Beruflich Dokumente
Kultur Dokumente
CT37002
Project Name:
Nishat
Brahmbhatt’s
Bungalow
Submitted by
By group 6
Hardi Shah – UC6216
Harshil Shah – UC6316
Khushi Shah – UC6416
Parth Shah – UC4517
GROUP-6 Page |1
Introduction to BIM-CT37002
INDEX
1 INTRODUCTION TO BIM: ...................................................................................................................................... 4
WHAT IS BIM? ........................................................................................................................................................ 4
WHAT IS BIM USED FOR? .......................................................................................................................................... 4
WHAT IS THE PROCESS OF BIM? ................................................................................................................................. 4
IMPORTANCE OF BIM: .............................................................................................................................................. 4
2 INTRODUCTION TO THE PROJECT: ........................................................................................................................ 5
BASIC DETAILS: ........................................................................................................................................................ 5
PROJECT DURATION:................................................................................................................................................. 5
AREA DETAILS.......................................................................................................................................................... 5
3 ARCHITECTURAL PLANS ........................................................................................................................................ 6
GROUND FLOOR PLAN ............................................................................................................................................... 6
FIRST FLOOR PLANS ................................................................................................................................................... 7
TERRACE PLAN ......................................................................................................................................................... 8
4 SECTIONS ............................................................................................................................................................. 9
SECTION A-A........................................................................................................................................................... 9
SECTION B-B ......................................................................................................................................................... 10
SECTION C-C ......................................................................................................................................................... 10
SECTION D-D ........................................................................................................................................................ 11
5 ELEVATIONS ........................................................................................................................................................12
FRONT ELEVATION .................................................................................................................................................. 12
RIGHT SIDE ELEVATION ............................................................................................................................................ 12
BACKSIDE ELEVATION .............................................................................................................................................. 13
6 COST DETAILS ......................................................................................................................................................14
7 BIM SCOPE OF STUDY: .........................................................................................................................................15
8 BIM METHODOLOGY ...........................................................................................................................................16
SCOPE OF WORK: ................................................................................................................................................... 16
9 WHAT IS LOD AND LOS ........................................................................................................................................16
LOD VS LOS ......................................................................................................................................................... 18
WHY IS LOD VS LOS REQUIRED? ......................................................................................................................... 29
10 3D MODELING PROCESS ......................................................................................................................................29
ARCHITECTURAL MODELING...................................................................................................................................... 29
STRUCTURAL MODELING .......................................................................................................................................... 29
11 QUANTITY TAKE OFF ...........................................................................................................................................29
CREATING QUANTITY OR MATERIAL TAKE-OFF SCHEDULES ............................................................................................ 29
SCHEMATIC DESIGN COST ESTIMATES ......................................................................................................................... 30
DETAIL DESIGN COST ESTIMATES ............................................................................................................................... 30
12 COMPARISON OF MANUAL VS BIM QUANTITIES .................................................................................................31
13 CLASH DETECTION ...............................................................................................................................................34
WHAT IS CLASH DETECTION? ................................................................................................................................... 34
TYPES OF CLASHES .................................................................................................................................................. 34
PROCEDURE .......................................................................................................................................................... 35
GROUP-6 Page |2
Introduction to BIM-CT37002
14 4D SIMULATION ..................................................................................................................................................35
BRIEF OF 4D ......................................................................................................................................................... 35
PROCEDURE .......................................................................................................................................................... 35
15 FINAL INFERENCES...............................................................................................................................................36
16 CONCLUSION .......................................................................................................................................................36
17 REFERENCES: .......................................................................................................................................................37
Table Index
Table - 1 Area details ........................................................................................................................................... 5
Table - 3 BIM Methodology ............................................................................................................................... 16
Table - 2 LOD vs LOS .......................................................................................................................................... 28
Figure Index
Figure 1 Process of BIM ....................................................................................................................................... 4
Figure 2 Ground Floor plan.................................................................................................................................. 6
Figure 3 First Floor plan ....................................................................................................................................... 7
Figure 4 terrace floor plan ................................................................................................................................... 8
Figure 5 Section A-A ............................................................................................................................................ 9
Figure 6 Section B-B........................................................................................................................................... 10
Figure 7 Section C-C ........................................................................................................................................... 10
Figure 8 Section D-D .......................................................................................................................................... 11
Figure 9 Front Elevation ................................................................................................................................... 12
Figure 10 Right Elevation ................................................................................................................................... 12
Figure 11 backside elevation ............................................................................................................................. 13
Figure 12 Cost Analysis ...................................................................................................................................... 15
Figure 13 LOD Details ........................................................................................................................................ 17
Figure 14 Quantity schedules ............................................................................................................................ 29
Figure 15 Types of Clashes ................................................................................................................................ 34
Figure 16 Clash detection .................................................................................................................................. 35
GROUP-6 Page |3
Introduction to BIM-CT37002
1 Introduction to BIM:
What is BIM?
