Sie sind auf Seite 1von 6

Powder Technology 221 (2012) 183–188

Contents lists available at SciVerse ScienceDirect

Powder Technology
journal homepage: www.elsevier.com/locate/powtec

An industrial comparative study of cement clinker grinding systems regarding the


specific energy consumption and cement properties
Cetin Hosten a,⁎, Berkan Fidan b
a
Department of Mining Engineering, Middle East Technical University, 06800 Ankara, Turkey
b
Cement Production Chief, Denizli Cement Plant, 20100 Denizli, Turkey

a r t i c l e i n f o a b s t r a c t

Article history: This paper is concerned with a comparative analysis of modern cement grinding systems, namely, combined
Received 30 September 2011 grinding (Comflex®), high-pressure roll mill (HPRM) grinding, and horizontal roller mill (Horomill®) grind-
Received in revised form 14 December 2011 ing. Cement production trials were run with these grinding systems in the same cement plant by using the
Accepted 28 December 2011
same clinker/gypsum feed to produce cements of almost identical chemical compositions and similar Blaine
Available online 4 January 2012
fineness values of about 3600 cm 2/g. The grinding systems were compared in terms of specific energy con-
Keywords:
sumption and mortar properties of the produced cements. The specific energy consumption and the cement
Cement manufacture setting times increased in the order of combined grinding, HPRM grinding, and horizontal roller mill grinding.
Grinding No significant difference was detectable among the water demands of the cements from the three grinding
Specific energy systems. The HPRM cement was superior in strength development, particularly at early ages.
Mortar properties © 2012 Elsevier B.V. All rights reserved.

1. Introduction favorable properties of the product cement. Ball mills, in fact, are
the most energy inefficient grinding mills. They suffer from consider-
Cement production is an energy intensive industry requiring ap- able energy loss in the form of heat due to friction in a tumbling mass
proximately 830–1100 kWh/t cement. Fuel energy represents about of balls which transfers input energy to an unconfined bed of
90% of this total specific energy consumption and the share of particles. In an unconfined bed of particles the entrapment of parti-
electrical energy is about 10%. The electrical energy consumed in cles in the impact zone between the balls is highly probabilistic and
the conventional cement making process is typically 95 to 110 kWh far from the conditions required for optimum conversion of the
per ton of cement [1]. Almost 70% of this electrical energy is used input energy to useful comminution energy. Energy efficiency of a
for comminution, which includes crushing and grinding of cement ball mill depends on a number of factors such as ball filling ratio,
raw materials and clinker grinding. The clinker grinding stage the mill length/diameter ratio, size composition of the ball charge,
accounts for approximately 40% of the electric energy consumed in circulation ratio, throughput, and the fineness of the feed and prod-
cement production. Because of such a high level of energy demand uct. High-pressure comminution with vertical roller mills, high-
and the inherent energy inefficiency of conventional ball mill grind- pressure roll mills (HPRM) or the horizontal roller mill (Horomill®)
ing, the cement industry has continually searched for new grinding has found considerable popularity over the last two decades for im-
mill designs and/or grinding system configurations that can reduce proving capacity and reducing specific energy consumption in clinker
the energy consumption. grinding circuits [1,4]. In high-pressure mills the input energy is
Besides energy consumption, the grinding system has an impor- directly transferred to a confined bed of particles under compression
tant influence on the particle size distribution and particle shape of where comminution occurs primarily by very large inter-particle
the product cement, as well as on the reactivity of the clinker phases stresses generated locally within the compressed bed. HPRM's are
and the temperature-dependent extent of dehydration of gypsum generally placed upstream of conventional ball mill systems as pre-
interground with clinker. All these factors, in turn, affect mortar grinding units to produce a fraction of the circuit product and weaken
properties of the product cement such as water demand, initial and the particles remaining coarser than the product size, which are
final setting times and strength development [2,3]. subsequently ground in ball mills. This combined mode of grinding re-
Despite their high specific energy demand, two-compartment ball quires many material transport units (belt conveyors, elevators and
mills in closed circuit with air separators have been traditionally used air-slides), hydraulic systems, and air classifiers, and this multitude of
for cement finish grinding because of their reliability and the equipment complicates the process. Horomill® operating in closed cir-
cuit with an air classifier, however, was introduced as a single-stage
grinding unit to overcome the operational drawbacks of the combined
⁎ Corresponding author. Tel.: + 90 312 2102661. grinding systems while achieving comparable energy efficiency. In
E-mail address: hosten@metu.edu.tr (C. Hosten). comparison with ball mills, vertical roller mills can achieve an energy

