Sie sind auf Seite 1von 28

Date :

QI - J01
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
Doc. No. : Page :
GRESIK - SEMARANG
of
INSTRUMENT CABLE INSULATION RESISTANCE AND CONTINUITY TEST RECORD AFTER
INSTALLATION Project No. :

Client : Project Title :

Location / Area : …………………………………… Serial No. : ……………………………………


Test Equipment Used : …………………………………… Calibration Expery date : ……………………………………
Insulation Tester Volt. : ………..Volt DC Calibration ID No. : ……………………………………
Cable Spect & Size : …………………………………… Drawing No. & Rev. : ……………………………………

Field Instrument. Junction Box

JB Tag No. :

From Field Instrument Cable Specification To Junction Box


Insulation
No. Terminal Terminal
Tag.No. Wire Color Cable Spect, Size & Lenght. Wire Color To Wire Color Resistance (MW)
No. Block No.

* CONTINUITY TEST PASSED : YES NO


INSULATION TEST : BETWEEN SHIELD TO SHIELD MW
BETWEEN SHIELD TO ARMOURED MW ( if any )
* NOTE : …………………………………………………………………………………………………………………………….

…………………………………………………………………………………………………………………………….

…………………………………………………………………………………………………………………………….

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J01a
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc No. : Page :
GRESIK - SEMARANG
of
INSTRUMENT CABLE INSULATION RESISTANCE AND CONTINUITY TEST RECORD
AFTER INSTALLATION
Project No. :

Client : Project Title :

Location / Area : …………………………….. Insulation Tester Volt : ……………………………


Test Equipment Used : …………………………….. Calibration Expery date : …………… Volt. DC
Serial No. : …………………………….. Calibration ID No. : ……………………………
Drawing No. & rev. : …………………………….. : ……………………………

Cable Specification
Cable Tag No. Cable Specification
From and Size
To Length .meters
(A) INSULATION TEST : BETWEEN EACH CORE TO GROUND / ARMOUR (MEGA OHMS)
(B) INSULATION TEST : BETWEEN EACH CORE TO SHIELD (MEGA OHMS)

Core 1 2 3 4 5 6 7 8 9 10
(A)

(B)

Core 11 12 13 14 15 16 17 18 19 20
(A)

(B)

Core 21 22 23 24 25 26 27 28 29 30
(A)

(B)

Core 31 32 33 34 35 36 37 38 39 40

(A)
(B)

INSULATION TEST : BETWEEN SHIELD / ARMOUR MW ( Average )

INSULATION TEST : CORE TO CORE MW ( Average )


( Detail Record see Attachment, if any )
CONTINUITY TEST PASSED : YES NO

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Cable No. : ………………………………………………………………
Doc No. : Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI ATTACHMENT
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG QI - J01a
Cable Specification : ……………………………………………………………..

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI QI - J02
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc. No. : Page :
GRESIK - SEMARANG of

TEST REPORT OF INSTRUMENT PRESSURE PIPING / TUBING Project No. :

Client : Project Title :

Location : ……………………………………………………… Test Equipment Used : …………………………………………………………


Area : ……………………………………………………… : …………………………………………………………
Drawing No. & rev. : ……………………………………………………… : …………………………………………………………

Visual Inspection Hydro Test Pneumatic Test

Press. Rating
Instrument
Measuring

Operating
Range of

(Kg/cm2)
Upstream &

Test Press.

Test Press.
Downstrea

Result

Material &

Press.

Test Fluid

Test Fluid
(Kg/cm2)

(Kg/cm2)
Support
NO. Tag No. REMARKS

Rating

Result
Slope
m

Date Sign

Note :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J03
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG
Doc. No. : Page :
of

TEST REPORT OF INSTRUMENT AIR SUPPLY PIPING Project No. :

Client : Project Title :

Location / Area : …………………………… Drawing No. & rev : ……………………………..

Branch / Header No. : …………………………… : ……………………………..

