1.0 OBJECTIVE OF THIS DSI :

a. To ensure that all manuals are updated by November 30, 2010 as per sub clause 4.6.1 of
PSM-PR-4
b. To ensure that intermediate Milestones, targets are set.
c. Adequate time is given for completion of chapters.

2.0 SCOPE & APPLICABILITY

This “Departmental Standing Instruction” is issued to the “Division Heads” and “Section Heads”
of the Operations Department and is applicable to the Operations Department only. Reference by
anyone else and usage in any other domain is not authorized.

3.0 RESPONSIBILITY

As mentioned in the standing instructions below.

4.0 DETAILS OF THE STANDING INSTRUCTION

A. For Process Units Block, Merox & ETP Block, DHDS Block, MS Block, P&U Block
and OM&S Block (TPH, ATP & LPG Units)

Sl. No. Activities Responsibility Date of


completion

1. Finalization of Section B : Table of Contents VSM, PSM, 08/07/2010


for each plant under respective block VRR, BRR, SB,
HRK, UN

2. Completion of Chapter – 2 (Introduction), VSM, PSM, 22/07/2010


Chapter-3 (Basis of Design) and Chapter – 4 VRR, BRR, SB,
(Feed and Product Characteristics) in soft form. HRK

3. Completion of Chapter – 5 (Brief Process VSM, PSM, 05/08/2010


Description & Process Chemistry), Chapter-6 VRR, BRR, SB,
(Detailed Description of Configuration and
HPCL VISAKH REFINERY Doc No. : DSI-O-2
OPERATIONS DEPARTMENT  Date : July 03, 2010.
Rev No. : 0
Date of First issue : July 03, 2010
Date of this Revision : July 03, 2010
  Page : Page 2 of 6

DEPARTMENTAL STANDING INSTRUCTION


TIME BOUND PLAN FOR PREPARING THE OPERATING MANUALS
FOR REFINERY PLANT FACILITIES
 
Sl. No. Activities Responsibility Date of
completion

Process) and Chapter – 7 (Description of HRK


Critical Control Schemes) in soft form.
4. Completion of Chapter – 8 (Description of VSM, PSM, 19/08/2010
Distributed Control System, DCS), Chapter-9 VRR, BRR, SB,
(Description of Advanced Process Controls) HRK
and Chapter – 10 (Pre-commissioning
Activities) in soft form.
5. Completion of Chapter – 11 (Preparatory VSM, PSM, 02/09/2010
Operations & Activities for Commissioning), VRR, BRR, SB,
Chapter-12 (Initial Start up Procedure, New HRK
Plant) and Chapter – 13 (Start up Procedure
after T&I / Long maintenance) in soft form.
6. Completion of Chapter – 14 (Operating Limits VSM, PSM, 16/09/2010
& Consequences of Deviations), Chapter-15 VRR, BRR, SB,
(Normal Operation of the Plant) and Chapter – HRK
16 (Major equipment description and Operating
Procedure) in soft form.
7. Completion of Chapter – 17 (Upset Conditions VSM, PSM, 30/09/2010
& Stabilization), Chapter-18 (Avoiding VRR, BRR, SB,
Deviations and Plant Upsets) and Chapter – 19 HRK
(Emergency Procedures and Shutdowns) in soft
form.
8. Completion of Chapter – 20 (Re-Startup after VSM, PSM, 07/10/2010
Emergency Shutdowns), Chapter- 21 (Normal VRR, BRR, SB,
Shutdown Procedure) and Chapter – 22 HRK
(Temporary Operations) in soft form.
9. Completion of Chapter – 23 (Process Safety VSM, PSM, 21/10/2010
Information), Chapter- 24 (Sampling VRR, BRR, SB,
requirement and Sampling Procedures) and HRK
Chapter – 25 (List of Plant Equipment) in soft
form.
10. Completion of Chapter – 26 (Plant Chemicals), VSM, PSM, 28/10/2010
Chapter- 27 (Occupational Safety & Health) VRR, BRR, SB,
and Chapter – 28 (Plant Drainage System HRK
Description) in soft form.
11. Completion of Chapter – 29 (Environmental VSM, PSM, 04/11/2010
Management), Chapter- 30 (Special or Unique VRR, BRR, SB,
Hazards) and Chapter – 31 (Safe Work
HPCL VISAKH REFINERY Doc No. : DSI-O-2
OPERATIONS DEPARTMENT  Date : July 03, 2010.
Rev No. : 0
Date of First issue : July 03, 2010
Date of this Revision : July 03, 2010
  Page : Page 3 of 6

