Beruflich Dokumente
Kultur Dokumente
Lot 2
Engineer Thilina
Covid preventive action recommended; use private transport to travel home biweekly
EA Suranga Sajeewika
Covid preventive action recommended; use private transport to travel home monthly private transport to Kurunegala office daily
Facilities recommended; fuel allowance for1 travelling turns in a month Motor bike allowance to travel office daily
Thalakolawewa
Certify the site cleaning of worked area completed as per the requirements
Collect and submit daily progress report (DPR)
Certify the As built drawings and verify submission of all necessary drawings
Certify any environmental protective measures taken
Involvement in material reconciliation
Verify the sealing of pipes using end caps
Certify compaction by random sampling
Pressure testing
Verify any open trench / incomplete work left
Certify the measurements for the final bill of the contractor
Rambepitiya
In addition
EA shall coordinate with relevant CBO members to update the status of supply of imported soil and inform the engineer on the progress against the
requirement.
Supervision at concrete chamber precast yard; cube testing shall conduct in approved lab and lab report shall use for approval
Kachchirawa Kuddetiyawa
EA’s input;
Pipe Laying
Participation in Surveying works including culvert crossing, trace marking and trial pit
WTP
Lot 1
Engineer Javahr
Covid preventive action recommended; use private transport to travel home biweekly
EAs
Two EAs to be appointed immediately, interview shall be conducted on 20 May 2020 in Anuradapura
Covid preventive action recommended; Priority for local candidates or willing to station near the site premises
Ihalagalkulama
Pipe laying
Surveying and testing works continue including trace marking, culvert crossing and trial pit
WTP
Setting out
Site cleaning and excavation
Adiyapulikulam
Pipe laying
Surveying and testing works continue including trace marking, culvert crossing and trial pit
PVC pipes at site change during 1st week, Pipe laying team mobilize in 2nd week
WTP
Important Notes
Construction work shall schedule as monthly shut down and all in-house workers do not allow to leave the work place without prior approval of the
Supervisor
All members strictly follow the health and safety guidelines and, the contractor should provide the provisions. In addition, the guidelines should be delivered to
each members