deflectors shall be made of forged steel or casting steel with martensitic
stainless-steel overlay as per standard practice.
15
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The deflector shall be firmly attached to the deflector shaft. The shaft shall
be supported by self-lubricated bearings in the turbine cover and at the
nozzle body.
The design of the deflector and operating mechanism shall permit removal
of the deflector without extensive dismantling of other parts.
A mechanical position indicator for each deflector shall indicate the setting
of the deflector cutting edge.
Replaceable orifices to adjust the period of time for full opening or closing
stroke shall be provided. The time shall be independently adjustable for both
stroke directions.
The design and manufacture of the runner shall be robust in size and
strength to withstand safely the centrifugal forces and hydraulic jet forces on
the buckets under the severe operating conditions without exceeding the
allowable stresses and undue vibrations. The case of emergency shutdown
under maximum head at runaway speed, and all nozzles open should also be
considered. As proof of his ability, the Contractor shall submit typical
16
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The surfaces shall be free from any defects. The dividing splitters of all
buckets shall accurately match the plane of the nozzle centre lines. The
surfaces on the back of the buckets which are in tangential contact with the
jet shall also be smoothly ground.
The finished turbine runner shall be statically balanced according DIN ISO
1940/VDI 2060 in the Manufacturer's workshop before shipment.
The Contractor shall be responsible for the final alignment and balancing of
the combined turbine generator rotor according to NEMA publication LG3
latest edition.
The fastening of the turbine runner on the turbine shaft shall be made in
such a manner that the transmission of the driving torque is guaranteed
under the severest working conditions and that the runner can be easily
removed. The coupling shall allow the interchange of the runners without
re-machining and additional adjustment of the coupling. Radial keys for
transferring the torque are acceptable, but the offered coupling shall be
described in detail. A sole friction coupling shall not be acceptable. The
coupling bolts and nuts shall be protected against the operating water by a
welded cover-ring, which shall also close the concentric hole of the turbine
shaft.
All necessary coupling bolts and accessories shall be supplied together with
suitable locking devices. The pre-stressing of the bolts shall be carried out
by a hydraulic jack.
2.2.10.7.1 Material
The turbine shaft shall be made of open-hearth carbon or alloy steel with
integrally forged upper and lower flanges for bolting to the generator shaft
and the runner respectively. The shaft shall be subject to careful heat
treatment after the forging process.
The shaft shall have a centre hole, not less than 150 mm in diameter, bored
axially throughout the entire length. The machining of this hole shall be
sufficiently smooth to permit visual inspection of the metal in the interior of
the shaft.
17
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
2.2.10.7.2 Dimensioning
The shaft shall be of robust size to operate in combination with the
generator shaft safely at any speed including runaway speed without
detrimental vibration or distortion. Operating at normal speed and maximum
output, the stress in the highest stressed cross section shall not exceed 25%
of the yield strength of the shaft material. For temporary overloads
exceeding the rated output, the unit stress shall not exceed 50% of the yield
strength.
The shaft and coupling dimensions shall be sufficient to safely transmit the
torque and bending load due to the maximum radial thrust at the most
unfavourable combination of jet impacts.
The Contractor shall coordinate the criteria about overall design, load
calculation and critical speed. The relevant criteria and the determination of
maximum starting torque, short-circuit forces, etc. shall be submitted in the
form of calculation to the Employer for approval before start of
manufacturing.
2.2.10.7.3 Coupling
All coupling dimensions shall conform to ANSI B 49.1, "Shaft Couplings,
Integrally Forged Flange Type for Hydroelectric Units".
The coupling bolts and nuts for the connection of the generator shaft to the
turbine shaft, suitable metal guards to cover the bolts and nuts and all
wrenches and special equipment necessary for shop and field assembly of
the couplings shall be supplied by the Contractor. The coupling bolts shall
be provided with locking devices and shall have dimensions and tolerances
in accordance with ANSI Standard B 49.1, Table 2, or an equivalent,
approved standard.
Tapped holes for jacking screws or other devices shall be provided for
separation of the coupling joint during disassembly.
