Cementing Job Model

Detailed Report
Well 9-9
9 5/8 casing 2nd stage ,New Case
7/2/2020

Created by:Magdy EL-Gohary

Approvals
Name Signature Date
Author Magdy El Gohary 2nd July, 2020
Egptco review Dr.Yasser 2nd July, 2020
Egptco Approval Dr.Yasser 2nd July, 2020
Customer Approval Wepco Drilling Team 2nd July, 2020
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Job Objectives

To succesfully pump 50 bbls of KCL Water followed by 229.6 bbls of Lead @ 12.5 ppg to cover 1200 m
then 45 bbls of Tail Slurry @ 15.8 ppg to cover 150 m

Acceptance Criteria

No losses during the cementing operation resulting


Good compressive strength across the DVT

No HSE/SQ incidents attributable to Schlumberger as a result of the cement job.


Design Criteria vs. Job Objectives

The well is drilled to 2300 m and will be cemented on 2nd stage using Conventional Cement

50 bbls of KCL Water will be used as spacer ahead for a better mud removal

The % of Excess agreed to be 35% for open hole .

It’s highly recommended to not apply any pressure or movement on casing before the cement set to avoid
any micro-annulas creation while cement setting time.

Expected Final Displacement Presure +/-600


CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

OPERATIONAL PROCEDURE
Ho l d se f a t y me e t i n g wi t h a l l t h e p e rso n a l i n ch a rg e i n t h e ce me n t i n g j o b

Flush the lines with 5 bbl of Water

Pressure test surface lines at low pressure start with 350 psi then to 4000 psi (Step By Step). Monitor for 5
minutes minimum.

Dro p DVT o o l s o p e n i n g b u mb a n d co n f o rm DV T o o l o p e n i n g

Ci rcu l a t e 2 x An n u l a r ca p a ci t y a b o ve t h e D V T o o l t o cl e a n f ro m t h e ce me n t sp a ce r a n d cl e a n mu d re t u rn s

Wa i t i n t h e ce me n t

Pump 50 bbls of KCL Water at 6 BPM)

Mix and pump lead and tail cement slurries as per Egptco recipe

Open Egptco circulating head and drop closing plug

Pump required mud volum to displace cement slurry reduce the rate in the last 40 bbl before the end of
displacement

Increase the pressure gradually to 1200 psi for closing DV TOOL and increase pressure again to 2500 psi for 10
min

blead the pressure and check for back flow

wait in the cement 12 to 16 hours


CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

LABORATORY TEST REPORT


Report
RE-EGY-LAB-CMT-1 Date : 6/22/2020
No.:
9 5/8 IN INTER CASING oF
Job Type MD ft BHST 200
LEAD
oF
Rig EDC-9 TVD ft BHCT 137
oF/100
Well Field BADR-3 T.G 1.60 ft
Type of Slurry Single
Cement Type Class "G"
Additives
NEAT 100%
ANTI FOAM 0.04 GPS
CC-10 0.3 % BWOC
R-4 0.2% BWOC
DW 11.734 gal/sk

Slurry Density (ppg) 12.50


Type of Water DRILL WATER
Water Req. (gal/sx) 11.73
Mixing Fluid (gal/sx) 11.81
Slurry Yield (cuft/sx) 2.058
Thickening Time @ BHCT
40 Bc (hr:min) 05:27
70 Bc (hr:min) 06:09
100 Bc (hr:min)
Reading at 80 F 2 3 20 32 43 YP:PV 8.5 34.5

Reading at BHCT 5 7 24.5 35 46 YP:PV 13.75 32.25


Fluid Loss @ BHCT (cc/30') N/A
API Free Fluid (%) 1%
50PSI Compressive Strength. @ BHST 5:30
500 PSI Compressive Strength. @
7:51
BHST
1000 PSI Compressive Strength. @
BHST
24 hr Compressive Strength. @ BHST 750 PSI
1. All tests carried out according to API RECOMMENDED
Remarks
PRACTICE 10B-2.
DRILL WATER , ANTI FOAM , CC-10 ,
2. Order of Mixing:
R-4, CEMENT

MAGDY
Requested by :
ELGOHARY
Distributed to :
YOUSSEF
Reported by : Signature
SEBAEY
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

