Beruflich Dokumente
Kultur Dokumente
Ministry of Communications
Roads and Highways Department
VOLUME 2 of 4
CONDITIONS OF CONTRACT
September 2001
CONDITIONS OF CONTRACT
SEPTEMBER 2001
CONDITIONS OF CONTRACT
Table of Clauses
CONDITIONS OF CONTRACT
A. General
1. Definitions 1.1 In the Contract, (as hereinafter defined) the following words
and expressions shall have the meanings hereby assigned
to them, except where the context otherwise requires :
2. Singular and 2.1 Words importing the singular only also include the plural
Plural and vice versa where the context requires.
3. Headings and 3.1 The headings and marginal notes in these Conditions of
Marginal Notes. contract shall not be deemed to be part thereof or be taken
into consideration in the interpretation or construction
thereof or of the contract.
5. Duties and 5.1 All works to be executed under the contract shall be
powers of executed under the direction and subject to the approval in
Superintending all respects of the superintending officer who shall be
Officer entitled to direct at what point or points and in what manner
they are to be commenced and from time to time carried
on. The Superintending Officer is the controlling officer for
the execution of the contract. He is also the controlling
officer of the Engineer and the Engineer is responsible for
his activities to him. For the execution of the work, the
Engineer will seek decisions whenever necessary from the
Superintending Officer and follow the instructions and
decisions of the Superintending Officer as per guidelines
given by the concerned head of the Executing Agency.
6. Duties and 6.1 The Engineer shall carry out such duties in issuing
Powers of decisions, certificates and orders as are specified in the
Engineer contract. The Engineer shall obtain the specific approval of
the Employer in writing before taking any of the following
actions :
a) Certifying additional cost; and
10 Removal of 10.1 If the Engineer asks the contractor to remove a person who
. Contractor’s is a member of his staff or his work force and states his
Personnel reasons the Contractor is to ensure that the person leaves
the Site within seven days and has no further connection
with the work in the contract.
13 Indemnities 13.1 Each party is liable for and indemnifies the other against
. losses, expenses and claims for loss or damage to physical
property, personal injury, and death caused by his own acts
or omissions.
16 No Night or 16.1 No work shall be done during the night or on Friday without
. Friday Work the sanction in writing of the Engineer.
17 Accommodation 17.1 The contractor shall make arrangement at his own cost for
. and welfare of accommodation, sanitation, water supply and medical
labourers facilities for his staff and labour.
18 Safety 18.1 The contractor is responsible for the safety of all activities
. on the Site.
21 Possession of 21.1 The Employer is to give possession of all parts of the Site
. the Site to the Contractor as early as possible. If possession of a
part is not given by the date as per approved program, the
Employer is deemed to have delayed the start of the
relevant activities and this is a Compensation Event in
respect of time.
22 Access to the 22.1 The Contractor shall allow the Engineer and any person
. Site authorised by the Engineer access to the Site and to any
place where work in connection with the Contract is being
carried out or is intended to be carried out.
23 Contract may be 23.1 The Contractor may subcontract with the approval of the
. rescinded and Engineer, but shall not assign the Contract without the
Performance approval of the Employer in writing. Subcontracting shall
Security deposit not alter the Contractor’s obligations. If the Contractor shall
forfeited for assign or subcontract his Contract without required
subcontracting approval as aforesaid, or attempt so to do, or become
without approval, insolvent or commence any insolvency proceedings or
bribing or if make any compositions with his creditors, or attempt so to
Contractor do, or if any bribe, gratuity, gift, loan, perquisite, reward or
becomes advantage, pecuniary or otherwise, shall either directly or
insolvent. indirectly be given, promised, or offered by the Contractor,
or any of his servants or agents to any officer or person of
the Employer in any way relating to his office or
employment, or if any such officer or person shall become
in any way directly or indirectly interested in the Contract,
the Engineer may thereupon by notice in writing rescind the
Contract, and the Performance Security deposit of the
Contractor shall thereupon stand forfeited and be
absolutely at the disposal of Employer, and the same
consequences shall ensue as if the Contract had been
rescinded under Clause 45 of this section and in addition
the Contractor shall not be entitled to recover or be paid for
any work theretofore actually performed under the
Contract.
24 Sum Payable by 24.1 All sums payable by way of compensation under any of
. way of these conditions shall be considered as reasonable
compensation to compensation to be applied to the use of Employer without
be considered as reference to the actual loss or damage sustained, and
reasonable whether or not any damage shall have been sustained.
compensation
without reference
to actual loss.
25. Supply of Plant, 25.1 Except otherwise provided in the Contract Documents, the
Materials and Contractor shall at his own cost supply and provide all the
Labour constructional Plant, Temporary Works, materials for both
Temporary and Permanent Works, labour (including the
supervision thereof), transport to and from the site and in
and about the works, and all other things of every kind
required for the construction, completion and maintenance
of the works.
