Beruflich Dokumente
Kultur Dokumente
Select one:
a. Informal verbal
b. Formal Written
c. Formal verbal
d. Informal written
a. Formal verbal
b. Formal Written
c. Informal verbal
d. Informal written
Select one:
a. Project Planning
b. Project Communication
c. Project control
d. Project Closure
Which of the following is NOT part of project communication management
Select one:
a. Information distribution
b. Project Procurement
c. Communication planning
d. Performance Reporting
Feedback
Select one:
a. 60
b. 50
c. 40
d. NONE
Feedback
Select one:
a. Progress Report
b. Status review meeting
c. Project Forecasting
d. Status Report
Feedback
Select one:
a. SMOOTHING
b. NONE
c. CONFRONTATION
d. WITHDRAWAL
Feedback
Select one:
a. Progress Report
b. Status Report
c. Status review meeting
d. Project Forecasting
Feedback
Select one:
a. Smoothing
b. NONE
c. Confrontation
d. Withdrawal
Feedback
Select one:
a. Push communication
b. Interactive communication
c. Pull communication
d. NONE
Feedback
Select one:
a. None
b. Planning phase
c. Execution phase
Feedback The correct answer is: None
Question 2
Complete
Mark 1.00 out of 1.00
How much risk is involved" is explained in which phase
Select one:
a. Planning phase
b. Initiation phase
c. Execution phase
The correct answer is: Initiation phase
Question 3
Complete
Mark 1.00 out of 1.00
Select one:
a. Planning
b. Control
c. Execution
Feedback
Question 4
Complete
Mark 1.00 out of 1.00
Select one:
a. Close out
b. Initiation
c. Planning
Select one:
a. Initiation
b. Planning
c. Execution
Feedback
Question 6
Complete
Mark 1.00 out of 1.00
Select one:
a. Planning
b. Close out
c. Intiation
Feedback the correct answer is: Close out
Question 7
Complete
Mark 1.00 out of 1.00
Select one:
a. Matrix organisation
b. Function Organisation
c. Project Organisation
The correct answer is: Function Organisation
Question 8
Complete
Mark 1.00 out of 1.00
Select one:
a. Matrix Organisation
b. Function Organisation
c. Project Organisation
Feedback
Question 9
Complete
Mark 0.00 out of 1.00
Select one:
a. FUNCTIONAL
b. MATRIX
c. PROJECT
Feedback
Select one:
a. PROJECT
b. MATRIX
c. FUNCTIONAL
The correct answer is: MATRIX
Select one:
a. Teamwork
b. NONE
c. Team building
The correct answer is: Teamwork
Question 2
Correct
Mark 1.00 out of 1.00
a. 3 to 11
b. 7 TO 12
c. 5 to 12
The correct answer is: 5 to 12
Question 3
Correct
Mark 1.00 out of 1.00
Select one:
a. NONE
b. 9
c. 10
The correct answer is: 10
Question 4
Correct
Mark 1.00 out of 1.00
................... in (1960s) published five stage model of team development
Select one:
a. Tuckman
b. Hertzberg
c. Masslow
The correct answer is: Tuckman
Question 5
Correct
Mark 1.00 out of 1.00
a. NORMING
b. STORMING
c. FORMING
Feedback
Question 6
Correct
According to Gersick maximum performance can be achieved …..
Select one:
Question 7
Correct
Mark 1.00 out of 1.00
Select one:
a. Analytical
b. Amiable
c. None
the correct answer is: None
Question 8
Incorrect
Mark 0.00 out of 1.00
Select one:
a. DRIVER
b. ANALYTICAL
c. AMIABLE
The correct answer is: DRIVER
Question 9
Correct
Mark 1.00 out of 1.00
Gardening is an example of
Select one:
a. INTRINSIC MOTIVATION
b. NONE
c. EXTRINSIC MOTIVATION
Feedback
………. Are the factors who’s presence does not motivate team members
but their absence demotivates team members
Select one:
a. BOTH OF THEM
b. MOTIVATION FACTORS
c. HYGIENE FACTORS
Feedback
Select one:
a. Cost plus fixed fee
b. Cost plus incentive fee
“The buyer pays the seller for allowable performance costs plus a
predetermined fee and an incentive bonus” is the definition of
Select one:
a. Cost plus fixed fee
b. Cost Plus Award Fee
Question 3
Correct
Mark 1.00 out of 1.00
“The buyer pays the seller for allowable performance costs plus a fixed
fee payment usually based on a percentage of estimated costs” is the
definition of
Select one:
a. Cost Plus Award Fee
b. Cost plus incentive fee
Select one:
a. Contract Administration
b. Contract close out
c. None
Feedback
Question 5
Incorrect
Mark 0.00 out of 1.00
Select one:
a. Solicitation
b. Source Selection
c. Solicitation planning
The correct answer is: Solicitation
Question 6
Incorrect
Mark 0.00 out of 1.00
Request for proposal RFP is issued after
Select one:
a. Solicitation planning
b. Solicitation
c. Source Selection
The correct answer is: Solicitation
Question 7
Incorrect
Mark 0.00 out of 1.00
Select one:
a. None
b. Contract close out
c. Contract Administration
The correct answer is: Contract Administration
Question 8
Incorrect
Mark 0.00 out of 1.00
Select one:
a. Firm Fixed price
b. Cost plus fixed fee
Question 9
Incorrect
Mark 0.00 out of 1.00
Select one:
a. Cost plus fixed fee
b. Firm Fixed price
Question 10
Incorrect
Mark 0.00 out of 1.00
Select one:
a. Cost plus fixed fee
b. Cost Plus Award Fee
20% 60%
5% 15%
Disadvantage of functional organization
Project Management?
Initiation
Planning
Closeout
Initiation phase
What is to be done
Why is it to be done
How is it to be done
o Schedule
o Performance Plan
o Procurement Plan
o Communications Plan
Team-building
is high interaction among group members to
increase trust and openness
2 Common Characteristics
Motivation factors
Help motivate workers directly eg. achievement,
recognition, work, responsibility
Hygiene factors
• project archives
• formal acceptance
• lessons learned
Too many projects with high cash flow needs in the same
year may not be able to be supported which will impact
profitability
Cost Estimating;
ROM
I. Scope of Work: Describe the work to be done to detail. Specify the hardware and
software involved and the exact nature of the work.
II. Location of Work: Describe where the work must be performed. Specify the
location of hardware and software and where the people must perform the work
III. Period of Performance: Specify when the work is expected to start and end,
working hours, number of hours that can be billed per week, where the work must
be performed, and related schedule information.
IV. Deliverables Schedule: List specific deliverables, describe them in detail, and
specify when they are due.
V. Applicable Standards: Specify any company or industry-specific standards that
are relevant to performing the work.
VI. Acceptance Criteria: Describe how the buyer organization will determine if the
work is acceptable.
VII. Special Requirements: Specify any special requirements such as hardware or
software certifications, minimum degree or experience level of personnel, travel
requirements, and so on.