Chapter 1 - Introduction
The Guidelines were originally published in September 1990 and subsequently updated in June 1996. They summarize FTA requirements, best practices, and
research results in the management of transit capital project development. The Guidelines are designed for use by FTA "grantees" (also used to mean
"owner" or "transit agency") and their consultants as well as the FTA staff and Project Management Oversight (PMO) contractors. FTA maintains oversight for
the grants that it awards, but assigns the grant administration and management responsibility to the grantees. FTA assigns the responsibility for oversight of
nearly all capital grants to the appropriate FTA Regional Office.
Dedicated use of the Guidelines should contribute to effective project management on the part of the grantee, and effective oversight and guidance by FTA
and the PMO contractor. Each project phase should: 1) start with inputs or a baseline, 2) have a process that refines the project definition and generates
outputs that, 3) become the inputs or baseline for the subsequent phase. By defining the requirements for each phase and sound approaches to their
accomplishment, the Guidelines allow grantees to define project requirements, allocate resources, perform project activities, monitor progress, and make
adjustments, as required, to obtain the proper information and assure decisions are made at the appropriate time. Adherence to the Guidelines should
minimize scope changes, schedule slippages, cost overruns, and quality problems, and contribute to fully meeting all the performance objectives of the transit
capital project.
There is a need for transit construction staff to be involved in planning and design. This
coordination is essential to ensure that plans are feasible from a construction standpoint.
Involvement by the local community also is essential at every stage of project
development, from planning through construction.
Because a sound management and control plan should be implemented early in the life of a project, the Guidelines encompass the planning phase, in addition
to the design and construction phases, where the greatest level of effort is expended.
For completeness, the operational or revenue service phase is also presented to encourage a comprehensive, life cycle management approach. This approach
systematically assesses the relationship between the constructed transit capital project and operational realities to determine future system needs, both
modernization and expansion.
1 of 5 1/28/2011 10:07 PM
Federal Transit Administration - Planning & Environment - [printable version] http://www.fta.dot.gov/printer_friendly/planning_environment_1335.html
The Guidelines address the full range of issues and present management principles applicable to all FTA-funded capital projects. These include projects that
could encompass a variety of modes (e.g., rail, bus, other fixed guideway); improvement types (e.g., equipment, facility); system evolutions (e.g., newly
developed, expanded, modernized); and grantee sizes, capabilities, and maturities (e.g., newly constituted or established with experienced staff).
The update process also provided an opportunity to review the structure and format of the Guidelines to improve its effectiveness. The resulting changes are
summarized in the following section.
Discussion has been expanded on the Planning Phase in Chapter 2, the Transit Capital Project Development Process, to include management
topics primarily addressed during that phase.
Chapter 3, General Project Management Principles, has been modified to address only those topics that apply to several project phases, which is
2 of 5 1/28/2011 10:07 PM
Federal Transit Administration - Planning & Environment - [printable version] http://www.fta.dot.gov/printer_friendly/planning_environment_1335.html
more consistent with the breakdowns suggested by the American Public Transportation Association (APTA) Construction Committee and the
structure of the NTI Course.
There are only three detailed, phase-oriented chapters: Design (Chapter 4), Construction (Chapter 5), and Testing & Start-Up (Chapter 6). The
Preliminary Engineering (PE) and Final Design Phases have been combined to avoid redundancy, but transitional requirements between the
phases are discussed within Chapter 2. The separate Revenue Service Phase Chapter has been eliminated; however, there is expanded
discussion of Revenue Service within Chapter 2.
Lessons learned/best practices and FTA guidelines and requirements document references have been incorporated (note the inclusion of text
boxes), and hyperlinks to the source documents have been created. The hyperlinks can be utilized in electronic versions of the Guidelines, but
simply appear as underlined text in printed versions.
An attempt has been made to address the needs of smaller projects that are not considered Major Capital Projects (MCPs). This is done primarily
in Chapters 2 and 3.
References regulatory requirements for the Project Management Plan (PMP). The actual PMP requirements are highlighted in the text.
Chapter 2 addresses transit capital project development with emphasis on FTA's funding process and grant requirements. For each development phase, the
major work program elements that influence effective project management are reviewed, noting significant milestones and decision points, and their inputs and
outputs. The development phases addressed include the following:
Planning
Preliminary Engineering
Final Design
Construction
Testing and Start-Up
Revenue Service
This chapter expands on the concept that the existing FTA requirements should be recognized as the basis for effective project management. For example,
FTA requirements during the planning and analysis phases and prior to capital grant funding commitment, are designed to provide assurances that issues of
project scope, cost estimation, environmental impacts, and local funding commitments have been properly resolved. These requirements are intended to
create a realistic project baseline for successfully managing the project, should it advance to subsequent phases.
Incentives are another tool FTA uses to encourage effective grantee project management. For an MCP, the Full Funding Grant Agreement (FFGA) concept
makes the grantee financially responsible for cost overruns. Thus, grantees have the incentive to establish a realistic project baseline and to maintain strong
3 of 5 1/28/2011 10:07 PM
Federal Transit Administration - Planning & Environment - [printable version] http://www.fta.dot.gov/printer_friendly/planning_environment_1335.html
A grantee should apply the management principles and guidance embodied in this document to their unique project environment through the development of a
PMP. Specific regulatory requirements for the PMP are covered in Chapter 2. A PMP, which is required by statute for MCPs, provides a blueprint for the
grantee's approach to managing in their unique project environment.
Chapter 3 outlines the general principles for managing the transit capital project development process applicable throughout all of the phases of project
development. In addition to the traditional project management requirements for managing scope, budget including financing, schedule, and quality, good
project management requires the application of some specialty management practices, such as procurement management, risk management, and
communications management. Because transit capital projects are publicly funded and often have significant urban development impacts, these projects have
many more legal and regulatory requirements than a privately developed project.
The general principles for managing transit capital projects are grouped into the following functional categories:
The project management principles are purposely presented in a general manner in Chapter 3. The implementing agencies will have the responsibility to apply
the general principles along with the specific guidance provided for the specific project phases. FTA and its PMO and Financial Management Oversight (FMO)
contractors monitor the project management process of grantees to assure compliance with FTA Requirements and that the management objectives (budget,
schedule, and quality) are being achieved. Thus, these Guidelines are intended to be firm in their definition of management principles and objectives, flexible in
their application of standard and alternative approaches and techniques, and dynamic in their ability to consider new approaches and techniques in the future.
Chapter 4 recommends specific management approaches for transit capital projects during the Design Phase.
Chapter 5 recommends specific management approaches for transit capital projects during the Construction Phase.
Chapter 6 recommends specific management approaches for transit capital projects during the Testing and Start-Up Phase.