Beruflich Dokumente
Kultur Dokumente
:
Concrete block plant for recycling of
coarse silica fume and quartz fines
First edition : 2019-04-10
Rev/date :
PROCESS DESIGN BASIS Page : 1
Table of contents
1 INTRODUCTION 2
1.1 A3 / BC and background 2
1.2 Process Description 2
1.3 Process Flow 2
1.4 Capacity Requirements / Demands 3
1.5 Consumption Figures and Calculations 3
1.6 External Factors 3
3 CONTROL SYSTEMS 5
4 UTILITIES 6
4.1 Electricity 6
4.2 Compressed air 6
4.3 Water 6
4.4 Utility 6
Chosen concept is a dry casting process. The materials should be thoroughly mixed since the silica fume is
hydrophobic. Expected density of the mix is 1,75 g/L. The visual appearance of the blocks is not important,
but the blocks should have hexagonal form and sized to 100 mm by 100 mm. Early strength is important,
since they will be handled in bulk after curing. The blocks should not produce fines during handling after 1
day of curing in a building heated to 15 °C.
Quartz fines and silicon metal fines are fed into bins with a wheel loader. Coarse silica fume is pneumatically
transported into a silo. Either cement or hydrated lime is fed into a silo with big bags using a forklift. The dry
materials are transported from the bins and silos and weighed before they are fed into the mixer. The mixer
discharges the dry castable mix, which is fed into a hopper above the concrete block machine. Expected
density of the mix is 1,75 g/L. Material is processed by the machine which produces hexagonal blocks or
other shapes suitable of further bulk handling in transportation belts with 13° incline and storage in silos.
Boards with blocks are stacked and transported by truck, cart or other automatic means to nearby curing.
After 1 day of curing, the blocks are de-boarded and transported outside to a 22 m 3 open steel container. The
de-boarding should be automatic. The empty boards and pallets are transported back to the concrete block
machine.
As seen in Figure 2, the plant is to be positioned near the sea, at 2,5 m above sea level with one long side
next to a slope and one short side next to existing factory. Since there are physical constraints, the project
must be categorized as brown field. Figure 3 and Figure 4 shows drawings of the planned building. This
building can be modified as no final decisions have been made. Nearby oxygen storage tank is positioned 20
m north of production plant, and should not interfere with the project. See Appendix C: Pictures of plant area
as of 10.4.2019 for more details. Current concrete structure and material will be removed and the site will be
leveled prior to the project construction phase.
Figure 2: Proposed layout for the surrounding area
3 CONTROL SYSTEMS
The level of automation must be enough to enable operation with one or two persons. Currently, Elkem
Thamshavn is using PLC hardware from Siemens, and these components will be preferred. Human Machine
Interface at site is expected. It should be possible to extract reports from the production plant.
4 UTILITIES
4.1 Electricity
100 kW 400 V-IT 50Hz is available near the site.
4.3 Water
Water is available
4.4 Utility
District heating is nearby and possible to connect. Need for drainage is mapped by supplier.