Sie sind auf Seite 1von 2

Format No.

Common Checklist for Piping


APIL-NCR-PP-CHKL-006
(For Site run Pipe Routing)
REV.00

Contract / Project Name


Contract / Project No.
Boiler Type
Drawing Nos.

SL. Status (Tick if


Checkpoints
No. Confirmed)
Print the latest checklist for Site run pipe routing from the master
1.
checklist.
2. Before start the drawing, read the contract data sheet.

3. Ensure the piping is under IBR or NON IBR.

If piping under IBR, Ensure the following.


a). DESIGN DATA
4.
b). Material Specification
c). Welding Details with IBR FIG.NO.

5. Check design pressure and design metal temperature of the pipe.


Check the pipe routing with latest General Arrangement, Plot Plan, PPA
6.
and structure GA drawings.
Check the location & elevation of equipments as per plot plan and vendor
7.
drawings
8. Check the pipe routing is fouling with equipment or structure.

9. Ensure all lines are covered as per P & ID.


Ensure the following items are provided in the drawings as per P & ID.
a). Valves and valve tag nos.
b). Pressure and temperature gauge.
10. c). Pressure and temperature transmitter
d). Sampling
e). Flow transmitter
f). Pressure killing device / Orifice Plate.
Check the item nos, material specification, item quantity as per piping
11.
layout.
12. Ensure the bought out items are numbered correctly.

13. Ensure the BOM for part drawing nos. are mentioned correctly.

14. Ensure the vendor drawings for connection between equipment to piping

Check the vendor drawing for pipe connection matting flange and
15. fasteners are released, if not released. Ensure these items are released
in this drawing.
Valves and instruments shall be installed in such a way it shall be
16.
operated either from platform, ground or conveniently from operating floor
Check whether the valve bodies or their hand wheels are fouling with
17
adjacent structures or pipe lines.
18.. Check the material specification for fittings with concern person.

1
Format No.
Common Checklist for Piping
APIL-NCR-PP-CHKL-006
(For Site run Pipe Routing)
REV.00

Ensure elevation and pipe routing dose not affect the free movement of
19.
operating personal
Ensure continuous dimensions are mentioned for piping from reference
20.
point.
Consider 10% extra length for pipe, in addition to total length of pipe as
21.
per layout
Provide extra quantity for elbows and support clamps for easy to pipe
22.
routing at site.
Provide supports for straight pipe every 3 meters and provide the
23
supports at bend location.
24. Ensure the typical support details are given in drawing.
For unequal tee socket weld fitting is not available, proceed with butt weld
25.
unequal tee fitting
Check and ensure that all the weld symbols along with the details are
26.
given correctly
Provide the pipe length and support clamps for drain pipe based on
27
trench or pit location.

28 Ensure the following notes are must.


The arrangement and dimensions shown in this drawing is tentative only.
a.
Erector can re-route the piping as per site conditions.
Support materials given in random length. Use these as per site
b.
requirement.
c. Item nos.xx & xx length are given in running meters.

d. Extra quantity are given for item nos. xx, xx & xx.

Checked by Approved by
Signature with date : Signature with date :

Name : Name :