Building Information Modeling (BIM) is an intelligent 3D model-based process that gives
architecture, engineering, and construction (AEC) professionals the insight and tools to more
efficiently plan, design, construct, and manage buildings and infrastructure. 1
What is BIM used for?
BIM is used to design and document building and infrastructure designs. Every detail of a building is
modeled in BIM. The model can be used for analysis to explore design options and to create
visualizations that help stakeholders understand what the building will look like before it’s built. The
model is then used to generate the design documentation for construction. 1
Importance of BIM:
1
There are five significant benefits of BIM in the design and construction process:
1. Cost and resource savings
2. Greater efficiency and shorter project lifecycles
3. Improved communications and coordination
4. More opportunities for prefabrication and modular construction
5. Higher quality results
1 https://www.autodesk.in/solutions/bim
GROUP-6 Page |4
Introduction to BIM-CT37002
Project Duration:
Start Date: August 2017
End Date: January 2018
Area Details
FLOOR BUILT-UP AREA (Sq.m)
GROUP-6 Page |5
Introduction to BIM-CT37002
3 Architectural Plans
Ground floor Plan
GROUP-6 Page |6
Introduction to BIM-CT37002
GROUP-6 Page |7
Introduction to BIM-CT37002
Terrace plan
GROUP-6 Page |8
Introduction to BIM-CT37002
4 Sections
Section A-A
GROUP-6 Page |9
Introduction to BIM-CT37002
Section B-B
Section C-C
GROUP-6 P a g e | 10
Introduction to BIM-CT37002
Section D-D
GROUP-6 P a g e | 11
Introduction to BIM-CT37002
5 Elevations
Front elevation
GROUP-6 P a g e | 12
Introduction to BIM-CT37002
Backside elevation
GROUP-6 P a g e | 13
Introduction to BIM-CT37002
6 Cost Details
No ITEM Cost (Rs.)
1 Earthwork 35490.16
2 Masonry 742495.71
3 Concrete 1784012.63
4 Formwork 423846.79
5 Reinforcement 1001441.68
7 Flooring 759280.18
10 Miscellaneous 94348.74
11 Fabrication 51068.92
Total 6349489.71
TOTAL 76,82,882.55
= 77 lakhs approx..
Built Plot Area: GF (m2) 119.57
Up
Area Plot Area: FF (m2) 122.07
Cost/m2 24308.30
GROUP-6 P a g e | 14
Introduction to BIM-CT37002
Cost Analysis
Fabrication
Miscellaneous
Door, window and ventilator
Flooring
Wall finishes
Reinforcement
Formwork
Concrete
Masonry
Earthwork
GROUP-6 P a g e | 15
Introduction to BIM-CT37002
8 BIM Methodology
Table - 2 BIM Methodology
architectural and
Selection of site for the Starting the 3D model
structural modeling is
course process of the site
done in the Revit
Structural and
Working out the bill of Assigning relevant levels archietctural models are
quantities for the site of LOD appended in Navisworks
for clash detection
Forming a detailed
Preparing the schedule worked breakdown Clash detection report is
for the site structure from the generated.
drawings
Scope of Work:
• Architectural modeling
• Structural modeling
• Material detailing
• Doors and windows detailing
• Schedule of the project
The LOD Framework addresses various issues faced by professionals by providing an industry-developed
standard to describe the state of development of various systems within a BIM. This standard enables
consistency in communication and execution by facilitating the detailed definition of BIM milestones and
deliverables.