0032-5910/$ – see front matter © 2012 Elsevier B.V. All rights reserved.
doi:10.1016/j.powtec.2011.12.065
184 C. Hosten, B. Fidan / Powder Technology 221 (2012) 183–188

saving of up to 30%, horizontal roller mills up to 35%, and HPRM's up to (Horomill®) circuit, available in the same industrial plant. The grind-
50% [5,6]. This comparison, however, reflects the power consumption ing systems were operated using the same clinker/gypsum feed to
of the mill only and does not include air classifier and auxiliary equip- produce CEM I 42.5 R Portland cements with almost identical
ment like conveyors and dust collectors. chemical compositions and similar Blaine specific surface areas so
A review of the literature showed that some energy-based com- that the sole influence of the grinding mode on the specific energy
parisons of the current cement grinding systems have been made. consumption and cement mortar properties could be delineated.
For example, Schnatz and Knobloch [7] reported specific energy con-
sumptions of 10.93 kWh/t and 16.28 kWh/t for the HPRM and the ball 2. Experimental work
mill, respectively, operated in a combined grinding process producing
CEM I 42.5 type cement of 3970 cm 2/g Blaine fineness at a throughput The same lots of Portland cement clinker and natural gypsum
of 140 t/h. Seebach and co-workers [5] reported plant results from of (CaSO4.2H2O) were used in this industrial-plant-scale experimental
a combined grinding process. The process had a closed-circuit HPRM work to eliminate the potential effects of variations in the feed to
system producing an intermediate product upstream of a convention- the grinding systems. Chemical compositions of the clinker and the
al closed-circuit ball mill system that produced a final cement product gypsum, measured by X-ray fluorescence analysis, are given in
of 3200 cm 2/g Blaine fineness at a throughput of 192.7 t/h. The Table 1. Dehydration behavior of the gypsum was determined by a
specific energy consumption for the major equipment of the com- simple thermal treatment because the extent of dehydration, and
bined process was reported to be 22.2 kWh/t. When only the HPRM hence its conversion to hemihydrate (CaSO4.1/2H2O), may be affected
system or the ball mill system was operated to produce cements of by the temperature of a grinding mill product. After removing the
the same fineness as the combined process cement, the system moisture from the gypsum test sample at 45 ± 5 °C in a drying oven,
throughput was reduced to 122.4 t/h in the HPRM-only case and to the sample was then heated in a furnace with controllable tempera-
72.3 t/h in the ball-mill-only case, with the corresponding specific ture settings. The temperature was increased in a stepwise manner
energy consumptions of 18.8 kWh/t and 35.7 kWh/t. The works men- with increments of 10 °C from 70 to 240 °C. The temperature was
tioned above, however, did not provide any comparison of the mortar held constant for 10 minutes at the end of each increment, and the
properties of the cements produced. weight loss of the gypsum sample was recorded at the end of this
There are comparatively fewer industrial results reported on the 10-minute period. Fig. 1 presents the temperature-dependent cumu-
energy consumption of the horizontal roller mill systems. The operat- lative percent weight loss of the gypsum as a measure of its dehydra-
ing results of the horizontal mill (Horomill®) in the Trino cement tion behavior.
works for the production of various types of cements having different A mix containing 95% clinker and 5% gypsum was ground in three
Blaine fineness and mill feed compositions indicated energy savings different types of grinding systems in the same plant to make CEM I
of 35 to 40% when compared with the specific energy consumption 42.5 R cements having almost identical chemical compositions and
of an optimized ball mill in the same plant [4]. The energy consump- similar Blaine values of about 3600 cm 2/g. Samples were taken from
