Manual Labor Output

EXCAVATION
Common Earth 0.16 cu.m/m-hr
Sand 0.104 cu.m/m-hr
Clay or heavy soil 0.08 cu.m/m-hr
Rocky soil 0.063 cu.m/m-hr
Rock (soft) 0.046 cu.m/m-hr
BACKFILLING
Common Earth 0.456 cu.m/m-hr
Sand 0.296 cu.m/m-hr
Clay or heavy soil 0.228 cu.m/m-hr
Rocky soil 0.192 cu.m/m-hr
Rock (soft) 0.152 cu.m/m-hr
COMPACTING
Manual:
Common Earth 0.75 cu.m/m-hr
Gravel 1.1 cu.m/m-hr
Plate Compactor:
7HP 9
12HP 11
HAULING OF SOIL (1 CU.FT = 0.0283168 cu.m)
5m 0.441 cu.ft/m-hr 0.012488 cu.m/m-hr
10m 0.223 cu.ft/m-hr 0.006315 cu.m/m-hr
Wheel barrow 10m 0.521 cu.ft/m-hr 0.014753 cu.m/m-hr
GRADING, SPREADING
Ordinary Soil 0.81 cu.m/m-hr
Gravel 0.6 cu.m/m-hr
SIEVING
50% Passing 0.54 cu.m/m-hr
CLEARING AND GRUBBING
Light vegetation, shrubs 60 sq.m/m-hr
Light vegetation, trees 30 sq.m/m-hr
Average vegetation, shrubs 40 sq.m/m-hr
Average vegetation, trees 20 sq.m/m-hr
Heavy vegetation, shrubs 20 sq.m/m-hr
Heavy vegetation, trees 10 sq.m/m-hr
MIXING CONCRETE
Hand Mix, 15m 0.105 cu.m/tm-hr 761.9048
Hand Mix, 10m 0.119 cu.m/tm-hr 672.2689

TRANSPORTING CONCRETE, using hand buckets


Manual Labor 0.257 cu.m/m-hr 155.642
CONCRETE COMPACTION
Concrete Vibrator 3.87 cu.m/m-hr
Hand Tools 0.42 cu.m/m-hr

