Beruflich Dokumente
Kultur Dokumente
Table of Contents
1. INTRODUCTION ................................................................................................. 1
1.1. Background..................................................................................................... 1
2. METHODOLOGY ................................................................................................ 6
3.3. Hydrology..................................................................................................... 12
3.3.4. Calculation of Linear Waterway, Scour Depth and High Flood Level (HFL)
........................................................................................................................ 19
5.3.2. Analysis Of Live Load For Both Intermediate And End Cross Girder ... 106
Page | ii
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | iii
Design of T Beam Bridge over Baskot Khola
1. INTRODUCTION
1.1. Background
A bridge is a structure erected as a linkage in physical impediments such as body of water
so as to permit smooth and safe passage over the said obstacles.
It is divided into an upper portion (the superstructure), which consists of the floor system,
the slab, kerb, parapet, and a lower portion (the substructure) that comprises the foundation,
abutment and piers. The former provides horizontal spans (deck and girders) and conveys
the traffic load while the latter functions as a support of the super structure of the bridge.
In this project we were assigned to design a bridge over Baskot Khola which provides a link
between AandhiKhola village left of the river with AandhiKhola Village right to the river
in Syangja district. This bridge is along Karkineta Road in Syangja district. . As it is a local
road, so a single lane bridge shall suffice. But as per the provisions in Nepal Road Standards
(a minimum of 6 m carriageway for bridges longer than 50 m), the bridge will be designed
as a two-lane bridge. We were supposed to design the most economic bridge for this section
based on the data provided by LRBSU. This report is also prepared as a part of project work
for the fulfilment of the Project-I as per the syllabus of Bachelor of Civil Engineering 4 th
Year Ist and IInd part.
1|Page
Design of RCC T-beam bridge over Baskot Khola, Syangja
Preparation of detail drawing of bridge superstructures with its all components, abutments,
pier, bearing and footing required for the construction of selected bridge type.
Page | 2
Design of RCC T-beam bridge over Baskot Khola, Syangja
It serves the ares of Aandhikhola 2,3,4,5,6 and some part of Parbat district. People from Zone of Influence
will be directly accessed to services and facilities as it connects Aandhikhola Village municipality and
Karkineta to Siddhartha Highway.
Page | 4
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 5
Design of RCC T-beam bridge over Baskot Khola, Syangja
2. METHODOLOGY
2.1.3. Hydrology
The maximum discharge which a bridge across a natural stream is to be designed to pass can be estimated
by the following methods:
By using one of the empirical formula applicable to the region
By using the rational method involving the rainfall and other characteristics.
By the area velocity method, using the hydraulic characteristics of the stream such as cross- sectional area,
and the slope of the stream
From any available records of the flood discharges observed at the or at any other site at the vicinity.
It is desirable to estimate the flood discharge by all or at least two of the above methods. These methods are
briefly discussed here.
Page | 6
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 7
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 8
Design of RCC T-beam bridge over Baskot Khola, Syangja
For the purpose of design, we adopted the required data provided by LRBSU.
Page | 9
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 10
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 11
Design of RCC T-beam bridge over Baskot Khola, Syangja
3.3. Hydrology
Hydrological Data of catchment:
Page | 12
Design of RCC T-beam bridge over Baskot Khola, Syangja
350
250
200
Series1
150 Log. (Series1)
100
50
0
1 10 100
Page | 13
Design of RCC T-beam bridge over Baskot Khola, Syangja
From Autocad:
82.55∗0.1+(0.87+2.27+2.44+1.22)∗0.6+(4.36+2.62)∗0.55+3.66∗.9
Runoff-coefficient=
100
=0.1974
Page | 15
Design of RCC T-beam bridge over Baskot Khola, Syangja
0.56∗0.1974∗0.756
= 0.212+1
=0.0685
From extreme rainfall data provided by LRBP,
I0= 14.712mm/hr
Finally, Design rainfall by rational method (Q)=AI ol
=1.8*14.712*0.0685
=1.814m3/s
2. Area velocity method:
Wetted Area (A) =18m2
Wetted perimeter (P) =13.6m
So, R=A/P
=18/13.6
=1.323m
Using L-profile of the stream,
s=1/400
n = rugosity coefficient =0.055
Thus the discharge is obtained by using Area velocity method as:
Q= (1/n) AR2/3s1/2
= (1/0.055)*18*1.3232/3*(1/400)0.5
=19.72m3/s
Calculations by Empirical Methods:
i) WECS formula(1940):
Given for ungauged sections of Nepal
From Google earth
A3000=1.8km2
Q100=14.63(A3000+1)0.7342
=14.63(1.8+1)0.7342
=31.156m3/s
=20.7(1.8)0.72
=31.6 m3/s
iii) Ryves Formula (1884):
C= 10.1 is used for limited areas near hills which suits our purpose
Area (A)= 1.8 sq.km
Q=CM2/3
=10.1*1.82/3
=15.931m3/sec
iv) Dicken's Formula(1865):
Here,A=1.8 sq.km.
Taking value of CD=11.37 from Northern regions to India:
The discharge is calculated from Dicken's Formula (1865) as:
Q=11.37*1.83/4=17.699 m3/sec
v) Modified Dicken's Formula:
Q=CA3/4
Where C=2.342log(0.6T)log(1185/P)+4
100(𝐴𝑠+6)
P= 𝐴
C=2.342 log(0.6*100)log(1185/333.33)+4
=6.243
Q=6.243*1.80.75
=9.78m3/sec
Page | 17
Design of RCC T-beam bridge over Baskot Khola, Syangja
All the values of discharges with respect to various formulas are tabulated below :
Table : Discharges obtained from different methods
S.N. Methods Discharge
value(m3/s)
1. Rational Method 1.814
2. Area Velocity Method 19.72
3. WECS Formula 31.156
4. Sharma and Adhikari 31.6
5. Ryves Formula 15.931
6. Dicken’s Formula 17.699
7. Modified Dicken’s formula 9.78
There seems to have large variation in the discharge calculated from various methods. This may be due to
applicability of corresponding empirical formula in particular region .so we cannot fully depends on them for
design discharge calculation. Inglis method, Nawab Jang Bahadur method, Maeyes method can be eliminated
.As per our supervisor area velocity method cannot be neglected for discharge calculation.
Hence we take the design discharge as 20m3/s.
Page | 18
Design of RCC T-beam bridge over Baskot Khola, Syangja
3.3.4. Calculation of Linear Waterway, Scour Depth and High Flood Level (HFL)
a) Calculation of linear waterway:
When the water course to be crossed is an artificial channel for irrigation or navigation, or when the banks
are well defined for natural streams, the linear waterway should be full width of the channel or the stream.
For large alluvial stream with undefined banks, the required effective linear waterway may be determined
using Lacey’s formula:
P = C√Q
where, P= the effective linear waterway in meters
Q= the designed maximum discharge in m3/s
C= a constant usually taken as 4.8 for regime channel, but may vary from 4.5 to 6.3
according to the local conditions
The effective linear waterway is the total width of the waterway of the bridge minus the mean submerged
width of the piers and their foundation down to the mean scour level. It is not desirable to reduce the linear
waterway below that for regime condition. If a reduction is affected, special attention should be given to the
afflux and velocity of water under the bridge. With reduced waterway, velocity would increase and greater
scour depths would be involved, requiring deeper foundations. Thus any possible saving from a smaller linear
waterway will be offset by the extra expenditure on deeper foundations and protective works. In view of the
deficiencies of the assumptions made in the computations for design discharge and for the effective waterway
by Lacey’s formula, it is often prudent to adopt the full natural width for the linear waterway, taking care not
to succumb to the trap of overconfidence in apparently precise methods of calculation.
Taking C=4.75, the linear waterway is given by:
P = 4.75√20
= 21.243 m
b) Calculation of scour depth:
Scour may be defined as the removal of material from the bed and banks of streams during the passage of
flood discharge, when the velocity of the stream exceeds the limiting velocity that can be withstood by the
particles of the bed material. If the bridge and its approaches do not constrict the natural flow, the scour will
be small. On the contrary, when the designer attempts to reduce the waterway, severe scour usually results
during the extraordinary flood conditions.
The scour is aggravated at the nose of the piers and bends. The maximum depth of scour should be measured
with reference to existing structures near the proposed bridge site, if this is possible. Such soundings are best
done during or immediately after the flood. Due allowance should be made in the observed values for
additional scour that may occur due to design discharge being greater than the flood discharge for which the
scour was observed, and also due to increased velocity due to obstruction of flow caused by the construction
of bridge.When the above practical method is not possible, the mean depth of scour may be computed by the
given equation for natural streams in alluvial beds:
2
Db
2
dsm = 1.35
Ksf
where, dsm = mean depth of scour below HFL in meters
Page | 19
Design of RCC T-beam bridge over Baskot Khola, Syangja
Db= discharge in m3/s per meter width, obtained as the toal design discharge
divided by the effective linear waterway
Ksf = silt factor for a representative sample of the bed material, as in the table below taken as 1.76 times the
square root of the particle size in mm (weighted mean diameter of the particle determined as indicated in
Appendix 2 of IRC:(5-1998).