tion varied in the range of 15.4–23.4 kWh/t for the mill only and of intermediate process streams and final product streams of the grind-
22.2–30.3 kWh/t for the grinding plant at a throughput range of ing systems while operating at steady states. The samples were
19.7–30.0 t/h. The water demand of the Horomill® cement paste analyzed for particle size distribution by means of a laser diffraction
was reported to be 2% higher than for the ball mill cement, with the analyzer. A series of tests were performed according to the relevant
same mortar strength. More recently, Genc and Benzer [8] compared Turkish standards (TS EN 196-1, TS EN 196-3) to determine the key
energy consumptions of an industrial horizontal roller mill grinding quality properties of the final cement products, namely, water
system and a hybrid HPRM/ball mill grinding system when the two demand, initial and final setting times, and compressive strength.
systems produced different types of cement with different pozzolanic Electrical energy consumption of the main equipment and that of
additives. Specific energy consumptions were reported as 20.9 kWh/t the complete grinding circuit were also recorded for an hour at the
in the horizontal roller mill system at a throughput of 106 t/h and steady-state operation during the sampling periods for each system.
28.5 kWh/t in the hybrid system at a throughput of 85 t/h. Blaine The three industrial grinding systems tested in this study were 1)
values and mortar properties of the cements, however, were not the combined grinding system (Comflex®) using a HPRM circuit up-
reported in their study. stream of the ball mill circuit to produce a combined final cement
An overview of the literature indicates that the three clinker product, 2) HPRM-only system in which the cement was produced
grinding systems mentioned above have been investigated separately only with the HPRM circuit of the combined grinding system, and
or two together on the basis of energy consumption by using different 3) the horizontal roller mill (Horomill®) system. Figs. 2 and 3 present
feed materials and producing different type of cements, mostly with- the simplified flow sheets of the tested systems. The combined
out the accompanying mortar properties of the produced cements. grinding system (Comflex®) is a combination of HPRM grinding and
Direct comparisons of the results, however, should suffer from some conventional ball milling. In this mode of plant operation, the feed
limitations since no two plants are the same as to machine design material (clinker and gypsum) is first crushed and fractured in the
and operating parameters. Extending the range of available data on HPRM and then dropped into a static V-separator, which functions
the comparison of these systems, particularly with tests conducted both as a disagglomerator and a classifier for the HPRM product.
in the same plant, would be beneficial for the industry with a goal The coarse product of the static separator is re-circulated into the
of better understanding the capabilities of the grinding systems. HPRM. The separator's fines are pneumatically transported into a
This paper presents an investigation carried out to compare the third generation, high-efficiency dynamic separator. The fine product
three clinker grinding systems, namely, the combined grinding (Com- stream of the dynamic separator is collected in a bag filter. The fine
flex®) circuit, HPRM-only circuit, and the horizontal roller mill particles collected on the filter fabric constitutes a part of the final

Table 1
Chemical compositions of the cement clinker and the gypsum used in the study.

SiO2 (%) Al2O3 (%) Fe2O3 (%) CaO (%) MgO (%) SO3 (%) Na2O (%) K2O (%) L.O.I (%) H2O* (%) Free CaO (%)

Clinker 21.07 5.17 3.88 65.47 1.77 1.43 0.14 0.77 0.30 – 1.61
Gypsum 0.29 0.01 0.03 33.56 0.57 43.93 – – – 18.43 –

* Water of hydration, excluding 0.92% of moisture.