FORMWORKS AND FALSEWORKS


Erection:
Footings 0.62 sq.m/m-hr 80.64516
Columns 0.47 sq.m/m-hr 106.383
Beams 0.37 sq.m/m-hr 135.1351
Slabs 0.69 sq.m/m-hr 72.46377
Stripping:
Footings 1.92 sq.m/m-hr 26.04167
Columns 1.33 sq.m/m-hr 37.59398
Beams 1.11 sq.m/m-hr 45.04505
Slabs 2.08 sq.m/m-hr 24.03846
STEEL SCAFFOLDINGS
0.0126
EARTHWORKS
EXCAVATION Labor Output Labor Output
Common Earth 0.16 cu.m/m-hr 1.28 cu.m/day
Sand 0.104 cu.m/m-hr 0.832 cu.m/day
Clay or heavy soil 0.08 cu.m/m-hr 0.64 cu.m/day
Rocky soil 0.063 cu.m/m-hr 0.504 cu.m/day
Rock (soft) 0.046 cu.m/m-hr 0.368 cu.m/day
BACKFILLING
Common Earth 0.456 cu.m/m-hr 3.648 cu.m/day
Sand 0.296 cu.m/m-hr 2.368 cu.m/day
Clay or heavy soil 0.228 cu.m/m-hr 1.824 cu.m/day
Rocky soil 0.192 cu.m/m-hr 1.536 cu.m/day
Rock (soft) 0.152 cu.m/m-hr 1.216 cu.m/day
COMPACTING
Manual:
Common Earth 0.75 cu.m/m-hr 6 cu.m/day
Gravel 1.1 cu.m/m-hr 8.8 cu.m/day
Plate Compactor:
7HP 9 cu.m/m-hr 72 cu.m/day
12HP 11 cu.m/m-hr 88 cu.m/day
HAULING OF SOIL (1 CU.FT = 0.0283168 cu.m)
5m 0.012488 cu.m/m-hr 0.100 cu.m/day
10m 0.006315 cu.m/m-hr 0.051 cu.m/day
Wheel barrow 10m 0.014753 cu.m/m-hr 0.118 cu.m/day
GRADING, SPREADING
Ordinary Soil 0.81 cu.m/m-hr 6.480 cu.m/day
Gravel 0.6 cu.m/m-hr 4.800 cu.m/day
SIEVING
50% Passing 0.54 cu.m/m-hr 4.320 cu.m/day
CLEARING AND GRUBBING
Light vegetation, shrubs 60 sq.m/m-hr 480.00 sq.m/day
Light vegetation, trees 30 sq.m/m-hr 240.00 sq.m/day
Average vegetation, shrubs 40 sq.m/m-hr 320.00 sq.m/day
Average vegetation, trees 20 sq.m/m-hr 160.00 sq.m/day
Heavy vegetation, shrubs 20 sq.m/m-hr 160.00 sq.m/day
Heavy vegetation, trees 10 sq.m/m-hr 80.00 sq.m/day
CUTTING OF TREES
Diameter 150-450mm 1 pc/m-hr 8.00 pc/day
Above Diameter 450-900mm 0.25 pc/m-hr 2.00 pc/day
Over Diamater 900mm 0.04 pc/m-hr 0.32 pc/day
REMOVAL OF STUMPS
Diameter 15-450mm 0.5 pc/m-hr 4.00 pc/day
Above Diameter 450-900mm 0.1 pc/m-hr 0.80 pc/day
Over Diamater 900mm 0.06 pc/m-hr 0.48 pc/day
DEMOLITION
Concrete by Hammer 0.062 cu.m/m-hr 0.50
CHB Wall 6" 1.85 sq.m/m-hr 14.80 sq.m/day
CHB Wall 4" 2.85 sq.m/m-hr 22.80 sq.m/day
Slab on Ground 4" 1.34 sq.m/m-hr 10.72 sq.m/day
Slab on Ground 5" 1.21 sq.m/m-hr 9.68 sq.m/day
Slab on Ground 6" 1.1 sq.m/m-hr 8.80 sq.m/day
Wall Footing (.40 x .20) 0.57 m/m-hr 4.56 m/day
STRUCTURAL CONCRETE
MIXING CONCRETE Labor Output Labor Output
Hand Mix, 15m, AAA 0.105 cu.m/tm-hr 0.84 cu.m/day
Hand Mix, 10m, AAA 0.119 cu.m/tm-hr 0.95 cu.m/day
Hand Mix, 15m, AA 0.122 cu.m/tm-hr 0.98 cu.m/day
Hand Mix, 10m, AA 0.141 cu.m/tm-hr 1.13 cu.m/day
Hand Mix, 15m, A 0.136 cu.m/tm-hr 1.09 cu.m/day
Hand Mix, 10m, A 0.158 cu.m/tm-hr 1.26 cu.m/day
One Bagger, 10m, A 0.329 cu.m/tm-hr 2.63 cu.m/day
Two Bagger, 10m, A 0.73 cu.m/tm-hr 5.84 cu.m/day
Transit Mixer 2.31 cu.m/m-hr 18.48 cu.m/day
TRANSPORTING CONCRETE, using hand buckets
Manual Labor 0.257 cu.m/m-hr 2.06 sq.m/day
CONCRETE COMPACTION
Concrete Vibrator 3.87 cu.m/m-hr 30.96 sq.m/day
Hand Tools 0.42 cu.m/m-hr 3.36 sq.m/day
FORMWORKS
FABRICATION Labor Output Labor Output
Fabrication 1.51 sq.m/m-hr 12.08 sq.m/day
ERECTION
Footings 0.62 sq.m/m-hr 4.96 sq.m/day
Columns 0.47 sq.m/m-hr 3.76 sq.m/day
Beams 0.37 sq.m/m-hr 2.96 sq.m/day
Slabs 0.69 sq.m/m-hr 5.52 sq.m/day
Walls, on ground 0.56 sq.m/m-hr 4.48 sq.m/day
Walls, above 3m 0.47 sq.m/m-hr 3.76 sq.m/day
STRIPPING
Footings 1.92 sq.m/m-hr 15.36 sq.m/day
Columns 1.22 sq.m/m-hr 9.76 sq.m/day
Beams 1.11 sq.m/m-hr 8.88 sq.m/day
Slabs 2.08 sq.m/m-hr 16.64 sq.m/day
Walls, on ground 4.54 sq.m/m-hr 36.32 sq.m/day
Walls, above 3m 0.88 sq.m/m-hr 7.04 sq.m/day
ERECTION OF STEEL SCAFFOLDINGS
H-Frames, A-Frames 3 assy/m-hr 24.00 assy/day
Above Ground Floor, H/A-Frame 2 sq.m/m-hr 16.00 sq.m/day
STRIPPING OF STEEL SCAFFOLDINGS
H-Frames, A-Frames 3.7 assy/m-hr 29.60 assy/day
STRIPPING
Footings 1.92 sq.m/m-hr 15.36 sq.m/day
Columns 1.22 sq.m/m-hr 9.76 sq.m/day
Beams 1.11 sq.m/m-hr 8.88 sq.m/day
Slabs 2.08 sq.m/m-hr 16.64 sq.m/day
Walls, on ground 4.54 sq.m/m-hr 36.32 sq.m/day
Walls, above 3m 0.88 sq.m/m-hr 7.04 sq.m/day
REINFORCING STEEL BARS
FABRICATION
Footings 12 kg/tm-hr 96.00 kg/day
Columns, Main Bars 30 kg/tm-hr 240.00 kg/day
Columns, Ties 5 kg/tm-hr 40.00 kg/day
Beams, Main Bars 30 kg/tm-hr 240.00 kg/day
Beams, Stirrups 5 kg/tm-hr 40.00 kg/day
Slabs 25 kg/tm-hr 200.00 kg/day
Walls, on ground 12 kg/tm-hr 96.00 kg/day
Walls, above 3m 25 kg/tm-hr 200.00 kg/day
FABRICATION
Footings 30 kg/tm-hr 240.00 kg/day
Columns 20 kg/tm-hr 160.00 kg/day
Beams 18 kg/tm-hr 144.00 kg/day
Slab 10 kg/tm-hr 80.00 kg/day
Walls, on ground 20 kg/tm-hr 160.00 kg/day
Walls, above 3m 10 kg/tm-hr 80.00 kg/day
MASONRY WORKS
CHB LAYING
Footings 12 kg/tm-hr 96.00 kg/day
Columns, Main Bars 30 kg/tm-hr 240.00 kg/day
Columns, Ties 5 kg/tm-hr 40.00 kg/day
Beams, Main Bars 30 kg/tm-hr 240.00 kg/day
Beams, Stirrups 5 kg/tm-hr 40.00 kg/day
Slabs 25 kg/tm-hr 200.00 kg/day
Walls, on ground 12 kg/tm-hr 96.00 kg/day
Walls, above 3m 25 kg/tm-hr 200.00 kg/day
FABRICATION
Footings 30 kg/tm-hr 240.00 kg/day
Columns 20 kg/tm-hr 160.00 kg/day
Beams 18 kg/tm-hr 144.00 kg/day
Slab 10 kg/tm-hr 80.00 kg/day
Walls, on ground 20 kg/tm-hr 160.00 kg/day
Walls, above 3m 10 kg/tm-hr 80.00 kg/day
0.00
brick laying 0.3 sq.m/tm-hr 2.40

