Beruflich Dokumente
Kultur Dokumente
Contents
1 Introduction...................................................................................................................................3
1.1 Report....................................................................................................................................3
2 Base Data.......................................................................................................................................4
2.1 Site Location & Description....................................................................................................4
3 Proposed Ground Investigation.....................................................................................................5
3.1 General..................................................................................................................................5
4 Field Investigation........................................................................................................................11
4.1 General Requirements.........................................................................................................11
4.1.1 Borehole Termination Criterion...................................................................................12
4.1.2 Rotary Mud Circulation Boring.....................................................................................12
4.1.3 Rock Boring..................................................................................................................12
4.2 In-Situ Testing......................................................................................................................12
4.2.1 Standard Penetration Test...........................................................................................13
4.3 Sampling..............................................................................................................................13
4.3.1 Representative Samples...............................................................................................14
4.3.2 Undisturbed Sample....................................................................................................14
4.3.3 Rock samples...............................................................................................................15
4.4 Ground Water......................................................................................................................15
4.4.1 Subsoil Water Samples.................................................................................................15
5 Laboratory Testing.......................................................................................................................17
5.1 Essential Requirements.......................................................................................................17
5.2 List of Laboratory Test.........................................................................................................17
5.2.1 Tests on disturbed samples..........................................................................................17
5.2.2 Tests on Undisturbed/Reconstituted samples.............................................................18
5.2.3 Tests on Rock samples.................................................................................................19
6 Other General Requirement........................................................................................................20
6.1 Codes and Standard.............................................................................................................20
7 Presentation of the Test Results..................................................................................................22
7.1 Data to be furnished............................................................................................................22
7.2 Recommendations to be provided.......................................................................................23
8 Summary.....................................................................................................................................24
Appendix - 1........................................................................................................................................25
1 INTRODUCTION
1.1 REPORT
This specification gives the methodology for carrying out geotechnical Investigation for the Dhaka
Metro Line 5 (South). The procedures to be adopted for conducting field and laboratory investigation
including sampling techniques to ascertain the sub-surface conditions for the proposed Metro Route
shall comply with the specifications given herein.
This report is prepared based on the relevant Bangladesh standards or Indian Standard codes related
to Geotechnical Investigation.
2 BASE DATA
The soil condition along the corridor will govern the project and the final choice of the construction
method. The total length of the section is 16.940 Km. Which includes 12 nos. of underground and 3
nos. of elevated stations. It also includes a Depot.
Alignment details:
3 PROPOSED GROUND INVESTIGATION
3.1 GENERAL
Consideration behind fixation of numbers of Bore Holes is as bellow:
i. Borehole spacing along the alignment (carried out by excavation and backfill
method; and excavated by tunnel boring machine (TBM) equipment) approximately 50
m/borehole.
ii. Viaduct section, 1 borehole for every pier location (about 30 m span).
iii. Approximately 7 boreholes for each station. Approximately 40 boreholes for depot
construction site.
Proposed ground investigation locations along the alignment are given in Table 1. In-situ and
laboratory tests in soil strata, rock and ground water as tabulated in Error: Reference source not
found and Clause 3.2 shall be carried out as per relevant codes related to Geotechnical
Investigations.
* The actual depth of the boreholes may vary as per actual geological conditions at site.
Table 2: Summary of Proposed In-situ testing
PART – A
Sieve Analysis
Test shall be conducted for soil samples of all depth based on sample availability.
Hydrometer Test
Test shall be conducted only in clayey soil samples on per layer for every 10 boreholes.
Atterberg’s Limits
Test shall be conducted only in clayey soil samples for classification purpose.
Shrinkage Limits
Test shall be conducted only in Cl – CH type of soil where organic matter is suspected.
Specific Gravity
One test shall be conducted at every 10th borehole for each stratum.
Test shall be conducted only in undisturbed soil samples (Cl – CH type of soil).
On the UD samples collected in clayey layer for depth below 10m, Conduct this test at 5 m depth
interval or for each layer in diagonally opposite boreholes at station and at every 250 m along the
tunnel alignment. σ 1 should be overburden pressure at initial confinement.