GROUP-6 P a g e | 16
Introduction to BIM-CT37002
• Concept Design
• A conceptual model where parameters like area, height, volume, location and
LOD 100 orientation are defined.
• Schematic Design
• A general model where elements are modeled with approximate quantities, size,
shape, location and orientation. Non-geometric elements can be embedded
LOD 200 with model elements at LOD 200.
• Detailed Design
• Accurate modeling and shop drawings where elements are defined with specific
assemblies, precise quantity, size, shape, location and orientation. Non-
LOD 300 geometric elements can be embedded with model elements at LOD 300.
• Construction Documentation
• It includes more detail and elements that represent building elements interface
with various building systems and other elements with clear graphics and
LOD 350 written definitions.
• As-Built
• Elements are modeled as constructed assemblies for operations and
maintenance. In addition to actual and accurate in size, shape, location, quantity
LOD 500 and orientation, non-geometric elements can be embedded with model
elements at LOD 500.
GROUP-6 P a g e | 17
Introduction to BIM-CT37002
LOD Vs LOS
WBS Task Name Project Phase Description LOD Levels Give Target Reference
Level LOD LOD Drawing
no
100 200 300 350 400 500
Bungalow Project
1
1.1 Pre Construction ✓
1.1.1 Permissions
1.1.1.1 Land Approval from Conceiving received ✓ ✓ ✓ ✓ ✓ 500
Government stage
1.1.1.2 Approval from Conceiving received ✓ ✓ ✓ ✓ ✓ 500
Municipality stage
1.1.2 Designing 500
1.1.2.1 Drawing of site as Development received ✓ ✓ ✓ ✓ ✓ 500
per Client need stage
1.1.2.2 Approval of plans Development received ✓ ✓ ✓ ✓ ✓ 500
from Client stage
1.1.2.3 Drawing as per Development received ✓ ✓ ✓ ✓ ✓ 500
Structural Engineer stage
1.1.2.4 Approval of Development received ✓ ✓ ✓ ✓ ✓ 500
Foundation drawings stage
by Structural
Engineer
1.1.3 Site Preparation 500
1.1.3.1 Clearance of Land Development received ✓ ✓ ✓ ✓ ✓ 500
stage
1.1.3.2 Surveying of Land Development received ✓ ✓ ✓ ✓ ✓ 500
and Soil stage
1.1.3.3 Mapping and line Development received ✓ ✓ ✓ ✓ ✓ 500
out of Land stage
1.1.3.4Material Development received ✓ ✓ ✓ ✓ ✓ 500
Procurement stage
1.2 Sub Structure 500
1.2.1 Lineout for Implementation ✓ ✓ ✓ ✓ ✓ 500
Excavation
1.2.2 Excavation for Implementation ✓ ✓ ✓ ✓ ✓ 500
Foundation
1.2.3 Footings
1.2.3.1 Excavation of at depth of 1500 mm - ✓ ✓ ✓ ✓ ✓ 500 Foundation
footings plan R0
F1 - 1680 * 2060
model
F2 - 1900 * 2210
F3 - 2120 *2440
F4 - 2290 * 2510
F5 - 2060 * 2440
RF1 -
`
GROUP-6 P a g e | 18
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 19
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 20
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 21
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 22
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 23
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 24
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 26
Introduction to BIM-CT37002
scaffolding.
