Sie sind auf Seite 1von 1

GENERAL NOTES:

D DESIGN BASIS
This lay-out has been prepared based on the information supplied to us by or
on the behalf of the customer. However, it is the client's responsibility to check
and verify that we have correctly interpreted. The requirements, information
and all loading in accordance with UNISTEEL Equiptment Data Sheets,
FORMWORK A Guide to Good Practice 2nd Edition, Ciria Report 108 Concrete
Pressure on Formwork.
UNISTEEL COPYRIGHT
2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m This drawing is an exclusive property of UNITED STEEL INDUSTRIES
WP-5 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-3 WP-6 COMPANY LIMITED. Any unauthorized use of this drawing is Not Valid Unless
Signed and Stamp by our Technical Department. UNISTEEL reserve the right
to amend drawing details and materials subject to stock availability.
MATERIAL PROPERTIES & SPECS.

WP-16
The mechanical properties of the of the raw materials used in fabrication of our
scaffold materials ( Falsework ).
WP-7
I. Steel Members :
WP-1 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-3 WP-4 Source : SABIC ( JIS G3132) Steel Grade SPHT3

WP-11
2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m
SCAFFOLD TUBES :
EN 10219 ; 320N/mm²(46 ksi) (32kg/mm²) (Fy) Min. Yield Stress @3.2mm. wall thickness

H H BS 1139 ; 235N/mm²(34 ksi) (24kg/mm²) (Fy) Min. Yield Stress @4.0mm. wall thickness

WP-9

2.0m

2.0m
II. Aluminum Beam Member : Source : SUPPLIER
Yield Stress, Fy ; 285.00Mpa
Modulus Elasticity ; 69000Mpa
III. Timber Member :
2.0m

2.0m

WP-13
No timber is supplied by UNISTEEL, the timber design is the responsibility of the contractor.

WP-14
To enable us to prepare the design on this drawing, we have assumed the following :
Source : American Forest and Paper Association (Douglas Fir or Southern Pine)
WP-2

Nominal Size ; 4"X4"


WP-2

WP-2

Nominal Size ; 3"X3"


Bending Stress, Fs ; 8.90Mpa
IV. Plywood : Source : Concrete Society Page 39
Species : 18mm. Plywood-European Standard-Birch Through

2.0m

2.0m
Permissable stresses stated in BS 5268 Part 2, assumed to be in sanded condition
2.0m

2.0m

Bending Stiffness Parallel ; 3.23 kNm²

G G Moment of Resistance Parallel ; 0.834 kNm


DESIGN LOADS APPLIED

WP-2

WP-2
WP *|
WP*

Loads on forms and falsework have been analyzed in accordance with Guide
for Formwork and/or Codes of Practice for Falsework. As a result, the structure
detailed on this drawing has been designed to support the following imposed
loads only :
Loads are assumed uniformly distributed

2.0m

2.0m
E E

B
FALSEWORK: FORMWORK:
Concrete Density : Max. Concrete Pressure :
Weight of Formwork : Concrete Temperature :
A

WP-2

WP-2
Liveload : 2.5 kN/m² Rate of Pour :
TIMBER FORMWORK
All timber formwork and bearers are to be provided by the contractor or client.
Timber should have been calculated using the design parameter detailed on
this drawing sheet.

2.0m

2.0m
ERECTION
The Customer is responsible for ensuring that all structure are adequately tied
WP*|*
WP**

F F and/or braced to carry the load and ensure stability as indicated on the
drawing. No ties or braces be removed without the authority of UNISTEEL.