Consolidation Test
At station location, for UDS samples, if clayey soil is available, conduct test at depths of 5.0/7.5/10 m.
For Tunnel alignment for every 100 m stretch, conduct one test for every clay layer or for every 5m
below 10m depth.
Conduct UCC test as an alternate to triaxial shear test in clayey samples where Φ is not expected.
Chemical Test
Chemical Test (PH, Chloride, Sulphates) both in PPM and % shall be reported both for soil and
ground water at every 250m interval along the alignment and one at each station location.
Note:
No duplication of tests to be done. In case direct shear/Tri-axial shear is done, UCC need not be
conducted on same sample. Similarly, for free swell pressure tests.
PART – B
At least one test shall be conducted in each borehole in each type of rock stratum.
If UCS could not be conducted due to non-availability of core sample of required length, then
conducted one-point load index tests on rock core samples, one in each type of rock strata.
Modulus of Elasticity
In a length of 500m if rock with RQD≥ 50% is encountered within the alignment of tunnel drive, this
test shall be conducted.
Note : If two types of rock strata are encountered, one test in each rock strata shall need to be
conducted.
Petrography Analysis
In a length of 250m if rock is encountered within the alignment of tunnel drive, this test shall need to
be conducted on each rock type.
Note : If two types of rock strata are encountered, one test in each rock strata shall need to be
conducted.
PART – C
Conducting Standard Penetration Tests in bore holes at every 3.0m starting from first sample at 1.5m
depth or at the change of stratum. If UDS is not collected at any depth as per its requirement, SPT
shall be conducted in lieu of UDS. In case of hard strata (intermediate geo material) the reporting shall
be as no. of blows / penetration achieved. It should not be shown as > 100 or refusal. In case of Zero
penetration, mention as rebound.
At Station locations, in-situ permeability test in soil shall be conducted by using Falling Head /
Constant Head method in the four corners of boreholes for each soil layer. In case of tunnel alignment
conduct at every 250m (10th borehole).
At Station locations in-situ permeability test in rock shall be conducted by using Double Packer
Method in the four corner boreholes. The test depth shall be 15.0m & 25.0m depth below EGL.
Along the tunnel alignment; In one borehole at every 250m intervals, double packer permeability tests
shall be conducted at 15.0m & 20.0m depth below EGL.
Test shall be conducted in clayey soil samples with SPT-N value less than 8.
At Station Location: For the purpose of determination of Earth resistivity of soil for designing the earth
connections – will be decided in the final stages of investigation.
ERT along the alignment: Wherever boreholes cannot be done due to existing buildings, after
consultation ERT shall be conducted at such locations to determine the subsoil and rock profiles.
Cross hole Seismic test: At Station locations and 500m interval along tunnel alignment, this test shall
be conducted to ascertain shear wave velocity etc. dynamic parameters for each soil and rock layer.
Pressure meter tests in rock shall be carried out by using 200 Bar capacity OYO High Pressure
Dilatometer equipment.
Test shall be conducted at Station location. Two tests in the rock strata per borehole shall be carried
out. The tests shall be conducted in two diagonal boreholes at each station location.
Along the Tunnel alignment: In one borehole at every 500m intervals at two different depths.
Test shall be conducted at station location. The tests shall be conducted at 5m, 10m & 15m depth
below EGL. The tests shall be conducted in two diagonal boreholes at each station location.
Along the tunnel alignment: In one borehole at every 250m intervals at 5m, 10m & 15m depth.
PART – D
Rock type with description of colour, texture / structure, core recovery, RQD,
discontinuities spacing, joint condition, orientation, dip of strata, cavities, fissures,
degree of weathering etc. change in rock stratum, ground water level as required as
per BIS codes.
During drilling in rock if the core recovery is not significant in a borehole after using double
tube core barrel, in adjustment borehole triple core barrel shall be used to ascertain the true
core recovery of strata.
During drilling in rock, the penetration of drilling in cm/min should be mentioned for each run
along with mentioning cavities if encountered by way sudden jump.
PART – A
Sieve Analysis
Test shall be conducted for soil samples of all depth based on sample availability.
Hydrometer Test
Test shall be conducted only in clayey soil samples on per layer for every 10 boreholes.
