Sie sind auf Seite 1von 2

CASE NOTE

DAMAGES FOR LOST When a contract is breached The assessment of


PROFITS—A QUESTION the question often arises as to contractual damages in
the extent of damages that may
OF REMOTENESS Australia relies on the well
be recovered by the aggrieved
established doctrine set
STUART PTY LTD V party. Damages that naturally
arise are generally recoverable out in Hadley v Baxendale
CONDOR COMMERCIAL (1854) 9 Ex 341, an old but
but compensation for the more
INSULATION PTY LTD remote and less foreseeable still very relevant English
[2006] NSWCA 334 damages will depend very much case.
Scott Alden, Partner on the facts of each individual
case. A recent decision of the
Alyson Eather, Solicitor Court of Appeal regarding a claim
TressCox Lawyers, Sydney for loss of profits went through
the relevant factors to consider in
relation to the recovery of remote
damages.
The assessment of contractual
damages in Australia relies on the
well established doctrine set out
in Hadley v Baxendale1 an old but
still very relevant English case.
This case set out the two limbs of
contractual damages being those:
1. arising naturally, i.e. according
to the usual course of things; or
2. such as may reasonably be
supposed to have been in the
contemplation of both parties, at
the time they made the contract,
as the probable result of the
breach of it.
It is the second limb which
was relevant in this case which
considered the situation where
a contractor sought damages
from its subcontractor for
loss of profits in a potentially
lucrative contract where that
contract was terminated due
to the subcontractor’s faulty
workmanship.
Stuart (the contractor) entered
into a contract with the
Commonwealth of Australia
to replace wool insulation in
residential properties as part
of the Sydney Aircraft Noise
Insulation Program. Relevant
to this case, the work to be
carried out on each property was
its own discrete contract, and
whilst it was expected that the
government would enter into a
number of such contracts with

56 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #117 NOVEMBER/DECEMBER 2007


Stuart, due to past experience and their likelihood is less than an may lead to agreement not being
other factors, this was not certain. even chance, the relevant test reached on the contract or to
is whether they are ‘not unlikely difficult risk discussions at the
Stuart subcontracted the work
to occur’. It is clear that ‘a great commencement of a project when
to Condor (the subcontractor)
many extremely unlikely results the parties are more interested in
which failed to properly box some
are reasonably foreseeable’.5 focussing on the positive aspects
downlights prior to installing the
of the project.
insulation leading to a fire at five (e) It is clear that a general loss of
of the properties. Following a profits is recoverable but loss of Notwithstanding this difficulty
quality audit the Commonwealth profits from a specially lucrative it is advisable for parties to
terminated the contract with contract of which a defendant is engage in a risk identification
Stuart for faulty workmanship and unaware is not. The parties must and allocation process in relation
Stuart brought an action against contemplate both the general to performance and non–
Condor for loss of profits resulting nature of the loss or damage performance of their contracts.
from the loss of this contract and and the general manner of its This ensures that the parties are
also the potential profits in the occurrence.6 fully aware of their position at
expected large number of future, the outset and are then able to
(f) The law is conscious of the
but now lost, contracts. At first make informed decisions about
injustice of visiting the party in
instance the trial judge found proceeding to contract and pricing
breach with the consequence of a
that the faulty workmanship for potential risks and damage.
loss that is not within that party’s
by the subcontractor was the reasonable contemplation when
reason for the termination of the contracting.7 REFERENCES
contract between Stuart and the
government but that the claim for In this case the court found that 1. (1854) 9 Ex 341
lost profits for future contracts the subcontractor was not liable
2. C Czarnikow Ltd v Koufos
was too remote. Stuart appealed for these damages as they were
[1969] 1 AC 350
this decision to the Court of outside of the second limb in
Appeal. Hadley v Baxendale. In finding 3. ibid
this the court focussed on the
The Court of Appeal, in this case, 4. ibid
disparity between the price
confirmed that when considering 5. R&H Hall Ltd v WH Pim (Junior)
payable to the subcontractor
contractual damages the two & Co Ltd (1928JJ) 33 Com Ca 324;
for the work and the very large
limbs of Hadley v Baxendale set [1928] All ER 763 at 388
and disproportionate claim for
out the relevant tests and then damages for lost profits. As a 6. Alexander v Cambridge Credit
proceeded to consider a number result of this disparity it was Corporation Limited (1987) 9
of subsequent decisions which seen that the presumption of NSWLR 310
have applied and clarified these acceptance by the defendant of
tests on their particular facts. 7. Castle Construction Pty Limited
the risk, due to actual knowledge
These subsequent cases have v Fekala Pty Limited [2006]
of the potential damage at
established the following: NSWCA 133
the time of contract, had been
(a) Not every type of damage rebutted.
reasonably foreseeable by the It is highlighted in the judgement
parties when the contract is made that one solution to this potential
can be considered as arising problem of uncertainty in relation
naturally or in the contemplation to the recoverability of damages
of the parties.2 following a breach is the inclusion
(b) It is not enough that, in fact, of an express clause in the
the plaintiff’s loss was directly contract which clearly allocates
caused by the defendant’s the risk in the event of the breach
breach.3 occurring as well as identifying
the damage which may flow and
(c) The crucial question is
responsibility for that damage. Of
whether the loss of the particular
course parties are often unwilling
kind was within the defendant’s
to clearly identify and allocate all
contemplation.4
potential risks and damage at
(d) Damages are not necessarily the start of a project, particularly
too remote merely because the higher value risks, as this

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #117 NOVEMBER/DECEMBER 2007 57

Das könnte Ihnen auch gefallen