Beruflich Dokumente
Kultur Dokumente
21 Lark Corp. has contract to construct a P5,000,000 cruise ship at an estimated cost of
P4,000,000. The company will begin construction of the cruise ship in early January
20x4 and expects to complete the project sometime in late 20x7. Lark corp. has
never constructed a cruise ship before, and the customer has never operated a cruise
ship. Due to this and other circumstances, Lark corp. believes there are inherent
hazards in the contract beyond the normal, recurring business risks. Lark corp.
expects to recover all its costs under the contract. During 20x4 and 20x5, the
company has the following activity:
20x4 20x5
Costs to date P 980,000 P 2,040,000
Estimated costs to complete 3, 020,000 1,960,000
Progress billings during the year 1,000,000 1,000,000
Cash collected during the year 648,000 1,280,000
For the year ended December 31, 20x5, how much revenue should Lark corp. recognize
on its income statement?
a P980,000 c P1,300,000
b P2,040,000 d P1,060,000
22 Lark Corp. has contract to construct a P5,000,000 cruise ship at an estimated cost of
P4,000,000. The company will begin construction of the cruise ship in early January
20x4 and expects to complete the project sometime in late 20x7. Lark corp. has
never constructed a cruise ship before, and the customer has never operated a cruise
ship. Due to this and other circumstances, Lark corp. believes there are inherent
hazards in the contract beyond the normal, recurring business risks. Lark corp.
expects to recover all its costs under the contract. During 20x4 and 20x5, the
company has the following activity:
20x4 20x5
Costs to date P 980,000 P 2,040,000
Estimated costs to complete 3, 020,000 1,960,000
Progress billings during the year 1,000,000 1,000,000
Cash collected during the year 648,000 1,280,000
On its statement of financial position at December 31, 20x5, what amount will be reported
to the Construction in process account?
a. P40,000 costs in excess of billings
b. P1,020,000 costs in excess of billings
c. P40,000 billings in excess of costs
d. P20,000 billings in excess of costs
23 Lark Corp. has contract to construct a P5,000,000 cruise ship at an estimated cost of
P4,000,000. The company will begin construction of the cruise ship in early January
20x4 and expects to complete the project sometime in late 20x7. Lark corp. has
never constructed a cruise ship before, and the customer has never operated a cruise
ship. Due to this and other circumstances, Lark corp. believes there are inherent
hazards in the contract beyond the normal, recurring business risks. Lark corp.
expects to recover all its costs under the contract. During 20x4 and 20x5, the
company has the following activity:
20x4 20x5
Costs to date P 980,000 P 2,040,000
Estimated costs to complete 3, 020,000 1,960,000
Progress billings during the year 1,000,000 1,000,000
Cash collected during the year 648,000 1,280,000
On its statement of financial position at December 31, 20x5, what amount will be reported
for accounts receivable?
a. P352,000 c. P72,000
b. P720,000 d. P2,000,000
24 For a construction firm using rge cost recovery method, if costs exceed billings on some
contracts by P1,000,000 and billings exceed costs by P800,000 on others, the contracts
should ordinarily be reported as a
a. Current asset of P200,000
b. current liability of P200,000
c. current asset of P1,000,000 less a contra-current asset of P800,000
d. current asset of P1,000,000 less a contra-current liability of P800,000
25 The key largo company uses the percentage of completion method to recognize profits on
long-term contracts. At the end of the second year of the contract, a project was 70%
complete and an overall loss of P100,000 was expected. A P20,000 profit had been recognized
in the first year of the contract. The loss to be recognized in the second year is:
a 70,000 d 120,000
b 80,000 e none of these
c 100,000
26 Hiser Builders, Inc. is using the cost recovery method for a P5,600,000 contract that will
take two years to complete. Data at December 31, 20x4, the end of the first year, are as
follows:
Costs incurred to date P2,560,000
Estimated costs to complete 3,280,000
Billings to date 2,400,000
Collections to date 2,000,000
27 Lake construction company uses the percentage of completion method for long term
construction contracts. The company has a project with a contract price of P7,000
on which P600of gross profit has been recognized in prior years. Information for current
year is as follows:
Total cost incurred through current year P5,000
Estimated costs remaining at the end of current year 2,800
28 At December 31,20x4, Seasons estimates that it is 30% complete with construction, based
on costs incurred. What is the total amount of revenue from Long-term contracts recognized
for 20x4 and what is the balance in the accounts receivable account assuming cannon cafe
has not yet made its last quarterly payment?
