PILING WORKS
GENERAL
The following machinery and manpower are to be used for piling works.
1) Piling rig with 2500 kg hydraulic hammer - 2 no.
2) Mobile Crane - 1 no.
3) Welding set - 2 nos
4) Supervisor - 1
5) Surveyor - 1
6) Skill workers - 4
7) Welder - 2
8) General labor - 2
1
SETTING OUT
1. Upon completion of earthwork to the required level Land Surveyor shall established the
control points and TBM at the nearest location. Control points and TBM shall be
protected and firmly planted.
2. Piling points shall be pegged as per construction drawing.
3. Piling points setting out shall be checked the correctness by joint inspection with
Consultants prior commencement of piling works. Nevertheless the Contractor is
responsible for the accuracy of setting out.
PILE
1 When receiving the materials, R.C. pile shall be checked for the quality and any
deviation.
2 Maximum allowable deviated of pile size are +- 6 mm.
3 Allowable deviated ( bowing or straightness ) of pile via horizontal from end to end are
+-6 mm.
4 Any crack shall be checked. Cracked pile cannot be used.
5 Only matured pile can be used for driving. Only piles are casted more than 21 days are
recommended for driving.
MACHINE
1. Piling frame shall be in good condition. The rig shall be secured and firmed.
2. The machine should have PMA Certificate ( Perakuan Kelayakan Mesin Angkat ) and
valid.
3. The Operator should have their certificate of competency to operate crawler crane.
2
HANDLING PILES
1. Highly precaution shall be taken in handling and slinging the piles. Mobile crane shall be
used for handling and slinging. Slinging rope has to use click system.
2. Mobile crane should have PMA Certificate( Perakuan Kelayakan Mesin Angkat )
3. The Operator should have legal licensed.
4. Pile shall be stacked properly and should follow manufacturer’s recommendation.
^ ^
0.2 L 0.6L 0.2L
DRIVING
1. Piles shall be pitched accurately in their positions and on the appropriate lines.
2. Adjustments shall be made to get the hydraulic piling frame in vertical as possible.
3. The verticality of pile shall be checked by spirit level and plumb bob at two direction.
4. Hydraulic hammer than start driving the initial pile. At the earlier stage check the
verticality of pile consistently. Driving of R.C. piles shall be continuous without
interruption.
5. Pile head shall be protected by helmet.
6. Plywood pack shall be packed in helmet as cushion.
7. Extension pile shall be joint by welding. Mild steel plate at the head of initial pile shall
be welded with mild steel plate at tow of extension pile.
8. Welder should have their competency certificate.
9. Welded plate shall be painted with anti rush paint.
10. The pile shall be waited to cool before subsequent driving can proceed.
11. Pile shall be driven to the specified depth as per required in the contract.
12. Deflected pile cannot be force back to the correct alignment. It will be damaged the pile.
3
13. A driving record shall be recorded with the particulars of date driven, pile position, pile
series number, no of blows and penetration depth.
14. A complete set of pile driving record shall be submitted to Consultant for verification.
1 Piles installation sequence shall be group by foundation slab panel. There are 27 numbers
of foundation slab panel and 1 number of service corridor slab.
Road A - 3 panels of foundation slab
Road B - 23 panels of foundation slab
Part Of Round About - 1 panel of foundation slab
Service Corridor Slab
2 Numbering system for each panel
Road A - 1A,2A and 3A
Road B - 1B,2B,3B,4B,5B,6B,7B,8B,9B,10B,11B,12B,13B,14B,15B,16B,
17B,18B,19B,20B,21B,22B and 23B
Part Round/A - 1C
Serv. Corridor - SC
3 Each panel of foundation slab has a total numbers of piling points. The number of piling
points was clearly stated in the proposed piling layout started from number
1,2,3……………..
example : 1A1,1A2,1A3……….
Please refer to layout plan that clearly indicate piles reference point
PILING PROGRAMME
4
2 Piles shall be completely driven panel by panel of foundation slab. Machine 1 shall be
driving started from Road A. The driving sequence for machine 1 is :
Panel SC,1A,2A,3A,1C,1B,2B,3B,4B,5B,6B,7B,8B and 9B
3 Machine 2 shall be started from Road B
The driving sequence are started from Panel 10B,11B,12B,13B,14B,15B,16B,
17B,18B,19B,20B,21B,22B and 23B.
Note : ER has absolute right to instruct the contractor to install working piles in any sequence deem
necessary to suit site conditions or for the satisfactory completion of the work.
DRIVEN TOLERANCE
1. The maximum permissible deviation from center point of each driven pile is 75 mm in
any direction.
2. The verticality of each driven pile shall be not deviated by more than 1 : 75 from true
vertical position.
LOAD TEST
1. The trial pile or pilot pile shall be tested by maintain load test.
2. Kentledge shall be used as static load and shall be supported by I-Beam and cribwork.
3. Pile head shall be cut and prepare using epoxy or non-shrink cement mortar for leveling
at the required level for the purpose of load test.
4. Detail of test procedure will be submitted before the commencement of load test.
CUTTING OF PILES
5
3. Pile reinforcement bar shall be exposed as per indicated in the drawing or 40 times the
diameter of bar for the purpose anchorage.
1. All welds will perform by metal arc welding and conform to BS 5135
2. Welding are carried out by welders who are qualified from the Welder Test to BS 4872
3. Welding electrodes for materials shall comply to BS 4360.