Beruflich Dokumente
Kultur Dokumente
net/publication/317931629
Rock seawall design and construction with deeper toes for climate change
CITATIONS READS
0 1,947
3 authors:
Bobbie B. Corbett
Griffith University; International Coastal Management
43 PUBLICATIONS 238 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Design of Safe Open Beach Swimming and Body-surfing Zones for Gold Coast Conditions View project
All content following this page was uploaded by Leslie Angus Jackson on 12 September 2017.
Rock seawall design and construction with deeper toes for climate
change
Martin G Mulcahy1 and Leslie A Jackson1, Bobbie B Corbett1
1 International Coastal Management, QLD, Australia; m.mulcahy@coastalmanagement.com.au
Abstract
With the impacts of climate change expected to have a resounding impact on the Australian Coastline, the
practicalities around the robustness of rock seawalls – in particular, undermining due to erosion events - must
be strongly considered in the design process.
The depth of the seawall toe is a key factor in the design and can result in seawall failure if not specified deep
enough for the structure’s anticipated exposure to erosion events. The toe depth can be a major factor in the
constructability and project cost as toes deeper than about MSL (about 0.0m AHD) are generally below the
water table and the excavation is unstable and subsequently more expensive.
Structural alternatives to deeper toes include horizontally wider toes, however given that many locations with
boulder seawalls have high beach usage, wider toes impact negatively on beach access and amenity. Another
alternative to deeper toes includes a holistic approach, considering other coastal management practices such
as beach nourishment and shoreline protection and retreat.
Historically, adaptation and deeper toes have been achieved in some locations through progressive slumping
of the toe during storms and subsequent post-storm maintenance of the upper wall – but with urbanisation
there is an increasing need to consider whole of life costs, future difficulty of transporting rock and accessing
the structure during flood / surge / erosion events.
We use the Gold Coast as an example as there is considerable practical experience with design, construction,
condition surveys and maintenance on the Gold Coast where the toe level of the standard wall is specified as
0.0m AHD and this has proven to be easily and economically constructed since the 1970’s. Whilst this toe
depth has proven to be structurally adequate to date under the present climate conditions – it has been assisted
in areas by the local coastal management practices such as: sand bypassing, sand nourishment, groynes and
an artificial reef.
topping up of the crest and face armour is immediately adjacent to the toe of the seawall. This
undertaken. scour hole leaves the seawall vulnerable to
undermining failure if the toe detail does not have
Given that seawalls are often constructed on a the capacity to accommodate this increased erosion
sandy base, the ability to be “flexible” is very (Figure 1).
Figure 1 Shape of scour hole near toe of seawall (Figure 45 from Steetzel, 1988)
important. It is likely that during the life of a rock The scour hole is formed due to erosion but often
seawall, it will experience some degree of induced by currents running alongshore to the
settlement either due to settlement of sandy seawall exacerbating the erosion depth. Local scour
foundation (due to the increased bearing load of the holes at the toe of seawalls have been previously
seawall), the movement of rocks within the structure observed at locations along the Gold Coast seawall
itself (due to hydraulic instability), or due to during storm conditions (Figure 2), although they
liquefaction (rocks sinking into the sand base due to typically infill rapidly during post-storm conditions.
increased pore water pressures reducing the
bearing capacity of the sandy base of the seawall Determination of scour depth is important but the
during wave attack). This settlement can often occur beach system is very 3 dimensional and scour
without much, or any, loss of performance of the levels are difficult to accurately predict with
seawall. When settlement is too great (such as if a presently available models and methods.
seawall is undermined due to erosion) this will soon
lead to a reduced crest height and leave the seawall
prone to overtopping, which ultimately leads to
functional failure of the seawall.
2. Methods
Climate change and sea levels cannot be predicted When constructed on the beachfront, deeper toe
with a high level of accuracy over the design life of details often result in construction difficulties when
a seawall structure. This adds another level of the depth extends below the water table.
uncertainty to determination of scour depths for
design. Flexible toe details are easier to construct and work
well in some applications (ports and harbours);
2.3 Toe Depth Design however, when applied to a sandy beach that has
“Experience and engineering judgement play an high public usage, the width and height of the
important role in selecting appropriate toe details flexible toe can cause a significant obstruction on
and applying the design rules presented, which are the beach that reduces visual and recreational
themselves largely based upon experience rather amenity, public accessibility and can cause safety
than systematic testing” (Rock Manual, 2007). issues.