LABORATORY TEST REPORT


Report No.: RE-EGY-LAB-CMT-1 Date : 6/30/2020
9 5/8 IN INTER oF
Job Type MD ft BHST 200
CASING TAIL
oF
Rig EDC-9 TVD ft BHCT 137
oF/100
Well Field BADR-3 T.G 1.60
ft
Type of Slurry Single
Cement Type Class "G"
Additives
NEAT 100%
ANTI FOAM 0.02 GPS
CC-344 0.35% BWOC
R-4 0.2% BWOC
FR-3 0.05% BWOC
FW 4.943 gal/sk

Slurry Density (ppg) 15.8PPG


Type of Water FRESH WATER
Water Req. (gal/sx) 4.94
Mixing Fluid (gal/sx) 5.01
Slurry Yield (cuft/sx) 1.149
Thickening Time @ BHCT
40 Bc (hr:min)
70 Bc (hr:min) 04:59
100 Bc (hr:min)
Reading at 80 F 2 3.5 30.5 57.5 83 YP:PV 4.25 78.75

Reading at BHCT 12 16 64.5 94.5 124 YP:PV 34.75 89.25

Fluid Loss @ BHCT (cc/30') 146


API Free Fluid (%) 0.00
50PSI Compressive Strength. @ BHST 5:39
500 PSI Compressive Strength. @
6:05
BHST
1000 PSI Compressive Strength. @
6:22
BHST
24 hr Compressive Strength. @ BHST 3600 psi
1. All tests carried out according to API RECOMMENDED PRACTICE
Remarks
10B-2.
FRESH , ANTI FOAM , CC-344, FR-3, R-4,
2. Order of Mixing:
CEMENT

MAGDY
Requested by :
ELGOHARY
Distributed to :
YOUSSEF
Reported by : Signature
SEBAEY
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Table of Contents
1. Well ........................................................................................................................................................ 1
1.1 General............................................................................................................................................. 1
1.2 Survey (Updated) ............................................................................................................................. 1
1.3 Formation ......................................................................................................................................... 3
1.4 Thermal (Updated) ........................................................................................................................... 3

2. Casing .................................................................................................................................................... 4
2.1 Basic................................................................................................................................................. 4
2.2 Open Hole ........................................................................................................................................ 4
2.3 Casing .............................................................................................................................................. 4
2.4 Fluid.................................................................................................................................................. 5

3. Operation ............................................................................................................................................... 6
3.1 Temperature ..................................................................................................................................... 6
3.2 Pumping ........................................................................................................................................... 6
3.3 Choke P. .......................................................................................... Error! Bookmark not defined.
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
4. Output .................................................................................................................................................... 7
4.1 Overview .......................................................................................................................................... 7
4.2 Hydraulics ...................................................................................................................................... 12
4.3 Temperature ................................................................................................................................... 18
4.4 Centralization ................................................................................................................................. 20
4.5 Torque and Drag ............................................................................................................................ 21
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

1. Well
1.1 General
Date 7/2/2020 Rig
Operator Country
Well Well 1 Contractor
Field By
Job
Comments

Well Location: Land Well


1.2 Survey (Updated)

Copyright © 2020 Pegasus Vertex, Inc


1
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Copyright © 2020 Pegasus Vertex, Inc


2
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

1.3 Formation
TVD Pore Frac.
Description Lithology
(m) (ppg) (ppg)
1 13.375 1300.00 9.00 14.00

2 9.625 2300.00 8.50 13.80

1.4 Thermal (Updated)


Surface Temperature: 60.0 (°F)
Geothermal
Bottom TVD Density Cond. Heat Cap. T. Gradient T.
(m) (lb/ft3) (Btu/hr/ft/°F) (Btu/lbm/°F) (°F/100ft) (°F)
1 2300.00 154.90 0.750 0.22 1.60 180.7
Thermal Properties
Density (lb/ft3) Cond. (Btu/hr/ft/°F) Heat Cap. (Btu/lbm/°F)
Pipe 490.00 26.000 0.11
Cement 131.00 0.840 0.21