If fitted both are used for transmitting the driving torque, the coupling bolt
holes rough drilled on "short measure" shall be reamed during site assembly
to "real measure". This work shall be carried out and the necessary tools
(reamer and equipment for parallel guiding of reamer) shall be delivered by
the Contractor.
The amount of shaft run-out shall be checked and shall not exceed the
tolerances recommended for shafts as per NEMA standard publication no.
5.1, paragraph 63, „Vertical Hydraulic-Turbine Generator Shaft Run-Out
Tolerances Shop Check “.
18
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
For the bearing temperatures the Contractor shall guarantee the following
values:
Temp (°C)
Max. Permissible Alarm Emergency Shutdown
Guide Bearing Pads 70 75 80
Bearing Oil 60 55 60
19
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
An oil reservoir shall be provided around the bearing from which the oil
shall circulate through the bearing. The major portion of the bearing shall be
continuously immersed by the oil to provide initial lubrication when starting
the unit.
The volume of the reservoir shall be determined in such a way that the
lubrication oil shall not circulate more than 15 times per hour.
The design of the coolers shall permit easy maintenance and cleaning during
turbine operation without unnecessary loss of time and leakage water. The
cooling pipes shall be of corrosion resistant material.
2.2.10.9.2 Accuracy
The acoustic system shall have proven accuracy of <+1.0% and shall be
suitable for conducting the site efficiency tests in accordance with IEC
60041.
The turbine flow meter electronic system shall automatically compensate for
changes in water temperature. The Contractor shall indicate any
penstock/branch taps to meet this requirement. These taps shall be provided
by the Contractor itself.
20
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· FMP
· Back power supply operating
· Power systems failure
· Transducer failure (for each transducer)
· Internal Fault
· Over velocity trip activated
· Unit control board (UCB)
· Turbine flow (for this the Contractor shall supply a suitable flow
indicator for mounting in the UCB).
Signals for:
21
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
A speed switch on the turbine shaft shall monitor the maximum admissible
overspeed.
· oil level indicator, to display oil level of guide bearing of turbine locally
· oil level relay for guide bearing, with upper and lower levels electric
contracts
· temperature monitoring and measuring device for guide bearing pads.
each pad is fitted with one resistance type temperature sensor, in which
two sets are connected to the electric contact thermometer via the
terminal board on the turbine pit wall with output of on-off quantity and
double upper limits; the others are connected to the unit RTU
· oil temperature monitoring and measuring device for the turbine guide
bearings. Three resistance type temperature sensors shall be provided, in
which one set is connected to the electric contact thermometer via the
terminal board on the turbine pit wall with output of on-off quantity and
double upper limits; the others are connected to the unit RTU
· monitoring of needle position to detect wear on needle tips and seat rings
of the injectors.
6.4.1.2. Governors
6.4.1.2.3.1 General
The governor shall be of the PID type with electric feedback between the six
(6) injector servomotors and the digital governor, as well as between the
deflector servomotors and the digital governor.
The turbine governor shall perform the following governing tasks for the
regulation and control of the generating units:
22
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Rated frequency: 50 Hz
23
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Opening and closing time of both, nozzle and deflector, servomotors shall
be adjustable. However, the minimum closing and opening time of the
governor shall be in accordance with the requirements in the turbine
specifications regarding speed and pressure variations.
· Speed monitors:
24
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· Creep detection:
Signal instruments and the wiring shall be redundant. For safety reasons, the
converters shall be designed for closing tendency.
25
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The converter and the feedback transmitter shall be connected to the digital
governor by electric wiring. The converter shall be designed for closing
tendency.
26
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· General
Oil pressure levels of the pressure oil system shall be defined by the
Contractor.
The oil pressure system shall be equipped with nitrogen filled piston type
accumulators. The capacity for the accumulators shall be three (3) full
servomotor strokes (close-open-close) of nozzle and one (1) full opening
of deflector without pumps active at lowest accumulator pressure level
and highest accumulator oil level.