C. Hosten, B. Fidan / Powder Technology 221 (2012) 183–188 185

100

90

80

70
Dehydration, %

60
Fig. 3. Simplified flow sheet of the horizontal roller mill (Horomill®) system.
50

40 conducted uses the HPRM-only circuit as an alternative to continue


its production when the ball mill circuit is under maintenance. The
30 Horomill® system is also a single-stage comminution system using
a horizontal roller mill operated in closed circuit with a high-
20 efficiency air classifier. The Horomill® is made up of a horizontal ro-
tating shell equipped with a grinding track within which a hydraulic
10 roller exerts pressure on the grinding bed. In the plant investigated,
this system is used more frequently for the production of CEM II
0
50 70 90 110 130 150 170 190
type Portland composite cement or CEM IV type pozzolanic cement
Temperature, °C and rarely for the production of CEM I 42 R cement.

Fig. 1. Dehydration behavior of the gypsum used in the study. 3. Results and discussion

3.1. Particle size distributions


cement product and joins the cement product from the downstream
ball mill circuit before being dispatched into the cement silo. The Table 2 presents the operating parameters of the three grinding
coarse particles that are collected at the bottom of the dynamic sepa- systems that processed the same clinker/gypsum feed to produce
rator flow into a splitter bin. The splitter bin separates the classifier cement products of almost identical Blaine fineness. Particle size dis-
coarse product into two streams. One stream feeds the ball mill circuit tributions of the final cement products of the grinding systems of this
at a controlled rate matching the ball mill operating capacity and the study were well described by the Rosin-Rammler-Sperling-Bennett
second stream, which is the coarse material in excess of the ball mill (RRSB) function which is defined as [9]
capacity, is directed to the HPRM re-circulation stream (Fig. 2). Since
xn
some clinker particles reach the required fineness in the HPRM com-
R ¼ 100 exp ½  ð1Þ
minution stage without passing through the ball mill, this combined k
mode of grinding obviously yields a final cement product composed
of material with mixed physical characteristics, which may affect ce- where R is the cumulative weight percent of particles coarser than
ment quality properties. The HPRM-only system is a simple commi- size x, while n and k are the fitted parameters of the RRSB function.
nution process where the ball mill circuit of the combined grinding The position parameter k, having the same units as x, is the particle
system is not operated and the coarse material in the splitter bin is to- size at which R takes the value of 36.8% (or, equivalently, the cumula-
tally re-circulated to the HPRM. The plant in which this study was tive mass of particles finer than size x is 63.2%). The smaller the

Fig. 2. Simplified flow sheet of the combined grinding (Comflex®) system.


186 C. Hosten, B. Fidan / Powder Technology 221 (2012) 183–188

Table 2 100
Operating parameters of the investigated grinding systems.
90 A
Combined grinding HPRM-only Horomill®
(Comflex®) system system system B
80

Cumulative mass % finer than size


Blaine value, cm2/g 3572 3656 3577
C
45-μm residue, mass % 14.1 7.6 9.3
RRSB position parameter, μm 26.6 22.6 25.0 70
D
RRSB slope 1.18 1.26 1.29
Cement temperature, °C 104 92 63 60
Product density, g/cm3 3.15 3.12 3.14
Throughput in this study, tph 200 95 48
Throughput in regular plant 210–215 110–115 55–60 50
operations *, tph
Specific energy in this study, 40
kWh/t
main-equipment basis 27.3 29.9 33.7
total grinding system 30.6 34.0 37.3 30

* Throughputs for the production of the same type of cement, but with 5% limestone
addition and slightly lower Blaine values. 20