RESULT ACCEPTED
NO. TAG NO. REMARKS
LEAK BLOW DATE SIGN

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
QI - J04
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of
INSTRUMENT CALIBRATION RECORD Project No.:
Client : Project Title :

Tag. No. :

Type : Serial No. : Accuracy :


Manufacture : Service : Data Sheet :
Range : Type/Model : Location :
Scale Range : Output : Amb. Temp :

Calibration Check (Before)


Input Output (rising input signal) Output (falling input signal)

% of Span Actual Actual Scale range % of Deviation Actual Scale range % of Deviation

0
25
50
75
100

Calibration Check (After)


Input Output (rising input signal) Output (falling input signal)

% of Span Actual Actual Scale range % of Deviation Actual Scale range % of Deviation

0
25
50
75
100

CALIBRATOR EQUIPMENT TEST


Test Equipment used : :
( w/ Accuracy)
: :

: :

Setting : [ ] direct [ ] reverse


Alarm settings : H : L :
HH : LL :

Range of automatic temperature correction :


Selected correction for spec. gravity or density :

Failure of auxiliary energy [ ] to max. scale deflection [ ] to min. scale deflection


Failure of input signal [ ] to max. scale deflection [ ] to min. scale deflection
Conform to specification [ ] yes [ ] no

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J05
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
Doc. No. : Page :
GRESIK - SEMARANG
of

CONTROL VALVE CALIBRATION / STROKE TEST REPORT Project No.:

Client : Project title :

: …………...………………...…… AREA : …………...………………...…………………

Tag. No. :
Location / Area : Service :
Size & Rating : Serial No. :
Manufacture : Output :
Type No. : Dwg No. & rev. :
Range : Spect/ Data sheet No. :
Scale Range : :

CALIBRATION CHECK

Degree of Input Valve


% of Output Valve Position Control Valve Position ON/OFF
Control Positioner Position Switch
Span Positioner ( Panel View ) Valve
Valve PID ( % )

25

50

75

100

75

50

25

REFERENCE
Type of Valve : Control Valve ON / OFF Valve

Open Time : ……….. Sec. Conforms to Specification : YES NO N/A

Closing Time : ……….. Sec. Conforms to Specification : YES NO N/A

Failur of Auxiliary Enegy : to maximum (opened) to minimum (closed) Freeze.


Failur of Input Signal : to maximum (opened) to minimum (closed) Freeze.

NOTE : …………………………………………………………………………………………………………………………………………..
…………………………………………………………………………………………………………………………………………..

…………………………………………………………………………………………………………………………………………..

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
QI - J06
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of
INTEGRAL LOOP FUNCTION TEST DCS RECORD Project No.:
Client : Project title :

LOOP No. :

LOOP DIAGRAM No. : …………...…………………… rev. :…….. AREA/LOCATION : …………...………………...……………

Analog Input (DCS/ESD) Measuring Scale Range Simulated Local DCS / ESD
Tag No. : Range (Unit) ( Unit ) Input Indicator Reading

W/Calibration Test used :


……………………………
……………………………

Alarm / Trip (ESD) Setting Result Alarm / Trip (DCS) Setting Result
Tag No. : HH Tag No. : HH
H H
L L
LL LL

Digital Input (DCS/ESD) Field DCS Alarm Annunciator ESD


Tag No. : Switch
Open
Close

Control output (DCS) Control Control Valve


Tag No. : output Position (mA)
0% .mA
25% .mA
50% .mA This Valve is Air Failure / Electric Failure
75% .mA [ ] Open [ ] Close
100% .mA note : as per data sheet

On/Off Valve (DCS/ESD) On / Off Valve


Output Position (%)
Tag No. : This Valve is Air Failure / Electric Failure
Open .% [ ] Open [ ] Close
Close .% note : as per data sheet

Digital Output (DCS/ESD) Output Field DCS / ESD Local Control Panel
Tag No. : Open
Close

Graphic Display on Console : ………………………………………………………………………………………….

NOTE : ………………………………………………………………………………………………………………………………..
………………………………………………………………………………………………………………………………..
………………………………………………………………………………………………………………………………..