The HPU shall include a tank, pumps, any required valve for the safe
operation of the hydraulic system (control valves, emergency shutdown
valves, manual shutdown valve and pressure relief valves), accumulators
with nitrogen bottles, all necessary instrumentation, etc.
All necessary piping, safety fittings and accessories such as safety valves,
pressure gauges and control devices with control switches, meters,
counters etc shall be included.
27
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Trip relevant signal (e. g. oil level) shall be redundant in the following
manor:
· multiple PT100 sensors at close position
· level switch (binary, tipping when closed) AND level sensor
(4…20 mA, trip created internally)
· pressure switch (binary, tipping when closed) AND pressure sensor
(4…20 mA, trip created internally)
· flow switch (binary, tipping when closed) AND flow sensor
(4…20 mA, trip created internally).
The main inlet valve shall be at the spherical type designed for minimum
head less and disturbance and having a net cross-sectional area at the throat
not less than that of the distributor inlet.
Under all operating conditions the main inlet valves shall be free from
excessive vibration and noise. Acceptable levels of vibration under all
operating conditions shall be guaranteed.
28
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The main elements of the valve shall be of cast, forged or fabricated steel. If
fabricated construction is used, all welds stressed directly or indirectly by
pipeline pressure shall, to the maximum extent practicable, be full
penetration butt or tee butt welds. All wearing parts shall be replaceable and
these in contact with water shall be of corrosion resistant material or be
sleeved with corrosion resistant material.
Sealing shall be achieved by solid metal contact between the rotor seals and
the body seats. There shall be two seals hydraulically operated by pipeline
pressure, a downstream located service seal comprising a stainless-steel
sealing ring against a stainless-steel body seat and a similar designed
upstream located maintenance seal. It shall be possible to adjust the sealing
elements without major dismantling of the valve. Both the service and
maintenance seals shall be double acting.
The trunnion and servomotor connecting rod bushes shall be of the self-
lubricating type. Provision shall be made to prevent dirt and foreign matter
from entering the top of the servomotor.
The seals, seats, trunnion bushes and trunnion glands shall be so arranged
that they can be removed or installed without dismantling the valve bodies
or removing the valves from the penstock when the penstock is drained.
Each valve shall be provided with manually operated scour valves and
appropriate piping for the services and maintenance seals. These scour
valves shall be located at the lowest point of the valve body.
Each main inlet valve shall be fitted with an air release valve mounted on
the highest point of the valve body. The air release valve shall be provided
with appropriate piping and controls.
6.4.1.2.4.3 Operation
The valve shall be capable of closing against any flow up to and including
that due to free discharge at the outlet of the valve with maximum flood
level in the headpond.
29
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The servomotor/s and its mounting, pressure piping and control valves shall
be adequate for the pressure produced in the servomotor with the most
adverse conditions of unbalanced closure against free discharge.
A manually operated mechanical lock for securing each main inlet valve
rotor in the closed and open position shall be provided and shall be of
adequate strength to resist both the thrust of the servomotor in the opening
direction and the force from the weights in the closing direction. The locks
shall embody provision for padlocking in the inserted and withdrawn
positions.
The initiation of opening of the main inlet valve shall be interlocked with
the establishment of a pressure in the distributor substantially equal to
pipeline pressure and that the maintenance seal is in the “off” position.
The inlet valve opening and closing times shall be independently adjustable,
but the adjustments shall be of a form that cannot be readily or inadvertently
be altered. In the interests of minimising the time necessary to shut down in
an emergency, the closing times shall be the minimum consistent with safe
operation.
Each unit pressure accumulator shall have sufficient active nitrogen and oil
storage at normal minimum oil level and pressure to complete an opening
and closing stroke of the main inlet valve without the pumps operating.
Duplicate a.c. motor driven pumps shall be provided for normal and standby
duty respectively, each rated 100 percent capacity. Each motor and pump
shall be of sufficient capacity to recharge a unit accumulator to normal
maximum level and pressure within 5 minutes after an opening stroke of
each main inlet valve. Each motor and pump shall be complete with its own
strainer, safety valve, non-return valve and stop valve so that either pump
with its accessories may be withdrawn from service without affecting the
other. The control of the pumps shall be by level switches on the
accumulators.