10

position parameter is, the greater the fineness of the particle 0


population. Parameter n is the slope of the straight line fitted to the 1 10 100
measured particle size distribution data and describes the width of Particle Size, µm
the distribution. The larger the slope is, the narrower the size distri-
Fig. 4. Particle size distributions of the cements from the three grinding systems: A) Ball
bution. Table 2 contains the position parameter and the slope of the mill cement of the combined grinding (Comflex®) system; B) HPRM cement of the
cement products as well as the cumulative mass percentage of parti- combined-grinding system; C) HPRM-only cement; D) Horomill® system cement.
cles coarser than some specific sizes. All three cements have more or
less the same slope parameter with values of about 1.2. This value of
the slope indicates relatively narrow size distributions which are at- cements of the same Blaine fineness of about 3600 cm2/g at different
tributed to sharp selectivity of the air separators closing the cement throughputs (tons of cement produced per hour) of the systems dictat-
grinding circuits [10]. The position parameter of the cement produced ed by the equipment design capacities. The main-equipment basis
in the combined grinding system is slightly coarser than that of the power consumption includes the main drive systems of the mills,
cements produced in the other two grinding systems. Table 2 also system fans and separators, while the whole-grinding-plant basis
shows that the combined grinding cement has a relatively higher per- consumption includes also the auxiliary equipment such as material
centage (14.1%) of 45-μm residue than the cements produced in the transport systems, weigh-feeders, filter fans, pneumatic and hydraulic
other two grinding systems (7.6% and 9.3% for the HPRM-only and units. We should note at this point that we did not attempt to determine
the horizontal roller mill system, respectively). The 45-μm residues throughput-dependent specific energies of the studied systems; how-
of the ball mill cement and the HPRM cement in the combined grind- ever, the throughputs attained during the investigation were quite
ing system were determined as 21.0% and 9.8%, respectively, by laser close to the normal operating ranges of the systems in regular produc-
diffraction particle size analysis. These values indicate that the higher tion operations of the plant as given in Table 2.
45-μm residue percentage of the combined cement results from the From Table 2 it can be seen that the combined grinding system
higher percentage of the residue in the ball mill cement. had the least specific energy consumption (30.6 kWh/t), followed
Particle size distributions of the cements from the three grinding by the HPRM-only system (34.0 kWh/t) and the horizontal roller
systems are presented in Fig. 4. The figure indicates that the HPRM mill system (37.3 kWh/t). The HPRM circuit in the combined grinding
cement of the combined grinding system has a relatively finer size system accounted for about 60% of the measured total energy (kW-
distribution than the ball mill cement of the same system, which hours) consumption. Considering the fact that about 53% of the final
resulted from the differences in the classification performances of cement product of the combined grinding system was produced by
the air separators producing these two cements. The Blaine values the HPRM circuit without being subjected to ball milling, we could
of these two cements, composing the combined cement, were mea- separately calculate the specific energy consumptions of the HPRM
sured to be 3682 cm 2/g and 3447 cm 2/g, respectively. The measured and ball mill circuits as 34.6 kWh/t and 26.0 kWh/t, respectively.
Blaine values of the combined cement and those of the HPRM and This lower specific energy consumption in the ball mill circuit could
ball mill cements enabled us to calculate that the HPRM cement con- be due partly to the lower size reduction ratio achieved in the ball
stituted 53% of the final combined cement product. This is a typical mill circuit than that in the HPRM circuit, and partly to the particle-
value that has been observed repeatedly in regular production opera- weakening effect of the upstream HPRM. The size reduction ratio,
tions of the plant. Size distributions of the cements from the HPRM which is defined as the ratio of the feed median size to the ground
circuit are expectedly quite the same irrespective of whether the product median sizes, provides a simple means for comparing size
HPRM is operated in the combined grinding mode or the reduction processes [11]. For the same energy efficiency, larger
HPRM-only mode, since the same high-efficiency dynamic separator reduction ratios demand larger specific energy consumptions. The
generated the cement products of similar fineness in both cases. size reduction ratio for the ball mill circuit in the combined grinding
circuit was only about 4 while receiving a HPRM-crushed feed of
3.2. Specific energy consumptions 100-μm median size and producing a cement product of 25-μm medi-
an size. The reduction ratio was about 335 for the HPRM circuit for
A comparison of the specific energy consumptions of the investigat- grinding the clinker feed with a median size of about 6 mm down to
ed grinding systems is given in Table 2 on both the main-equipment a cement product of 18-μm median size. This large difference be-
and the whole-grinding-plant basis. The comparison condition for the tween the reduction ratios must be the main reason for having
three systems was to attain the steady state operation while producing lower specific energy consumption in the ball mill circuit despite
C. Hosten, B. Fidan / Powder Technology 221 (2012) 183–188 187