PCCP 180 php/ln.m


Cutting/Asphalt 20 php/ln.m
transit mixer 350 php/cu.m
grouted riprap 550 php/cu.m
Manpower Labor Rate Paykaw Rate 20%
L 320 php/day 250 php/cu.m 300 php/cu.m
L 320 php/day 385 php/cu.m 462 php/cu.m
L 320 php/day 500 php/cu.m 600 php/cu.m
L 320 php/day 635 php/cu.m 762 php/cu.m
L 320 php/day 870 php/cu.m 1044 php/cu.m

L 320 php/day 88 php/cu.m 106 php/cu.m


L 320 php/day 136 php/cu.m 164 php/cu.m
L 320 php/day 176 php/cu.m 212 php/cu.m
L 320 php/day 209 php/cu.m 251 php/cu.m
L 320 php/day 264 php/cu.m 317 php/cu.m

L 320 php/day 54 php/cu.m 65 php/cu.m


L 320 php/day 37 php/cu.m 45 php/cu.m

L 320 php/day 5 php/cu.m 6 php/cu.m


L 320 php/day 4 php/cu.m 5 php/cu.m

L 320 php/day 3204 php/cu.m 3845 php/cu.m


L 320 php/day 6335 php/cu.m 7602 php/cu.m
L 320 php/day 2712 php/cu.m 3255 php/cu.m

L 320 php/day 50 php/cu.m 60 php/cu.m


L 320 php/day 67 php/cu.m 81 php/cu.m

L 320 php/day 75 php/cu.m 90 php/cu.m

L 320 php/day 1 php/sq.m 2 php/cu.m


L 320 php/day 2 php/sq.m 3 php/cu.m
L 320 php/day 1 php/sq.m 2 php/cu.m
L 320 php/day 2 php/sq.m 3 php/cu.m
L 320 php/day 2 php/sq.m 3 php/cu.m
L 320 php/day 4 php/sq.m 5 php/cu.m

