Beruflich Dokumente
Kultur Dokumente
To define the instructions for everyone when carrying out removal, pipe repair, pipe
fabrication, pipe renewal and installation of various pipes including line tests and hydraulic
line tests.
2 SCOPE
This Specific Procedure applies to but is not limited to the following pipe systems: -
3 DEFINITIONS I ABBREVIATIONS
3.1 Repair - Pipe repair includes, but is not limited to the followings:-
a) Complete Renewal
b) Partial Renewal
d) Pitting Repair
h) Pipe Turning
j) Pressure Test
3.2 Ferrous Metal Pipe includes, but is not limited to the following types of
pipes:
3.3 Non-Ferrous Metal Pipe includes, but is not limited to the following types
of pipes:
a) Aluminum Brass
b) Copper Nickel
3.4 Non-Metal Pipe includes, but is not limited to the following types of
pipes:
a) GRP
b) PVC I CPVC
c) Polyurethane
The Head, Piping and valve shall be responsible for the establishment, implementation
and maintenance of this instruction.
5 REFERENCES
6.1 Work scope shall be clearly confirmed by the Ship Owner's Authorized
Representative.
6.2 Permit to Work (PTW) shall be applied for and work activities highlighted
during the VSCC meeting.
6.3 The vessel's duty Engineer or Officer in-charge shall be duly informed and
permission granted prior to the commencement of the work.
6.4 Lockout and TagOut (LOTO) procedure shall be carried out on the hydraulic
/pneumatic system.
6.5 Workers shall be briefed on the works cope and procedure during the Toolbox
briefing; prior to the commencement of the work.
6.7 Safe access and sufficient lighting shall be provided to carry out the work.
6.8 Personal Protective Equipment (PPE) and Safety Equipment shall be used at all
times.
6.9 All tools used to carry out the work activities shall be appropriate for the
work, in good working condition and of the correct size.
6.10 For lifting & rigging safety precaution, please refer to:-
7.2.3 Communication,
6.11 Any related hot work activities refer to 'Hot Work ' Safety Precaution
Guideline, Specific Procedure, and Doc. No. MMHE/SP/MBU/H/25.
7 PROCEDURE
Valve in Confined Space" form is to be duly completed and the Safety Section
shall be advised accordingly . All procedures for confined space entry shall be complied with.
7.1.2 If removal of piping requires hot work to be carried out, a Hot Work
Certificate shall be duly applied for, especially when working in the vicinity of
hydrocarbons.
7.1.3 Ensure that all cutting and welding tools I equipment are in a good
condition and with a valid certificate.
7.1.4 All spills from pipes during removal shall be immediately cleaned up;
to avoid combustion , slippages of personnel or allowing a hazardous situation to develop.
7.1.5 All required openings and/or if removed pipes contain oily residue
shall be blanked accordingly with the appropriate blank material prior to transportation to the
workshop
a) Hot work shall as far as possible be avoided for the safe removal of
pipes.
e) Prior taking out the existing pipe, all dimensions of pipe spools
and between langes shall be recorded.
Fla nge ( a) Flange (b)
-----------g
·- :i
Existi ng Spool
site- -·
Dimension (t ) means the measurement between flange (a) and (b) that to be taken in four
(4) places at the top, left, bottom and right as marked with e1, e2 , e3 and e4 respectively.
f)The gap between flanges (without gasket) shall be taken and recorded for
future reference.
-----1 ---------
JI G2
Gap (G) means the dimensions between two t1bnges that shall be taken in four (4)
g) All overboard pipe shall be properly blanked once the pipe is taken out from its position in
order to avoid any item (e.g.: blasting grit) from outside flying into the engine room and hit
the workers who is working near the overboard area and also to avoid the engine room from
being contaminated.
7.2.1.2
All new pipe materials and fittings shall be checked
and verified to be as per the Mill Certificates and
Specifications. Prepare the Incoming Material
Inspection Record.