Copyright © 2020 Pegasus Vertex, Inc


3
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

2. Casing
First Casing Driven or Jetted: Yes
2.1 Basic
Top of
Bit Top Shoe TOC Mud FF
Description Type Mud
(in) (m) (m) (m) (ppg) (-)
(m)
1 Surface Casing - 0.00 1300.00 0.00 - - -
9 5/8 casing
2 Casing 12.250 0.00 2300.00 1200.00 9.10 - -
2nd stage *
*: Current Casing or Liner
**: Tieback
2.2 Open Hole
ID (in) Btm MD (m) EX (%) FF (-) Top MD (m) Len. (m)
1 12.250 2300.00 35.00 0.33 1300.00 1000.00
Zone of Interest
MD (m) 1300.00 2300.00 2300.00
Pore (ppg) 9.00 8.50 8.50
Frac. (ppg) 14.00 13.80 13.80

2.3 Casing
Casing
Coupling Collapse Burst Btm
Len. OD Wt. ID Grade Yield
Description Str. Str. MD
(m) (in) (lb/ft) (in) OD (in) ID (in) (kPa)
(kPa) (kPa) (m)
9 5/8 casing
1 2300.00 9.625 47.000 8.681 9.625 8.681 2300.00
2nd stage
Joint Len.: 12.19 (m), Coupling Len.: 10.000 (in)
Pipe End: Wide Open

Copyright © 2020 Pegasus Vertex, Inc


4
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

2.4 Fluid
Fluid Properties
Gel P. \ T.
Density Ref. T. PV YP n K (lbf/100ft2) Cond. Heat Cap. Dependent
Description Type Model
(ppg) (°F) (cP) (*) (-) (**) (Btu/hr/ft/°F) (Btu/lbm/°F) (D / R) ***
10 sec 10 min

1 WATER BASE Drilling Fluid 9.00 105.0 Bingham 18.0 15.0 - - 10.0 30.0 0.392 0.79 -
2 MUD
3% KCL Water Washer 8.50 80.0 Bingham 1.0 1.0 - - 0.392 0.83 -
3 Lead 12.5 ppg Cement 12.50 158.0 Bingham 25.0 10.0 - - 0.392 0.63 -
4 9 5/815.8 ppg 9
Tail Cement 15.80 158.0 Bingham 80.0 30.0 - - 0.392 0.54 -
5 5/8
9 5/8 Drilling Fluid 9.00 157.0 Bingham 18.0 15.0 - - 0.392 0.79 -
displacement
*: (lbf/100ft2)
**: (lbf-s^n/100ft2)
***: D: Density; R: Rheology

Copyright © 2020 Pegasus Vertex, Inc


5
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

3. Operation
3.1 Temperature
Specified – Geothermal

3.2 Pumping
Flow Direction: Forward
Stage: First Fluid is Native Fluid.
Front (m) Len. (m)
Stage Input Vol. (bbl)
Ann. Pipe Ann. Pipe
WATER
1 Front - Ann. 0.000 0.00 2300.00 2094.48
BASE MUD
3% KCL
2 Vol. 50.000 205.52 0.00 205.52
Water
3 2nd Stage
Lead 12.5
4 Vol. 229.603 1146.88 960.98 0.00
ppg 9 5/8
Tail 15.8 ppg
5 Vol. 45.000 2107.86 182.14 0.00
9 5/8
9 5/8
6 Front - Pipe 510.653 2290.00 0.00 2126.11
displacement
9 5/8
7 Vol. 40.000 163.89 0.00 163.89
displacement
2nd Stage
DV Depth Nozzles TFA
Discharge Coeff.
(m) (1/32in) (in2)
2290.00 0.95 6x1 0.007
Cement Length inside Casing
TOC (m) Tail Length (m) Total Vol. (bbl) Total Time (min)
(m)
1146.88 0.00 0.00 875.256 160.709

3% KCL Water, Surface line , Inlet T. 60.0 (°F)


Total Vol.: 50.000 (bbl); Total Time: 8.333 (min)
Pump Q (bpm)
Vol. (bbl) N2 Ratio (scf/bbl) N2 Q (scfm) N2 Vol. (scf) ET (min)
1st 2nd
1 50.000 6.00 - - - - 8.333