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J06A
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

INTEGRAL LOOP FUNCTION TEST PLC RECORD PROJECT NO. :

Client : Project title :

LOOP No. :

LOOP DIAGRAM No. : …………...…………………. rev. :…….. AREA/LOCATION : …………...………………...……………

Analog Input Measuring Scale Range Simulated Local DCS PLC


Tag No. : Range ( Unit ) ( Unit ) Input (mA) Indicator Reading Reading

Alarm / Trip Setting Result


Tag No. : HH
H
L
LL

Field Field Indication Panel


Digital Input ( Valve ) D.I/Limit. Switch View - PLC
Tag No. : Open
Close

Control output Control Control Valve


Tag No. : output Position (%)
0% %
25% %
50% %
75% % This Valve is Air Failure
100% % [ ] Open [ ] Close

On / Off Valve On / Off Valve


Output
Tag No. : Position
Open % This Valve is Air Failure
Close % [ ] Open [ ] Close

Field Field D.O / Indication Panel Indication on


Digital Output ( Valve ) Limit. Switch View on PLC DCS
Tag No. : Open
Close

NOTE : ……………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………..

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J07
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc No. : Page :
of

INSPECTION REPORT FOR PANEL AND JUNCTION BOX INSTALLATION Project No. :

Client : Project Title :

Location / Area : …………………………………. Equipment / Panel No. : ………………………………………

Drawing No. : …………………….. rev.: ….. Brand & Manufacture : ……………………………………...

RESULT ACCEPTED
No. INSPECTION REMARKS
YES NO N/A DATE SIGN
1. Visual and Dimensional out side Panel as per Outline
Drawing / Arangement.
2 Check Orientation & Position Panel.

3 Check internal Installation Equipment as per document.

4 Check Support installation.

5 Check Complete All Sim, Bolt, Nuts & Screw.

6 Check Removable Plate,Cable entry protection & Position.

7 Touch-Up Painting.

8 No Conflict with Other Installations.

9 Check Tag Number & Name Plate.

10 Check Cable Marking.

11 Check Tube Marking & Cable Lug.

Note :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J08
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

SEQUENCE TEST RECORD Project No.:

Client : Project Title :

Equipment Tag No. of Sequence :

Status of Sequence :
Location / Area :
Interlock Logic Diagram No. :

Sheet No. :
Panel No. :

Result :

The Squence as per logic number have tested correctly ( see attachment drawing ).

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J.09
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No : Page :
of

TRANSMITTER INSTALLATION CERTIFICATION RECORD Project No.:

Instr. Type : ……………………………………… Service Line : ………………………………………….

Mfr. : ……………………………………… Output : ………………………………………….


Range : ……………………………………… Data sheet No.: ………………………………………….
Serial No. : ……………………………………… Hook-Up Dwg : ………………………………………….

Tag No. :

RESULT ACCEPTED
NO ITEM TO CHECK REMARKS
YES NO N/A DATE SIGN
1 Tag Number is Correct

2 Description of Tag Plate Conform to Data Sheet

3 Process Connection and Material are Correct

4 Stanchion and Support Installation are Correct

5 Description Cable Marker is Correct

6 Conform with Hook-Up drawing

7 Cable Entry, Marker & Termination is Correct

8 Completely & tightening of Bolts and Nuts

9 Orientation is Correct

10 No Conflict with Other Installation

11 Touch-up & painting

12 Routing perforated tray are Correct

13 Installation Gasket is Correct (if any)

14 Insulation is Correct (other sub-cont, if any)

15 Steam Tracing is Correct (if any)

16 Easy to Maintenance Location

Reff Document : - Instrument Hook-Up Drawing - Manual Book & Vendor Drawing (if Any)
- Individual Specification or data sheet
Note :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J.09a
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No : Page :
of

PRESSURE & TEMPERATURE GAUGE INSTALLATION CERTIFICATION RECORD Project No.:

Instr. Type : ………………………………………. Service Line : ………………………………………………


Mfr. : ………………………………………. Output : ………………………………………………
Size & Rating : ………………………………………. Data Sheet No. : ………………………………………………
Serial No. : ………………………………………. Hook-Up Dwg : ………………………………………………

Tag No. :

RESULT ACCEPTED
No. ITEM TO CHECK REMARKS
YES NO N/A DATE SIGN

1 Tag Number

2 Conform to data sheet

3 Conform to Drawing Specification

4 Conform to P & ID Drawing

5 Process Connection and Material, Gasket are Correct

6 Check Orientation

7 Completely Bolts and Nuts

8 No Conflict with Other Installation

9 Conform to Hook-Up drawing

10 Insulation Completed (other sub-cont, if any)

11

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
`
Date :
QI - J10
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