The oil pumping system shall be complete with sump tank, oil level gauges
for the accumulators and sump tank, means for automatically maintaining
the correct quantity of nitrogen in the receiver, and all necessary pipes,
valves, coolers, drain connections and other fittings including oil level and
pressure relays required for the control of the pumps. A continuous and
30
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
independent all purification system shall be provided. Suction and return oil
connections for oil centrifuge equipment shall be provided in the sump tank.
A strainer shall be provided in the main oil pressure supply pipe to each unit
main inlet valve of sufficiently fine filtering capacity to prevent damage to
any portion of the valve control and operating mechanism by foreign matter.
The by-pass valve shall be hydraulically operated using high pressure oil
from the main inlet valve hydraulic pump unit.
In order to reduce cavitation within the by-pass piping and valve, the by-
pass valve shall be located adjacent to the distributor and its discharge set at
an angle reducing potential erosion effects on the surfaces within the
distributor.
Isolation guard valves shall be provided both upstream and down stream of
the by-pass valves for maintenance purposes.
Trip relevant signal (e. g. oil level) shall be redundant in the following
manor:
· multiple PT100 sensors at close position
· level switch (binary, tipping when closed) AND level sensor
(4…20 mA, trip created internally)
· pressure switch (binary, tipping when closed) AND pressure sensor
(4…20 mA, trip created internally)
· flow switch (binary, tipping when closed) AND flow sensor
(4…20 mA, trip created internally)
31
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The design of the dismantling joint shall allow for removal of the
dismantling joint from the penstock and replacement with the bulkhead to
be bolt directly onto the inlet valve downstream flange.
Stub pipes shall be provided with each value, including a flange for bolting
to the upstream side of the inlet valve and a cylindrical length of pipe of the
same nominal bore as the inlet valve. The cylindrical section shall be made
of a steel of equivalent strength and quality and compatible for welding to
the penstock.
6.4.1.2.4.8 Bulkhead
One flanged circular steel bulkhead, complete with all necessary bolts, nuts
and sealing rings and suitable for installation on either the main inlet valve
downstream body flange or the upstream pipeline flange mating with the
main inlet valve shall be provided for pressure testing and maintenance
purposes.
The bulkhead shall be supplied complete with drainpipe and isolation valve.
32
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Selection of tools and devices for delivery shall be made considering the
facts that all maintenance and repair works which require standstill of the
turbine must be carried out within the shortest possible time. Therefore, all
turbine components to be dismantled shall be equipped with eyebolts, lugs
and/or other devices to facilitate handling, installation and removal.
The Contractor shall provide electronic file(s) of spare parts with complete
data (identification number, description, quantities, address/phone/fax of
suppliers and manufacturers, unit prices, delivery time, etc.). The lists shall
be cross-indexed with the assembly, sub-assembly drawings.
One set means of specified spare parts shall be understood as one set for all
four units.
Turbine:
· one (1) turbine runner
· one (1) set of injector nozzle tip and seat ring
· one (1) jet deflector
· one (1) set of turbine bearing pads
· one (1) oil cooler of each type
· one (1) complete pump unit with motor of each type
· one (1) measuring instrument/sensor of each type.
Turbine governor:
· two (2) motor pump sets for the governor pressure oil unit
· two (2) limit switches of each type (pressure, temperature, level etc.)
· one (1) set of all measuring and indicating instruments, transducers etc.
33
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
34
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
35
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· load rejection tests at 25, 50, 75, 100% of rated load and at the maximum
load
· no-load tests under manual control in discrete steps up to the maximum
overspeed
· load acceptance tests
· governor stability and response tests
· pressure fluctuations, vibrations, and noise measurements
· reliability run on all four units.
The raw water for each unit (primary circuit) shall be taken from the tailrace
tunnel by one of two centrifugal pumps (one operating and one standby)
through check valves, flow meters, maintenance valves, regulating orifices,
automatic self-cleaning filters and intermediate heat exchanger and
discharged to the tailwater.
