Daily Site Progress Report Date: 03/10/2020

Saudi Electricity Co. DPR No : #0177


ProjectDepartment-East Temperature: 43°C/29°C
CIVIL & ELECTRO-MECHANICAL PROJECTS Weather: Sunny
Program-East Page:01 to 04

REPLACEMENT OF EXISTING OUTDOOR TCC Date : 31/05/2021


Project title UTHMANIYAH P/P 115KV WITH NEW GIS Contract # 4400012370
SUBSTATION
LARSEN AND TOUBRO SAUDI ARABIA
Contractor Sub-Contractor : ERAM Arabia
LLC
Location and Type of Work :
A. GIS and SWGR
1. Precast Beam and wall panel erection GIS
2. Hollow core slab installation.
B. Control room area
1. Precast beam and slab erection
2. Back filling below the grade Slab.
C. Transmission line
1. Access road and Structure Pad formation.
2. Pile drilling for foundations works.

ACTIVITIES AT SITE

Targe Completion
Sl No Civil Work Status Today Total Remarks
t
01 Precast wall panel erection for On going 3% 6% 9%
GIS Building %)
Shuttering and reinforcement
02 for the Shear Walls 5 Nos (1st On going 20% 40% 60%
and 2nd Lift)
TT slab, H.core,
03 Casting of Precast elements. On going 2% 1.5% 93.0% colums, beams
(stair case and Canopy) completed

04 Tower line access road On going 1% 0.5% 46.5%


structure pad formatiuon
05 Ground floor slab On going 5% 10% 90%
Deshuttering
06 Hollow core slab Erection in On going 20% 20% 20%
SWGR
07 TT slab Erection ACDC and On going 50% 50% 50%
Battery Room.
08 Block work in GIS and SWGR On going 2% 2% 2%
Total structure numbers Vs actual
Sl No Activities Total Qty Previous
Today Completed Balance
Loc # 1-F and
01
Pile Drilling for lattice tower 28 0 1 1 1-G under
foundations # PI – 1F and I G progress

1
TOOLS AND MACHINERY USED FOR TODAY’S WORK
S.No Equipment Nos
01 Shovel 01
02 Dump Trucks 02
03 Dozer 00
04 Excavators 03
05 Bobcat 01
06 Roller 01
07 Grader 01
08 Water tank 01
09 Piling Rig 01

NEXT DAY WORK PLANNED


Sl Work Planned Discipline
nNo
1.0 Precast elements erection in GIS Buiding - Wall
No
Precast elements erection in CR building – Beams
2.0
and TT slab
3.0 De shuttering works in cable basement
4.0 Pile Drilling for TL towers
4.0 Block work on the Ground floor

Sl Designation Sl
No' Status Designation No' Statu
No No
s s s
Manpower: -
01 Project Manager 1 08 Foreman/Supervisor 2 At
Site
02 Site Manager 1 At Site 09 Workers 47 At
Site
Office and
03 Engineers 6 10 Surveyor 1 At
Site
Site
04 Safety officer 2 At Site 11 Driver/EQ operator 2 At
Site
05 Admin officer 1 At Site 12 Steel Fixer 17 At
Site
06 Office secretary 1 At Site 13 Camp watchman At
Site
07 Support staff 1 At Site 14 Site watchmen 1 At Site
15 Flag man 1
16 Scaffolders 6

Total 13 Total 78

2
PROGRESS PHOTOS

Precast wall Panel installation in GIS Shear Wall shuttering in GIS building
outer wall

Block work in GIS and SWGR under Hollow core slab Installation in SWGR
Progress

3
Pile Drilling under Progress for Pile Drilling for PI-IE completed
tower no PI-1F