26. Contractor is 26.1 The contractor shall provide all necessary fencing and
liable for lights at his own cost required to protect the public from
damages arising accident and shall be bound to bear the expenses of
from non- defense of every suit, action or other proceedings at law
provision of that may be brought by any person for injury sustained
lights, fencing owing to neglect of the above precautions and to pay any
etc. damages and cost which may be awarded in any such suit,
action or proceedings.
27. Accident or 27.1 The Employer shall not be liable for or in respect of any
Injury to damages or compensation payable at law in respect of or
workmen in consequence of any accident or injury to any workman or
other person in the employment of the Contractor. The
contractor shall indemnify and keep indemnified the
Employer against all such damages and compensation and
against all claims, demands, proceedings costs, charges,
and expenses whatsoever in respect thereof.
28. Settlement of 28.1 Except where otherwise provided in the Contract all
disputes questions and disputes relating to the meaning of the
specifications, designs, drawings, and instructions of the
Contract and all questions and disputes relating to the
quality of workmanship or materials used on the Works, or
as to any other question, claim, right, matter or thing
whatsoever, in any way arising out of, or relating to, the
Approved by Ministry of Law on 16/2/99 page 7 of 18
CONDITIONS OF CONTRACT
SEPTEMBER 2001
B. Time Control
29 Program 29.1 The Contractor shall submit to the Engineer for his
. approval a detailed program within the period stated in the
Contract Data after the date of signing the Contract
Agreement showing the general methods, arrangements,
order, and timing for all the activities in the works. For good
progress of the work the Engineer may instruct the
contractor to submit revised program from time to time
during execution of the work with a view to covering up the
short fall of progress if any during that period. In the revised
program the Contractor shall take all necessary measures
to complete the Work in time.
29.2 The Engineer’s approval of the program does not alter the
Contractor’s obligations. The Contractor may revise the
program and submit it to the Engineer at any time, which is
to be approved by the Engineer.
30 Extension of 30.1 If the contractor shall desire an extension of the time for
. time completion of Works on the grounds of his having been
unavoidable hindered in its execution, the Contractor shall
give an immediate report of such hindrance to the Engineer
in writing and if he shall desire an extension of time for
completion of the Works on the ground thereof he shall
apply in writing to the Engineer within 10 days of the date
Approved by Ministry of Law on 16/2/99 page 8 of 18
CONDITIONS OF CONTRACT
SEPTEMBER 2001
31. Extension of 31.1 The period for the completion of the work shall be extended
time in in the proportion that the altered, additional or substituted
consequence of work bears to the original Contract Works, and the
alterations certificate of the Engineer shall be conclusive as to such
proportion.
32 Delays Ordered 32.1 The Engineer may instruct the Contractor to delay the start
. by the Engineer or progress of any activity within the works.
33 Management 33.1 Either the Engineer or the Contractor may require the other
. Meetings to attend a management meeting. The business of a
management meeting shall be to review the plans for
remaining work and to deal with other matters related to
Works.
34 Early Warning 34.1 The Contractor shall warn the Engineer at the earliest
opportunity of specific likely future events or circumstances
that may adversely affect the quality of the work, increase
the Contract Price or delay the execution of the Works. The
Engineer may require the Contractor to provide an estimate
of the expected effect of the future event or circumstance
on the Contract Price and Completion Date. The estimate
shall be provided by the Contractor as soon as reasonably
possible.
C. Quality Control
37 Action where no 37.1 In the case of any class of work for which there is no
. specification specification, such work shall be carried out in accordance
with the specification of the Executing Agency, for the time
being in force in the area where the Work is located and in
the event of there being no specification of the Executing
Agency, in such case the work shall be carried out in all
respects in accordance with the instructions and
requirements of the Engineer.
38 Works to be 38.1 The Contractor shall execute the whole and every part of
. executed in the works in the most substantial and workman like manner
accordance with and both as regards materials and otherwise in every
specifications, respect in strict accordance with the specifications. The
drawings, Contractor shall also conform exactly, fully and faithfully to
orders, etc. the designs, drawings and instructions in writing relating to
Works signed by the Engineer and lodged in his office and
which the Contractor shall be entitled to have access at
such office or on the site of the work for the purpose of
inspection during office hours and the Contractor shall if he
so requires, be entitled at his own expense to make or
cause to be made copies of the specifications, and of all
such designs, drawing and instructions as aforesaid.
40. Notice to be 40.1 The Contractor shall give not less than five days’ notice in
given before writing to the Engineer or his representative in charge of
work is covered the work before covering up or otherwise placing beyond
up. the reach of measurement any work in order that the same
may be measured, and correct dimensions thereof be
taken before the same is so covered up or placed beyond
the reach of measurement and shall not cover up or place
beyond reach of measurement any work without the
consent in writing of the Engineer or his representative in
charge of the work and if any work shall be covered up or
place beyond the reach of measurement without such
notice having been given or consent obtained, the same
shall be uncovered at the Contractor’s expense, or in
default thereof no payment or allowance shall be made for
such work or the materials with which the same was
executed.