the well-known fact that size reduction in the ball mill is intrinsically time minus the initial setting time. The total setting time was the
less energy efficient than in the HPRM. In addition, inter-particle same (69 minutes) for the combined grinding and the HPRM-only
stresses generated within the compressed bed of the HPRM has systems even though the cement from the former system displayed
been claimed to impart internal flaws in the particles, leading to the a more rapid initial setting than that of the latter system. The initial
weakening effect which was shown to enhance energy efficiency in and final setting times seem to follow a trend with the measured tem-
the subsequent ball milling step [12]. peratures of the cements from the grinding systems of this study
(Table 2); the higher the cement temperature is, the shorter the set-
3.3. Mortar properties of the cements produced ting times. The cement temperature dependency of the setting times
suggests that, in agreement with the previous studies [16,17], the
Table 3 compares the most important mortar properties of the ce- form of calcium sulfate produced by mill conditions might have
ments produced in the investigated grinding systems, namely, water affected the setting times. The increased temperature and long resi-
demand, setting times, and compressive strength. These properties dence times in the grinding mill can cause dehydration of the added
are particularly influenced by chemical composition and reactivity gypsum from dihydrate (CaSO4.2H2O) to hemihydrate (CaSO4.1/
of cements, particle size distribution, particle shape, surface area, 2H2O), which dissolves more readily than dihydrate, and/or to soluble
and by the type and quantity of the added sulfate agent. anhydrite III (CaSO4). An adequate proportion of hemihydrates is very
The water demand has two components, namely, the physical effective for controlling the early C3A hydration but, if the hemihy-
water demand and the chemical water demand. The physical compo- drates content is too high, then stiffening or even a false set may
nent of the water demand is for moistening of the particles and filling occur in cements with low quantity and reactivity of C3A due to the
of the void volume between the particles. This physical component precipitation of part of the hemihydrates to yield secondary gypsum
constitutes the majority of the total water demand and is determined crystals [2]. Considering the fact that about 47% of the cement
primarily by particle size distribution. The chemical component is of produced in the combined grinding system was exposed to a tempera-
much smaller quantity which is required for the chemical reactions ture of about 112 °C in the ball mill and considering the dehydration
between the cement constituents and the added water, essentially behavior of the gypsum used in this study (Fig. 1), combined-
for initial hydration of the tricalcium aluminate (C3A) to form ettrin- grinding cement might have had an excessive amount of hemihydrate
gite (calcium trisulfoaluminate) [10]. The quantities and reactivities causing shorter setting times by secondary gypsum formation. This
of the C3A and the sulfate agent (gypsum) are mainly responsible argument, however, remains to be the subject of further investigations
for the chemical component of the water demand and the setting be- involving direct measurement of the form of calcium sulfate in the ce-
havior. A previous study [13], however, indicated that, with cements ment products from the grinding systems of this study.
of different reactivities but of the same size distribution and the Compressive strength development for all ages, from 1 day to
same Blaine fineness of 3000 cm 2/g, the water demand of the 28 days, in the HPRM-only cement was significantly higher than
sulfate-adjusted cements differed by only about 0.5 to 1.5 percentage those of the combined-grinding and horizontal-roller-mill cements,
points around a water demand of 25%. the latter two having almost the same strength development
The water demand test results shown in Table 3 do not allow any (Table 2). The superiority of the HPRM cement was more noticeable
differentiation to be made between the cements investigated in this at early strength (1 to 7 days) development. This might be attributed
work, confirming the findings of the earlier works [13,14] in that to the possible increase in the reactivity of the tricalcium silicate (C3S)
the water demand is predominantly governed by the particle size dis- phase by high-pressure compression, which to a great extent controls
tribution rather than the mode of grinding. In another investigation the short-term strength development. The form of the calcium sulfate
[15], however, water demands of HPRM products were reported to in the cement is another factor that is likely to affect strength devel-
be higher than ball mill products of similar particle size distribution opment. It is reported that the presence of hemihydrate reduces the
and chemical composition, and the difference was attributed to the in- strength of cement mortars due to rehydration of part of the hemihy-
ternal surface area generated by the cracks within the clinker particles drate present in the cement [16]. The combined-grinding cement had
produced by high compression stressing in the HPRM. It is possible that a higher potential for gypsum-to-hemihydrate conversion because of
the internal surface area can increase, at least to a certain extent, the having been exposed partly to a much higher temperature in the ball
total surface area available for hydration reactions, thereby, increasing mill. However, it showed almost the same strength development as
the chemical water demand, a comparatively insignificant component the horizontal-roller-mill cement which had no potential for hemihy-
of the total water demand. It appears from the results in this work drate formation at the measured cement temperature of 48 °C. There-
that such a potential effect of the HPRM was not detectable for practical fore, the effect of hemihydrate on cement strength, if any, does not
purposes under the tested operating conditions. seem to be important in this study.
The variation in the initial and final setting times of the investigat-
ed cements was considerably different. The combined-grinding ce- 4. Conclusions
ment had the shortest initial and final setting times, followed by the
HPRM-only and horizontal-roller-mill cements, in the increasing Based on the data obtained from the industrial production and
order. The horizontal-roller-mill cement demonstrated the longest testing for mortar properties of CEM I 42.5 R Portland cements pro-
total active setting time (111 minutes), defined as the final setting duced from the same clinker/gypsum feed ground to almost identical

