Beruflich Dokumente
Kultur Dokumente
Preferred by contractors
• Milestone
Preferred by owners
Retention
b
a
Remember this is all cumulative
Gross
Profit
Overdraft
Zone
Profit (Markup)
2 19
B Activity ID
Duration
17
19 20
0 2 8 11 13 19 G
A C E
1
2 3 6
3 8 11 13
D F Target Schedule
5 2
Target Schedule: is the schedule that will be used in the field. we get it after
resource allocation and leveling
Activities Details
Activity B 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
Activity C 3 3 3
Activity D 1 1 1 1 1
Activity E 2 2 2 2 2 2
Activity G 1
Direct Cost 0.5 0.5 0.2 1.2 1.2 1.2 1.2 1.2 3.2 3.2 3.2 0.7 0.7 2.2 2.2 2.2 2.2 2.2 2.2 1
Cumulative Direct Cost 0.5 1 1.2 2.4 3.6 4.8 6 7.2 10.4 13.6 16.8 17.5 18.2 20.4 22.6 24.8 27 29.2 31.4 32.4
Indirect Cost 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
Cumulative Indirect Cost 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4
Total Cost 0.7 0.7 0.4 1.4 1.4 1.4 1.4 1.4 3.4 3.4 3.4 0.9 0.9 2.4 2.4 2.4 2.4 2.4 2.4 1.2
Cumulative Total Cost 0.7 1.4 1.8 3.2 4.6 6 7.4 8.8 12.2 15.6 19 19.9 20.8 23.2 25.6 28 30.4 32.8 35.2 36.4
Values ×1,000
Cash-out Curve
40
35
30
25
Cost ($)
10
0
0 5 10 15 20 25 30
Time(weeks)
Cash-In Calculations
Case 1:
Retention = 10%
Maximum retention = 5% of bid price
= 5% × $42,000
= $ 2,100
Pay Bid Unit Pay Cumulative Period Cumulative Due
Activity % Complete Quantitiy Price Retention
Period Quantity Price Request Retention Payment Payment Date
1 A (2/2)*100 = 100.0 0 0 0 0.0
(0-4) B (2/17)*100 = 11.8 20 2.4 300 720.0 720 72 72 648 648 8
D (1/5)*100 = 20.0 1 0.2 7,000 1,400.0
2 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
8,410.0 841 913 7,569.0 8,217.0 12
(4-8) D (4/5)*100 = 80.0 1 0.8 7,000 5,600.0
3 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
(8-12) C (3/3)*100 = 100.0 6 6 2,000 12,000.0 14,410.0 1187 2100 13,223.0 21,440.0 16
F (1/2)*100 = 50.0 2 1 1,000 1,000.0
4 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
(12-16) E (3/6)*100 = 50.0 6 3 2,500 7,500.0 9,910.0 0 2100 9,910.0 31,350.0 20
F (1/2)*100 = 50.0 2 1 1,000 1,000.0
5 B (3/17)*100 = 17.6 20 3.5 300 1,050.0
(16-20) E (3/6)*100 = 50.0 6 3 2,500 7,500.0 8,550.0 0 2100 10,650.0 42,000.0 28
G (1/1)*100 = 100.0 0 0 0 0.0
40000
35000
30000
Cash-In ($)
25000
20000 Cash-In
15000
10000
5000
0
0 5 10 15 20 25 30 35
Time (weeks)
Net Cash Flow
45000
40000
35000
30000
25000
20000
15000 Cash-Out
$$
10000 Cash-In
Net Cash
5000
0
0 5 10 15 20 25 30 35
-5000
-10000
-15000
Case 2:
Retention = 10%
Advanced payment ( down payment ) = 10% of
bid price
= 10% × $42,000
= $ 4,200
Pay Bid Unit Pay for down- Cumulative Period Cumulative Due
Activity % Complete Quantitiy Price Retention
Period Quantity Price Request payment Retention Payment Payment Date
0 4,200.00 4,200.00 0
1 A (2/2)*100 = 100.0 0 0 0 0.0
(0-4) B (2/17)*100 = 11.8 20 2.4 300 720.0 720 72 72 72 576.00 4,776.00 8
D (1/5)*100 = 20.0 1 0.2 7,000 1,400.0
2 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
8,410.0 841 841 913 6,728.00 11,504.00 12
(4-8) D (4/5)*100 = 80.0 1 0.8 7,000 5,600.0
3 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
(8-12) C (3/3)*100 = 100.0 6 6 2,000 12,000.0 14,410.0 1441 1441 2354 11,528.00 23,032.00 16
F (1/2)*100 = 50.0 2 1 1,000 1,000.0
4 B (4/17)*100 = 23.5 20 4.7 300 1,410.0
(12-16) E (3/6)*100 = 50.0 6 3 2,500 7,500.0 9,910.0 991 991 3345 7,928.00 30,960.00 20
F (1/2)*100 = 50.0 2 1 1,000 1,000.0
5 B (3/17)*100 = 17.6 20 3.5 300 1,050.0
(16-20) E (3/6)*100 = 50.0 6 3 2,500 7,500.0 8,550.0 0 855 3345 11,040.00 42,000.00 28
G (1/1)*100 = 100.0 0 0 0 0.0
40000
35000
30000
Cash - In ($)
25000
20000 Cash-In
15000
10000
5000
0
0 5 10 15 20 25 30 35
Time (Weeks)
Net Cash Flow
45000
40000
35000
30000
25000
20000
15000 Cash-In
$$
10000 Cash-Out
Net Cash
5000
0
0 5 10 15 20 25 30 35
-5000
-10000
-15000
-20000
Time (Weeks)