7.2.2.1 All pipes shall be cut to size as per the pipe piece plan.
7.2.2.3
7.2.2.4 7.2.2.5
7.2.2.6
Dissimilar type of material shall be separate
during al phase of construction to avoid any direct
contacts to prevent corrosion.
7.2.2.10 In the event that the pipe requires bending, the pipe shall be
sent to the pipe bending section.
7.2.2.11 The accuracy of the pipe fittings shall be carried out and
verified as per the MMHEP iping Yard Standard .
7.2.3.2
7.2.3.4
7.2.3.3
7.2.4 Welding
For Carbon Steel pipe Steel/CuNi. All sizes shall be cut mechanically
below 2" shall be using carbon free cutting disc. Plasma cutters are
mechanically cut and for not allowed to be used for cutting these materials.
larger pipe may be cut with
flame cutter. The surface to be welded shall be bevel in
accordance with the WPS and shall grounded
For Stainless Steel/Duplex smooth.
7.2.4.3
7.2.4.4
7.2.4.5
7.2.4.6
Refer to Document No: heating. The use of OXY-Acetylene is prohibited.
Welder/Welding Operator lnterpass temperatures are to be monitored and
Qualification Test maintained as per section 3.0 Reference
Procedure and
Performance Control Prior to start of welding, the welder shall write his
MMHE/SP/MBU/W/01. welder's number adjacent to the joint with marker.
7.2.5.1 In the event that an NOT is required to be carried out on a pipe, a request I
application shall be prepared and submitted for the NOT to be carried out on a particular
pipe.
7.2.5.2
Upon completion of the NOT, a report on the
results of the NOT shall be provided by the
person-in-charge of the NDT.
Note 2:
7.2.6
An NOT shall be Classification Society or as stipulated under the
carried out only if specifications, or as directed by the Client's Rep.
required by the
vessel's Post Weld Heat Treatment (PWHT)
7.2.6.1
PWHT shall be carried out in accordance to
approved procedure. Refer to Document No: Post
Weld Heat Treatment MMHE/SP/MBU/W/02.
7.2.6.2
7.2.7.2
The line test shall be in conjunction with
section 7.7 Line Test and the form Line or
Leak Testing Report (Acceptance Test).
MMHE/SP/MBU/QA/02 - Appendix Ill - ITP Piping
Work
7.3.1 After a pipe has been fabricated, the treatment shall be carried out as
per Owner's requirements. The handling prior to and after the treatment shall be as follows:
7.3.1.1
Pipe for blasting and painting (ferrous metal pipes):
(iv) specified below, but damaged parts shall be touched up with an approved cold
galvanizing.
i.
Sleeve welding joint
ii. iii. fabricated onboard .
Flange of adjusted
onboard pipes.
Reinstatement Procedure
7.4.1 Ensure that the temporary supports are able to take on the total
load of the pipes.
7.4.5 Always roll pipes from the ends or from behind in order to be in
the clear position if pipe gets out of control during movement.
7.4.6
The span of the pipe supports should be pre-adjusted to
suit the length of pipes. Refer MMHE Piping Yard Standard.
7.4.7 All temporary pipe supports shall be removed after all permanent supports are in
place. Area shall ground flush and NDT shall be performed in accordance with NDT plan.
7.5.1 Upon completion of pipe repair, joint inspection with the Owner's
representative is to be carried out, documented and acknowledged. MMHE/SP/MBU/QA/02 -
Appendix 111 - ITP Piping Work.
7.5.4 Ensure that all cutting and welding tools I equipment are in a good
condition and with a valid certificate.
c) In the event the original bolts and nuts are damaged during
removal, only same size and material bolts and nuts shall be used as replacement.
7.6.1 All clash check against structural members, cable ladder and tray shall be carried out
prior to fabrication.
7.6.2 The pipe spools shall be installed in accordance with the approved
drawings. Pipe spool installation shall commence when most of the pipe supports have
been fabricated.
7.6.3 MMHE shall check and verify that the spools and pipe supports are
installed at proper elevation and correct tie-in locations . Pipes to be properly supported,
free from stress and fitted with Teflon packer under supports on deck.