The secondary (closed loop) water circuit shall also be provided with two
pumps. The pumps shall circulate the cooling water through the various
equipment coolers. Water returns to the pump suction side through the
intermediate heat exchanger where it is re-cooled. The cooling water system
shall be filled with clean fresh water treated with anticorrosion additives.
The anticorrosion additives must be compatible with local environmental
rules and regulations.
A make up water tank with an automatic filling valve in the feed line shall
be provided for the secondary systems.
36
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
reliable, durable and safe operation of the complete cooling water system
with low maintenance and inspection effort.
The capacity of the cooling water system shall be such that requirements of
temperature rise for generator air temperatures and of the bearing and
governor oil temperatures specified in the pertinent section of these
Technical Specifications shall be met.
Heat exchangers, filters, strainers etc. shall be designed for cold water
working pressure rating of not less than 6 bar.
The valves, piping, regulating orifices shall be selected for cold water
working pressure rating of not less than 10 bar.
Differential pressure switches between inlet and outlet on both sides of the
heat exchanger with visual indication and potential free electrical contacts
for alarm purposes shall also be installed.
37
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The speed of pumps shall not be more than 1500 rpm. Pump bearings shall
be water lubricated in case of wet-rotor pumps.
38
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
6.4.1.3.1.4 Tests
The complete systems shall be tested for correct operation, indication and
function of protection devices. Insulation resistance measurements as per
relevant IEC standards shall be performed.
A simultaneous shut down test of all pumps with measurement of the water
hammer shall prove that the design pressure is not exceeded.
The drainage and dewatering system consist of two free surface sumps sized
to collect all leakage from the shaft seals and from the floor drains.
During emptying of the units for inspection and/or maintenance the water
volume between the closed main inlet valve and the distributor shall be
drained through the drainage and dewatering sump and pumped into the
tailrace tunnel.
39
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
All seepage and leakage (including water resulting from fire fighting
operation) into the powerhouse shall be collected in a sump.
All drainage water from the powerhouse shall pass through an oil separator
before entering the drainage and dewatering sump. The oil separator shall be
sized large enough to collect appropriate leakage volume according to the
oil volume of the governing system and the bearings.
The sump shall have two continuous duty submersible pumps with water
level switches for auto starting and stopping of pumps. One local control
panel for automatic/manual operation of pumps shall also be provided with
pumps.
Two emergency float switches shall be provided for the case of local
flooding at the main inlet valve floor.
The water from powerhouse drainage sump shall be pumped out into the
tailrace tunnel.
All pipes in the power station, embedded as well as surface mounted, shall
be made of stainless-steel tubes.
Each pump line shall have a flow meter for monitoring and alarm purposes.
40
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
6.4.1.3.2.2 Tests
The complete systems shall be tested for correct operation, indication and
function of protection devices. Insulation resistance measurements as per
relevant IEC standards shall be performed.
A simultaneous shut down test of all pumps with measurement of the water
hammer shall prove that the design pressure is not exceeded.
41
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· three (3) air accumulators supplying the mechanical generator brakes and
the inflatable maintenance seals on the turbine shaft. The air
accumulators shall be located on the generator floor each having enough
capacity for three braking operations without recharging. The feeding
lines to those accumulators shall connect directly to the main air tank,
without service taps.
· four (4) tapping points at the machine hall elevation.
· four (4) tapping points at the generator floor elevation.
· four (4) tapping points at the turbine floor elevation.
· four (4) tapping points at the valve floor elevation.
The low pressure compressed air system shall be designed for automatic
operation with the possibility of local manual control of the individual
compressors from the local control panel. In the automatic mode, the
compressors shall respond automatically to pressure fluctuation in the main
air receiver. An automatic change over shall be initiated in case of failure of
the operating compressor.
The low pressure compressed air system shall be rated for a nominal
pressure of 10 bar with an hourly delivery of not less than 150 m³/h. The
42
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The air receiver and the pressure accumulators shall be designed for normal
working pressure of 12 bar in compliance with applicable international
standards, considering national rules and regulations for obtaining
operational allowance.