29 At December 31, 20x5, Seasons construction estimates that it is 75% complete with the
building; however, the estimate of total costs to be incurred has risen to P7,200,000 due
to unaticipated price increases. What is the total amount of construction expenses that
Seasons will recognize for the year ended December 31, 20x5?
a 5,400,000 c 3,195,000
b 3,150,000 d 3,270,000
30 At December 31, 20x5, Seasons construction estimates that it is 75% complete with the
building; however, the estimate of total costs to be incurred has risen to P7,200,000 due
to unaticipated price increases. What is reported in the balance sheet at December 31,20x5
for seasons as the difference between the construction process and the billings on construction
in process accounts, and is it a debit or a credit?
31 Seasons construction complete the remaining 25% of the building construction on December
31, 20x6, as scheduled. At that time the total costs of construction are P7,500,00. What is
the total amount of revenue from long term contracts and construction expenses that Seasons
will recognize for the year ended December 31,b20x6?
Revenue Expense
a 7,440,000 ###
b 1,860,000 ###
c 1,860,000 ###
d 1,875,000 ###
32 For the year ended December 31, 20x4, Cooper would recognized gross profit on the building
of:
a 316,250 c 405,000
b 345,000 d 0
33 At December 31, 20x4, Cooper would report construction in process in the amount of:
a 345,000 c 4,140,000
b 3,795,000 d 3,540,000
34 During 20x4, Gates corp. started a construction job with a total contract price of P3,500,00.
The job was completed on December 15, 20x5. Additional data are as follows:
20x4 20x5
Actual costs incurred 1,350,000 1,525,000
Estimated remaining costs 1,350,000 -
Billed to customer 1,200,000 2,300,000
Received from customer 1,000,000 2,400,000
Under the cost recovery method, what amount should Gates recognize as gross profit for
20x5?
a 225,000 c 475,000
b 312,000 d None of the above
Balance sheet:
Accounts receivable - construction contract 100,000
billings 300,000
construction in progress 240,000 60,000
Less: Contract billings
Income statement:
Income (before tax) on the contract recognized
in 20x4 60,000
36 What was the initial estimated total income before tax on this contract?
a 300,000 c 400,000
b 320,000 d 480,000
37 For the year ended December 32, 20x4, Eilert would recognize gross profit on the building of
a 0 c 575,000
b 527,083 d 675,000
38 At December 31, 20x4, Eilert would report construction in process in the amount of
a 6,900,000 c 5,900,000
b 6,325,000 d 575,000
39 Belgium Co. is constructing a tunnel for P800 million. Construction began in 20x4 and is estimated
to be completed in 20x8. At December 31, 20x6, Belgium has incurred costs totaling P356
million with P85 million of that incurred in 20x6, P143 million inb20x5, and theremainder during
20x4. Belgium believes that it completed 30% of the tunnel during 20x6, although that may change
based on future activity. Belgium Co. uses PAS 11 for its accounting and regards its cost number
as very uncertain (cost recovery method/zero profit approach). What amount of revenue
should Belgium Co. recognize for the year ended December 31, 20x6?
a No revenue should be recognized until the contract is completed in 20x8
b 356 million
c 240 million
d 85 million
40 Wynn, Inc. has a contract to construct a large hotel for P12,000,000. The contract was signed
on January 2, 20x4 and it was expected that the hotel would be complete on December 31, 20x7.
At the date the contract was signed, Wynn, Inc. anticipated the costs of construction would total
P11,000,000. At the end of 20x5 the total cost estimate rose to P11,870,000 and at the end
of 20x6 the total cost estimate rose to P12,000,000. Due to certain circumstances, Wynn, Inc.
believes there are inherent hazards in the contract beyond the normal, recurring business risks.
Wynn, Inc. expects to recover all its costs under the contract. Under these conditions, what
amount of loss, if any, should Wynn, Inc. recognize in each of the following years?
s on some
f P800,000
of P800,000
ze profits on
d been recognized
ear, are as
uld be recognized
uction, based
cts recognized
g cannon cafe
counts receivable
P2,480,000
ember 31,20x5
gs on construction
n on December
0,00. What is
ses that Seasons
a P9,000,000
stimated total
1,800,000 and
it on the building
of P3,500,00.
P15,000,000
estimated total
,000,000 and the
mpletion method.
n the building of
mpleted in 20x8