Table 3
Mortar properties of the product cements.

Water Setting times Compressive strength, MPa*


demand
Initial (min.) Final (min.) 1 day 2 days 7 days 28 days
(%)

Combined grinding system 28.9 145 214 16.25 (0.37) 27.85 (0.55) 42.13 (0.39) 55.10 (0.98)
HPRM-only system 29.5 160 229 22.53 (0.38) 35.63 (0.82) 48.98 (0.82) 57.85 (0.59)
Horomill® system 28.6 182 293 17.23 (0.33) 28.20 (0.59) 43.13 (0.86) 53.63 (0.39)

* Figures in parentheses are standard deviations of four replicates.


188 C. Hosten, B. Fidan / Powder Technology 221 (2012) 183–188

Blaine fineness with three different grinding systems, the following [3] Y.M. Zhang, T.J. Napier-Munn, Effects of particle size distribution, surface area and
chemical composition on Portland cement strength, Powder Technology 83
conclusions could be deduced: (1995) 245–252.
[4] S. Buzzi, The Horomill – a new mill for fine comminution, ZKG International 50
• Due to the high efficiency of the air classifiers closing the grinding (3) (1997) 127–138.
[5] H.M. von Seebach, E. Neumann, L. Lohnherr, State-of-the-art of energy-efficient
mills, the three grinding systems produced cements with quite sim-
grinding systems, ZKG International 49 (2) (1996) 61–67.
ilar particle size distributions having more or less the same RRSB [6] H. Rosemann, H.-G. Ellerbrock, Grinding technology for cement production, ZKG
slope parameter. The RRSB position parameter of the cement from International 51 (2) (1998) 51–62.
the combined grinding system (HPRM/ball mill, each having its [7] R. Schnatz, O. Knobloch, Influence of the ball mill filling factor on the power con-
sumption and throughput of ball mills in combined grinding plants, ZKG Interna-
own air classifier) was, however, slightly coarser because of the tional 53 (8) (2000) 438–447.
coarser size distribution of the cement product from the air classifi- [8] O. Genc, A.H. Benzer, Horizontal roller mill (Horomill®) application versus hybrid
er closing the ball mill. HPGR/ball milling in finish grinding of cement, Minerals Engineering 22 (2009)
1344–1349.
• The combined grinding system had the lowest specific energy [9] H. Masuda, K. Higashitani, H. Yoshida, Powder Technology Handbook, third ed.
consumption (30.6 kWh/t) followed by the HPRM-only system CRC/Taylor & Francis, Boca Raton, 2006.
(34.0 kWh/t) and the horizontal roller mill system (37.3 kWh/t) [10] H.-G. Ellerbrock, S. Sprung, K. Kuhlmann, Particle size distribution and properties
of cement- Part III: Influence of the grinding process, ZKG 43 (1) (1990) 13–19.
when the systems were operated at throughputs close to their [11] D.W. Fuerstenau, J. Vazquez-Favela, On assessing and enhancing the energy
plant design capacities. In the absence of throughput-dependent efficiency of comminution process, Minerals and Metallurgical Processing 14
specific energy measurements with each of the systems, this com- (1) (1997) 41–48.
[12] D.W. Fuerstenau, J.J. Lutch, A. De, The effect of ball size on the energy efficiency of
parison should be considered more of case-specific rather than an hybrid high-pressure roll mill/ball mill grinding, Powder Technology 105 (1–3)