Second coat of Implementation 20 mm thick mala plaster in two coat with first ✓ ✓ ✓ ✓ ✓ 500
external plaster coat of 12 mm in mortar ratio (1:4) and second
coat of 8 mm in mortar ratio (1:3) including
making keys for second layer after first coat is
done finishing with cement slurry, curing,
scaffolding.
FLOORING Implementation ✓ ✓ ✓ ✓ ✓ 500
Flooring and skirting Implementation 75mm skirting in neat cement paste including ✓ ✓ ✓ ✓ ✓ 500
on ground floor joint filling, with appropriate coloured cement,
cutting, cleaning.
Dado on wall of Implementation Dado till specified height in bathroom in neat ✓ ✓ ✓ ✓ ✓ 500
ground floor cement paste including joint filling, with
bathrooms appropriate coloured cement, cutting, cleaning.
Flooring and skirting Implementation 75mm skirting in neat cement paste including ✓ ✓ ✓ ✓ ✓ 500
on first floor joint filling, with appropriate coloured cement,
cutting, cleaning.
dedo on wall of First Implementation Dado till specified height in bathroom in neat ✓ ✓ ✓ ✓ ✓ 500
floor bathrooms cement paste including joint filling, with
appropriate coloured cement, cutting, cleaning.
Flooring and skirting Implementation 75mm skirting in neat cement paste including ✓ ✓ ✓ ✓ ✓ 500
in stair cabin joint filling, with appropriate coloured cement,
cutting, cleaning.
China mosaic on Implementation ✓ ✓ ✓ ✓ ✓ 500
terrace
PAINTING Implementation ✓ ✓ ✓ ✓ ✓ 500
Internal painting Implementation Double coat plastic paint on newly plastered ✓ ✓ ✓ ✓ ✓ 500
surface, on the interior part of structure including
finishing.
external painting Implementation Double coat plastic paint on newly plastered ✓ ✓ ✓ ✓ ✓ 500
surface, on the exterior part of structure
including finishing.
FINISHING WORK Implementation ✓ ✓ ✓ ✓ ✓ 500
Fixing of doors Implementation ✓ ✓ ✓ ✓ ✓ 500
D Implementation Size - 2440 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D1 Implementation Size - 1750 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D2 Implementation Size - 1680 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D3 Implementation Size - 1600 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D4 Implementation Size - 1370 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D5 Implementation Size - 1220 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D6 Implementation Size - 1070 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D7 Implementation Size - 910 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
D8 Implementation Size - 840 * 2130 mm ✓ ✓ ✓ ✓ ✓ 500
`
GROUP-6 P a g e | 27
Introduction to BIM-CT37002
`
GROUP-6 P a g e | 28
Project-CT3002
LOD vs LOS gives us a brief idea as to what type of details are required at what time of the process giving us
a clear heads up for gathering all the required data for further activities.
10 3D modeling Process
Architectural modeling
Structural modeling
2 https://www.modelical.com/en/gdocs/quantity-takeoff/
GROUP-6 P a g e | 29
Introduction to BIM-CT37002
Cost analysis is most beneficial in the early design stages of a project, when design decisions have the less
impact on the project and they are easier to implement. For this reason, cost estimates based on the area or
volume of a proposed conceptual design and comparison to historical data for facilities with similar functions
and programming are especially valuable for confirming that the design is accurate and in accordance with
the owner’s proposed project budget.
GROUP-6 P a g e | 30
Project-CT3002
GROUP-6 P a g e | 31
Introduction to BIM-CT37002
GROUP-6 P a g e | 32
Introduction to BIM-CT37002
There have been certain design changes made for the purpose of modeling.
1) Instead of trapezoidal footing, isolated footing in modeling are done.
2) The thickness of slab has been changed from 75 mm to 125mm
3) The type of windows is changed and is as available in revit family.