Silt factor:
S.N Type of bed material Size of particles, mm Silt factor
1 Very fine silt 0.08 0.50
2 Fine silt 1.12 0.60
3 Moderately fine silt 0.16 0.70
4 Medium silt 0.23 0.85
5 Standard silt 0.32 1.00
6 Medium sand 0.50 1.25
7 Coarse sand 0.73 1.50
8 Heavy sand 1.29 2.00
In order to provide an adequate margin of safety, the design discharge for the above calculation is increased
by 30%, 25 to 20%, 20 to 10% and 10% for catchment areas of below 500 sq. km, between 500 and 5000 sq.
km, between 5000 to 25000 sq. km and over 25000 sq. km, respectively. When the effective linear waterway
L is less than the regime width W, the value of d sm computed from the above mentioned formula is to be
increased by multiplying the same by the factor (W/L) 0.67.
The maximum depth of scour D below the HFL is to be taken as below:
dsmax = 2.0dsm for pier
= 1.27dsmwith approach retained or lowest bed level whichever is deeper for abutment
= 2.0dsm for scour all round for abutment
dsmax = 2.0dsm in the right angled bend
= 1.75 dsm at the severe bend
= 1.5 dsm at moderate bend
= 1.27dsm in a straight reach
The minimum depth of foundations below HFL is kept at 1.33 D for erodible strata. If the river is of a flashy
nature and the bed does not submit readily to the scouring effects of the floods, the maximum depth of scour
should be assessed by observations and not by the above calculations.
When a bridge is located close to the mouth of a river joining the sea, the possibility exists for the situation
of the high tide opposing the flood discharge, resulting in heading up of the water level in the river. At the
end of the high tide, the flood discharge may be relatively sudden, which may cause scour in excess of the
values computed by the above equation to calculate the average scour depth. Considerable engineering
judgements is required in assessing the required depth of foundation in such cases.
Page | 20
Design of RCC T-beam bridge over Baskot Khola, Syangja
where, x=afflux
v=velocity of normal flow in the stream
g=acceleration due to gravity
L= width of stream at HFL
L1= linear waterway under the bridge
c = coefficient of discharge through the bridge, taken as 0.7 for sharp entry and 0.9 for bell mouthed
entry
The afflux should be kept minimum and limited to 1 to 1.5 m. afflux causes increase in velocity on the
downstream side, leading to greater scour and requiring deeper foundations. The road formation level and the
top level of guide bunds are dependent on the maximum water level on the upstream side including afflux.
The increased velocity under the bridge should be kept below the allowable safe velocity for the bed material.
Typical values for the safe velocities are given below:
S.N. Nature of soil Safe velocities
1 Loose clay or fine sand Up to 0.5 m/s
2 Coarse sand 0.5 to 1.0 m/s
3 Fine gravel, sandy or stiff clay 1.0 to 1.5 m/s
4 Coarse gravel, rocky soil 1.5 to 2.5 m/s
5 Boulders, rock 2.5 to 5.0 m/s
Page | 21
Design of RCC T-beam bridge over Baskot Khola, Syangja
The normal flow velocity is determined by using Manning’s equation taking Manning’s roughness coefficient
as 0.06 and bed slope as 1/336 similar to previous calculation. But the wetted area and wetted perimeter are
calculated from Autocad drawing of actual bridge axis cross section at BaskotKhola provided by LRBSU.
v = (1/n)×R2/3S1/2
n=rugosity coefficient =0.06
S=slope of the stream =1/336
R=Hydraulic mean depth in meters
𝑊𝑒𝑡𝑡𝑒𝑑 𝐴𝑟𝑒𝑎
= 𝑊𝑒𝑡𝑡𝑒𝑑 𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟
Here, Wetted Area =18 m2 and Wetted Perimeter =13.6 m
Thus, R=18 /13.6 = 1.323
Hence, v = (1/n)×R2/3S1/2
= (1/0.06)×(1.323)2/3×(1/336)1/2
= 1.096m/sec(safe value is within 1 to 1.5 m/sec)
Also, from Autocad drawing, L=21m
L1=15m and
c=0.9 for bell mouthed entry
𝑣2 𝐿2
Finally, x =2𝑔 (𝑐 2𝐿2 − 1)
1
1.0962 212
= 2×9.81 (0.92 ×152 − 1)
= 0.087 m=87mm<300mm(O.K.)
Page | 22
Design of RCC T-beam bridge over Baskot Khola, Syangja
The calculation for Section 1 and Section 3 are done similar to calculation of
section 2 as shown above
Feasibility comparison of 3 different sections:
S.N. Criteria Section 1 Section 2 Section 3
1 Perimeter 15.83m 13.6m 13m
2 X sectional area 24.82m^2 18m^2 18m^2
3 Hydraulic depth 2.28m 1.33m 1.38m
4 Scour depth 2.08m 2.049m 1.82m
5 Approach road length 31.5m 50m 62.5
nearly
6 Bank Stability nearly stable stable stable
7 Landslide vulnerability 2% 1% 5%
Foundation depth(below
8 HFL) 2.5m 2.725m 3.3m
9 Height of Abutment 7.3m 6m 5.2m
Page | 23
Design of RCC T-beam bridge over Baskot Khola, Syangja
Bridge economy is the controlling factor for selection of bridge deck type. For bridge of span ranging from
8 to 25 m, RC T-Girder bridge is economically and technically feasible. In our case span of bridge is 15m
so RC T –Girder bridge is adopted.
The geometry and size of slab, longitudinal girder, cross girder, carriageway footpath/safety kerb, wearing
course, railing are assigned based on codal provision and handbooks.
Width of carriageway
The width of carriageway shall not be less than 4.25 m for a single lane bridge.
The width shall be 7.5 m for two lane bridge.
Based on daily traffic data and carriageway width of existing road two lane bridge is selected.
Width of carriageway=7.5 m
Width and height of safety kerb
Width of kerb should be more than 0.75 m
Height of kerb should be more than 0.225 m
Width of safety kerb = 0.95 m including the width of railing post of .15 m width
.075
=3.75 ∗ 100% =2%
Page | 24
Design of RCC T-beam bridge over Baskot Khola, Syangja
Railing post
Minimum height of 1.1 m less one half the horizontal width of the top rail above safety kerb surface.
𝑠𝑝𝑎𝑛
Spacing of post=𝑛𝑜 𝑜𝑓 𝑝𝑜𝑠𝑡
15−.15
= 4
=3.713 m
1100*150*150 mm with 3 heavy steel pipes of 48.3 mm dia. @4.37 Kg per running meter.
Drainage spout
Standard drainage spout of 100mm dia. is adopted @3 m c/c spacing.
Size of RC slab
Minimum thickness of slab =200 mm for restrained slab
Minimum thickness =150 mm at tip for cantilever slab
Restrained slab of depth 250 mm and cantilever slab with depth 250 mm at girder face linearly varying to 150
mm at the tip is provided.
Longitudinal girder
Overall Depth =span/10 – span/15 by deflection criteria
Width of web =minimum 250mm
Spacing of girder=2-3 m
Number of main girder shall not be less than three, except for single lane bridge
𝑠𝑝𝑎𝑛
Depth of main girder = 12.5
15
=12.5
=1.2 m
Number of girder = 3
Page | 25
Design of RCC T-beam bridge over Baskot Khola, Syangja
=3.675 m
=900 mm
Page | 26
Design of RCC T-beam bridge over Baskot Khola, Syangja
=87.5 mm
Page | 27
Design of RCC T-beam bridge over Baskot Khola, Syangja
Partial factor of safety for verification of structural strength for load are used as per IRC 6:2014.
Page | 28
Design of RCC T-beam bridge over Baskot Khola, Syangja
The heaviest wheel of 114 KN axle of IRC Class A load is placed with clearance 0.15 m from the face of
kerb. Live load per unit width is found by dividing live load by effective width of slab b eff.
beff=1.2a+b1<l/3
= 225 mm
= 425 mm
1.550
beff = 1.2*0.225+0.425 < l/3 = 3
=0.596 m
=224 KN
=50.4KN-m
=18+50.4
=68.4KN-m
Design transverse BM in direction of traffic =0.2 BM due to dead load +0.3 BM due to live load.
=0.2*18+0.3*50.4
=18.72 KN-m
Design of reinforcements
Provide an overall depth of 400 mm and using 10 mm diameter bars and clear cover of 40mm
=355 mm
𝑀𝑢 68.4∗10^6
𝑑bal=√𝑄∗𝑏 = √4.15∗1000
=128.4 mm
=4.15
Since, dbal < dprov , section of slab is designed as Singly Reinforced Under-Reinforced Section (SRURS).
Page | 30
Design of RCC T-beam bridge over Baskot Khola, Syangja
Primary Reinforcement
𝑀𝑢 = 68.4∗10^6
=0.55
𝑏𝑑^2 1000∗355^2
0.156∗1000∗355
Hence, Ast= =555 mm2
100
1000∗𝜋∗102 /4
Spacing of bar = 555
=142 mm
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 605 mm2
Ast = 𝟏𝟑𝟎
Transverse reinforcement
Effective depth d=355-10/2-10/2=345
𝑀𝑢 = 18.48∗10^6
=0.16
𝑏𝑑^2 1000∗345^2
0.12∗1000∗355
Hence, Ast= =426 mm2
100
1000∗𝜋∗102 /4
Spacing of bar = 426
Page | 31
Design of RCC T-beam bridge over Baskot Khola, Syangja
=185 mm
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 462mm2
Ast = 𝟏𝟕𝟎
Temperature reinforcement
As per clause 305.17.4 0f IRC 21 for cantilever slab, minimum reinforcement of 4 nos of 16 mm dia HYSD
bars shall be provided parallel to the free edge at 150 mm spacing at the tip divided equally between the
top and bottom surface.