Lead 12.5 ppg 9 5/8, Surface line , Inlet T. 60.0 (°F)


Total Vol.: 229.603 (bbl); Total Time: 38.267 (min)
Pump Q (bpm)
Vol. (bbl) N2 Ratio (scf/bbl) N2 Q (scfm) N2 Vol. (scf) ET (min)
1st 2nd
1 229.603 6.00 - - - - 38.267

Tail 15.8 ppg 9 5/8, Surface line , Inlet T. 60.0 (°F)


Total Vol.: 45.000 (bbl); Total Time: 9.000 (min)
Pump Q (bpm)
Vol. (bbl) N2 Ratio (scf/bbl) N2 Q (scfm) N2 Vol. (scf) ET (min)
1st 2nd
1 45.000 5.00 - - - - 9.000

9 5/8 displacement, Surface line , Inlet T. 60.0 (°F)


Total Vol.: 510.653 (bbl); Total Time: 85.109 (min)
Pump Q (bpm)
Vol. (bbl) N2 Ratio (scf/bbl) N2 Q (scfm) N2 Vol. (scf) ET (min)
1st 2nd
1 510.653 6.00 - - - - 85.109

9 5/8 displacement, Surface line , Inlet T. 60.0 (°F)


Total Vol.: 40.000 (bbl); Total Time: 20.000 (min)
Pump Q (bpm)
Vol. (bbl) N2 Ratio (scf/bbl) N2 Q (scfm) N2 Vol. (scf) ET (min)
1st 2nd
1 40.000 2.00 - - - - 20.000

Copyright © 2020 Pegasus Vertex, Inc


6
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Output
3.3 Overview
Fluid Schematic
Annulus Pipe
MD (m) MD TVD MD TVD
0.00 0.00
0

163.89 163.89

500

891.93 891.93

1000

1144.66 1144.66

1500

2000
2105.84 2105.84

2289.32 2289.32
2300 ○

WATER BASE MUD 9.... 3% KCL Water 8.50...

Lead 12.5 ppg 9 ... Tail 15.8 ppg 9 5...

9 5/ 8 displacemen...

Copyright © 2020 Pegasus Vertex, Inc


7
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Summary
During the Job
P. @ ECD @ ECD @
Q Pump P. Pump HHP Free Fall
Variables 2300.00 m 2300.00 m 1300.00 m
(bpm) (psi) (HP) (m)
(psi) (ppg) (ppg)
Max. Value 6 50000 7351.2 4433 11.3 9.67 0
Min. Value 2 285 41.9 3679 9.38 9.26 0
Max. @ Time (min) 0.214 8.44 8.44 160.709 160.709 160.709 -
Min. @ Time (min) 140.817 0.214 0.214 101.564 101.564 140.817 -
Final Fluid Position
Ann. Pipe
C Fluid Front (m)
Len. (m) Vol. (bbl) Len. (m) Vol. (bbl)
1 WATER BASE MUD 0.00 901.93 177.272 10.00 2.402
2 3% KCL Water 891.93 253.47 49.675 0.00 0.000
3 Lead 12.5 ppg 9 5/8 1144.66 961.26 229.596 0.00 0.000
4 Tail 15.8 ppg 9 5/8 2105.84 183.00 45.213 0.09 0.021
5 9 5/8 displacement 2289.32 0.35 0.086 2126.02 510.632
6 9 5/8 displacement (163.89) 0.00 0.000 163.89 39.363
*() Means position in pipe
Pressure at the End of the Job (psi)
MD (m)
@ 1300.00 m @ 2300.00 m - -
Pore 1996 3335 - -
Frac. 3105 5415 - -
Hydro. P. - Ann. 2067 4296 - -
P. 2145 4433 - -
Hydro. P. (Ann. - Pipe) 71 765 - -
Volume (bbl)
CH Ann. 254.776
OH Ann. (No EX) 183.011
OH Ann. 247.065
Ann. 501.841
2 Bottoms-up 1003.682
DP Displ. 0
Casing Displ. 126.676
Total Displ. 126.676
Shoe Track -
Above Shoe Track -
Pipe Interior 552.417
Ann. + Interior 1054.259
Hole (No Pipe) 1180.935
Rat Hole 0
Event Table
Label ET (min) Pumping Entering Ann. Free Fall (m)
1 0.107 3% KCL Water WATER BASE MUD 0.00
2 8.440 Lead 12.5 ppg 9 5/8 WATER BASE MUD 0.00
3 46.815 Tail 15.8 ppg 9 5/8 WATER BASE MUD 0.00
4 55.708 9 5/8 displacement WATER BASE MUD 0.00
5 141.031 9 5/8 displacement WATER BASE MUD 0.00