DEPARTMENTAL STANDING INSTRUCTION


TIME BOUND PLAN FOR PREPARING THE OPERATING MANUALS
FOR REFINERY PLANT FACILITIES
 
Sl. No. Activities Responsibility Date of
completion

Practices) in soft form. HRK

12. Completion of Chapter – 32 (Standard UN 26/08/2010


Operating Procedures of Process equipment) in
soft form.
13. Completion of Chapter- 33 (Chemical/HC VSM, PSM, 11/11/2010
spillage Handling Procedure) and Chapter – 34 VRR, BRR, SB,
(Unit master blind list, Individual equipment HRK
blind list, List of vendor manuals, Start-up &
Shutdown checklists) in soft form.
14. Finalization of Administrative Requirements of VSM, PSM, 25/11/2010
the Manual like Section A: Foreword; Section VRR, BRR, SB,
C: Annual Certificate of Validity and HRK
Accuracy; Section D: Document control;
Section F: List of Abbreviations; Section G:
List of Copy Holders; Section H: Record of
Revisions to the Manual; Section I: List of
Standing Instructions
15. Updating the old manual VSM, PSM, 28/11/2010
VRR, BRR, SB,
HRK

16. In case of new printing

a) LPR generation for the printing VSM, PSM, 19/08/2010


VRR, BRR, SB,
HRK

b) Finalization of printer VSM, PSM, 21/10/2010


VRR, BRR, SB,
HRK

c) Giving the last soft copies in word file VSM, PSM, 23/11/2010
(soft copies to be given as and when VRR, BRR, SB,
chapters are completed) HRK

d) Collection of printed documents VSM, PSM, 30/11/2010


VRR, BRR, SB,
HPCL VISAKH REFINERY Doc No. : DSI-O-2
OPERATIONS DEPARTMENT  Date : July 03, 2010.
Rev No. : 0
Date of First issue : July 03, 2010
Date of this Revision : July 03, 2010
  Page : Page 4 of 6

DEPARTMENTAL STANDING INSTRUCTION


TIME BOUND PLAN FOR PREPARING THE OPERATING MANUALS
FOR REFINERY PLANT FACILITIES
 
Sl. No. Activities Responsibility Date of
completion

HRK

B. For Marine

Sl. No. Activities Responsibility Date of


completion

1. Finalization of Section B : Table of Contents HRK 08/07/2010


for each plant under respective block

2. Completion of Chapter - 2 (Introduction) and HRK 22/07/2010


Chapter – 3 (Facilities available in Oil Wharf)
and Chapter - 4 (Product Loading & Unloading
in Oil Wharf) in soft form.
3. Completion of Chapter - 5 (Introduction of HRK 05/08/2010
OSTT) and Chapter – 6 (Facilities available in
OSTT) and Chapter - 7 (Operation of
equipments in OSTT) in soft form.

4. Completion of Chapter - 8 (Unloading of tanker HRK 19/08/2010


at OSTT) and Chapter – 9 (Marine co-
ordination) and Chapter - 10 (Attachments -
Marine Documentations) in soft form.