Pt min=0.12%
0.12∗1000∗275
Areq= =330 mm2
100
1000∗𝜋∗102 /4
Spacing of bar = 330
=238 mm
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 342mm2
Ast = 𝟐𝟑𝟎
Page | 32
Design of RCC T-beam bridge over Baskot Khola, Syangja
From preliminary sizing longitudinal beam are provided at c/c spacing 3.0 m and with rib width 300 mm.
5 cross girders are provided with c/c spacing of 3.675 m and rib width 300 mm.
The slab is supported on four sides by longitudinal and cross girders. The effective span will be taken as the
clear span of the slabs since these are the continuous slabs.
For bridge deck supported on T-beams and cross girders, deck slab is two way slab supported on four edges.
The moments in two orthogonal direction are computed by using design curve developed by M. Piegeaud,
which is applicable for slab supported on four sides subjected to symmetrically placed load at its center.
For eccentric loading Pigeaud’s design curve can’t be used. For such, we use an approximate method to
calculate moments. Load is assumed to occupy area placed symmetrically on the panel with intensity as equal
of actual loading. We deduct the moment for loaded area beyond actual loaded area.
Moment due to dead load
Dead weight of slab = 0.25x25 *1.35
=8.44 KN/m2
=3.37 KN/m2
=107.62 KN
Page | 33
Design of RCC T-beam bridge over Baskot Khola, Syangja
= 5.17 KNm
=3.62 KNm
For maximum bending moment to be occurred, the load dispersion is taken to be occurring through wearing
coat only. The load is disperses at 450 through the wearing coat as per Annex-B of IRC 112:2011.
𝑠ℎ𝑜𝑟𝑡 𝑠𝑝𝑎𝑛 𝐵 2.7
K = 𝑙𝑜𝑛𝑔 𝑠𝑝𝑎𝑛 =𝐿 = 3.375 = 0.8
Impact allowance = 25 %
V/L = 3.375/3.375 = 1
Page | 34
Design of RCC T-beam bridge over Baskot Khola, Syangja
= 469.37*(8.2+4.4*0.15)*10-2
=41.59 KN-m
= 469.37*(4.4+8.2*0.15)*10-2
= 26.43 KN-m
possibility all four loads of first axle is place symmetrically with all four wheels of second axle following it
as shown in figure . A third possibility should also be tried in which four wheel loads of the first axle are so
placed that the middle 62.5KN wheel load is placed centrally, with the four wheel loads of second axle
following it as shown in figure .
Case 1: All four loads of 37.5 KN and four loads 62.5 KN are placed symmetrical to both the axis as
shown in figure.
W1=37.5KN
W2=62.5KN
U1=0.3+2*0.0875=0.475
V1=0.15+2*0.0875=0.325
Page | 36
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 37
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑈 2.676 𝑉 0.876
= =1 =3.375= 0.26
𝐵 2.7 𝐿
Page | 38
Design of RCC T-beam bridge over Baskot Khola, Syangja
X = 0.263 m Y= 0.438 m
Page | 39
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 40
Design of RCC T-beam bridge over Baskot Khola, Syangja
W1=37.5KN
W2=62.5KN
Page | 41
Design of RCC T-beam bridge over Baskot Khola, Syangja
X = 0.263 m
Page | 42
Design of RCC T-beam bridge over Baskot Khola, Syangja
m1=13.5*10-2 m2=13.0*10-2
1.476∗0.325
W=62.5*0.475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=291.32 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=291.32*(13.5+0.15*13.0) *10-2
=45.0 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=291.32*(13.0+0.15*13.5)*10-2
=43.77 KN-m
X = 0.863 m Y= 1.038 m
Page | 43
Design of RCC T-beam bridge over Baskot Khola, Syangja
2.676∗2.076
W=37.5*0.475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=2024.227 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=2024.227*(6.8+0.15*3.8) *10-2
=149.19 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=2024.227*(3.8+0.15*6.8)*10-2
=97.57 KN-m
4) U=2X = 2*0.863 = 1.726 m
V=2(v1+Y) = 2(0.325+1.038) = 2.726 m
𝑈 1.726 𝑉 2.726
𝐵
= 2.7
=0.64 𝐿
=3.375= 0.808
Referring to Pigeaud’s curve for k=0.8
m1=8.1*10-2 m2=3.4*10-2
1.726∗2.726
W=37.5*0.6475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=1714.401 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=1714.401*(8.1+0.15*3.4) *10-2
=147.61 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=1714.401*(3.4+0.15*8.1.0)*10-2
=79.12 KN-m
Final
BM in shorter span MB =0.5*(165.13+160.92-149.19-147.61) = 14.62 KN-m
BM in longer span ML =0.5*(96.23+94.34-97.57-79.12) = 6.94 KN-m
Page | 45
Design of RCC T-beam bridge over Baskot Khola, Syangja
m1=8.5*10-2 m2=3.9*10-2
1.476∗2.726
W=62.5*0.6475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=2443.468 KN
BM in shorter span MB = W*(m1+μm2)*10-2
=2443.468*(8.5+0.15*3.9) *10-2
=221.99 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=2443.468*(3.9+0.15*8.5) *10-2
=126.45 KN-m
Page | 46
Design of RCC T-beam bridge over Baskot Khola, Syangja
=185.44 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=1860.836*(5.1+0.15*9.2)*10-2
=120.59 KN-m
4. U=2X = 2*0.263 = 0.526 m
V=2(v1+Y) = 2(0.325+1.038) = 2.726 m
𝑈 0.526 𝑉 2.726
= =0.195 =3.375= 0.808
𝐵 2.7 𝐿
Page | 47
Design of RCC T-beam bridge over Baskot Khola, Syangja
Case3: four wheel loads of the first axle are so placed that the middle 62.5KN wheel load is placed centrally,
with the four wheel loads of second axle following it as shown in figure
W1=37.5KN W4=37.5KN
W2=62.5KN W5=62.5KN
W3=62.5KN W6=62.5KN
Page | 48
Design of RCC T-beam bridge over Baskot Khola, Syangja
1.676∗0.325
W=37.5*0.475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=198.474 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=198.474*(11.8+0.15*12.0) *10-2
=27.0 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=198.474*(12.0+0.15*11.8)*10-2
=27.33 KN-m
Page | 49
Design of RCC T-beam bridge over Baskot Khola, Syangja
X=0.763
Page | 50
Design of RCC T-beam bridge over Baskot Khola, Syangja
m1=13.0*10-2 m2=12.6*10-2
1.526∗0.325
W=62.5*0.475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=301.185 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=301.185*(13.0+0.15*12.6) *10-2
=44.85 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=301.185*(12.6+0.15*13.0)* 10-2
=43.83 KN-m
Final
BM in shorter span MB =0.5*(49.19-44.85)=2.17 KN-m
BM in longer span ML = 0.5*(50.85-43.83) =3.51 KN-m
X = 0.363 m Y= 1.038 m
Page | 51
Design of RCC T-beam bridge over Baskot Khola, Syangja
Y=1.038
i. U= u1= 0.475 m
V =2(v1+Y) = 2.726 m
𝑈 0.475 𝑉 2.726
= =0.176 =3.375= 0808
𝐵 2.7 𝐿
ii. U=0.475 m
V = 2Y=2.076 m
𝑈 0.475 𝑉 02.076
= =0.176 = 3.375 = 0.616
𝐵 2.7 𝐿
Page | 53
Design of RCC T-beam bridge over Baskot Khola, Syangja
X = 0.763 m Y= 1.038 m
Page | 54
Design of RCC T-beam bridge over Baskot Khola, Syangja
m1=10.1*10-2 m2=5.1*10-2
1.526∗2.076
W=62.5*0.475∗0.325 ∗ 1.5 ∗ 1.25 ∗ 0.8=1923.873 KN
BM in shorter span MB = W*(m1+μm2)* 10-2
=1923.873*(10.1+0.15*5.1) *10-2
= 209.03KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=1923.873*(5.1+0.15*10.1) *10-2
=127.27 KN-m
Page | 55
Design of RCC T-beam bridge over Baskot Khola, Syangja
=238.86 KN-m
BM in longer span ML = W*(m2 +μm1)* 10-2
=2526.241*(3.7+0.15*8.9.0)*10-2
=127.2 KN-m
Final
BM in shorter span MB =0.25(269.1+209.03-233.19-238.86) =1.52 KN-m
BM in longer span ML =0.25*(164.58+127.27-150.93-127.2) =3.43 KN-m
W1=57KN
Page | 56
Design of RCC T-beam bridge over Baskot Khola, Syangja
U1=0.5+2*0.0875=0.675 m
V1=0.25+2*0.0875=0.425 m
4.5
Impact factor fraction =6+2.7 = 0.515
We adopt impact factor of 1.5
U = 0.675 m
V = 0.475 = 0.475 m
𝑈 0.675 𝑉 0.475
= =0.25 =3.375= 0.126
𝐵 2.7 𝐿
Y=0.988
𝑈 0.675 𝑉 2.826
= =0.25 =3.375= 0.838
𝐵 2.7 𝐿
iv. U=0.675 m
V = 2Y=1.976 m
𝑈 0.675 𝑉 01.976
= =0.25 = 3.375 = 0.586
𝐵 2.7 𝐿
Page | 58
Design of RCC T-beam bridge over Baskot Khola, Syangja
=11.81*2.7/3+0.5*0.3*0.15*0.25*25*3.375*1.35
=11.27 KN
SF is calculated by using effective width method as Pigeaud’s method is not applicable. Shear Force will be
maximum when dispersed edge of the load touches the face of the support.