Geometry
Start End Vol. Vol.
Description
(m) (m) (bbl) (bbl/ft)
1 Pipe: ID = 8.681 (in), 2300.00 (m) 0.00 2300.00 552.417 0.073
2 Ann.: 12.415 x 9.625 (in), 1300.00 (m) 0.00 1300.00 254.776 0.060
3 Ann.: 13.045 x 9.625 (in), 1000.00 (m) 1300.00 2300.00 247.065 0.075
4 Vol. - Pipe 0.00 2300.00 552.417 0.073
5 Vol. - Ann. 0.00 2300.00 501.841 0.067

Copyright © 2020 Pegasus Vertex, Inc


8
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Start End Vol. Vol.
Description
(m) (m) (bbl) (bbl/ft)
6 Vol. - (Pipe + Ann.) 0.00 2300.00 1054.259 0.140
7 Pipe Surface Area - 36163.8 (ft2) 0.00 2300.00 - -
8 Wellbore Surface Area - 25066.8 (ft2) 0.00 2300.00 - -

Material
Cement Sacks and Water Requirement
Water
Slurry Density Cement Sacks Slurry Vol. Slurry Vol. Slurry Yield Water Vol.
Cement Requirement
(ppg) (lbm) (bbl) (ft3) (ft3/sk) (bbl)
(gal/sk)
1 Lead 12.5 12.50 625.79 229.603 1289.131 2.060 11.78 175.520
2 ppg 9 5/8
Tail 15.8 15.80 219.70 45.000 252.657 1.150 4.94 25.841
ppg 9 5/8

Copyright © 2020 Pegasus Vertex, Inc


9
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Recap

Annulus Pipe
MD (m) MD TVD MD TVD
0.00 0.00
0

163.89 163.89

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Recap

7 60000 8000 2000000 11.5


1 2 3 4 5

500
7000
50000
6 11.0
6000 1500000

B urs t / Collapse P. (psi)


891.93 891.93 40000
5000
Flow Rat e (bpm)

P ump HHP (HP )


P res s ure (ps i)
5 10.5
1000

E CD (ppg)
1144.66 1144.66 30000 4000 1000000

4 10.0
3000
20000

1500 2000 500000


3 9.5
10000
1000

2 0 0 0 9.0
0 50 100 150 200

2000 Elapsed Time (min)


2105.84 2105.84
Q - in Q - out Pump P. Choke P.

2289.32 2289.32
2300 ○ Pump HHP Burst P. @ POI Collapse P. @ POI ECD @ TD

WATER BASE MUD 9.... 3% KCL Water 8.50...

Lead 12.5 ppg 9 ... Tail 15.8 ppg 9 5...

9 5/ 8 displacemen...

Copyright © 2020 Pegasus Vertex, Inc


10
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Snapshot

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Snapshot

Critical Static Gel Temperature Profile (°


ECD (ppg) Flow Potential Strength (lbf/100ft2) F)

Annulus Pipe
MD (m) MD TVD MD TVD
0.00 0.00
0

163.89 163.89

500

891.93 891.93

1000

1144.66 1144.66

1500 8 9 10 11 12 13 14 0 50 100 150 200 250 300 60 80 100 120 140 160 180 200

Max. ECD Minor In Pipe


Pore Moderate Ann. Wall
Frac. Severe Rock API

2000
2105.84 2105.84

2289.32 2289.32
2300 ○

WATER BASE MUD 9.... 3% KCL Water 8.50...

Lead 12.5 ppg 9 ... Tail 15.8 ppg 9 5...

9 5/ 8 displacemen...