PRESSURE SAFETY VALVE TEST RECORD Project No.:

Client : Project title :

A. DATA FOR SAFETY VALVE.


1. TAG. No. :

2. DATA SHEET No. :

3. DRAWING No. :

4. LOCATION / SERVICE :

5. SERIAL No. :

6. INSTALLED ON EQUIPMENT No. :

7. EQUIPMENT DESIGN PRESSURE :

8. TYPE :

9. SIZE :

10. CAPACITY :

11. NORMAL OPERATION TEMPERATURE :

12. SETTING PRESSURE :

13. FACTOR CORRECTION :

B. TEST DATA
1. TEST MEDIUM :

2. AMBIENT TEMPERATURE :

3. ACTUAL POPPING PRESSURE / CDTP :

4. SEAT LEAK TEST :

5. BACK PRESSURE TEST :

6. RESULT :

Remarks : repair for remove Plug or re-setting

NOTE : ………………………….……………………………………………………………………………………………………………………

………………………….……………………………………………………………………………………………………………………

………………………….……………………………………………………………………………………………………………………

………………………….……………………………………………………………………………………………………………………

………………………….……………………………………………………………………………………………………………………

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
QI - J11 Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

INSTRUMENT CALIBRATION RECORD


Project No :
FOR DEFFERENTIAL PRESSURE AND SWITCH

Client : Project Title :

Tag. No. :
Type : Service :
Manufacture : Output No. :
Range : Spec No. :
Span : Data Sheet :
Serial No. : Ambient Temperature : o
C.

Calibration Check
Input INCREASE Input DECREASE

Desired Actual Desired Actual


% of Span % of Deviation % of Span % of Deviation
( Calibrator ) ( Indicator ) ( Calibrator ) ( Indicator )

0 100
25 75
50 50
75 25
100 0

CALIBRATOR EQUIPMENT TEST

Test Equipment used : Test Equipment used :

Test Equipment used : Test Equipment used :

Setting : [ ] direct [ ] reverse


Alarm settings : H : L :
HH : LL :

Range of automatic temperature correction :


Selected correction for spec. gravity or density :

Failure of auxiliary energy [ ] to max. scale deflection [ ] to min. scale deflection


Failure of input signal [ ] to max. scale deflection [ ] to min. scale deflection
Conform to specification [ ] yes [ ] no

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J12
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

INSPECTION FOR CABLE LADDER AND TRAY INSTALLATION Project No. :

Client : Project Title :

RESULT ACCEPTED
No. INSPECTION REMARKS
YES NO N/A DATE SIGN

1. Visual & Dimensional


2 Check Support of Cable Tray Accepted
3 Check completely of Accessories
4 Check Cable Tray of Alignment
5 Check Installation of Separator (if any)
6 Check Complete & Tightening All Bolt & Nuts
7 Check Grounding Connection
8 Check completely of cover with Clamp (if any)
9 No Conflict with Other Installations
10 …………………………………………………
11 …………………………………………………

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J13
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
Doc. No. : Page :
GRESIK - SEMARANG
of

CONTROL VALVE INSPECTION RECORD Project No. :

Client : Project Title :

TAG NO. :

Loop Tag. No. : ……………………………. Service : …………………………….. Serial No. : …………………………………

Type : ……………………………. Type No. : …………………………….. Spec. No. : …………………………………

Manufacture : ……………………………. Order No. : …………………………….. Output : …………………………………

Range : ……………………………. Span : …………………………….. : …………………………………

No. INSPECTION YES NO N/A DATE SIGN REMARKS

1. Flow Direction Conform to P & ID Drawing

2. Conform to Data Sheet

3. Conform to Specification and Drawing Control Valve

4. Bolt & Nut Dimensional and Material for Flange to Flange

5. Gasket Material for Flange to Flange

6. Air Supply pipe / Tubing Route and Support

7. Cable Tray Route and Support

8. Touch-up Paint

9. Color code

10. Cable Ties and Dressing for Cable entry

11. Power Supply

12. Cable Connection

Note :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J14
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc No. : Page :
of

INSTRUMENT CALIBRATION RECORD FOR TEMPERATURE Project No :

Client : Project Title :

Serial No. : Accuracy : +/- % (see vondor data if any)


Line / Service : Model /Type :
Range Temperature : Amb't Temperature : o
C.
Burn Out : Up Down :

type of Element : S - type N - type K - type E - type J - type RTD - type


T - type W - type B - type R - type KP - type Bimetal type

Tag. No. :
MEASURED RANGE.

