Sie sind auf Seite 1von 9

BOQ for Repair Work of 40'X20' Building at

A/Selesthimaduwa Vidyalaya

PROVINCIAL EDUCATION DEPARTMENT


CIVIL ENGINEERING UNIT
NORTH CENTRAL PROVINCE
ANURADHAPURA
BOQ for Repair Work of 40'X20' Building at A/Selesthimaduwa Vidyalaya
A - DEMOLISHER

Rates for Demolisher shall include for:


(a) Scaffolding, shoring and shores required.
(b) Protection of site personal, plant and equipment by taking precautions against uncontrolled collapse,
(c) electrical
Materials hazards and fire
arising from the or explosionworks
demolition risks. shall be removed as directed by the Engi

Item
No Description Unit Qut Rate Amount
01 Door or window with frame size over 4 sqm no. 2.00 2,880.00 5,760.00
removed from existing walls and stacked.
02 Floors brick paved, demolished and debris sqm 39.93 362.00 14,454.66
cleared away within the site.
03 Cement, lime plastering chipped and debris sqm 107.26 94.00 10,082.44
cleared away within the site.
04 Removing of existing roof (tiles, asbestos sheets sqm 128.59 281.00 36,133.79
or GI sheets) with timber frame, stacking usable
material and clearing debris in single storied
building.
Sub Total 66,430.89

D - CONCRETOR

Grade of concrete used in the construction and recommended mixes as follows.


(a) Grade C20/25 Recommended Mix 1 : 1 ½ : 3 (20mm)
(b) Grade C16/20 Recommended Mix 1 : 2 : 4 (20mm)
(c) Grade C12/15 Recommended Mix 1 : 3: 6 (40mm)

Rate shall include,


(a) Mixing, hoisting, placing and compacting on the surfaces of any material or on formwork.
(b) Forming any construction joint and before concreting edge should be chipped and cleaned
(c) Vibrating, curing and protecting concrete surfaces from harmful weather conditions.
(d) Forming slope on upper surfaces where required.
(e) Maximum water Cement ratio 0.55
(f) Making good after removal of form work.
Instructions
(a) Prior approval for any concrete work should be taken from the Engineer.
(b) Approval for constituent materials and test reports for properties of concrete should be taken from
(c) Quality
Cement Control Engineer,
used should be SLSQuality Control
certified lab, approved
products Kekirawafor
with contractor's expense.
concrete.
(d) Reinforcement and formwork paid separately where not mentioned.
(e) Any mix design should be approved from material testing laboratory - Kekirawa.

Item
No Description Unit Qut Rate Amount
5 112x150mm Stiffness Columns in 1:2:4(20mm) lm 4.35 976.00 4,245.60
cement concrete including formwork &
Reinforcement
Sub Total 4,245.60

H- PLASTERER

Rates for wall finishing shall include for:


(a) Temporary rules, screeds, ground etc.
(b) Ranking out joints of brickwork and backing concrete surface for forming key.
(c) Joints between different surfaces should be formed with chicken mesh or suitable bonding method
(d) Forming arises and stopping against joinery work, metal work etc.
(e) Making good around pipes, sanitary fittings and fixtures.
(f) Straight cutting and raking cutting holes, notching and other sundries Labour of a like nature.
(g) Preparing sample panel of different finishes described below for the approval of the Engineer. Each
(h) panel not area
Plastered less than
to be0.5 m2 in area.
protected from sunlight to avoid cracking.
(i) Cement used should be SLS Certified Products

Item
No Description Unit Qut Rate Amount
06 20mm thick plinth plaster in 1:3cement - sand sqm 16.82 1,118.00 18,804.76
mortar finished smooth with red cement floating.

07 Cement plaster with 1:5 mix, 15mm thick sqm 107.26 916.00 98,250.16
finished smooth with skim coat in internal walls
- up to first floor level
Sub Total 117,054.92

I - PAVIOR

Rates for paving and tiling shall include for:


(a) Preparing surfaces of concrete / brick to receive rendering plaster bedding etc.
(b) Joints between different surfaces.
(c) Finishing to slopes and cross falls.
(d) Straight cutting and waste of tiles and other types of floor finishes.
(e) Protecting finished surfaces.
(f) For temporary rules, screeds, ground etc.
(g) All normal cutting arises, rounded edges, bedding and pointing.
(h) Slope should be maintained to a suitable direction to flow the water towards out side.
(i) Expansion joints so that no cracks propagated.
(j) Tiles should be approved by the Architect.

Item
No Description Unit Qut Rate Amount
08 Floor ramp 75mm thick, 750mm width cement lm 40.22 2,522.00 101,434.84
concrete 1:21/2:5(25mm) on gauge 750
polythene layer and cement rendered, expansion
joints filled with 1:2 bitumen sand including
filling and compacting gravel on the base and
providing 150x225mm curb at the edge finished
smooth with red cement floating
Sub Total 101,434.84

J - ROOFER

Rates for Roof work shall include for:


(a) Hoisting and placing roofing materials in position.
(b) Laps, straight cutting and waste.
(c) Galvanized iron “J” bolts, nuts, limpets and bituminous felt washers, nails screw clips, rivets straps and the like.
(d) Rafter hooks fixing rafters to the wall.
Rates for joinery work shall include for:
(a) Framing together all works in accordance with the best practices.
(b) Nails Screws, Glue, plugs etc.
(c) Priming backs before fixing.
(d) Rawl plugs, brass screws etc.
(e) Drilling and making goods.
Instructions
(a) Approval for all Roofing materials should be taken from the Engineer before using.
(b) All the timber used to be treated with wood preservative to the specifications.
(c) Ceiling sheets to be painted with one coat of acetic filler and two coats of emulsion p
(d) All the beading to be painted with one coat of wood primer and two coats of enamel paints.
(e) For exposed rafter roofs, timber should be well planed and varnished. Timber sizes indicated in the
description are the sizes before planning.
Item
No Description Unit Qut Rate Amount
09 Zink Alum. Sheet- Corrugated Type -colour- sqm. 128.59 1,903.00 244,706.77
(Thickness 0.47 mm, Base metal thickness
0.42mm , strength 550Mpa) roof on existing
framework including necessary fasteners as per
Manufacturer's Specifications

10 Supply and fix Zn-Al ridging (Colour) - 0.47 lm 14.32 2,030.00 29,069.60
mm thick with necessary bolts and nuts
(Corrugated Type)
11 Supply & fixing Zn-Al Valance Board (Colour) lm 46.60 1,053.00 49,069.80
thickness 0.47mm with necessary bolt and nuts

12 Furnishing and fixing of 50x100mm Imported lm 150.00 731.00 109,650.00


treated timber and apply one coat of wood
preservative
13 Furnishing and fixing of 100x150mm Imported lm 7.30 3,857.00 28,156.10
treated timber and apply one coat of wood
preservative
14 Furnishing and fixing of 50x50mm Imported lm 143.20 328.00 46,969.60
treated timber and apply one coat of wood
preservative
Sub Total 507,621.87
K - CARPENTER AND JOINER

Rates for carpentry work shall include for:


(a) All Labour in framing together all work in accordance with the best practices,
(b) complete withfixing
Hoisting and all necessary nails, spikes, screws etc.
in position.
(c) Drilling and making good.
(d) Applying two coats of and approved wood preservative before fixing.
(e) Testing to establish properties to conformity to specification.
Rates for joinery work shall include for:
(a) Framing together all works in accordance with the best practices.
(b) Nails Screws, Glue, plugs etc.
(c) Priming backs before fixing.
(d) Drilling and making goods.
(e) Rawtering all squares.
Rates for Glazing shall include for:
(a) Straight cutting and grinding edges where required.
(b) External miters to polishing and leveled edges.
(c) Curving edges.

Item
No Description Unit Qut Rate Amount
15 Supply and fix Front door, 95x70mm frame and sqm 3.87 15,742.00 60,921.54
28mm thick sash with designs in Teak timber
(Fit panels) complete with brass furniture, 2 nos.
150mm barrel bolts and 3 nos. hinges including
preparation of surface and application of two
coats of Varnish

Sub Total 60,921.54

M - PAINTER AND DECORATOR

Rates for painting shall include for:


(a) Preparation of surfaces, cleaning down.
(b) Smoothing, knotting, stopping etc.
(c) Protecting floors and fittings etc.
(d) Removing and replacing doors furniture and cleaning upon completion.
(e) Providing samples and specification of all paints to be used in the works.
(f) Providing painting to an approved colour scheme design.
(g) All the paints are to be done up to the manufacturers specification.
(h) Preparation sample panels of different finishes for the approval of the Engineer. Each panel not less
than 0.5 sqm in area.
Item
No Description Unit Qut Rate Amount
16 Prepare surface and apply two coats of floor sqm 18.36 495.00 9,088.20
paint, red, gray or black
17 Painting walls with Emulsion paint, 2 coats, sqm 90.35 408.00 36,862.80
including preparation of surface
18 Painting walls with Weather shield paint, 2 sqm 98.45 485.00 47,748.25
coats, including preparation of surface
Sub Total 93,699.25

SUMMARY
No. ITEM AMOUNT

1 DEMOLISHER 66,430.89

2 CONCRETOR 4,245.60

3 PLASTERER 117,054.92

4 PAVIOR 101,434.84

5 ROOFER 507,621.87

6 CARPENTER AND JOINER 60,921.54

7 PAINTER AND DECORATOR 93,699.25

TOTAL AMOUNT 951,408.91

Prepared by :-

Checked by :-

Approved by :-
the like.
PROVINCIAL EDUCATION DEPARTMENT CIVIL ENGINEERING UNIT - NCP - ANURADHAPURA.

BOQ for Repair Work of 40'X20' Building at A/Selesthimaduwa Vidyalaya

Ammount
Specification Qty Items
Rs. Cts. Rs. Cts.

This estimate provides for all the cost of 01 Estimate cost 951,408.91
Labour materials, tools transport and
Over heads etc. necessaru for 02 Vat 15% 142,711.34
03 Engineering and Administration 5% 46,738.87
BOQ for Repair Work of 40'X20' Building at
A/Selesthimaduwa Vidyalaya 04 Physical Contingencies 10% 95,140.89

284,591.09
All as per the body of the estimate plan and
attached B.O.Q. Total Estimate 1,236,000.00

Name :-U.G.P.P.K Suraweera


Prepared by :- I.S.W

Name :-K.Anura Peris


Checked by :- S.W.E (Acting)

Approved by :- ………………………… …………………………


Name :-Eng. A.S.Kurukularathna, J.K.U.A.Jayalath,
School Works Engineer Provincial Director of Education
Provincial Education Department Provincial Education Department
Anuradhapura Anuradhapura