𝐵 3.375
= = 1.25
𝐿 2.7
Class A loading
Page | 59
Design of RCC T-beam bridge over Baskot Khola, Syangja
FOR WHEEL I
500+2(87.5+250)
a= = 0.5875 𝑚
2
b1=W+2h=.25+2*0.0875=4.25 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.5875
=2.38*0.5875*(1- ) + 0.425
2.7
=1.519 m
Beffmod=0.3+0.25/2+1.2+beff/2=2.385 m
FOR WHEEL II
b1=W+2h=.25+2*0.0875=4.25 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
Page | 60
Design of RCC T-beam bridge over Baskot Khola, Syangja
0.3125
=2.38*0.3125*(1- ) + 0.425
2.7
=1.083 m
Since there is no over lapping, effective width of both wheel and their load intensity is same.
57∗1.5∗1.5
Load due to wheel I = = 118.43𝑘𝑁
1.083
107.55∗0.5875+118.43∗0.3125
Ra= = 97.9 𝑘𝑁
2.7
107.55∗0.5875+118.43∗2.388
Rb= = 128.2 𝑘𝑁
2.7
So there can be two possibilities for placing the loads for Shear Force computation. In first possibility, left
most wheel is placed such that it spreads up to bottom reaches the face of the rib. In second possibility, third
wheel from left is placed as near to the face of right hand support as possible as.
Case 1: Left most wheel is placed such that its spread up to bottom reaches the face of the rib.
Page | 61
Design of RCC T-beam bridge over Baskot Khola, Syangja
FOR WHEEL I
300+2(87.5+250)
a= = 0.488 𝑚
2
b1=W+2h=.15+2*0.0875=0.325 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.488
=2.38*0.488*(1- ) + 0.325
2.7
=1.277 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.214 m
FOR WHEEL 2
b1=W+2h=.15+2*0.0875=0.325 m
Page | 62
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
1.088
=2.38*1.088*(1- ) + 0.325
2.7
=1.871 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.511 m
FOR WHEEL 3
b1=W+2h=0.15+2*0.0875=0.325 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.612
=2.38*0.612*(1- ) + 0.325
2.7
=1.451 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.3 m
63.51∗2.212+93.34∗1.612+101.9∗0.612
Ra= = 130.9 𝑘𝑁
2.7
63.51∗0.488+93.34∗1.088+101.9∗2.088
Rb= = 127.9 𝑘𝑁
2.7
Page | 63
Design of RCC T-beam bridge over Baskot Khola, Syangja
Case 2: Third wheel from left is placed as near to the face of right hand support as possible.
FOR WHEEL I
300+2(87.5+250)
a= = 0.488 𝑚
2
b1=W+2h=.15+2*0.0875=0.325 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.488
=2.38*0.488*(1- ) + 0.325
2.7
=1.277 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.214 m
Page | 64
Design of RCC T-beam bridge over Baskot Khola, Syangja
FOR WHEEL 2
b1=W+2h=.15+2*0.0875=0.325 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
1.212
=2.38*1.212*(1- ) + 0.325
2.7
=1.915 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.532 m
FOR WHEEL 3
b1=W+2h=0.15+2*0.0875=0.325 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.612
=2.38*0.612*(1- ) + 0.325
2.7
=1.451 m
Beffmod=0.3+0.15/2+1.2+beff/2=2.3 m
Page | 65
Design of RCC T-beam bridge over Baskot Khola, Syangja
61.2∗2.088+92.6∗1.488+105.9∗0.488
Ra= = 117.5 𝑘𝑁
2.7
61.2∗0.612+92.6∗1.212+105.9∗2.212
Rb= = 142.2 𝑘𝑁
2.7
Page | 66
Design of RCC T-beam bridge over Baskot Khola, Syangja
b1=W+2h=3.6+2*0.0875=3.775 m
𝑎
Beff = ∝*a*(1-𝑙𝑜)+b1
0.612
=2.38*0.763*(1- ) + 3.775
2.7
Page | 67
Design of RCC T-beam bridge over Baskot Khola, Syangja
As the width is limited to 3.375 m we take size of panel 3.375 m as an effective width.
Intensity of load is modified as the slab do not accommodate whole track load on it.
350∗3.375
Modified intensity of load = = 328.1 𝑘𝑁
3.6
328.1∗1.25∗1.5
Load = = 182.3 𝑘𝑁
3.375
182.3∗1.937
Ra= = 130.8 𝑘𝑁
2.7
182.3∗0.763
Rb= = 51.52 𝑘𝑁
2.7
The calculated bending moments and shear force for restrained slab at different loading conditioned are
summarized as follows.
Transverse Longitudinal
direction direction
Page | 68
Design of RCC T-beam bridge over Baskot Khola, Syangja
Design of reinforcements
Provide an overall depth of 400 mm and using 16 mm diameter bars and clear cover of 40 mm
=205 mm
𝑀𝑢 53.14∗10^6
𝑑bal=√𝑄∗𝑏 = √ 4.15∗1000
=113.16 mm
=4.15
Since, dbal < dprov , section of slab is designed as Singly Reinforced Under-Reinforced Section (SRURS).
Primary Reinforcement
𝑀𝑢 = 53.14∗10^6
=1.27
𝑏𝑑^2 1000∗205^2
0.37∗1000∗205
Hence, Ast= =758.5 mm2
100
1000∗𝜋∗102 /4
Spacing of bar = 758.5
=103.55 mm
Page | 69
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 786 mm2
Ast = 𝟏𝟎𝟎
Transverse reinforcement
0.31∗1000∗195
Hence, Ast= =604.5 mm2
100
1000∗𝜋∗102 /4
Spacing of bar = 604.5
=129.92mm
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 655 mm2
Ast = 𝟏𝟕𝟎
Temperature reinforcement
Since there is no negative moments minimum reinforcement is provided in tension part of slab.
1000∗𝜋∗102 /4
Spacing of bar = = 320 𝑚𝑚
246
Page | 70
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝟏𝟎𝟎𝟎∗𝝅∗𝟏𝟎𝟐 /𝟒
prov = 262 mm2
Ast = 𝟑𝟎𝟎
depth (d)=250+150-40-10/2=355 mm
𝑉𝑢 125.1∗1000
Τv =𝑏𝑑 = = 0.35𝑁/𝑚𝑚^2
1000∗355
Page | 71
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 72
Design of RCC T-beam bridge over Baskot Khola, Syangja
∴Design uniform dead load on each of the end girders =49.065 +12.675 = 61.74 KN/m
∴Design uniform dead load on the inner girder =35.418+12.675 = 48.1 KN/m
15000
R=492.66KN R=492.66KN
Fig:
dead load on end main girder
Dead load shear at 3.825m from extreme end at just left position is,
(Vdead)3.8525=492.66-7.746-61.74*3.825 = 248.758 KN
Dead load shear at 7.5m from extreme end at just left position is,
(Vdead)7.5=492.66-7.746-14.58-61.74*7.5 = 7.284 KN
Page | 74
Design of RCC T-beam bridge over Baskot Khola, Syangja
15000
R=390.366 KN R=390.366 KN
Fig: dead
load on end main girder
Reaction on middle girder=390.366KN
Maximum dead load bending moment at center of span is,
(Mmax)dead load = 390.366*7.5-7.746*7.35-14.58*3.675-48.1*7.52 /2 = 1464.42KNm
Dead load shear at 3.825m from extreme end at just left position is,
(Vdead)3.8525=390.366-7.746-48.1*3.825 = 198.64 KN
Dead load shear at 7.5m from extreme end at just left position is,
(Vdead)7.5=390.366-7.746-14.58-48.1*7.5 = 21.87 KN
Page | 75
Design of RCC T-beam bridge over Baskot Khola, Syangja