Atterberg’s Limits
Test shall be conducted only in clayey soil samples for classification purpose.
Shrinkage Limits
Test shall be conducted only in Cl – CH type of soil where organic matter is suspected.
Specific Gravity
One test shall be conducted at every 10th borehole for each stratum.
Test shall be conducted only in undisturbed soil samples (Cl – CH type of soil).
Consolidation Test
At station location, for UDS samples, if clayey soil is available, conduct test at depths of 3 to 10 m
depth. For Viaduct alignment for every 100 m stretch, conduct one test for every clay layer or for
every 5m below 10m depth.
Conduct UCC test as an alternate to triaxial shear test in clayey samples where Φ is not expected.
Chemical Test
Chemical Test (PH, Chloride, Sulphates) both in PPM and % shall be reported both for soil and
ground water at every 250m interval along the alignment and one at each station location.
Note:
No duplication of tests to be done. In case direct shear/Tri-axial shear is done, UCC need not be
conducted on same sample. Similarly, for free swell pressure tests.
PART – B
At least one test shall be conducted in each borehole in each type of rock stratum.
If UCS could not be conducted due to non-availability of core sample of required length, then
conducted one-point load index tests on rock core samples, one in each type of rock strata.
Modulus of Elasticity
Petrography Analysis
In a length of 500m if rock is encountered within the alignment of tunnel drive, this test shall need to
be conducted on each rock type.
Note : If two types of rock strata are encountered, one test in each rock strata shall need to be
conducted.
PART – C
Conducting Standard Penetration Tests in bore holes at every 3.0m starting from first sample at 1.5m
depth or at the change of stratum. If UDS is not collected at any depth as per its requirement, SPT
shall be conducted in lieu of UDS. In case of hard strata (intermediate geo material) the reporting shall
be as no. of blows / penetration achieved. It should not be shown as >100 or refusal. In case of Zero
penetration, mention as rebound.
At Station locations, in-situ permeability test in soil shall be conducted by using Falling Head /
Constant Head method in the four corners of boreholes for each soil layer for top 10m.
Test shall be conducted in clayey soil samples with SPT-N value less than 8.
At Station Location: For the purpose of determination of Earth resistivity of soil for designing the earth
connections – will be decided in the final stages of investigation.
ERT along the alignment: Wherever boreholes cannot be done due to existing buildings, after
consultation ERT shall be conducted at such locations to determine the subsoil and rock profiles.
PART – D
Rock type with description of colour, texture / structure, core recovery, RQD,
discontinuities spacing, joint condition, orientation, dip of strata, cavities, fissures,
degree of weathering etc. change in rock stratum, ground water level as required as
per BIS codes.
During drilling in rock if the core recovery is not significant in a borehole after using double
tube core barrel, in adjustment borehole triple core barrel shall be used to ascertain the true
core recovery of strata.
During drilling in rock, the penetration of drilling in cm/min should be mentioned for each run
along with mentioning cavities if encountered by way sudden jump.
3.3 BOQ SUMMARY
TOTAL
ITEM DESCRIPTION UNIT QTY Rate
AMOUNT
1 PRELIMINARIES
4 FIELD INVESTIGATION
I. All boreholes and field tests should be located and extended up to depth as indicated in the
Table 1 or as indicated elsewhere in this specification. The reduced levels (RLs) at these
locations should also be determined with respect to the single bench Mark (BM). Any deviation in
Location or depth of borehole should be specified indicating the reason for the deviation in the
location.
II. The minimum diameter of the borehole should be 150 mm and boring should be carried out in
accordance with any local provisions of Bangladesh or IS: 1892 and as per this specification.
III. Casing pipe should be used in the boreholes to support its sides when a caving is suspected to
occur inside the borehole. When casing pipe is used, it should be ensured that its bottom is
always above the bottom level of the bore hole by a minimum of 15 cm. In case of cohesionless
soils the advancement of the casing pipe should be such that it does not disturb the soil to be
tested or sampled. The casing should be advanced by slowly turning the casing pipe and not by
driving.
