Beruflich Dokumente
Kultur Dokumente
productmanagementreview
In the final installment of his series on product management, Donald McNaughton
reaches the Product Management Review, which provides an update on the status
of projects and doubles as step one of the monthly S&OP process
In the previous article in this project team. Projects are also subject Process steps 11-13 of the project
series on product management, to an evaluation by the portfolio management enabling process steps
project management was defined as a management committee (PMC) at and roles define and describe the
methodical approach to planning and a gate review, which occurs when requirements for the preparation and
managing projects from start to finish. a work stage has been completed. execution of the monthly product
It also focused on process steps 6-10 However, the duration between gate management review.
of the 13-step product management reviews varies, sometimes up to Monthly project status update
process (Figure 1). Part four of this several months, depending on the (process step 11)
series discusses the monthly status type of project.
update and product management This situation highlights the need
review (step one of the sales and for a regular and routine monthly
operations planning process), which process that evaluates the status of
encompasses the remaining process projects and addresses issues affecting
steps (11-13). their status. The most effective way to
Keeping current with project status address this is to establish a monthly
Typically, projects are managed product management review (PMR) © Oliver Wight Table 1
on a daily and weekly basis by the as part of the sales and operations
project manager and his or her planning (S&OP) process. The project team leader, on a
monthly basis, submits a project status
Thirteen-step product management process update to the product coordinator.
The project team leader completes the
project status templates with input
from the project team.
The project team identifies and
develops the key milestones for their
specific project and the date by which
each milestone will be completed
during their project planning activity.
The PMC approves the milestones for
each project.
In support of the key milestones
each project has a stage and gate
model. Each stage outlines the
general tasks that each function is
expected to perform and by when
each general task is to be completed.
However, it also must be realized that
© Oliver Wight Figure 1 the duration of a task may span one
8 www.bus-ex.com May 08
Strategicmanagement
or more stages. • 3 milestones are coded blue project team to evaluate the impact on
In support of the general tasks (completed milestones) the bottleneck resources as they plan
outlined in the stage and gate model • 2 milestones are coded red and re-plan their projects.
there is a detailed project plan. The • 4 milestones are coded yellow 4. Rolling 24-month volume,
project plan outlines the detailed tasks • 3 milestones are coded green revenue and margin data with
that each function is to complete in Therefore, the summary project supporting assumptions
order to achieve the general tasks. Each status (Figure 3) is coded red. Each project must have a supporting
task has a duration / due date, and an 3. Rough cut capacity planning volume (Figure 5), and revenue
identified person who is assigned the (RCCP) and margin (Figure 6) plan with
responsibility for its completion. Project management, it must be supporting assumptions. There is
The project team leader monitors recognized, is not just about developing often reluctance on the part of product
the progress of the general and valid plans. It also is about ensuring managers to provide this information.
detailed tasks to ensure that they are
Last approved date (LA date) and latest best estimate date (LBE date)
completed on schedule to achieve the
key milestone dates. He/she receives
periodic progress reports from the
project team members, and conducts
project team meetings as frequently
as is necessary to keep the project on-
scope, on-budget and on-schedule.
The monthly project status reports
that are prepared by the project team
leader with input from the project team
include the following four documents:
1. Key milestone status report
In this report, the project team leader
evaluates the status of the general and
detailed project tasks and with input
from the project team updates the
status of the key milestones (Figure 2).
© Oliver Wight Figure 2
The color-codes represent:
• Red: A milestone date has changed.
• Yellow: A milestone date has not that the plans are achievable with the They are often fearful that they will
changed but there are issues to resolve available resources. be held accountable for delivering the
to ensure that the date is achieved. If The best tool for this is rough cut numbers provided in the plans even
no action is taken there is a potential capacity planning, which takes the though some projects may be in an
that the milestone date will have to general and detailed tasks contained early stage of their development.
change and become red.
• Green: A milestone date has Original launch date (OL Date), last approved date (LA Date), latest best
not changed and there are no estimate date (LBE Date) and next gate review date (NGR Date)
issues to resolve.
• Blue: A milestone that has been
completed prior to the S&OP cycle.
2. Summary project status report
The overall project status is
determined by the lowest level status © Oliver Wight Figure 3
of the key project milestones in the in the project plan and applies their What must be realized and
key milestones status report. In our load against bottleneck resources understood by all involved in the
example there are 12 key milestones (Figure 4). Developing an RCCP model business planning and review is that
(Figure 2) with the following status: allows the project manager and the the goal is to provide a rolling 24-
May 08 www.bus-ex.com 9
© Oliver Wight Figure 4
month view of the business that is as inputs from all of the project team must assure that the required
accurate as possible. leaders in preparation for the product supporting information for these items
Product coordinator (process step 12) management review (PMR). is included. The product coordinator
The project team leaders complete the The product coordinator also then prepares the presentation for
monthly project status reports for each of evaluates the inputs received from the PMR, briefs the PMR owner, and
their projects with input from the project all of the project team leaders. With attends the PMR.
teams and submit them to the product the primary focus on any item coded Product management review
coordinator. He/she consolidates the yellow or red, the product coordinator (process step 13)
10 www.bus-ex.com May 08
Strategicmanagement
Donald McNaughton, an Oliver Wight principal, is a consultant and educator providing guidance on the design and
implementation of effective business processes, including sales and operations planning and product management. May 08 www.bus-ex.com 11