Longitudinal girder:
y
3000
250
950
300
x
o
𝐴1 𝑦 + 𝐴2 𝑦2
y̅ =
𝐴1+ 𝐴2
0.25×3×1.075+0.3×0.95×0.475
=
3×0.25+0.3×0.95
=0.908 m
3×0.253 0.3×0.953
ILG= + (3 × 0.25) × (1.075 − 0.908)2 + + (0.3 × 0.95) × (0.475 − 0.908)2
12 12
= 0.0996 𝑚4
Cross girder:
250
3675
650
300
x
o
Page | 76
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝐴1 𝑦 + 𝐴2 𝑦2
y̅ =
𝐴1+ 𝐴2
3.675×0.25×0.775+0.3×0.65×0.325
= 1.33×0.25+0.3×0.65
=0.696m
3.675×0.253 0.3×0.653
ICG= + (3.675 × 0.25) × (0.25 − 0.204)2 + + (0.3 × 0.65) × (0.325 − 0.696)2
12 12
= 0.04 𝑚4
Now,
12 𝐿 3 𝑛𝐸𝐼𝑇
α=(𝜋4 )(ℎ) ( )
𝐸𝐼
12 15 3 5×𝐸×0.04
α = 𝜋4 × ( 3 ) × 𝐸×0.0996 = 30.921
and,
𝜋2 h CJ
β =(2𝑛) (𝐿 )(𝐸𝐼 )
𝑇
(b/a)=3000/250=12 R=0.333
(b/a)=950/300=3.167 R=0.266
I0=0.33*2503*3000+0.266*3003*950=2.24*1010mm4=0.0224m4
𝜋2 3 0.4∗E∗0.0224
β =(2∗5) (15)( )=0.044 = 0
𝐸∗0.04
Page | 77
Design of RCC T-beam bridge over Baskot Khola, Syangja
W W W W
400 1800 1700 1800
A B C
1700 3000 3000 1700
𝑅𝐴 = 1.792𝑊
𝑅𝐵 = 1.397𝑊
𝑅𝐶 = 0.809𝑊
Page | 78
Design of RCC T-beam bridge over Baskot Khola, Syangja
Intermediate Girder
144.53KN
144.53KN
34.22KN
34.22KN
86.2KN
86.2KN
1100 3200 1200 4300 3000
144.53KN
34.22KN
86.2KN
86.2KN
fig: Positioning of live load after including reaction factor of 1.397 and impact factor 1.21 and partial safety factor 1.5
Page | 79
Design of RCC T-beam bridge over Baskot Khola, Syangja
144.53KN
86.2KN
86.2KN
86.2KN
86.2KN
1200 4300 3000 3000 3000
144.53KN
34.22KN
86.2KN
86.2KN
0.75
0.67 0.38 0.18 fig:
Positioning of live load after including reaction factor of 1.397 and impact factor 1.21 and partial safety factor 1.5
W 1.67W 1.67W W
1500 600 1000 600
A B C
1700 3000 3000 1700
𝑅𝐴 = 2.675𝑊
𝑅𝐵 = 2.166𝑊
𝑅𝐶 = 1.164𝑊
Page | 81
Design of RCC T-beam bridge over Baskot Khola, Syangja
Intermediate Girder
253.83KN
253.83KN
1200
3.75 3.15
fig: Positioning of live load after including reaction factor of 2.166 and impact factor 1.25 and partial safety factor 1.5
253.83KN
1200
2.81 2.51
fig: Positioning of live load after including reaction factor of 2.166 and impact factor 1.25 and partial safety factor 1.5
Page | 82
Design of RCC T-beam bridge over Baskot Khola, Syangja
253.83KN
1200
1 0.92 fig:
Positioning of live load after including reaction factor of 2.166 and impact factor 1.25 and partial safety factor 1.5
253.83KN
1200
0.75
0.67 fig:
Positioning of live load after including reaction factor of 2.166 and impact factor 1.25 and partial safety factor 1.5
Page | 83
Design of RCC T-beam bridge over Baskot Khola, Syangja
W W
1625 2050
𝑅𝐴 = 1.025𝑊
𝑅𝐵 = 0.734𝑊
𝑅𝐶 = 0.240𝑊
Page | 84
Design of RCC T-beam bridge over Baskot Khola, Syangja
Intermediate Girder
423.88KN
End Girder
Page | 85
Design of RCC T-beam bridge over Baskot Khola, Syangja
W1=350KN
girder B
3600
2050
W2=350KN
950
girder A
15000
Maximum Live load shears with impact factor 1.1, partial safety factor 1.5 and reaction factor 0.644 in:
Inner Girder=405.53*0.734*1.1*1.5=491.137KN
Outer Girder=210.47*1.025*1.1*1.5=355.957KN
Page | 86
Design of RCC T-beam bridge over Baskot Khola, Syangja
W1=350KN
girder B
3600
2050
W2=350KN
950
girder A
15000
fig: Positioning of live load after including reaction factor of 0.644 and impact factor 1.1 and partial safety factor 1.5
Maximum Live load shears with impact factor 1.1, partial safety factor 1.5 and reaction factor 0.68 in:
Inner Girder=345.62*1.1*0.734*1.5=418.58KN
Outer Girder=179.39*1.1*1.025*1.5=303.393KN
Page | 87
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 88
Design of RCC T-beam bridge over Baskot Khola, Syangja
D=1200mm
d=1200-40-32/2=1144mm
𝑏𝑓 =Lo/5+𝑏𝑤 =3000/5+300=900mm
𝑀𝑢 =0.36𝑓𝑐𝑘 𝑏𝑓 𝑥𝑢 (𝑑 − 0.42𝑥𝑢 )
Solving,
𝑥𝑢 = 328.92𝑚𝑚 > 𝐷𝑓
𝑦𝑓
𝑀𝑢,𝑙𝑖𝑚 = 0.36𝑓𝑐𝑘 𝑏𝑤 𝑥𝑢,𝑙𝑖𝑚 (𝑑 − 0.42𝑥𝑢.𝑙𝑖𝑚 ) + 0.446𝑓𝑐𝑘 ∗ (𝑏𝑓 − 𝑏𝑤 )𝑦𝑓 (𝑑 − )
2
Or, 𝑀𝑢,𝑙𝑖𝑚 = 0.36 ∗ 30 ∗ 300 ∗ 549.12(1144 − 0.42 ∗ 549.12) + 0.446 ∗ 30 ∗ (900 − 300) ∗ 244.87 ∗ (1144 −
244.87
)
2
Page | 89
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝐴𝑠𝑡1 = 6106.13𝑚𝑚2
=3215.85-2013.63
=1202.22KNm
𝑀𝑢2
𝐴𝑠𝑡2 =
0.87𝑓𝑦 (𝑑 − 𝑑 ′ )
1202.22 ∗ 106
=
0.87 ∗ 415(1144 − 50)
= 3043.68𝑚𝑚2
𝑥𝑢,𝑙𝑖𝑚 − 𝑑 ′
ɛ𝑠𝑐 = 0.0035 ( ) = 0.00318
𝑥𝑢,𝑙𝑖𝑚
𝑓𝑠𝑐 =355.47MPa
Then;
𝑀𝑢2 1202.22∗106
𝐴𝑠𝑐 =( 𝑓 = ( 355.47−13.38)(1144−50) = 3212.37𝑚𝑚2
𝑠𝑐 −𝑓𝑐𝑐 )(𝑑−𝑑′ )
Page | 90
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑀𝑢 =0.36𝑓𝑐𝑘 𝑏𝑓 𝑥𝑢 (𝑑 − 0.42𝑥𝑢 )
Solving,
𝑥𝑢 = 243.24𝑚𝑚 < 𝐷𝑓
Hence, our assumption is true and NA lies in flange. Design SRURS section.
Then,
𝐴𝑠𝑡 = 8509.9𝑚𝑚2
And,
Page | 91
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑀𝑢 =0.36𝑓𝑐𝑘 𝑏𝑓 𝑥𝑢 (𝑑 − 0.42𝑥𝑢 )
Solving,
𝑥𝑢 = 427.95𝑚𝑚 > 𝐷𝑓
𝑦𝑓
𝑀𝑢,𝑙𝑖𝑚 = 0.36𝑓𝑐𝑘 𝑏𝑤 𝑥𝑢,𝑙𝑖𝑚 (𝑑 − 0.42𝑥𝑢.𝑙𝑖𝑚 ) + 0.446𝑓𝑐𝑘 ∗ (𝑏𝑓 − 𝑏𝑤 )𝑦𝑓 (𝑑 − )
2
Or, 𝑀𝑢,𝑙𝑖𝑚 = 0.36 ∗ 30 ∗ 300 ∗ 549.12(1144 − 0.42 ∗ 549.12) + 0.446 ∗ 30 ∗ (900 − 300) ∗ 244.87 ∗ (1144 −
244.87
)
2
𝐴𝑠𝑡1 = 6106.13𝑚𝑚2
=4011.01-2013.63
Page | 92
Design of RCC T-beam bridge over Baskot Khola, Syangja
=1997.38KNm
𝑀𝑢2
𝐴𝑠𝑡2 =
0.87𝑓𝑦 (𝑑 − 𝑑 ′ )
1997.38 ∗ 106
=
0.87 ∗ 415(1144 − 50)
= 5056.80𝑚𝑚2
𝑥𝑢,𝑙𝑖𝑚 − 𝑑 ′
ɛ𝑠𝑐 = 0.0035 ( ) = 0.00318
𝑥𝑢,𝑙𝑖𝑚
𝑓𝑠𝑐 = 355.47MPa
Then;
𝑀𝑢2 1997.38∗106
𝐴𝑠𝑐 =( 𝑓 )(𝑑−𝑑′ )
= ( 355.47−13.38)(1144−50) = 5337.07𝑚𝑚2
𝑠𝑐 −𝑓𝑐𝑐
Page | 93
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑀𝑢 =0.36𝑓𝑐𝑘 𝑏𝑓 𝑥𝑢 (𝑑 − 0.42𝑥𝑢 )
Solving,
𝑥𝑢 = 312.00𝑚𝑚 > 𝐷𝑓
𝑦𝑓
𝑀𝑢,𝑙𝑖𝑚 = 0.36𝑓𝑐𝑘 𝑏𝑤 𝑥𝑢,𝑙𝑖𝑚 (𝑑 − 0.42𝑥𝑢.𝑙𝑖𝑚 ) + 0.446𝑓𝑐𝑘 ∗ (𝑏𝑓 − 𝑏𝑤 )𝑦𝑓 (𝑑 − )
2
Or, 𝑀𝑢,𝑙𝑖𝑚 = 0.36 ∗ 30 ∗ 300 ∗ 549.12(1144 − 0.42 ∗ 549.12) + 0.446 ∗ 30 ∗ (900 − 300) ∗ 244.87 ∗ (1144 −
244.87
)
2
𝐴𝑠𝑡1 = 6106.13𝑚𝑚2
=3072.02-2013.63
Page | 94
Design of RCC T-beam bridge over Baskot Khola, Syangja
=1058.39KNm
𝑀𝑢2
𝐴𝑠𝑡2 =
0.87𝑓𝑦 (𝑑 − 𝑑 ′ )
1058.39 ∗ 106
=
0.87 ∗ 415(1144 − 50)
= 2679.54𝑚𝑚2
𝑥𝑢,𝑙𝑖𝑚 − 𝑑 ′
ɛ𝑠𝑐 = 0.0035 ( ) = 0.00318
𝑥𝑢,𝑙𝑖𝑚
𝑓𝑠𝑐 = 355.47MPa
Then;
𝑀𝑢2 1058.39∗106
𝐴𝑠𝑐 =( 𝑓 )(𝑑−𝑑′ )
= ( 355.47−13.38)(1144−50) = 2828.06𝑚𝑚2
𝑠𝑐 −𝑓𝑐𝑐
Page | 95
Design of RCC T-beam bridge over Baskot Khola, Syangja
=2850𝑚𝑚2
Curtailment of bars
Bending moment at quarter span is less. Hence curtailment of bars can be done for economic design.