All pipes and armatures with inside diameter less than 50 mm shall be
stainless steel. Other pipes shall be made of hot dip galvanized steel
seamless tubes.
· two (2) shut-off valves, control valves, non-return valves, drain valves of
each type used
· two (2) pressure gauges of each type used
· two (2) pressure switches of each type used
43
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The fire fighting system study shall form the basis for the Contractor’s
design of the fire fighting system.
A manually controlled filling pump shall be used to fill the storage tank
from the tailwater.
44
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The deluge valve shall be actuated by rupture due to heat of one or more
quartzite bulb heat detectors placed around the equipment to be protected.
The system shall be suitable for operation automatically as well as by
remote and local manual control.
The water requirement for fire protection of the main transformers shall
meet the requirements of NFPA Standard 15.
Hose reels carts shall have two tyred wheels and shall be suitable to
accommodate 40 m of fire hose, 63 mm diameter, in two equal lengths, with
necessary hose couplings and nozzles.
Provision shall be kept outside the fire hose boxes for mounting one
portable carbon dioxide cylinder of 5 kg capacity.
Fire extinguishers of foam and dry powder type shall be provided for valve
floor, turbine floor, cable trenches, diesel engine room, stores, offices, etc.
45
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
None of the mentioned detector types shall contain any moving parts or
parts subject to wear and tear.
All detector types shall be designed for low voltage (DC supply). In order to
keep the electric energy consumption as low as possible, the quiescent
current shall not exceed 0.3 mA per detector unit.
The fire detection system shall be designed such that the actuated detector
remains in the self hold state, even if the fire phenomenon no longer exists.
Within a detector zone only one detector unit shall simultaneously release
an alarm signal.
46
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The alarm system shall consist of annunciation windows for visual and
audio signalling of outbreak of fire in any particular zone of the supervised
respectively protected areas.
The fire control panel shall have at least the following provisions:
47
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· two (2) air handling units, 100 % of the total required capacity each, with
air coolers
· appropriate number of air supply and exhaust fans in the ventilation
tunnel, transformer cavern and the access tunnel to ensure fresh air
supply and the required air exhaustion rates
· battery room exhaust system consisting of one (1) exhaust fan, air duct of
flame-resistant plastic material and exhaust louver
· intake screens, louvers, filters, air ducts and accessories including
registers, grilles, dampers, vanes etc.
· electrical control and instrumentation
· air-conditioning and ventilation system for the service building which
contains the control room, offices, associated facilities rooms, workshops
etc., consisting of:
· two (2) split air-cooling units for outdoor installation, 100 % of the
total required capacity each
· individual (per each room) air control units for control room, offices
and facility rooms (with possibility of independent temperature
controls in each air-conditioned room)
· one (1) air supply blower with air coolers for the workshops
· air ducts, piping, valves and accessories including intake filter, louver
screens ceiling diffusers and dampers, and access doors and electrical
control and instrumentation
· washrooms exhaust system consisting of two (2) exhaust fans, air ducts,
grilles and accessories.
The air conditioning and ventilation system must function as an integral part
of the overall fire protection and evacuation plan for the underground
complex.
The following criteria and assumptions shall be adopted for the design of
the air conditioning and ventilation system.
48
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
· the gallery and transformer cavern are normally not classified as working
areas, and here the principal consideration shall be to control
temperatures to meet equipment operating requirements.
· the major potential fire hazard and source of smoke and products of
combustion are the transformers. The ventilation system must minimize
the circulation of combustion products should a fire occur.
· the heat losses generated by some equipment located in the rooms shall
be transported by means of air flow.
· toilets, battery or oil store / treatment or similar rooms must be ventilated
by exhaust air ventilation systems to prevent bad smelling air.
The proposed system shall draw fresh air through the ventilation and cable
tunnel and discharge it into the machine hall from where it shall circulate
down to the generator and the turbine floor, inlet valve gallery and be then
discharged through the transformer gallery and the access tunnel to the
outside. Air circulation shall be controlled by fans.