41. Correction of 41.1 In these conditions the expression “Defects Liability Period”
defects in shall mean the period stipulated in the Contract Data and
“Defects be calculated from the date of completion of the Works,
Liability Period” certified by the Engineer in accordance with Clause 60 of
this section.
41.3 All such work shall be carried out by the Contractor at his
own expense if the necessity thereof shall, in the opinion of
the Engineer be due to the use of materials or
workmanship not in accordance with the Contract or to
neglect or failure on the part of the Contractor to comply
with any obligation, expressed or implied, on the
Contractor’s part under the Contract.
D. Cost Control
42 Bill of 42.1 The Bill of Quantities shall contain items for the
. Quantities construction, installation, testing, and commissioning work
to be done by the Contractor.
44 Compensation 44.1 The time allowed for carrying out the Works as entered in
. for delay the Tender shall be strictly observed by the Contractor and
shall be reckoned from the date on which the notice to
commence the Work is given to the Contractor. The Works
shall throughout the stipulated period of the Contract be
proceeded with all due diligence (time being deemed to be
of the essence of the Contract, on the part of the
Contractor) and the Contractor shall pay as compensation
an amount equal to the amount stated in the Contract Data
for every day that the work remains uncommenced or
Approved by Ministry of Law on 16/2/99 page 12 of 18
CONDITIONS OF CONTRACT
SEPTEMBER 2001
45 Action when 45.1 In any case in which under any clause or clauses of this
. whole of Contract the Contractor shall have rendered himself liable
Performance to pay compensation amounting to the whole of his
Security Deposit Performance Security deposit, the Engineer on behalf of
to be forfeited. the Employer shall have power to adopt any of the
following courses, as he may deem best suited to the
interest of Employer:
46 Powers to take 46.1 In any case in which the powers conferred upon the
. possession of Engineer by Clause 45 hereof shall have become
or require exercisable and the same shall not have been exercised,
removal of or the non-exercise thereof shall not constitute a waiver of any
sell Contractor’s of the conditions hereof and such powers shall
Plant. notwithstanding be exercisable in the event of any future
case of default by the Contractor for which by any Clause
or Clauses hereof he is declared liable to pay
compensation amounting to the whole of his Performance
Security deposit, and the liability of the Contractor for past
and future compensation shall remain unaffected. In the
event of the Engineer putting in force either of the powers
(a) or (c) vested in him under the preceding Clause he
may, if he so desires, take possession of all or any tools,
plant, materials and stores, in or upon the Works, or the
site thereof belonging to the Contractor, or procured by him
and intended to be used for the execution of the Work or
any part thereof, paying or allowing for the same in account
at the contract rates or in case of these not being
applicable, at current market rates to be certified by the
Engineer whose certificate thereof shall be final; otherwise
the Engineer may by notice in writing to the Contractor or
his clerk of the Works, foreman or other authorized agent
require him to remove such tools, plant, materials or stores
from the premises (within a time to be specified in such
notice); and in the event of the Contractor failing to comply
with any such requisition, the Engineer may remove them
at the Contractor’s expense or sell them by auction or
private sale on account of the Contractor and at his risk in
all respects, and the certificate of the Engineer as to the
expense of any such removal and the amount of the
proceeds and expense of any such sale be final and
conclusive against the Contractor.
47 Alterations in 47.1 The Engineer shall have power to make any alterations in,
. specifications omissions from, addition to or substitution for, the original
and designs do specifications, drawings, designs, and instructions that may
not invalidate appear to him to be necessary or advisable during the
Contract. progress of the Works and the Contractor shall be bound to
carry out the Works in accordance with any instructions
which may be given to him in writing signed by the
Engineer and such alterations, omissions, additions or
substitutions shall not invalidate the Contract and any
altered, additional or substituted work which the Contractor
may be directed to do in the manner above specified as
part of the work shall be carried out by the Contractor on
same condition in all respect on which he agreed to do
main Works and at the same rates as are specified in the
Tender for the main work.
48 Rates for works 48.1 If the altered, additional or substituted work includes any
. not contained in items of work, for which no rates are specified in the
the tender Contract, then such items of work shall be carried out at the
rates entered in the Schedule of Rates of the Executing
Agency on the date 28 days prior to the latest date for
submission of Tender applicable for the area where the
Work is located and if the rates of the altered, additional or
substituted work are not entered in the said Schedule of
Rates, then the Contractor after receipt of the order from
the Engineer to carry out the work shall submit to the
Engineer the rates which it is his intention to charge for
such items of work. The Employer shall not be bound to
accept the rates submitted by the Contractor and reserves
the right to fix new rates if the rates submitted by the
Contractor are not reasonable in the opinion of the
Employer. The decision of the Employer in this respect is
final and binding upon the Contractor.