L 320 php/day 40 php/pc 48 php/pc


L 320 php/day 160 php/pc 192 php/pc
L 320 php/day 1000 php/pc 1200 php/pc

L 320 php/day 80 php/pc 96 php/pc


L 320 php/day 400 php/pc 480 php/pc
L 320 php/day 667 php/pc 801 php/pc

L 320 php/day 646 php/cu.m 776 php/cu.m


L 320 php/day 22 php/sq.m 27 php/sq.m
L 320 php/day 15 php/sq.m 18 php/sq.m
L 320 php/day 30 php/sq.m 36 php/sq.m
L 320 php/day 34 php/sq.m 41 php/sq.m
L 320 php/day 37 php/sq.m 45 php/sq.m
L 321 php/day 71 php/m 86 php/m

Manpower Labor Rate Paykaw Rate 20%


2L 640 php/day 762 php/cu.m 915 php/cu.m
2L 640 php/day 673 php/cu.m 808 php/cu.m
2L 640 php/day 656 php/cu.m 788 php/cu.m
2L 640 php/day 568 php/cu.m 682 php/cu.m
2L 640 php/day 589 php/cu.m 707 php/cu.m
2L 640 php/day 507 php/cu.m 609 php/cu.m
2L 640 php/day 244 php/cu.m 293 php/cu.m
2L 640 php/day 110 php/cu.m 132 php/cu.m
2L 640 php/day 35 php/cu.m 42 php/cu.m 202
287 344.4
L 320 php/day 156 php/sq.m 188 php/cu.m

L 320 php/day 11 php/sq.m 14 php/cu.m


L 320 php/day 96 php/sq.m 116 php/cu.m

Manpower Labor Rate Paykaw Rate 20%


C 400 php/day 34 php/sq.m 41 php/sq.m

C 400 php/day 81 php/sq.m 98 php/sq.m


C 400 php/day 107 php/sq.m 129 php/sq.m
C 400 php/day 136 php/sq.m 164 php/sq.m
C 400 php/day 73 php/sq.m 88 php/sq.m
C 400 php/day 90 php/sq.m 108 php/sq.m
C 400 php/day 107 php/sq.m 129 php/sq.m

C 400 php/day 27 php/sq.m 33 php/sq.m


C 400 php/day 41 php/sq.m 50 php/sq.m
C 400 php/day 46 php/sq.m 56 php/sq.m
C 400 php/day 25 php/sq.m 30 php/sq.m
C 400 php/day 12 php/sq.m 15 php/sq.m
C 400 php/day 57 php/sq.m 69 php/sq.m

C 400 php/day 17 php/sq.m 21 php/sq.m


C 400 php/day 25 php/sq.m 30 php/sq.m

C 400 php/day 14 php/sq.m 17 php/sq.m

C 400 php/day 27 php/sq.m 33 php/sq.m


C 400 php/day 41 php/sq.m 50 php/sq.m
C 400 php/day 46 php/sq.m 56 php/sq.m
C 400 php/day 25 php/sq.m 30 php/sq.m
C 400 php/day 12 php/sq.m 15 php/sq.m
C 400 php/day 57 php/sq.m 69 php/sq.m

2S 800 php/day 9 php/kg 11 php/kg


2S 800 php/day 4 php/kg 5 php/kg
S, L 720 php/day 18 php/kg 22 php/kg
2S 800 php/day 4 php/kg 5 php/kg
S, L 720 php/day 18 php/kg 22 php/kg
S, L 720 php/day 4 php/kg 5 php/kg
2S 800 php/day 9 php/kg 11 php/kg
2S 800 php/day 4 php/kg 5 php/kg

2S 800 php/day 4 php/kg 5 php/kg


2S 800 php/day 5 php/kg 6 php/kg
2S 800 php/day 6 php/kg 8 php/kg
2S 800 php/day 10 php/kg 12 php/kg
2S 800 php/day 5 php/kg 6 php/kg
2S 800 php/day 10 php/kg 12 php/kg

2S 800 php/day 9 php/kg 11 php/kg


2S 800 php/day 4 php/kg 5 php/kg
S, L 720 php/day 18 php/kg 22 php/kg
2S 800 php/day 4 php/kg 5 php/kg
S, L 720 php/day 18 php/kg 22 php/kg
S, L 720 php/day 4 php/kg 5 php/kg
2S 800 php/day 9 php/kg 11 php/kg
2S 800 php/day 4 php/kg 5 php/kg

2S 800 php/day 4 php/kg 5 php/kg


2S 800 php/day 5 php/kg 6 php/kg
2S 800 php/day 6 php/kg 8 php/kg
2S 800 php/day 10 php/kg 12 php/kg
2S 800 php/day 5 php/kg 6 php/kg
2S 800 php/day 10 php/kg 12 php/kg
L, M 802 php/day 335 php/kg 402 php/kg