METHOD OF STATEMENT

MS.01

CLAY TILES WORKS

REVISION HISTORY

0 Revision 0 08-31-2020

Rev. Revision information Date

Originated by Reviewed by Approved by

Eng. Mohamed Salah Eng. Ahmed Mohamed

CLAY TILES WORKS


Page 1 of 6
Clay tiles Works
1.0 OBJECTIVE

1.1 To define the requirements for the supply and execution Clay Tiles works for the
constructions of the Latin quarter
2.0 SCOPE

2.1 Supply and install wood installation system , clay tile, hand over.

3.0 REFERENCE

- EGYPTIAN STANDARD SPECIFICATIONS ES NO. (EN 1304)

4.0 PROCEDURE

4.1 The contractor shall obtain approval from consultant the wood and clay tiles as
specified in the project specification.
4.2 The contractor shall obtain approval from consultant for the sources of all materials
used in the scope of work

4.3 All the equipment necessary for the proposed work should be made available in
working condition at site.
4.4 Before start must be make Samples for work

5: PERSONAL RESPONSIBILITIES

A full and detailed description of the roles and responsibilities of all staff is included within
the Project Quality Plan. For the works as covered by this method statement, the following
personnel have specific duties.

5.1 Technical office Engineer : specific responsibility include :

• Responsible for ensuring that the various submittals are timely


undertaken (materials, workshop drawings, subcontractors issues,
technical issues)

CLAY TILES WORKS


Page 2 of 6
• Responsible for quotations as required (materials, subcontractors).

• Responsible for ensuring RFI’s are timely undertaken on behalf of


Ismailia Co.

• Responsible for the distribution of documents within Ismailia Co. site


personnel.

5.2 Site Engineer : specific responsibility include :

• Ensuring that the project is managed in a safe manner and meets the
requirements of the project documentation.

• Ensuring that subcontractors and suppliers achieve the on-site


required standards.

• Shall refer to the QA/QC Department and the HSE Department for
advice and guidance when required.

• Shall ensure that operatives comply with the relevant method


statements, Toolbox Talks and general site briefings.

5.3 HSE Site reprehensive: specific responsibility include :

• Assisting in the production of any health, safety and environmental


documents.

• Monitoring the implementation of health, safety and environmental


requirements.

• Undertaking audits and ensuring that corrective and preventive


actions are taken where required.

• Liaison with the senior site staff on health, safety and environmental
related matters.

5.4 QA/QC Site representative(s) specific responsibility include :

• Carrying out phased inspections as required.

CLAY TILES WORKS


Page 3 of 6
• Ensuring that all required tests are performed and are in compliance
with appropriate specifications.

• Maintaining a record of all QA/QC activities on site.

• Controlling and ensuring all measuring and test equipment on site is


properly calibrated.

• Controlling all non-conforming products or workmanship, and


implementing the required preventive actions.

• Ensuring that corrective and preventive actions are taken when


required.

• Ensuring that the required testing is undertaken by approved


independent laboratories, and that all test results are reviewed.

5.5 Supervisor (s): specified responsibilities include

• To ensure that all operatives and appropriate subcontractors have


been briefed as to the content of the method statement and the works.
• To adequately control the works as required.
• To ensure the works are undertaken in a safe manner.
• To ensure all operatives are adequately training in their respective
works.
• Reporting any un-safe practices on site to the site team.
.
6. Equipment:
• Hand tools .
7. Materials
• Wood elements
• Counter lath
• Isolated sheet layer
• Wooden stud
• Anchor bolts
• Self drilling screw
• screw
• Clay Tiles

CLAY TILES WORKS


Page 4 of 6
8. Safety:

• Project Safety Plan shall be strictly enforced at all times. All works
shall be regularly monitored to ensure full compliance.
• Ismailia Co. resource as appropriate the supervision of the works.

• All waste materials (rubbish and debris) shall be removed from the
workplace to a suitable area.

• Tools and equipment will be inspected periodically by the Contractor


to ensure that remain in proper working order and certifications is
current.

• Provide additional lighting facility to carryout works in poor daylight.

• All workers have to wear hard hats, safety shoes and gloves.

• Establish first aid station and maintain adequate first aid supplies.

• Stairs, walkways and work areas to be free of debris, grease and oil,
also provide warning tapes and signs at potential fall hazard areas.

• Scaffolding and ladder frames to be properly secured and braced.

• Ensure proper curing periods and procedures.

• Plan routing of work area and other equipment.

9. Testing and Inspection:

• Tests are prepared as specified in approved lap.


10. Submittals:

• Wood installation system


• Isolated layer
• Clay tile works
• Curing Compound.

11. STORAGE OF MATERIALS:

CLAY TILES WORKS


Page 5 of 6
• Materials shall be delivered to batch plant in sealed bags bearing the
manufacturer's name and the type of tiles,
• Materials shall be fully protected during handling and transport from
adverse weather conditions, moisture and over stacking at batch
plant.
• Wood will be delivered and handled in a manner to prevent bending
and damage.
• All used material will be stored as per approval mobilization plan
protected from weather conditions, moisture and over stacking.

18. Finishing

• Any defective area requiring remedial works shall be rectified in


accordance with an approved repair.
• all surface must be level for top and bottom of slab,

19. Q.C AND INSPECTIONS

• Material Test Certificates for wood and the clay tiles like are checked
approved.
20. Stages of installation

1- First fix
• Determination of the finishing level of clay tiles
• Cut elements as in drawing and as built on site
• Install Fischer bolts with concrete elements and solid brick
• Install main beam between top level and bottom level
• Install supports between main beam and main support which flushing
with walls.
• Check all self-drilling screws 100 and blat 100*50 mm with 35 mm screw
which connect all elements .

2- Second fix
• Install isolated sheet layer.
• Install studs on main beam with screws 7 mm.
• Check span between wood studs as in clay tiles data Sheet.
• Ensure integrity in installation.

3- Clay tiles installation


• Install clay tiles with screw 45 mm
• Install clay tile accessories with screw 45 mm

CLAY TILES WORKS


Page 6 of 6