Building a Single-Level Raised Deck

WHAT YOU'LL NEED

SKILL SCALE
Hard

TIME REQUIRED
Building a Single-Level Raised deck
should take about 88-101 hours.

Decks are a perfect area for outdoor entertaining and outdoor relaxing. The style
of deck you choose to build determines how you use your deck, as well as how
you build it. Although similar in appearance, different decks can require different
construction techniques.

Out Installation Services Associates built this Single-Level Raised deck and
documented the steps taken in order to help you build your own outdoor living
area.

Batterboards and mason's string lines are used here to lay out footing locations
for a deck that is 24 feet long and 14 feet wide. A 2x12 ledger board was first
attached to the house to establish the deck position. The deck structure,
including number of footings, is designed to be enclosed as a four-season porch
in the near future.

Approximate time for a novice (with a helper) to lay out footing locations for this
deck: 12-14 hours. Time includes removing siding and attaching the ledger.

Holes for seven 12-inch-diameter footings were dug. A standard single-level


raised deck would only need four, parallel to the house. The extra footings are
necessary on this deck to handle the additional weight of the roof and future
remodeling project structures. Holes are 48 inches deep to get below the local
frost line. The bottom of the center footing in the row parallel to the house is
flared to 24 inches. The remaining footings are flared to 18 inches. Footings
were dug with a power auger. Forty-four 60-pound bags of ready-mix concrete
were mixed in a portable power mixer. Post anchors for 6x6 posts were installed
and aligned after the concrete cured for 48 hours.

Approximate time (not including curing time): 14-16 hours.

6x6 posts were plumbed and temporarily braced in place. Post tops were
trimmed to the proper height after posts were positioned. Trimming lines level
with the bottom of the ledger were established using a water level. The beam
supported by the posts will have joists attached to its inner face.

Approximate time: 6-7 hours.


A 24-foot-long beam made of doubled 2x12s was built in place on top of the row
of posts parallel to the house. Adjustable post caps attach the beam to the tops
of the posts. This beam serves as the header joist because joists will be
attached to its inner face. The two rim joists also are beams on this deck
because of the future remodeling. They will help carry the weight of the roof. The
extra beams are 14 feet long and also were built in place. The remaining length
of visible ledger will support the landing at the top end of the stairs. The end of
the adjacent 14-foot beam is attached to the ledger with a double joist hanger.

Approximate time: 7-8 hours.

14-foot-long 2x12 joists were installed. The large size of the framing on this deck
accommodates the future remodeling. Joist hangers attach joists to the ledger
and beam header joist. Blocking pieces were fastened between joists in the
middle of the span to prevent twisting of the joists. Most of the temporary bracing
was removed after joists were installed.

Approximate time: 8-9 hours.

5/4x6 decking was attached perpendicular to the joists and fastened with deck
screws. No additional blocking was necessary because seams between boards
were centered over joists. The seams were staggered between adjacent rows of
decking for best appearance.

Approximate time: 7-8 hours.

Footings for stair landings and pad were located after the main deck platform
was built. Locating stair footings is more accurate when done relative to an
existing deck structure. One 12-inch-diameter footing was made for a 6x6 post
that will support the upper landing. Four 8-inch-diameter footings were made for
4x4 posts that will support a small transition landing in the stair run. The stair run
makes a 90-degree turn at the landing to end on the 4x4-foot pad. The pad is 4
inches thick. Thirty-two 60-pound bags of concrete were mixed in a portable
power mixer.

Approximate time (including making a form for the pad): 6-7 hours.

Post anchors were attached to the footings. Posts were plumbed and the
framing for the landings installed. Decking was attached to the joists. Note: The
landing could be replaced by another deck level on a multilevel deck if desired.
Calculations for the stair runs were checked and the stringers for the stairs were
made. The upper and lower stair runs were built in place.

Approximate time: 16-18 hours.


Railing post locations were calculated and the railing posts installed. Posts were
notched and attached to the outside of the perimeter framing and stringers. The
two posts at the bottom end of the upper stair run are longer than other posts
because they also serve as posts for adjoining railings. This saved the time and
money of installing two additional posts.

Approximate time: 12-14 hours.

Total approximate time for this deck: 88-101 hours.