There are two standard design options when These standard designs should be used as a
determining toe designs. starting point, but site-specific project objectives
should drive the design and consideration should be
I) Design to a level deeper than maximum given to:
erosion level (Figure 3)
• constructability
II) Design a “flexible” toe that can self- • cost (upfront and lifecycle)
deepen during erosion (Figure 4) • performance
• usability
• safety
3.1 General
Deeper toe depths are often below the water table
and this presents challenges for construction, which
must be managed with practical methodologies.
These methodologies often come with an increase
in cost and time; however ultimately would be
simpler, more practical and more cost-effective than
undertaking a major re-build during a storm event
when rock supply and delivery could be problematic
Coasts & Ports 2017 Conference – Cairns, 21-23 June 2017
Rock seawall design and construction with deeper toes for climate change
Martin G Mulcahy, Leslie A Jackson, Bobbie B Corbett
and accessibility to the site is likely limited by a piling, limited infilling of sand prior to placement of
narrow foreshore. armour rock and rapidly stabilising the batter.
In high value beach areas such as the Gold Coast, Sheet piling was investigated as a method to assist
approval of large flexible toe details is unlikely on with dewatering, however, due to existing boulders
high usage public foreshores. As such, in many from existing seawall present within the excavation
cases, the construction of a deeper toe is required footprint, however in this location with the old rubble
to address potential for scour while minimising layers it was not practical to drive sheets. It is noted,
impacts on public use and access. Alternatives to however, that this methodology has been
deeper toes should be considered. Alternatives successfully undertaken at other sites.
suitable for Gold Coast conditions include beach
nourishment, submerged reef breakwaters and
groynes.
5. References
[1] Carley, J. (2015). Establishing the Design Scour Level
for Seawalls
Figure 8: Microslips occurring at base of batter cut below
water table [2] CIRIA, CUR, CETMEF (2007). “The Use of Rock in
Hydraulic Engineering” 2nd Edition
[3] Jackson L A, Hill P (2013): History of the
3.3 Observations
Implementation and Evolution of Sand Nourishment
Toe design is important to the future integrity of Methods on the Gold Coast.
seawalls, but text book designs are often overly
simplistic and do not take into account site-specific [4] Tomlinson R, Jackson L A, Hunt S (2016): Creating
project objectives. and Maintaining a Coastal Management Knowledge Hub.
[5] Tomlinson R, Mulcahy M, Jackson L A, Todd D,
The design depths need to accommodate Corbett B, McGrath J, Hunt S (2014): Design Review Of
significant uncertainty and this can lead to The Gold Coast Seawall For Climate Change
overdesign and unnecessary cost and impacts on [6] Salyer A, Jackson L A, Corbett B, Jackson L (2016):
the beach amenity. The best solution may be an Coastal Stabilisation – Advancements in Geotextile
integrated solution that reduces the impacts of Design & Construction Methods as An Alternative to
climate change on the wall by protecting the beach Rock.
to seaward of the wall
[7] Steetzel, H. (1988). Scour holes - analyses of the
factors that determine the shape of a the scour hole based
This has the advantage of protecting the beach itself on available literature of physical model tests (in Dutch).
and the wall remains as a terminal structure to Technical report, Delft Hydraulics.
protect private and public assets during erosion
events. Alternatives suitable for Gold Coast
conditions include beach nourishment, submerged
reef breakwaters and groynes (Jackson 2013,
Jackson 2015). Design and implementation of
seawalls and such structures needs good
understanding of the local coastal processes
(Tomlinson 2016).
4. Summary
With the influence of climate change, and potential
long term erosion, many existing seawalls are
becoming increasingly vulnerable, in many cases
requiring review and adaptation. Many newly
designed seawalls are being designed with deeper
toes.