Input Output (rising input signal) Output (falling input signal)


deg Desired Actual Scale Range % of Actual Scale Range % of Remarks
0
C Value Ohm / Volt / mA deg. Deviation Ohm / Volt / mA deg. deviation

Configuration Data : See Attached Not Applicable (N/A)


Ohm Micro Volt mile Ampere
Calibration Equipment Test
: :
: :

We certify that the switches provided on this order have been tested and calibrated at our works
and are in and unsed condition

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J15
JASA PERANCANGAN PENGADAAN DAN
KONSTRUKSI PEMBANGUNAN PIPA TRANSMISI GAS
DARI GRESIK - SEMARANG Doc. No. : Page :
of

INSTRUMENT SWITCHES TEST AND SET DATA RECORD Project No. :

Client : Project title :

Type : …………………………. Serial No. : ………………………… Accuracy : …………………………


Manufacture : …………………………. Service : ………………………… Data Sheet : …………………………
Range : …………………………. Type/Model : ………………………… Location : …………………………
Scale Range : …………………………. Output : ………………………… Amb. Temp : …………………………

TAG NO. :

Maximum Working Pressure : .kg/cm2g / Psi / Bar.

Setting range : .kg/cm2g / Psi / Bar.

Input set point Set Reset Dead Band Remarks


No
( ) ( ) ( ) ( )
( )

( )

( )

( )

( )

* Set Point should be confirmed and recorded three times.

Switch Configuration : Hig at Contact Low at Contact


Make Break

Test Medium : Inst. Air Nitrogen


Hand Pump

CALIBRATOR EQUIPMENT TEST

Test Equipment used :


( w/ Accuracy)

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
Q I- J16
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. Page :
of
ANALYZER CALIBRATION RECORD Project No.

Client : Project Title :

Tag No. :

Equipment : Serial No. : Spec. No. :


Manufacture : Service : Location :
Range : Type/Model : Amb. Temp :
Accuracy : Output : :

TRANSMITTER

DCV Standard OUTPUT


TB 2 - 1 Before After
Temperature
Remarks
o
C Conductivity / Conductivity /
TB 2 - 2 mA Error (%) mA Error (%)
pH / O2 / Chlorine pH / O2 / Chlorine

PROBE & TRANSMITTER

OUTPUT
Before After
BUFER SOLUTION
RANGE Remarks
STANDARD Conductivity / Conductivity /
pH / O2 / Chlorine mA Error (%) pH / O2 / Chlorine mA Error (%)

Test Equipment used


: :
w/Accuracy ( if any )

: :

: :

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J17
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No. : Page :
of

INSTRUMENT PIPING & TUBING INSTALLATION RECORD Project No.:

Client : PROJECT :

Sheet No. : ……………………………………… Area/Location : ……………………………


Drawing hook-up No : ……………………………………… Unit / Facility : ……………………………
: ……………………………………… : ……………………………

RESULT ACCEPTED
No. ITEM TO CHECK REMARKS
YES NO N/A DATE SIGN

1. Visual & Dimensional of Drawing/Hook-up type


2. Check of Support, Brace & Coloumn type
3. Check of Piping/Tubing, Fitting, Valve & Accessories
4. Check of welding & NDT ( Radiography & Penetrant Test) (see Attached if any)
5. Check of Threaded Connection & seal tape teflon
6. Check Standard Material & Class
7. Check Service, Fluid, Line number & Press. Rating
8. Check orientasion & no conflic w/other installation
9. Check of Clamp, Bolt & Nuts
10. Touch-Up Panit
11. Space allowance for thermal expansion
12. ……………………………………………………………

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J18
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
Doc. No. : Page :
GRESIK - SEMARANG
of

CABLE LAYING ON LADDER & TRAY Project No. :

Client : Project Title :

LOCATION / AREA :…………………………………… MATERIALS :……………………………………


REFERENCE DRAWING :…………………………………… MANUFACTURE :……………………………………
:…………………………………… :……………………………………

RESULT ACCEPTED
No. INSPECTION
YES NO N/A DATE SIGN REMARKS

1. Dressing Cable & Tie Wrapping Correct


2. Cable Markers Complete
3. Cable Specification Correct
4. Documentation Correct
5. Check Power & Signal Cable of Cross Section Correct
6. No Conflict with other Installation
7. Installation Cover Plate after release
8.
9.
10.
11.

