No Description Unit Qut Rate Amount
01 Door or window with frame size over 4 sqm no. 2.00 2,880.00 5,760.00
removed from existing walls and stacked.
02 Floors brick paved, demolished and debris sqm 39.93 362.00 14,454.66
cleared away within the site.
03 Cement, lime plastering chipped and debris sqm 107.26 94.00 10,082.44
cleared away within the site.
04 Removing of existing roof (tiles, asbestos sheets sqm 128.59 281.00 36,133.79
or GI sheets) with timber frame, stacking usable
material and clearing debris in single storied
building.
Sub Total 66,430.89
D - CONCRETOR
Item
No Description Unit Qut Rate Amount
5 112x150mm Stiffness Columns in 1:2:4(20mm) lm 4.35 976.00 4,245.60
cement concrete including formwork &
Reinforcement
Sub Total 4,245.60
H- PLASTERER
Item
No Description Unit Qut Rate Amount
06 20mm thick plinth plaster in 1:3cement - sand sqm 16.82 1,118.00 18,804.76
mortar finished smooth with red cement floating.
07 Cement plaster with 1:5 mix, 15mm thick sqm 107.26 916.00 98,250.16
finished smooth with skim coat in internal walls
- up to first floor level
Sub Total 117,054.92
I - PAVIOR
Item
No Description Unit Qut Rate Amount
08 Floor ramp 75mm thick, 750mm width cement lm 40.22 2,522.00 101,434.84
concrete 1:21/2:5(25mm) on gauge 750
polythene layer and cement rendered, expansion
joints filled with 1:2 bitumen sand including
filling and compacting gravel on the base and
providing 150x225mm curb at the edge finished
smooth with red cement floating
Sub Total 101,434.84
J - ROOFER
10 Supply and fix Zn-Al ridging (Colour) - 0.47 lm 14.32 2,030.00 29,069.60
mm thick with necessary bolts and nuts
(Corrugated Type)
11 Supply & fixing Zn-Al Valance Board (Colour) lm 46.60 1,053.00 49,069.80
thickness 0.47mm with necessary bolt and nuts
Item
No Description Unit Qut Rate Amount
15 Supply and fix Front door, 95x70mm frame and sqm 3.87 15,742.00 60,921.54
28mm thick sash with designs in Teak timber
(Fit panels) complete with brass furniture, 2 nos.
150mm barrel bolts and 3 nos. hinges including
preparation of surface and application of two
coats of Varnish
SUMMARY
No. ITEM AMOUNT
1 DEMOLISHER 66,430.89
2 CONCRETOR 4,245.60
3 PLASTERER 117,054.92
4 PAVIOR 101,434.84
5 ROOFER 507,621.87
Prepared by :-
Checked by :-
Approved by :-
the like.
PROVINCIAL EDUCATION DEPARTMENT CIVIL ENGINEERING UNIT - NCP - ANURADHAPURA.
Ammount
Specification Qty Items
Rs. Cts. Rs. Cts.
This estimate provides for all the cost of 01 Estimate cost 951,408.91
Labour materials, tools transport and
Over heads etc. necessaru for 02 Vat 15% 142,711.34
03 Engineering and Administration 5% 46,738.87
BOQ for Repair Work of 40'X20' Building at
A/Selesthimaduwa Vidyalaya 04 Physical Contingencies 10% 95,140.89
284,591.09
All as per the body of the estimate plan and
attached B.O.Q. Total Estimate 1,236,000.00