Name: Charles Emmanuel D. Brusas Date: June 17-21, 2019


Company: QUEZELCO I Area of Assignment: Metering Department

Objective
To gain significant amount of new knowledge regarding the functionality of Quezelco
I’s Engineering Department and one of its sub-department, the Metering Department.

Reflections from the Objective


The objectives were satisfied by the passing days in this fist week. New knowledges.
Were unlocked and the better understanding of Quezelco’s service.

Accomplishments
We’ve been told how and why there were always electrical interruptions within the
Quezelco’s scope. Apprehesion of jumpers were witnessed and meters were first calibrated
and tested before they will be available to consumers.

Realization about the Task


Some things were simple, some are more complex but with good lecture and training
these would all be understood. Risks and dangers are always present and considered with this
kind of workplace.

University Site, Brgy. Ibabang Dupay, Lucena City, Quezon, Philippines 4301. *Telefax No. (042) 710-3151 *E-mail Address:
engg.dept_mseuf@yahoo.com.ph
Manuel S. Enverga University Foundation
Lucena City, Philippines
Granted Autonomous Status
CHED CEB Res. 076-2009
ON-THE-JOB-TRAINING NARRATIVE REPORT

Name: MARC LORENZE PINION Date: June 17-21, 2019


Company: QUEZELCO I Area of Assignment: Metering Department

Objective
To gain significant amount of new knowledge regarding the functionality of Quezelco
I’s Engineering Department and one of its sub-department, the Metering Department.

Reflections from the Objective


The objectives were satisfied by the passing days in this fist week. New knowledges.
Were unlocked and the better understanding of Quezelco’s service.

Accomplishments
We’ve been told how and why there were always electrical interruptions within the
Quezelco’s scope. Apprehesion of jumpers were witnessed and meters were first calibrated
and tested before they will be available to consumers.

Realization about the Task


Some things were simple, some are more complex but with good lecture and training
these would all be understood. Risks and dangers are always present and considered with this
kind of workplace.