EXCAVATION
Common Earth 0.16 cu.m/m-hr
Sand 0.104 cu.m/m-hr
Clay or heavy soil 0.08 cu.m/m-hr
Rocky soil 0.063 cu.m/m-hr
Rock (soft) 0.046 cu.m/m-hr
BACKFILLING
Common Earth 0.456 cu.m/m-hr
Sand 0.296 cu.m/m-hr
Clay or heavy soil 0.228 cu.m/m-hr
Rocky soil 0.192 cu.m/m-hr
Rock (soft) 0.152 cu.m/m-hr
COMPACTING
Manual:
Common Earth 0.75 cu.m/m-hr
Gravel 1.1 cu.m/m-hr
Plate Compactor:
7HP 9
12HP 11
HAULING OF SOIL (1 CU.FT = 0.0283168 cu.m)
5m 0.441 cu.ft/m-hr 0.012488 cu.m/m-hr
10m 0.223 cu.ft/m-hr 0.006315 cu.m/m-hr
Wheel barrow 10m 0.521 cu.ft/m-hr 0.014753 cu.m/m-hr
GRADING, SPREADING
Ordinary Soil 0.81 cu.m/m-hr
Gravel 0.6 cu.m/m-hr
SIEVING
50% Passing 0.54 cu.m/m-hr
CLEARING AND GRUBBING
Light vegetation, shrubs 60 sq.m/m-hr
Light vegetation, trees 30 sq.m/m-hr
Average vegetation, shrubs 40 sq.m/m-hr
Average vegetation, trees 20 sq.m/m-hr
Heavy vegetation, shrubs 20 sq.m/m-hr
Heavy vegetation, trees 10 sq.m/m-hr
MIXING CONCRETE
Hand Mix, 15m 0.105 cu.m/tm-hr 761.9048
Hand Mix, 10m 0.119 cu.m/tm-hr 672.2689