49. No 49.1 If at any time after the commencement of the Works the
compensation Employer shall for any reason whatsoever not require the
for alteration in whole Works as specified in the Tender to be carried out,
or restriction of the Engineer shall give notice in writing of the fact to the
work to be Contractor who shall have no claim to any payment or
carried out compensation whatsoever on account of any profit or
advantage which he might have derived from execution of
the work in full, but which he did not derive in consequence
of the full amount of the work not having been carried out,
neither shall he have any claim or compensation by reason
of any alteration having been made in the original
specifications, drawings, designs, and instructions which
shall involve any curtailment of the work as originally
contemplated.
50 Price 50.1 Prices shall be adjusted for fluctuations in the cost of inputs
. Adjustment only if provided for in the Contract Data.
51 Foreign 51.1 The prices tendered by the Contractor shall include all
. Taxation taxes, duties, and other charges imposed outside the
Employer’s country on the production, manufacture, sale,
and transport of the Contractor’s Equipment, Plant,
materials, and supplies to be used on or furnished under
the Contract, and on the services performed under the
Contract.
52 Local Taxation 52.1 The prices tendered by the Contractor shall include all
. customs duties, import duties and taxes (income taxes,
Value added taxes and other taxes) that may be levied in
accordance with the laws and regulations in force on the
date 28 days prior to the latest date for submission of
tenders in the Employer’s country on the Contractor’s
Equipment, Plant, materials and supplies (permanent,
temporary and consumable) acquired for the purpose of the
Contract and on the services performed under the
Contract. Nothing in the Contract shall relieve the
Contractor from his responsibility to pay any tax that may
be levied in the Employer’s country on profits made by him
in respect of the Contract.
55 Interim Payment 55.1 The Contractor is entitled to receive interim payment upon
. submission of the payment certificates for the executed
works approved and passed by the Engineer whose
certificate of such approval and passing of the sum so
payable shall be final and conclusive against the
Contractor. But all such interim payments shall be regarded
as payment by way of advance against the final payment
only and not as payments for work actually done and
completed, and shall not preclude the requiring of bad,
unsound and imperfect or unskillful work to be removed
and taken away and reconstructed or re-erected or be
considered as an admission of the due of performance of
the Contract or any part thereof, in any respect, or the
accruing of any claim, nor shall it conclude, determine or
affect in any way the powers of the Engineer under these
conditions or any of them as to the final settlement and
Approved by Ministry of Law on 16/2/99 page 16 of 18
CONDITIONS OF CONTRACT
SEPTEMBER 2001
58 Retention 58.1 The Employer shall retain 10 percent from first and
. following interim payment certificates until such time as the
cumulative total of such retention ( hereinafter referred to
as “Retention Money” ) shall amount to 5 percent of the
Contract Price named in the Letter of Acceptance. Upon
issue of the completion certificate with respect to the whole
of the Works, one half of the Retention Money shall be
certified by the Engineer for payment to the Contractor.
Upon certification of the Defects Liability period for the
Works the other half of the Retention Money shall be
certified by the Engineer for payment to the Contractor.
59 Payment of 59. 1 The Contractor will pay his labour at reasonable rate in
. Labour time. In case of delaying for making payment the Employer
may make the requisite payment as would have been paid
by the Contractor and recover the cost from the Contractor.
61 Taking Over 61.1 The Employer shall take over the Site and the Works within
. seven days of the Engineer’s issuing a Certificate of
Completion.
62 Final Payment 62.1 The Contractor shall supply the Engineer through Final
. Certificate Payment Certificate a detailed account of the total amount
that the Contractor considers payable under the Contract
before the end of the Defects Liability Period. If the Final
Payment Certificate submitted by the Contractor is incorrect
or incomplete the Engineer shall make necessary corrections
which shall be binding upon the Contractor. The Engineer
shall certify any final payment that is due to the Contractor
after the issue of Defects Liability Certificate.
63. Property 63.1 All Materials on the Site, Plant, Equipment, Temporary
Works, and Works shall be deemed to be the property of the
Employer if the Contract is terminated because of the
Contractor’s default.
64. Termination 64.1 The Employer may terminate the Contract at his
convenience.
65. Frustration 65.1 If the Contract is frustrated by the outbreak of war or by any
other event entirely outside the control of either the Employer
or the Contractor the Engineer is to certify that the Contract
has been frustrated. The Contractor is to make the site safe
and stop work as quickly as possible after receiving this
certificate and is to be paid for all work carried out before
receiving it and for any work carried out afterwards to which
he was committed.