IV. In-situ tests should be conducted and undisturbed samples should be obtained at specified
intervals in the boreholes. Representative samples should be preserved for conducting various
tests in the laboratory. Water table in the borehole should be carefully recorded and reported. No
water/drilling mud should be added while boring above ground water table. For cohesionless soil
below water table, the water level in the borehole should at all times be maintained sufficiently
above the water table.
V. The borehole should be cleaned using suitable tools up to the depth of testing or sampling,
ensuring that there is minimum disturbance of the soil at the bottom of the borehole. The process
of jetting through an open tube sampler shall not be permitted.
VI. In cohesive soils, the borehole may be cleaned using a bailer with flap valve. Gentle circulation
of drilling fluid should be done when rotary mud circulation boring is adopted.
VII. On completion of the boreholes, the Contractor should backfill all the bore. It should be back-
filled using selected earth in order that the ground is restored to its original condition.
The test shall be carried out by driving a standard split spoon sampler in the bore hole by means of a
650N hammer having a free fall of 0.75 m. The sampler shall be driven to 450 mm recording the
number of blows for every 150 mm. The number of blows required for each 150 mm penetration
should be recorded and furnished in the report. The number of blows for last 300 mm drive shall be
reported as N Value. The test shall be discontinued when the blow count is equal to 100 or
penetration is less than 25 mm for 50 blows whichever is earlier. At location where test is discontinued
the penetration and number of blows shall be reported. Sufficient quantity of representative soil
samples should be collected from the split spoon sampler (attached to the SPT) for identification and
laboratory testing. The sample should be visually classified and recorded at the site and should be
properly preserved without loss of moisture content and labelled for future identification.
Within the alluvial deposits alternate SPT and open driven U76 samples should be carried out where
possible, reducing to only SPTs where soil is too stiff to obtain undisturbed samples without causing
excessive disturbance. Within decomposed rock, if encountered, SPT testing will be conducted when
successive rotary runs proved abortive due to poor recovery.
4.3 SAMPLING
Sufficient number of undisturbed and representative soil samples should be collected depending upon
the type of soil for reliable estimation of engineering properties of soil. Representative soil samples
should be collected for field identification and for conducting the tests such as sieve analysis, index
properties, specific gravity, chemical analysis, etc. Undisturbed samples should be collected to
estimate the physical strength and settlement properties of the soil. All the accessories required for
sampling and the method of sampling should conform to IS: 2132. All samples collected in the field
should be classified at the site as per IS: 1498.
All the samples should be identified with date, borehole number, depth of sampling etc. It is also
essential to mark an arrow pointing towards the top surface of the sample as the soil was in-situ.
Care should be taken to keep the core samples and box samples vertically with the arrow directing
upwards. The tube samples should be properly trimmed at both ends and suitably capped and sealed
with molten paraffin wax.
When the collection of undisturbed soil sample at a specified depth is not possible, the reason for the
same should be indicated in the bore log. In such a case, undisturbed sampling may be replaced by
any suitable field test such as SPT test to determine the in-situ Engineering properties of the strata.
Precaution should be taken to ensure that the samples are not disturbed and no change in moisture
content takes place during handling, transportation and storing. They should be placed in a temporary
store at the end of the day’s work. Packing and transporting all the samples from site to the laboratory
should be as per IS 4078 within seven days after sampling with proper protection against loss and
damage.
In elevated areas, if superficial material is available in plenty, then bulk samples from a depth of about
0.5 m below ground level should be collected to establish all the required properties to use it as a fill
material. Representative samples weighing about 25 Kg should be collected at shallow depths and
immediately stored in polythene bags as per IS: 1892. The bags should be sealed properly to avoid
any change in moisture content and they should be kept in wooden boxes.
A general guideline is given in the Table 3 to choose the type of sampler depending upon the nature
of the soil.
Gravel Large Diameter thick-walled open drive sampler with catcher device.
Rock Double tube/ Triple tube core barrel with air, mud or foam flush.
In permeable soils, the water level in the bore hole should be allowed to stabilise after depressing it
adequately by bailing. When the water level inside the bore hole is found to be stable, the depth of
water level below ground level should be measured. Stability of sides and bottom of the bore hole
should be ensured at all time.
