Beruflich Dokumente
Kultur Dokumente
Construction Method
Statement Sample
Client Ref: 123457
For
Location xxx
E-mail: support@structures-made-easy.co.uk
Principal: xxx
Consultant: xxx
Unless explicitly stated otherwise, all rights including those in copyright in the content of this document are owned by
or controlled for these purposes by Structures Made Easy
Except as otherwise expressly permitted under copyright law , the content of this document may not be copied,
reproduced, republished, broadcast or transmitted in any way without first obtaining written permission from the
copyright owner.
1. Scope of Work 1
5. Design Philosophy 2
6. Construction Sequence 3
9. Appendices 5
1. SCOPE OF WORK
This Construction Method Statement (CMS) is produced for submission to the London
Borough of [borough name] in relation to a planning application at [property address],
for a front and rear basement extension.
The CMS is only to be used for this purpose and may not be reproduced and used for
any other property without the express permission of its author, without which, no
liability for the accuracy of the contents contained within can be granted or guaranteed.
The property is a mid-terrace dwelling arranged over 3 floors above ground level with a
partial lower ground floor. The property is constructed in solid brickwork (no cavity) with
suspended timber floors above basement under a slate covered traditional cut and
pitched mansard roof.
There are no trees in the vicinity of the proposed excavations that would normally
constitute further design considerations in accordance with B.S.5837:2012 ‘Trees in
relation to design, demolition and construction – Recommendations’.
The adjoining property at [neighbouring property address] has very recently carried out
a full excavation of the front and rear garden areas to form a new lower ground floor
throughout the property.
The existing ground conditions are noted from the British Geological Records as being
Kempton Park Gravels overlying London Clay.
No formal trial pit or borehole log has been carried out at the property given the
prevailing conditions whereby there is an existing basement and no obvious hydro-static
ground water problems manifest in the existing basement area.
Additionally, no pump system was used to enable the excavation to the adjoining
basement at [property address] further reinforcing our opinion that the level of the
water-bearing strata is below the excavations and intrusions.
Architect drawings [drawings number] show the existing and proposed basement
layouts.
Structural drawings [drawings number] show the underpinning sequence and retaining
wall sequence and sections.
5. DESIGN PHILOSOPHY
The basement design will be carried out following relevant statutory design guidance in
the British Standards, namely: B.S.8102:2009 ‘Code of practice for protection of below
ground structures against water from the ground’; B.S.8004:2015 ‘Code of practice for
foundations’; and B.S.8002:2015 ‘Code of practice for earth retaining structures’.
6. CONSTRUCTION SEQUENCE
1. Excavation will commence at the front of the property with arisings being removed
by ‘grab lorry’ on a daily basis. When complete, excavation will continue at the rear
of the property with arisings being moved from rear to front by small Bobcat
skidsteer machine and/or wheel barrow. The arisings will be lifted from basement
level to ground floor for removal using a mechanised conveyor belt.
2. The new retaining walls 1-5 are formed in sequence so that the back of the
excavation can be utilised for supporting the back props until the last wall is
constructed. Wall 5 will be propped using a sacrificial thrust block cast into the base
below the drainage runs to support the inclined props supporting the shutter
forming the wall.
3. The existing walls to be retained will be underpinned as necessary using traditional
methods in a ‘hit and miss’ sequence as outlined on SME drawing [drawing no.] with
underpins typically 1000mm width. Each underpin must be 48 hours old before dry
packing. After underpin 3 is formed and dry packed a further 72 hours must pass
before excavating for the last underpin 4 is excavated in order to preserve the
structural integrity of the other underpins and the party fence wall above.
4. Each underpin is formed using a base and stem. The base is cast first then the stem
with continuity reinforcement supplied to tie the two elements together and
laterally.
5. Dry packing 75mm thick will be carried out in a specific time sequence to each
underpin as outlined in a specification accompanying the underpin installation
design to ensure structural stability of the property is maintained throughout the
operations.
6. Temporary Works (TW) design to support the front and rear party fence walls and
footpath will be designed by a qualified Engineer and followed as excavation
proceeds to full depth. Lateral support props will be incorporated at specific depths
of the excavation in line with the TW Method Statement.
7. The retaining walls will be formed in elevational sequence with starter bars to
connect to the adjacent wall subject to the TW design.
8. The basement slab will be designed to provide lateral support to the finished
retaining wall base.
9. Propping for basement wall removal and back propping for ground floor alterations
and new steelwork will then be carried out and completed prior to the next item.
10. The sump pump chamber and below slab drainage for both foul and surface water
will then be installed to correct falls leading to the existing main sewer connection
for foul and surface water.
11. The new basement slab will then be constructed with soft joints formed around each
drainage pipe before pouring concrete.
12. The waterproof membrane will then be applied to the slab and walls in accordance
with the warranted design for the membrane and immediately covered with the
appropriate level of rigid insulation to protect against damage and for thermal value.
13. The correct thickness of screed will then be applied including any underfloor heating
provision to the required floor level prior to applied floor finishes.
Where the ground is found to be stable, excavations can proceed in accordance with the
TW design and method statement. Ground water should not present a problem given
the absence of hydrostatic ground water arising in the existing basement; however,
should ground water ingress occur, a sump pump must be supplied and discharged into
a skip or other receptacle to first permit silts to settle before the pumped water is
allowed into the below ground drainage system.
The primary risk comes from inadequate propping during underpinning and wall
removals by not following a clearly defined methodology for Temporary Works.
The existing impermeable areas at the front and rear are not materially increased by the
construction of the proposed extended basement and therefore do not constitute a net
increase of surface water run-off to be considered in design.
9. APPENDICES
[SME Consultant]
Beam over
Sacrificial Thrust Block
Beam over
Beam over
Beam over
Beam over
New
Column
1 3 4 2
Proposed Basement
Existing wall
Wall to be properly propped during construction
17
MS PARSONS
Sample GREEN LANE Structural Details
Contact:-
· Support@structures-made-easy.co.uk A3
· www.structures-made-easy.co.uk
MS Sample