WP-14
This drawing has been prepared using the safe working loads of UNISTEEL

WP-13
equiptment no modification to components, assembly, loading or any other
aspects must be without authority from Technical Dept. of UNISTEEL. No
2.0m

2.0m

responsibilty accepted by UNISTEEL for the design or permormance of


materials not supplied by UNISTEEL.
FOUNDATIONS
WP-10

F
Unless otherwise noted, no soleplates or other means of spreading the

2.0m

2.0m
imposed loads are supplied by UNISTEEL. The customer must ensure that the

WP-12
foundations provided are adequate, where UNISTEEL is supported,
suspended, anchored or tied to a structure or ground is adequate to safety
WP-8

2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m 2.0m support the additional imposed loads.
WP-1 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-3 WP-4

WP-15
TEMPORARY WORKING PLATFORMS
Unless specially stated, It is assumed that any other working platforms ( for
erection or dismantling purposes ) will be designed, supplied and fitted by the
customer. It is the client's responsibility to ensure that working platforms or
means of access necessary for safe access are provided whether shown on
this drawing or not.
TYING AND BRACING / LATERAL STABILITY
WP-6 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-2 2.0m WP-3 2.0m WP-5 The lateral bracing and horizontal butting restraint force required to be
transmitted through the braces is specified in BS 5975 " FALSEWORK ". The
code specifies a minimum lateral stability criteria equivalent to the grater of
either 2.5% of the vertical load in the standard (Post) acting horizontally at the
point of application the load, or horizontal forces from wind, erection
tolerances, non-vertically, concrete pressures and other forces acting as
described in the code.
US DATEDthat
Tensuring ! all structure are adequately tied
The Customer is responsible
and/or braced toN G
carry
TAfor
Sthe ND
KED Aand ensure stability as indicated on the
load
Wor I braces HE C

F
C
drawing.R NoAties WHENbe removed without the authority of UNISTEEL.
C D L ALID
YV
N FUL ( Re-Shoring )
Back RPropping
UCTIO Y
T
CONS propping R
Back N A Back propping
may be required.
I eckin
g is the responsibility of the

1 FORMWORK LAYOUT PLAN(FIRST POURING) customer.


STA
TUS P R EL
IM
isc u s
for d o part
s
pricin
d ch
g an ment un
e
ion, any agre structio
of its co
in
n
n
til

ing is forms n hecked


draw It c
This e client. arked as
ION
by th nd m
ed a
issu s. CT
statu T RU and
ings of the
TUS NS load n
STA CO che c k ed for rpretatio
inte
been with our
E

a s
ing h rdance
draw o
This ity in acc ments.
il e
stab s requir
t'
WP-7 WP-2 WP* WP** WP-8 clien
Scaffolding & Formwork
webmail : www.unisteel.com.sa

WP-15 WP-13 WP-2 WP-2 WP-14 WP-16


CONSULTANT/CLIENT COMMENTS:
( A ) - APPROVED

( B ) - APPROVED WITH COMMENTS

( C ) - APPROVED WITH COMMENTS,


RESUBMITTAL IS REQUIRED
(D)-REJECTED
E

/ /
A ELEVATION B ELEVATION SIGNATURE: DATE:

MAIN OFFICE - FACTORY : RIYADH K.S.A.


TEL. NO.: +966 1 410-5544 FAX. : +966 1 475-5231
P.O. BOX 40555, RIYADH 11511
KINGDOM OF SAUDI ARABIA
Jeddah Branch:
WP-6 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-3 WP-5 Scaffolding & Formwork Tel. No. : +966 2 621-2525 Fax. No. :+966 2 621-2255
webmail : www.unisteel.com.sa
Universal Access No. Dammam Branch:
Tel. No. : +966 3 814 -2075 Fax. No. :+966 3 814 -2079
9200 00 864

A member of Al-Fozan Group of Companies

DENNIS DSM ENGR. MOHAMED ADEL EZZAT

SEP.30.2020 NOV.09.2020

THIS DRAWING IS NOT BE USED FOR CERT. BY :


CONSTRUCTION UNLESS CERTIFIED BY
C ELEVATION ENGINEERING DEPARTMENT.
DATE :

CLIENT:

WP-6 WP-3 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-2 WP-5
SSEM
Qassim Braidah, Kingdom of Saudi Arabia

PROJECT TITLE :

MASHTAL PUMP STATION


DRAWING TITLE :
FORMWORK LAYOUT & ELEVATION
DRAWING NUMBER
D ELEVATION
SCALE A1 DWG 1 UNI20-R-300-WL-001-R0

Das könnte Ihnen auch gefallen