GROUP-6 P a g e | 33
Project-CT3002
13 Clash detection
“Clash Detection” is about playing a “Detective” role and finding out clashes among trades in the virtual
building design model. Any building design comprises mainly five trades/disciplines—Architectural,
Structural, Mechanical, Electrical, and Plumbing.
All the building systems have to function in-sync to achieve performance and functional expectations in
terms of energy efficiency, sustainability, operational efficiency, etc. A BIM coordinator makes sure that
there are no clashes between any building disciplines and virtual building design is ready for construction.
Clash detection will only come into the picture when all the building design trades (Architectural, Structural,
Mechanical, Electrical, Plumbing, Fire Protection, and others) are integrated into the BIM model.
Types of Clashes
A conflict occurs when the elements of different MEPFP or other trades occupy the same space. This conflict
can be geometrical (for example, HVAC crossing through structural beam), schedule-based (when the
sequence of work is not as per the schedule or multiple things take place at once), or the changes are not
updated in the drawings.
Autodesk Navisworks acts as a model aggregator as it brings together 3D models and associated design data
into a single working environment for the purpose of design review, coordination analysis, simulation of the
model, and presentation.
There are many specialized tools in Navisworks such as Clash Detective, TimeLiner, Animator, etc. It allows
an interactive review of the virtual project model in order to validate the design and provide accurate
predictions for construction and operations.
GROUP-6 P a g e | 34
Introduction to BIM-CT37002
Procedure
14 4D Simulation
Brief of 4D
4D simulations for construction planning and scheduling for architects, contractors, engineers and designers
helps visualize construction sequences and assess onsite and offsite progress across project lifetime.
4D construction simulation models enhance the collaboration between project teams and clients; ultimately
providing clear project milestones and improved construction plans.
It focusses on importing schedules into Autodesk Navisworks and assigning elements to tasks, allowing you
to simulate the building construction over time. This is really useful to visualize the construction process in
steps.
Procedure
Detailed procedure is mentioned in the PPT.
GROUP-6 P a g e | 35
Introduction to BIM-CT37002
15 Final Inferences
The final inference can be concluded in 4 different parts:
1) Architectural Modeling:
- With the development of modern advanced technologies, current architectural models can be
fabricated in less time and have a higher level of detail. The architectural model helps clients and
investors to imagine how the design looks like in reality by visualizing the 2D drawings or 3D digital
models.
- Making architectural models is an effective and efficient way to help the architect and the client to
communicate.
- Modifications to the design can be made before the building is taking place to ensure desired
results.
2) Structural Modeling: this providing the physical and the analytical model of the structure. The
physical model can be used for construction documentation, shop drawings and fabrication.
- This also helps the execution team in better execution as the drawings become even more clear and
there is no communication problems.
- Design determines the feasibility of the structural concept and is a milestone in the planning
process. Without proper design, other services could be delayed.
3) Quantity take off: this helps in estiating a detaiked material requirement as well as cost estimation
for the project.
4) Clash detection: Clash Detection helps us to identify, review and report clashes from the 3D BIM
Model which is created by combining a model of different disciplines in a shared single BIM Model.
At the initial stage if clashes are detected and resolved can minimize cost, effort and time.
16 Conclusion
- This subject gave us an incredible opportunity to understand how architectural and structural
modelling can be done in a single user space.
- It also helped us thoroughly understand the importance of BIM and the entire process associated
with it.
- We also learned how to solve the discrepancies beforehand in the architectural and structural model
which is often observed on site during execution.
- While working on the 3D model of the project and highlighting the joinery details, we realised how
each minute mm of deflections results in the overall significant deviation of the building.
- BIM overall, helped us understand the importance of working on a single platform and how better
communications and effective use of technology can help minimize the challenges faced in everyday
task during the construction.
GROUP-6 P a g e | 36
Introduction to BIM-CT37002
17 References:
1
https://www.autodesk.in/solutions/bim
1
https://www.modelical.com/en/gdocs/quantity-takeoff/
GROUP-6 P a g e | 37