𝑙𝑑 =∝1 ∝2 𝑙0 =∝1 ∝2 𝑛∅
∝1 = 1
1 𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
= ≈ 1.05
∝2 𝐴𝑠𝑡,𝑟𝑒𝑞
𝑙0 = 𝑛Ф
𝑛 = 40 (IRC21, table 12)
Ф=32mm
the length of extension of bar beyond the
theoretical cutoff point ;
=∝1 ∝2 𝑛∅
=1/1.1*40*32
=1219.05mm
2ф=64mm
Page | 96
Design of RCC T-beam bridge over Baskot Khola, Syangja
Anchorage length
2
Extension of bar beyond the face of support = ∗
3
𝑙𝑑 = 568.89 mm
𝐴𝑠𝑡,𝑟𝑒𝑞
Where, 𝑙𝑑 = 0.7 ∗ 𝑙0 ∗ 𝐴 for bars with hook
𝑠𝑡,𝑝𝑟𝑜𝑣𝑖𝑑𝑒𝑑
end
= 835.33mm
l/d=15000/1144=13.11
α=20
β=10/15=0.7
δ=1.4(Pc=1.87%)
λ=0.8
αβγδλ=20*0.7*0.8*1.35*0.8=13.17
l/d=15000/1144=13.11
α=20
Page | 97
Design of RCC T-beam bridge over Baskot Khola, Syangja
β=10/15=0.7
δ=1.5(Pc=3.05%)
λ=0.8
αβγδλ=20*0.7*0.8*1.5*0.8=13.44
Page | 98
Design of RCC T-beam bridge over Baskot Khola, Syangja
D=1200mm
d=1200-40-32/2=1144mm
𝑏𝑓 =Lo/5+𝑏𝑤 =3000/5+300=900mm
881.503 ∗ 1000
=
300 ∗ 1144
=2.57𝑁𝑚𝑚−2
𝑃𝑡 = 3.52%
=552.03KN
=169.24mm>100mm
<300mm
<858mm
Page | 99
Design of RCC T-beam bridge over Baskot Khola, Syangja
617.22 ∗ 1000
=
300 ∗ 1144
=1.8𝑁𝑚𝑚−2
𝑃𝑡 = 2.81%
=292.896KN
=141.767mm>100mm
<300mm
<858mm
Page | 100
Design of RCC T-beam bridge over Baskot Khola, Syangja
1094.54 ∗ 1000
=
300 ∗ 1144
=3.189𝑁𝑚𝑚−2
𝑃𝑡 = 4.69%
=765.068KN
=122.17mm>100mm
<300mm
<858mm
693.898 ∗ 1000
=
300 ∗ 1144
Page | 101
Design of RCC T-beam bridge over Baskot Khola, Syangja
=2.022𝑁𝑚𝑚−2
𝑃𝑡 = 3.52%
=364.426KN
=178.035mm>100mm
<300mm
<858mm
Page | 102
Design of RCC T-beam bridge over Baskot Khola, Syangja
3000 3000
longitudinal Girder
3675
1500
3675
Cross Girder
Page | 103
Design of RCC T-beam bridge over Baskot Khola, Syangja
25.811 KN/m
C.G. C.G. C.G.
3000 3000
Since dead load is contributed by only one contributory I.E. half as that of intermediate cross girder.
Page | 104
Design of RCC T-beam bridge over Baskot Khola, Syangja
10.332×6
Reaction on longitudinal girder is = 3
= 20.664 𝐾𝑁
10.332 KN/m
C.G. C.G. C.G.
3000 3000
Page | 105
Design of RCC T-beam bridge over Baskot Khola, Syangja
5.3.2. Analysis Of Live Load For Both Intermediate And End Cross Girder
For maximum Bending moment, the Live loads should be kept at equal distance from intermediate longitudinal
girder of both sides of cross girder.
5.3.2.1. Class AA Track Vehicle
3000 3000
longitudinal Girder
850
3675
Tracks
1800
3675
1975 2050 1975
Cross Girder
264.286KN 264.286KN
3000 3000
Page | 106
Design of RCC T-beam bridge over Baskot Khola, Syangja
Max. Bending moment on cross girder under live load =176.19×1.975=347.975 KN-m
Page | 107
Design of RCC T-beam bridge over Baskot Khola, Syangja
3000 3000
3675
600 1000 600
1500
1200
CLASS AA WHEELS
3000 3000
Reaction on each longitudinal girder without considering impact factor and partial safety factor;
75∗2+625∗2
= = 91.67 𝐾𝑁
3
Max. Bending moment on cross girder under live load considering partial safety factor 1.5 and impact factor
1.25;
Page | 108
Design of RCC T-beam bridge over Baskot Khola, Syangja
3000 3000
3675
1500
1200
3000 3000
fig: load and reactions on CG due to two class A wheel live load
Reaction on each longitudinal girder without considering impact factor and partial safety factor;
57∗4
= = 76 𝐾𝑁
3
Max. Bending moment on cross girder under live load considering partial safety factor 1.5 and impact factor
1.25;
Page | 109
Design of RCC T-beam bridge over Baskot Khola, Syangja
(1.975) 2
Mu,dead=51.622 × 1.975 − 25.811 × = 51.614 KNm
2
𝐵𝑓 = Lo/5+Bw = 3/5+0.3=900mm
D=900mm
Assuming Xu=𝐷𝑓
=0.36*30*900*250(900-0.42*250)
=1931.85KNm
𝑓𝑦 ∗ 𝐴𝑠𝑡
𝑀𝑢 = 0.87 ∗ 𝑓𝑦 ∗ 𝐴𝑠𝑡 (𝑑 − )
𝑏𝑓 ∗ 𝑓𝑐𝑘
415∗𝐴𝑠𝑡
Or, 707.067 ∗ 106 = 0.87 ∗ 415 ∗ 𝐴𝑠𝑡 (844 − )
900∗30
Solving;
𝐴𝑠𝑡 = 2416𝑚𝑚2
Page | 110
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑜𝑑𝑒𝑑 = 2463𝑚𝑚2
Also, since d>450mm, Provide side reinforcement equal to 1% of exposed web area.
=1950𝑚𝑚2
381.99 ∗ 1000
=
300 ∗ 844
=1.51𝑁𝑚𝑚−2
𝑃𝑡 = 1.17
=381.99-0.69*300*844/1000
=207.28KN
=147.8mm
Page | 111
Design of RCC T-beam bridge over Baskot Khola, Syangja
(1.975) 2
Mu,dead=20.664 × 1.975 − 10.332 × = 20.661 KNm
2
𝐵𝑓 = Lo/5+Bw = 3/5+0.3=900mm
D=600mm
Assuming Xu=𝐷𝑓
=0.36*30*900*250(544-0.42*250)
=1066.77KNm
𝑓𝑦 ∗ 𝐴𝑠𝑡
𝑀𝑢 = 0.87 ∗ 𝑓𝑦 ∗ 𝐴𝑠𝑡 (𝑑 − )
𝑏𝑓 ∗ 𝑓𝑐𝑘
415∗𝐴𝑠𝑡
Or, 673.144∗ 106 = 0.87 ∗ 415 ∗ 𝐴𝑠𝑡 (544 − )
900∗30
Solving;
𝐴𝑠𝑡 = 3844.9𝑚𝑚2
𝐴𝑠𝑡,𝑝𝑟𝑜𝑣𝑜𝑑𝑒𝑑 = 3885.365𝑚𝑚2
Page | 112
Design of RCC T-beam bridge over Baskot Khola, Syangja
Also, since d>450mm, Provide side reinforcement equal to 1% of exposed web area.
=1050𝑚𝑚2
351.032 ∗ 1000
=
300 ∗ 544
=2.15𝑁𝑚𝑚−2
𝑃𝑡 = 2.36
=351.032-0.89*300*544/1000
=205.784KN
=144.755mm
i. DL from Superstructure
Weight of superstructure= (61.74*2+48.1)*15+43.74*5=2792.4KN
Total DL reaction from super structure (Wu) =2792.4/1.35=2068.44KN
= 940.6*(9.4*15) *2*0.75/1000=199KN
Wind load in vertical direction on a bearing (F WV) = 199KN /6= 33.16KN
v. Seismic Load
Seismic loads acts on c. g. of seismic weight. It creates additional vertical load on bearing. Consider c. g. of
seismic weight = 0.9 m from bearing.