7.6.4 Lifting belt or nylon sling shall be used for lifting or handling of pipe
spools or supports after completed blasting/painting. This is to prevent damage on pipe
spools or supports coating.
7.6.5 Flange faces shall be closely mated and bolts holes aligned before
making up the joint. The pipes shall not be strained into position in order to make them fit.
Pipes which do not fit satisfactorily shall be corrected and then re-stress relieved where
necessary.
7.6.6 Mating pipes, valves and fittings shall be installed with their bores
concentric and line. Any jointing fitted shall not protrude into the bore.
7.6.7 Valves are installed upon completion of hydro test and painting activities.
7.6.8 Bellows pieces or flexible units shall be installed free of distortions and
in accordance with instruction regarding offsets for thermal expansion.
accuracy so that it can be fitted in place without undue manual effort and so that flanges
are closely mated and the bolts can be inserted freely . The flanges of the closing length
may be welded on-board . The tolerance of the angle between pipe and flange shall be ±3°
maximum.
7.6.1OAll piping must be internally air blown prior to installation to remove debris and
blasting grid. Deck piping must installed a Teflon pad to prevent from rusting.
d) Ensure that all other works on the system to be tested have been
completed, re instated and proper LOTO procedure have been disengaged.
e) Ensure that all other works in way of the system to be tested have been
completed or precautions have been taken to avoid damage due to failure of the system being
tested. i.e. water or oil leaks occurring during testing in the vicinity of blasting & painting
works, electrical works, steel renewal, machinery works, etc.)
7.7.1.1 The whole system shall be completely filled with fresh water, including a header
tank fitted at its base a connecting pipe with an outlet valve; which shall be kept shut prior
to commencement of testing.
7.7.1.2
7.7.1.4
7.7.1.3
The header tank valve Related systems
shall be opened and allow
the system to be tested Black Water Line, Grey Line, and Sanitary Line
by gravity pressure only. (Medium - Fresh Water).
The top level of the
water in the header tank Environmental Instruction
shall determine the
testing pressure on the Effluent shall be discharged to Potable oily water
system. tank or sewage treatment plant before discharging
overboard.
7.7.2.2
7.7.2.3
7.7.2.4
The whole system shall so as to enable the entire system to be checked for
be filled with fresh leaks. Related systems:
water, which shall be
gradually pressurised to a) L.O service line, Marpool Line, Bunker
1.25 times the working Line, D.O Line, HFO &
pressure of the system or
the Owner's MOO Service & Transfer Line, - (Medium: Air)
requirements.
b) Foam line, Steam Line, Cargo Line, Fire
At commencement of the Line, Condensate Line, Boiler Feed Water Line,
pressurisation, the line Fresh Water Cooling Line, Distilled and Make-up
shall be bled (through a Water Line, Inert Gas System, Compressed Air
valve in the line) to Line, Oily Water Separator Line, Bilge line,
release air locked in the Chemical Dosing Line. (Medium - Freshwater)
system.
c) Ballast Line, Sea Water Cooling Line,
Anti Fouling line, Bilge Line, (Medium - Sea
All joints and equipment
Water)
connected to the system
shall be inspected d) Sea chest area:
thoroughly for leakages
and the testing pressure Ensure no people are working at the sea chest
maintained for such time area during blowing through the air pipeline.
• Throughout the test, the Nitrogen cylinder shall be kept upright and
secured.
• Ensure that all hoses, nozzles, couplings and regulators being used for
the test have a valid certificate, correct pressure rating and in good condition.
7.7.3.1 7.7.3.4
7.7.3.2
7.7.3.5
7.7.3.6
7.7.3.3
Related systems:
7.7.4.2
Request for ship staff to operate all equipment
and machinery connected to the system.
Related systems
Flushing and hydro test shall be carried out, refer to MMHE/SP/MBU/Pl/05 - Hydro
test, Flushing, Pickling & Reinstatement Procedure