Copyright © 2020 Pegasus Vertex, Inc


11
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
3.4 Hydraulics
Flow

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Flow Rate

6.0 50000
1 2 3 4 5

5.5

40000

5.0

4.5
Flow Rat e (bpm)

30000

P ump P . (ps i)
4.0

20000
3.5

3.0
10000

2.5

2.0 0
0 50 100 150 200

Elapsed Time (min)

Q - in Q - out Pump P.

Copyright © 2020 Pegasus Vertex, Inc


12
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Pump P.

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Pump Pressure

2000000
1 2 3 4 5

1500000
P res s ure (ps i)

1000000

500000

0
0 50 100 150 200

Elapsed Time (min)

Pump P. Max. Pump P. Wellhead P. Choke P.

Copyright © 2020 Pegasus Vertex, Inc


13
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
ECD @ ZOI

W e ll 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: ECD @ 1300.00 m

14 3105
1 2 3 4 5

13 2883

12 2661

P res s ure (ps i)


E CD (ppg)

11 2440

10 2218

9 1996

8 1774
0 50 100 150 200
Elapsed Time (min)

Hydro. P. ECD - Medium ECD - SO ECD - PU Pore Frac.

Copyright © 2020 Pegasus Vertex, Inc


14
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
ECD Profile

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: ECD Profile

500

1000
MD (m)

1500

2000

2500
8 9 10 11 12 13 14

Density (ppg)

Max. ECD Min. EMW Pore Frac.

Copyright © 2020 Pegasus Vertex, Inc


15
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Front

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Fluid Fronts

0
1 2 3 4 5

500

1000
MD (m)

1500

2000

2500
0 50 100 150 200

Elapsed Time (min)

3% KCL Water Lead 12.5 ppg 9 5/ 8 Tail 15.8 ppg 9 5/ 8 9 5/ 8 displacement 9 5/ 8 displacement

Copyright © 2020 Pegasus Vertex, Inc


16
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Contact Time

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Annular Contact Time

500

1000
MD (m)

1500

2000

2500
0 10 20 30 40 50 60

Co nta ct Time (min)

3% KCL Water Lead 12.5 ppg 9 5/ 8 Tail 15.8 ppg 9 5/ 8 9 5/ 8 displacement 9 5/ 8 displacement

Copyright © 2020 Pegasus Vertex, Inc


17
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

3.5 Temperature
Profile

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Temperature Profile - End of Job

500

1000
MD (m)

1500

2000

2500
60 80 100 120 140 160 180 200

T e mp erature (°F)

T - in T - Pipe T - Ann. T - Wall T - Rock T - API

Copyright © 2020 Pegasus Vertex, Inc


18
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

Slurry

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Cement Placement Temperature

200
1 2 3 4 5

180

160
Temperat ure (°F)

140

120

100

80

60
0 50 100 150 200

Elapsed Time (min)

Front - 1st Cement Front - Last Cement Trail - Last Cement

Copyright © 2020 Pegasus Vertex, Inc


19
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case

3.6 Centralization
Standoff

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: STDF

500

1000
MD (m)

1500

2000

2500
98 99 100

ST D F (% )

@ Mid Span @ Cent.

Copyright © 2020 Pegasus Vertex, Inc


20
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
3.7 Torque and Drag
Cementing
Hook Load

Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Hook Load - Cementing

360000
1 2 3 4 5

340000

320000
Hook Load (lbf )

300000

280000

260000

240000
0 50 100 150 200
Elapsed Time (min)

SO PU Static

Copyright © 2020 Pegasus Vertex, Inc


21
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Axial Force

W e ll 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Axial Force @ 1300.00 m - Cementing

200000
1 2 3 4 5

150000
A x ial Force (lbf)

100000

50000

0
0 50 100 150 200

Elapsed Time (min)

SO PU Tensile Str.

Copyright © 2020 Pegasus Vertex, Inc


22
CEMPRO+ - Well 1, 9 5/8 casing 2nd stage , 9.625 in, New Case
Max. AF

W e ll 1, 9 5/8 casing 2nd stage , 9.625 in, New Case: Max. AF - Cementing

500

1000
MD (m)

1500

2000

2500
0 50000 100000 150000 200000 250000 300000 350000 400000

Axial Force (lbf)

SO PU Tensile Str.

Copyright © 2020 Pegasus Vertex, Inc


23