505.9∗0.9∗0.5
Vert. reaction on a bearing when s. load acts in tr. dir. (FSvT) = = 69.81𝐾𝑁
3
465.399∗0.9∗0.5
Vert. reaction on a bearing when seismic load acts in long. dir. (FSvL) = = 13.96𝐾𝑁
15
Page | 115
Design of RCC T-beam bridge over Baskot Khola, Syangja
DLsup DLsup
I
LL LL 100%
[N]
DLsup DLsup
II(A) LL LL
115%
[N+T]
Fcst
DLsup DLsup
LL LL
III(A)
133%
[N+T+W]
Fcst
DLsup DLsup
0.2 LL 0.2 LL
VI
0.5 0.5 150%
[N+T+S]
Fcst
Page | 116
Design of RCC T-beam bridge over Baskot Khola, Syangja
1. Geometrical design
In geometrical design, approximate length, breadth and thickness of elastomeric pad and number, thickness
and cover of steel laminates are found. Geometrical design is carried out using the guidelines of IRC.
[Refer standard plan dimensions of IRC 83, Part II, Cl. 916.2, Appendix I]
Nmin = DL = 344.74KN; Nmax = Tot. Vertical load on bearing = 757.05KN; H = 33.33 KN
Take,
b0 = 300 mm, b = 290mm
l0 = 450 mm, l = 440 mm
hi = 10 mm
he = hi/2 = 5 mm
hs = 3 mm
n=3
c = 6 mm
h0 = (n +1)hs +nhi + 2he = 52 mm
h= nhi+ 2he = 40 mm
Page | 117
Design of RCC T-beam bridge over Baskot Khola, Syangja
2. Structural design
Bearing is further checked for translation, rotation, friction and shear
Page | 118
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 119
Design of RCC T-beam bridge over Baskot Khola, Syangja
Size of bearing provided for loads of combination I (N) is not sufficient for loads of combination VI
(N+T+S). Check for translation shows that provided size of bearing could not accommodate the horizontal
force of combination VI. In the situation it is suggested to provide elastomeric pad bearing with pin on one
side of support to resist horizontal load
3. Diameter of Pin
Shear stress in pin due to horizontal loads ≤ Allowable shear stress in pin (𝜏≤𝜏𝑎)
Take pin of Fe250 grade
𝐻𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 𝑙𝑜𝑎𝑑𝑠 100.56∗103
= = 0.4𝑓𝑦
𝐶𝑟𝑜𝑠𝑠 𝑆𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑝𝑖𝑛 𝜋∗𝑟 2
Hence, r=13.89mm
Provide 28mm dia. stainless steel pin. Pin should be extended up to the depth of cap of support.
Design summary:
Provide bearing of 300mm×450mm size
b0 = 300 mm, b = 290mm
l0 = 450 mm, l = 440 mm
hi = 10 mm
he = hi/2 = 5 mm
hs = 3 mm
n=3
c = 6 mm
h0 = (n +1)hs +nhi + 2he = 52 mm
h= nhi+ 2he = 40 m
Page | 120
Design of RCC T-beam bridge over Baskot Khola, Syangja
Design Summary
Type of bearing elastomeric pad bearing
Size of bearing 500*320*40
Diameter of pin 40mm
Material of pin Fe 250
Page | 121
Design of RCC T-beam bridge over Baskot Khola, Syangja
b) Material Selection:–
M25 grade of concrete for abutment stem
M30 grade of concrete for abutment cap
Fe 415 HYSD bars for all RC work.
c) Geometry of abutment:–
i) Seating width:
Minimum seating width = 305+2.5×span+10×Ht.of abutment
= 305+2.5×15+10×7
= 412.5 mm
Width of expansion joint ≥ 15×1000×0.000012×50×0.5 = 3.72 mm
≥ 5×10–4×15×1000×0.5 = 3.75mm
≥ 20mm
Thus, adopt expansion joint width = 40mm
Also,
Seating width ≥ Bearing width+150+expansion joint + projection of
cap
≥ 0.3+0.15+0.04+0.1
≥ 0.59m
Thus, seating width > 590mm
ii) Height of dirt wall
= Ht. of girder+ Ht. of bearing – Thickness of approach slab
= 1.2+0.052–0.4
= 0.852 m
iii) Thickness of dirt wall = 0.25m
Ht. of dirt wall
Thickness of dirt wall ≥ 200mm and = 0.122 m
7
Adopt thickness of dirt wall =250 mm
Page | 122
Design of RCC T-beam bridge over Baskot Khola, Syangja
v) Thickness of footing
H
Thickness of footing = 0.875
8
Adopt thickness of footing 1 m
Page | 123
Design of RCC T-beam bridge over Baskot Khola, Syangja
approach slab
girder
750 100
4000 1250
6000
450 7450
Page | 124
Design of RCC T-beam bridge over Baskot Khola, Syangja
Load on abutment cap from the superstructure= 974 kN. (refer to design of abutment).
𝜏𝑢𝑣≤ 𝜏𝑐,max.
𝑊h𝑒𝑟𝑒,
𝜏𝑢𝑣= 974*1000 /(2 *450 + 2 × d + 2× 300 + 2 × d) × d = 1.56 N/mm2
Steel work required= 1% of 250*850 = 2125 mm^2, Area required on one side = 2125/2= 1062.5
mm^2.
20 nosØ12
12mmØ bars nos. 83
Page | 125
Design of RCC T-beam bridge over Baskot Khola, Syangja
Total 1728
1728
Dead load per unit length of abutment =2∗7.45 = 116𝑘𝑛/𝑚
Page | 126
Design of RCC T-beam bridge over Baskot Khola, Syangja
girder)
430.91+2∗408.6
= = 832.1𝑘𝑛
1.5
832.1
Load on an abutment per unit length (LL) = = 111.7 𝐾𝑁/𝑀
7.45
d) Wind load:
47
Basic wind speed =33 ∗ 17.8 = 25.35𝑚/𝑠𝑒𝑐
47^2
Basic pressure =33^2 ∗ 190.5 = 386.42𝑁/𝑚^2
Increase pressure by 20% (clause 209.2 note 4 irc 6)
Load in transverse direction = 1.2*386.42*2*24.78*2.25=51.71 KN
Load in longitudinal direction=0.25*51.71=12.93
51.71
Transverse wind load per unit length (FwT) = = 3.47kn/m
2∗7.45
12.93
Longitudinal wind load per unit length (FwL) = 2∗7.45 = 0.87 KN/m
Vertical load = pz*A3*G*Cl=(1.2*386.42)*(9.4*15)*2*0.75=98.1KN
98.1
Vertical wind laod per unit length (FwV) =2∗7.45 = 6.58 KN/m
Z I Sa
e) Seismic load (Fsh) = × × ×W
2 R g
Take seismic zone–V, soil strata–medium, Damping = 5%,
Bridge Class = Normal
Z I Sa
Where, Ah = h = × ×
2 R g
Sa
Z = 0.36, I = 1, R = 3, = 2.5
g
Ah = 0.15
W = 1944.6KN in longitudinal direction
W = 1944.6+200=2144.6 KN in transverse direction
FshL = 1944.6*0.15=291.7 KN
FsHt=2144.6*0.15=321.7KN
Seismic load in transverse direction per unit length;
321.7
FshT = 2∗7.45 = 21.6KN
Seismic load in longitudinal direction per unit length;
Page | 127
Design of RCC T-beam bridge over Baskot Khola, Syangja
273.6
FshL =2∗7.45 = 19.58KN
Vertical reaction due to seismic load on support of bridge in transverse
direction
321.7∗0.9
FsvT = = 6.48KN/M
6∗7.45
Vertical reaction due to seimic load on support of bridge in
273.6∗0.9
longitudinal direction = 15∗7.45 = 2.2 KN/m
37.9
Load per unit length (Fcst) = 7.45 = 5.1 KN/m
Where
KA
𝜑 = 350, i = 0 = 18 KN/m3, H= 7 m
Page | 128
Design of RCC T-beam bridge over Baskot Khola, Syangja
Horizontal component of load per unit length PEPH(s) = PA cos (24°) = 98.3
KN/m
Vertical component of load per unit length PEPV(s) = PA sin (24°) =
43.77 KN/m
Where,
𝜑 = 350, i = 0
𝑍 𝐼 𝑆𝑎
∝H=2 ∗ 𝑅 ∗ =0.15
𝑔
∝v=2/3*0.15=0.1
soil = 18 KN/m3, H= 7 m
Horizontal component of load per unit length P EPH(d) = PA cos(24°) = 161.15 KN/m
Vertical component of load per unit length PEPV(d ) = PA sin(24°) = 71.75
KN/m
Page | 129
Design of RCC T-beam bridge over Baskot Khola, Syangja
k) Surcharge load:
1.2 m earth fill from road surface is taken as surcharge load.
Psur = KA × 𝛾s × h × W = 0.244 × 18 ×1.2 × 7 = 36.89 KN/m
Horizontal component of load per unit length PsurH = Psur cos (24°) = 33.7
KN/m
Vertical component of load per unit length PsurV = Psur sin (24°) = 15
KN/m
m) Weight of footing:
Wfooting = 6*1*7.45*25=1117.5 KN
1117.5
Load per unit length, Wfooting = = 150 KN/m
7.45
Page | 130
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 131
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 132
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 133
Design of RCC T-beam bridge over Baskot Khola, Syangja
resoponses of abutment at its bottom in seismic combitation of load at 2 m distance above abutment.