For both permeable and impermeable soils, the following method is suitable. The bore hole should be
filled with water and then bailed out to various depths. Observations on the rise or fall of water level
should be made at each depth. The level at which the water level stabilises should be considered as
the water table elevation. This should be established by three successive readings of water level
taken at an interval of two hours.
In case any variation in ground water level is observed in any special boreholes, then the water level
in these boreholes should be recorded during the course of the field investigation. Precautions should
be taken so that water (rain, etc.) does not enter the bore hole if the hole is left open for 24 hours for
water level reading.
The sample should be collected in a clean vessel and allowed to settle so that the supernatant liquid
can be poured into a clean well-rinsed glass or polythene bottle. Sufficient quantity and number of
samples should be collected to carry out the chemical analysis and sent to a laboratory in airtight
bottles with proper labelling. The following chemical analysis should be performed on the water
samples: determination of pH value, calcium and magnesium content, turbidity, sulphate, carbonate,
nitrate and chloride contents; presence of organic matter and suspended solids.
5 LABORATORY TESTING
Laboratory tests should be conducted using approved apparatus complying with the requirements and
specifications of Indian Standards or other approved standards for this class of work. It should be
checked that the apparatus are in good working condition before starting the laboratory tests.
Calibration of all the instruments and their accessories should be done carefully and precisely. All the
laboratory tests should be conducted at an approved laboratory.
Undisturbed soil samples retained in liners or seamless tube samples should be taken out without
causing any disturbance to the samples using suitably designed extruders just prior to actual testing.
If extruder is horizontal, proper support should be provided to prevent the samples from breaking. For
screw type extruders, the pushing head should be free from the screw shaft so that no torque is
applied to the soil sample; the sample tube should be cut by means of a high speed hacksaw to
proper test length and placed over the mould before pushing the sample into it with a suitable piston.
While extracting a sample from the liner or tube, care should be taken to see that its direction of
movement is the same as that during sampling to avoid stress reversal.
This test should be carried out on undisturbed cohesive soil samples as per IS: 2720 (Part XV) to get
information regarding the one dimensional loading and unloading-reloading stress path, e-log p′ curve
(including both loading and unloading-reloading path), P o, eo, Cc, Cs and mv for all pressure
increments. The e-log P curve, square-root of time plot and logarithm of time plot should be plotted
and various consolidation parameters should be presented.
The following other general requirements should be taken care of while carrying out Geotechnical
Investigation.
1. Advantage of existing local knowledge, records of trial pits, bore holes, etc. in the vicinity and
the type of foundations adopted and behaviour of existing structures particularly those of similar
nature to the ones proposed for this project may be taken.
2. It is essential that the equipment/instruments used in field as well as laboratory, are properly
calibrated prior to the commencement of the work so that they represent true values. .
3. The work includes mobilization of all necessary equipment providing necessary engineering
supervision and technical personnel, skilled and unskilled labour etc., as required to carry out the
entire field as well as laboratory investigations, analysis and interpretation of data collected and
preparation of a Geotechnical report including recommendations.
4. Arrangements have to be made for accurately locating the coordinates and positions of bore
holes and field tests as per the drawings/sketches supplied and for determining the Reduced Levels
(RLs) at these locations with respect to the single Bench Mark (BM) using adequate survey
instruments.
5. All the field and laboratory data should be recorded in the standard format in the relevant
Indian Standard Codes (listed in the Reference section). Two copies of field bore logs and the entire
field records have to be submitted soon after the completion of each test, within a day’s time.
6. One copy of all the laboratory test data/records should be submitted every week during the
progress of laboratory testing.
7. All work meant within this specification should be carried out even if not explicitly mentioned
under the scope. The contractor should make his own arrangements to access and mobilise men and
materials to the location of investigation.