Noise
49
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The noise levels caused by operation of the systems shall not exceed:
For the purpose of fire ventilation, the powerhouse is divided into the
following areas:
· machine hall
· generator floor
· turbine floor, valve gallery
· transformer and switchgear cavern
· cable/ventilation tunnel
· access tunnel.
50
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
All remaining spaces in the power station shall be air ventilated. The air
coolers shall be capable of maintaining an indoor temperature not higher
than 30°C.
Oil purifiers for the main transformer oil is included in the section of the
specification relevant to the main transformer.
51
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The fixed transfer pump shall be located adjacent to the oil sump tanks and
shall have capacity of one oil sump tank to be transferred to the oil filtration
unit within a 2-hour period.
The mobile transfer pump shall be a skid mounted self-contained unit with
all pipe work, valves, fittings and controls. The pump shall be sized to be
capable of transferring all the lubricating oil to or from the oil sumps of one
turbine/generator unit within a 4-hour period.
The skid shall be provided with lifting lugs to also allow lifting and
movement by the powerhouse crane as necessary.
The oil filtration plant shall have a capacity of 2.000 litre/hour. The self-
contained plant shall include a vacuum suction pump, thermostatically
controlled heaters, oil purifier, dehumidifier and degasser.
The oil filtration plant shall include all the necessary vacuum pumps,
vacuum tank with heating equipment, pressure pump, filter compartment
and the necessary drives and controls.
The filter elements shall remove all particulars of size greater than one
micron. They shall be designed and installed for easy removal and re-fitting.
It shall be possible to clean the filters without dismantling and their normal
service life should be at least ten years.
All inlet and outlet connections shall be provided and shall include fine
gauge filters of an easily removable type for cleaning.
52
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The oil filtration plant shall be provided with steel-armoured hoses, with
connectors of sufficient length for the duty together with all other devices
and equipment required for the effective processing of the oil.
At least, the following machines and tools, with all necessary accessories,
shall be provided:
53
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The scope of supply shall include, but not be limited to the following:
The final capacity of the crane shall be verified by the Contractor within the
scope of his design according to the heaviest part to be lifted (generator
rotor) with safety. The capacity of the auxiliary hook shall be sufficient to
lift the heaviest part of the turbine (i.e. head cover or runner).
The crane shall be operable from the operator cabin control panel. As an
option, additional crane control form from a portable radio station shall be
offered.
54
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Bumpers shall be attached to the bridge trucks and the trolley. The bumpers
shall be spring or rubber type, capable of bringing the crane and the trolley
to stop when travelling at rated speed in either direction.
A signal horn shall sound automatically as soon as any movement of the
crane is initiated by the operator.
Crane classification:
The crane shall travel the full length of the power station, including the
erection bay.
55
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
The crane shall be equipped with access ladders and platforms, handrails,
cover plates, curbing, etc., under consideration of applicable safety
standards.
and then operated and function tested in the shop checking for adequacy of
design and suitability for reliable, safe and proper operation.
Hoisting device parts from motors to drums shall be load tested using a load
equivalent to the full testing load in final operation conditions.
· verification of dimensions
· all electric hoist shall be tested as per national/international standards
· operation of brakes
· hoisting devices parts from motors to drums shall be load tested using a
load equivalent to the full testing load in final operation conditions.
56
Upper Tamor HPP Part 6.4 Particular Technical Specifications
Electro-Mechanical Works Equipment
Running Test:
· operation of each control switch, contactor relay and other control
devices
· test of all circuits, interlocks and sequences of operation
· test of all protective devices
· all crane motions operate correctly.
Load Test:
The crane shall have each motion tested with the main and auxiliary hook
carrying overload (110 % of the rated load).
Hoist brakes shall be tested with overload (125 % of the rated load).
Deflection Test:
The tests shall be carried out with the rated load at rest and the trolley in the
central position. The deflection measurement shall be taken only after the
load has been applied several times.
Brake Tests:
All brakes shall be tested under full-load conditions, from maximum speed
to rest, three times in quick succession without overheating.
57