Page | 134
Design of RCC T-beam bridge over Baskot Khola, Syangja
We know,
750mm
Fig.: Stem Of Abutment In Plan For 1 M Unit Length (Treating It As A Slab)
d= 750.-40-(25/2) =697.5mm.
Here,
M= 367.82 KNm.
b = 1000mm
𝑋𝑢
Q =0.36*fck*(xu/d)*(1-0.42 * 𝑑 ) =0.36*25*0.48*(1-0.42*0.48) =3.45
367.82∗10^6
d= √ =326.99 mm.
3.45∗1000
Page | 135
Design of RCC T-beam bridge over Baskot Khola, Syangja
415∗𝐴𝑠𝑡
Or, 0.87*415* Ast* (697.5-25∗1000 ) = 367.82*106
On solving we get:
Ast =1517mm2
Take nos =4
Take 0.12% of gross area [Refer detailing criteria of IRC 112-2011 and IS 4]
C. Horizontal reinforcement:
= 0.001*750*4.498*1000 or 0.25*1516.1
Provide: 12mm dia bars then the spacing would be (4498*0.25*π*12 2)/3739 =147mm.
take spacing as 150mm c-c.
Page | 136
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝜏𝑢𝑣≤ K 𝜏𝑢𝑐………………………………………….(1)
212.3
𝜏𝑢𝑣 =1000∗697.5=0.3 N/mm2.
Since condition (1) is satisfied so its safe in shear and no additional reinforcements is
required for shear.
We know,
750mm
Figure: stem of abutment in plan for 1 m unit length (treating it as a slab)
d= 750.-40-(25/2) =697.5mm.
Here
Page | 137
Design of RCC T-beam bridge over Baskot Khola, Syangja
M= 155.01 KNm.
b = 1000mm
𝑋𝑢
Q =0.36*fck*(xu/d)*(1-0.42 * 𝑑 ) =0.36*25*0.48*(1-0.42*0.48) =3.45
155.01∗10^6
d= √ =211.74 mm.
3.45∗1000
A) Amount of steel work required (main vertical bars) in the side of backfill
𝑓𝑠𝑡∗𝐴𝑠𝑡
0.87*fst* Ast* (d- 𝑓𝑐𝑘∗𝑏 ) =M
415∗𝐴𝑠𝑡
Or, 0.87*415* Ast* (697.5-25∗1000 ) = 155.01*106
On solving we get:
Ast =647.48mm2
Take 0.12% of gross area [Refer detailing criteria of IRC 112-2011 and IS 4]
Page | 138
Design of RCC T-beam bridge over Baskot Khola, Syangja
C) Horizontal reinforcement:
= 0.001*750*(4.498-2)*1000 or 0.25*1636.25
=1873.5mm^2 or,409.1mm^2.
a) surcharge loads.
Since the point of action of surcharge, earth (static/dynamics) lies below the dirt-wall
i.e. on the stem of abutment so only the horizontal components of such force is
important for dirtwall.
Dirt wall have been designed as a cantilever slab of unit width. Detailing of wall is
carried out by IRC 112 - 2011 Cl. 16.3.
Page | 139
Design of RCC T-beam bridge over Baskot Khola, Syangja
i. Calculations of loads:
= 9.52*0.5*1.102 +4.37*0.5*1.064+1.033*0.5*1.102
= 7.814 KN-m.
Taking clear cover of 40mm and 12mm dia bars are provided
415∗𝐴𝑠𝑡
Or, 0.87*415* Ast* (204-25∗1000 ) = 7.814*106
On solving we get:
Similarly for horizontal reinforcement take 10mm bars and provide c-c spacing of
200mm…
300
Nos. of bars in along 852mm length = 0.25∗𝜋∗10^2 = 3.82 provide 4nos.
Page | 140
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝜏𝑢𝑣≤ K 𝜏𝑢𝑐………………………………………….(1)
14.92
𝜏𝑢𝑣 =1000∗204 =0.073 N/mm2.
K*𝜏𝑢𝑐 =1.9*0.29=0.511N/mm2. ( values of K and 𝜏𝑢𝑐 From IRC 456 table 19 and
40.2.1.1)
Since condition (1) is satisfied so its safe in shear and no additional reinforcements is
required for shear.
Page | 141
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 142
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 143
Design of RCC T-beam bridge over Baskot Khola, Syangja
surcharge
horizontal 33.7 1.2 3.5 0 40.44 141.54 40.44
surcharge
vertical 15 1.2 1 18 18 0
backfill load 403.2 1.35 -1 544.32 -544.32 0
footing weight 150 1.35 0 202.5 0 0
TOTAL 1562.786 846.94 212.3
Page | 144
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑃𝑢 𝑀∗𝑌
Toe/ heel intensity due basic combinations = ±
𝐴 𝐼𝑥𝑥
1562.786 846.94∗12∗3
= ±
6 6^3
Page | 145
Design of RCC T-beam bridge over Baskot Khola, Syangja
𝑃𝑢 𝑀∗𝑌
Toe/ heel loads intensity due seismic combinations = ±
𝐴 𝐼𝑥𝑥
721.1 541.2∗12∗3
= ±
6 6^3
Since basic combination has higher value of intensity so it’s designed for basic
combinations :
Taking 25 mm dia bars for footing and the effective depth would be for 40 mm clear
cover.
d = 1000-40-12.5 =937.5 mm.
d=0.9375m
2
343.5
308
120 402
6 3
4 8
8
After calculating load intensity on the both side of face of stem of abutment (for
moment calculation) and at a distance of effective depth for footing d (one way shear )
from the the face of stem of abutment . Reinforcement requirement is calculated.
308+120
M at section 1 = ( )*4*0.5*4. = 1712 KN-m.
2
343.25+402
M at section 2 =( )*1.25*0.5*1.25=291.11 kN-m.
2
Page | 146
Design of RCC T-beam bridge over Baskot Khola, Syangja
d= 1000.-40-(25/2) =937.5mm.
Here,
M= 1712 KNm.
b = 1000mm
𝑋𝑢
Q =0.36*fck*(xu/d)*(1-0.42 * 𝑑 ) =0.36*25*0.48*(1-0.42*0.48) =3.45
1712∗10^6
d= √ 3.45∗1000 =705 mm.
415∗𝐴𝑠𝑡
Or, 0.87*415* Ast* (937.5-25∗1000 ) = 1712*106
On solving we get:
Ast =5616.37mm2
Spacing required = 1000/12 = 83.33 take 100mm (for practical view point)
Page | 147
Design of RCC T-beam bridge over Baskot Khola, Syangja
For section 2:
415∗𝐴𝑠𝑡
Or, 0.87*415* Ast* (937.5-25∗1000 ) = 291.11*106
On solving we get:
Ast = 874mm2
123.33
Nominal shear stress = 𝜏𝑢𝑣 =1000∗937.5 = 0.132𝑁/𝑚𝑚^2.
Page | 148
Design of RCC T-beam bridge over Baskot Khola, Syangja
588
Nominal shear stress = 𝜏𝑢𝑣 =1000∗937.5 = 0.627𝑁/𝑚𝑚^2.
K =1 from IRC 456 cl.40.2.1,, = 0.49 for pt=0.5% and M25 (table 19,Irc 456)
Where,
Now,
Page | 149
Design of RCC T-beam bridge over Baskot Khola, Syangja
Asphalt concrete
2 for wearing coat 1 15 7.5 0.0875 9.85 cum
Page | 150
Design of RCC T-beam bridge over Baskot Khola, Syangja
4.2 Stem portion of abutment M25) 2 7.45 0.75 4.498 50.27 cum
5 Formwork
Page | 151
Design of RCC T-beam bridge over Baskot Khola, Syangja
4 GI pipe= 90 rm
Page | 152
Design of RCC T-beam bridge over Baskot Khola, Syangja
8. REFERENCES
[1] Johnson, Victor. D, Essentials of Bridge Engineering, Oxford & IBH Publications,
New Delhi, 1980
[2] T.R. Jagadeesh & M.A. Jayaram “Design of Bridge Structure” PHI Learning Pvt.
Ltd, New Delhi, 2010 [4] Pillai and Menon, Reinforced Concrete Design
[3] IRC 5 -2000: Standard specification and code of practice for road bridges, Section
I, General features of Design, 20000
[4] IRC 6 – 2000: Standard specification and code of practice for road bridges, Section
II, Loads and Stresses, 2000
[5] IRC 21 – 2000: Standard specification and code of practice for road bridges, Section
III, Cement Concrete (Plain and Reinforced), 2000
[6] IRC 112– 2011: Code of practice for concrete road bridges
[7] IS 456 – 2000: Indian standard Plain and Reinforced concrete – Code of Practice
[8] SP 16 - 1980: Design aids for Reinforced Concrete to IS: 45 – 1978
[9] SP 34 - 1987: Hand book on concrete reinforcement and detailing
[10] IRC 83– 1987: Standard specification and code of practice for road bridges,
Section IX, Bearings, Part –II: Elastomeric Bearings, 1987
[11] IRC 78– 1983: Standard specification and code of practice for road bridges,
Section VII, Foundations and Substructures, 1988
[12] Design Examples by Nabin Chandra Sharma
Page | 153
Design of RCC T-beam bridge over Baskot Khola, Syangja
9. Annex
Page | 154
Design of RCC T-beam bridge over Baskot Khola, Syangja
Page | 155