IS: 1904 Code of practice for design and construction of foundation in soils: General
requirements
IS: 2911 Code of Practice for design and construction of Pile Foundations
IS: 2950 Code of practice for design and construction of raft foundation (Part – I)
IS: 3025 Methods of sampling and testing (Physical and Chemical) for water used in industry
IS: 4078 Code of practice for indexing and storage of drill cores
IS: 6403 Code of practice for determination of allowable bearing capacity on shallow
foundation
IS: 8009 Code of practice for calculation of settlement of foundation subjected to symmetrical
(Part I) vertical loads: Shallow foundations
IS: 8009 Code of practice for calculation of settlement of foundation subjected to symmetrical
(Part II) vertical loads: Deep foundations
IS: 8763 Guide for undisturbed sampling of sands and sandy soils
IS: 9143 Method for the determination of unconfined compressive strength of Rock Materials
IS: 9179 Method for preparation of Rock Specimen for laboratory testing
IS: 10074 Specification for compaction mould assembly for Light and Heavy compaction
IS: 10108 Code of practice for sampling by thin wall sampler with stationary piston
IS: 12070 Code of Practice for Design and Construction of Shallow Foundations on Rocks
IS: 14593 Design and Construction of Bored Cast-In-Situ Piles founded on Rocks – Guidelines
On completion of all the field and laboratory works, the Contractor should submit a formal report
containing Geological information of the region, procedure adopted for investigation, field
observations, summarised test data, conclusions and recommendations for suitable foundation of the
proposed structure. The report should include detailed bore logs, subsoil sections, field test results,
laboratory observations and test results both in tabular as well as graphical form wherever applicable.
The practical and theoretical considerations for the interpretation of test results, the supporting
calculations for the conclusions drawn, etc. should be clearly mentioned in the report. Initially, a report
in draft form has to be submitted for review and discussion. The detailed final report should be
submitted after doing suitable modifications to the draft report along with one set of reproducible and
soft copies of all the graphs, tables etc. All drawings, graphs etc. should be prepared in the latest
version of relevant software’s.
I. Past observations and historical data, if available for the area or for other areas having similar
soil profile with similar structures in the surrounding areas.
II. A plot plan showing the locations and reduced levels of all field tests e.g. bore holes, trial pits,
etc., properly drawn to scale and dimensioned with reference to the established grid lines. Each
of the above should be clearly located (horizontally and vertically) with reference to some datum
or permanent monument.
III. A true cross-section of all individual boreholes and trial pits with reduced levels and coordinates
showing the classification and thickness of individual stratum, position of ground water table. The
location of various in-situ tests conducted and samples collected at different depths and the rock
stratum, if met with. The record of boring should be presented in the format as given in the
Appendix D of IS 1892.
IV. A set of longitudinal and transverse soil/rock profiles to a suitable vertical scale connecting
various boreholes in order to give a clear picture of the variation of the subsoil strata and cross
section to demonstrate site conditions.
V. Plot of Standard Penetration Test N values (both uncorrected and corrected) with depth for
identified areas and results of any in-situ tests carried out.
VI. The stress strain curves and readings in table format along with Mohr-Circle plots should be
furnished.
VII. Results of all laboratory tests should be summarised and a consolidated table giving the layer-
wise soil and rock properties in a standard format. The relevant tables, graphs, figures,
supporting calculations, conclusions and photographs of representative rock cores and trial pits
should be furnished.
IX. Results of chemical analysis of ground water and soil samples shall be furnished.
7.2 RECOMMENDATIONS TO BE PROVIDED
Recommendations should be limited to the following:
I. Protective measures based on chemical nature of soil and ground water with due regard to
potential deleterious effects on concrete, steel and other building materials etc. should be
suggested. Remedial measures for sulphate attack and acidity should be dealt in detail.
8 SUMMARY
The soil investigation should be carried out as per this Standard detailed specification, prepared
based on Indian Standard Codes, at those locations specified in the drawings supplied. The salient
points are listed here.
Item Description
Termination criteria (For i. Minimum depth of exploration should be as per Table 1.
Bore holes taken into bed
rock ) ii. Maximum depth of exploration should be 70 m
OR
Test on Rock:
All the in-situ tests, sampling and laboratory tests should be carried out as per the specifications given
in this document and relevant Indian standards. The depth of the bore hole in the bore log must be
supplemented with the reduced levels derived from the given bench mark. Bore log data should be
submitted in standard format, periodically after the completion of exploration in each bore hole. The
detailed report incorporating the laboratory and field test results along with recommendation should be
submitted soon after the completion of the investigations.
APPENDIX - 1