NOTE :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
QI - J19
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc No. : Page :
of

SETTING PROBE AXIAL OR VIBRATION RECORD Project No :

Client : Project Title :

Tag. No. :

Model / Type : Prox Scale Factor :


Serial No. : Zero Voltage : .Vdc
Manufacture : Total Clearence : .mm
Location / Service : Accuracy : +/- % (see vondor data if any)
Amb't Temperature : :

SEETING RECORD DATA

In Action Side Action Side Location / Position


Measuring Remarks
( ) ( ) Probe

Dial .mm .mm

Voltage .Vdc .Vdc

DCS .mm .mm

Note :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date
QI - J20
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI
GRESIK - SEMARANG Doc. No Page
of

INSPECTION OF GROUNDING SYSTEM Project No :

Location : Erection by. :


Number of electrodes : Weather :
Type of conductors : Temperature :
Type of electrodes :
Reference drawing :

RESULT ACCEPT
ITEM TO CHECK REMARKS
YES NA DATE SIGNATURE

1 Visual inspection during pulling cable

2 Check cable size and installation

3 Check underground cable jointing

4 Check construction electrodes

5 Check cable clamp and layout

6 Check protective measurement

7 Check grounding connection

8 Grounding continity test

9 Inspect resistance of each electrodes

10 Insulation resistance measurement

11

Remarks :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date
QI - J21
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc. No Page
GRESIK - SEMARANG
of

GROUNDING CONTINUITY TEST DATA Project No :

Owner : Test Instrument :_________________________


Standard : Type :_________________________
Category : Range :_________________________
Location : Serial No. :_________________________
Reference Drawing : Manufacture :_________________________
Temperature :
Weather :

Termination CONCLUSION
Equipment No. Continuity
Connection ACCEPTED/ REJECTED

REMARKS :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date
QI - J22
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc. No Page
GRESIK - SEMARANG
of

GROUNDING RESISTANCE TEST DATA Project No :

Owner : Test Instrument


Location : Type :
Reference Drawing : Range :
Temperature : Serial No. :
Weather : Manufacture :

EQUIP. NO. LOCATION/ GROUNDING CONCLUSION


GROUND ROD NO. TEST POINT RESISTANCE (Ohm) ACCEPTED/ REJECTED

REMARKS :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date
QI - J23
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc. No. Page
GRESIK - SEMARANG
of

INSULATION RESISTANCE TEST DATA FOR CONTROL CABLE Project No :

Owner : Test Instrument


Location : Type :
Reference Drawing : Range :
Temperature : Serial No. :
Weather : Manufacture :

RATING INSTALLED MEGGER TEST (M ohm) RESULT


NO. CABLE NO.
VOLTAGE FROM TO CORES TO CORES ACCEPTED REJECTED

REMARKS :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :
Date :
JASA PERANCANGAN PENGADAAN DAN KONSTRUKSI QI - J24
PEMBANGUNAN PIPA TRANSMISI GAS DARI Doc. No. : Page :
GRESIK - SEMARANG
of

MATERIAL IDENTIFICATION RECORD Project No. :

Client : _________________________________________________ Project Title : _________________________________________________


Location : _________________________________________________

NO. DATE DESCRIPTION SIZE GRADE HEAT NO. BATCH NO. MILL CERTIFICATE SUPPLIER COLOUR EXPIRED DATE DOC NO. REMARKS

Notes :

Prepared by : : Review/Witness/Approved by : :
Konsorsium Wika Rabana Kelsri PMC/PT Pertamina Gas
QC Representative/QC

Name : Name :

Sign : Sign :

Date : Date :