5. Finalization of Administrative Requirements of HRK 02/09/2010


the Manual like Section A: Foreword; Section
C: Annual Certificate of Validity and
Accuracy; Section D: Document control;
Section F: List of Abbreviations; Section G:
List of Copy Holders; Section H: Record of
Revisions to the Manual; Section I: List of
Standing Instructions
6. Updating the old manual HRK 16/09/2010

7. In case of new printing


HPCL VISAKH REFINERY Doc No. : DSI-O-2
OPERATIONS DEPARTMENT  Date : July 03, 2010.
Rev No. : 0
Date of First issue : July 03, 2010
Date of this Revision : July 03, 2010
  Page : Page 5 of 6

DEPARTMENTAL STANDING INSTRUCTION


TIME BOUND PLAN FOR PREPARING THE OPERATING MANUALS
FOR REFINERY PLANT FACILITIES
 
Sl. No. Activities Responsibility Date of
completion

a) LPR generation for the printing VSM, PSM, 19/08/2010


VRR, BRR, SB,
HRK

b) Finalization of printer VSM, PSM, 21/10/2010


VRR, BRR, SB,
HRK

c) Giving the last soft copies in word file VSM, PSM, 23/10/2010
(soft copies to be given as and when VRR, BRR, SB,
chapters are completed) HRK

d) Collection of printed documents VSM, PSM, 30/10/2010


VRR, BRR, SB,
HRK

C. For Operation Planning

Sl. No. Activities Responsibility Date of


completion

1. Finalization of Section B : Table of Contents LVS 08/07/2010


for each plant under respective block

2. Completion of Chapter – 2 (Introduction), LVS 22/07/2010


Chapter-3 (Scope) and Chapter – 4 (Roles of
Operations Planner) in soft form.
3. Completion of Chapter – 5 (Guidelines of LVS 05/08/2010
Operation Planner), Chapter-6 (Modalities of
interaction by Operation Planner) and Chapter
~~~~~~~~
~~~~ ~ ~~~
~~~~~~~~~~~~ ~~~~ ~~~~
~~~~~
~~~ ~~~ ~~~~~~~
~~~~~~~~~~~ ~~~ ~~~ ~~~~~~~~~~~~~~~~~~~~~~
~~~~~~~~~~
~~~ ~~~ ~~~~~~~~~~~
~~~
~~~~ ~~~ ~~~~~~
~~~ ~~~~~~ ~~
~~~~~~~~~~~~~~~~~ ~~~~
~~~~~~~~~~~~~~~~~
~~~~
~~~ ~~~~~~~~~~

~~~~~~ ~~~~~~~~~~
~~~~~~~~~~~~
~~~~~~~~~~~~~
~~~~~~~~~~
~~~ ~~~~~~~~
~ ~~~~~~~~~~
~~~~~~~~~~
~~~~~~~~~
~~~~~~~~~~~~
~~~~~~~~~~
~~~~~~~~~~
~~~~~~~~~
~~~~~~~~~~~~~
~~~~~~~~~ ~ ~~~~~~~~
~~~~~~~~~~~~
~~~
~~~
~~~~~~~~~
~~~~~~~~~~~~~~~
~~~~~~~~~~
~~~~~~~~~~~
~~~~~~~
~~~~~~
~~~~~~~~~
~~ ~~
~ ~~~~~~~~ ~~~~~~~~~~~~~~~~
~~ ~~~
~~~~~~~~~~~~~~~
~~~~
~~~~~~~~~~~
~~~~~~~~~~
~~ ~~~~
~~ ~~~~~~~~~~~~
~~~~~~~
~~~~~~~~~~~
~~~~~~~~~
~~~~
~~ ~~~~~
~~~~~~~~~~~
~~~~~~~~~~~
~~~~~~~~~~~~~~~~
~~~~~~~~~~~~
~~~~~~~~
~~~~~~~~~~~~~~~~~~
~~~~~
~~~~~~~
~~~~~~~~~
~~~~~~~~ ~~~~~~~
~~~~ ~~~~~~~~~
~~ ~~~~~~~~ ~~~~~~~~
~~~~~~~~~~~~
~~~~~~~ ~~~~~~~~~~

~~ ~
~~~~
~~~~ ~~~~~~