Civil team

Contractor:- :- OROK GLOBAL CO. Well Pad:- Ru-94

Location:- S-Rumaila
Date:- 25-Mar-19
Degassing Station:- MARKAZIA

PTW No.:- 0150424


Site Supervisor:- Mustafa maan

Weather condition:- 28 C Work completion:-98%

Man Power No. Equipment No.


Site supervisor 1 Excavator 1
HSE supervisor 1 Shovel
Surveyor 1 Dump truck
Equipment Operator 2 Water tanker
Carpenters Compactor
Steel fixer Grader
Foreman 1 Van
Skilled Labourers Ladder
Labourers 2 Pickup 1
Masons Lorry
Cement Finishers Truck Mixer
Total man power 8 Total No. Equipment 2

Item Start Finish Work Activity Activity


No. time time %
1 6:15 6:25 TBT

2 6:30 12:30 Excavation around flow line %85

3
4

Item No. Next Day Plan


1 Excavation around flow line
2
3

Rev.2 Page 1
Wells Dep. Daily report
Civil team

No. Visitor Name Company Arriving time leaving time Reason of visit
1 Haitham taha civil 9:30 11:00 check
2

NPT (HRS) Reason

Photos

Rev.2 Page 2

Das könnte Ihnen auch gefallen