absolute one. (1999) 199–204.
• The type of the grinding system did not have a clearly noticeable [13] R. Schnatz, H.-G. Ellerbrock, S. Sprung, Influencing the workability characteristics
of cement during finish grinding with high-pressure grinding rolls, ZKG Interna-
effect on water demand, whereas it was noticeably influential on
tional 48 (5) (1995) 264–273.
setting times and strength development. The cement generated in [14] I. Odler, Y. Chen, Influence of grinding in high-pressure grinding rolls on the
the combined grinding system had the shortest setting times, and properties of the portland cement, ZKG 43 (6) (1990) 145–147.
the HPRM-only cement had the highest strength development. [15] I.B. Celik, M. Oner, N.M. Can, The influence of grinding technique on the liberation
of clinker minerals and cement properties, Cement and Concrete Research 37
• The variations in the setting times seemed to be related with the (2007) 1334–1340.
temperature differences in the product cements probably causing [16] G. Goswami, B. Mohapatra, J.D. Panda, Gypsum dehydration during comminution
different extents of gypsum dehydration, but this must be substan- and its effect on cement properties, Journal of the American Ceramic Society 73
(1990) 721–723.
tiated with further investigations. [17] P.K. Panigrahy, G. Goswami, J.D. Panda, R.K. Panda, Differential comminution of
gypsum in cements ground in different mills, Cement and Concrete Research 33
(2003) 945–947.
Acknowledgement

The authors gratefully acknowledge the plant management at the C. Hosten received his B.S. degree in 1973 and M.S. degree in 1976 in mining engineer-
ing from Middle East Technical University (METU), Ankara-Turkey. After receiving his
Denizli Cement Plant (Turkey) for their permission to conduct and Ph.D. degree in mineral process engineering from University of California at Berkeley in
publish this work. The plant staff is also thankfully acknowledged 1982, he joined the faculty in the Department of Mining Engineering of METU, where
for their help and close interest during the work. he continues as Professor. His major research interests have been directed towards
the processing of minerals and particulate materials, and particularly comminution,
coagulation/flocculation and filtration.
References
B. Fidan received his B.S. degree in mining engineering in 2006 and M.S. degree in
[1] J. Harder, Advanced grinding in the cement industry, ZKG International 56 (3) cement engineering in 2011 from Middle East Technical University (METU), Ankara-
(2003) 31–42. Turkey. In 2007, he started to work at the Denizli Cement Plant (Turkey) as raw materials
[2] I. Odler, Hydration, setting and hardening of portland cement, in: P.C. Hewlet engineer, where he continues as the cement production chief. He has been actively in-
(Ed.), Lea's Chemistry of Cement and Concrete, fourth ed., Elsevier Ltd., 2003, volved in commissioning of new cement grinding systems since 2009.
pp. 241–297.

Das könnte Ihnen auch gefallen