Sie sind auf Seite 1von 2

Date : 28-Sep-20

Project : PROPOSED MULTI-PURPOSE GYM ( STEEL STRUCTURE ) Phase 1


Location : C-5 Access Road, Brgy. IVC, Marikina City
Subject : PROJECT SCHEDULE
Duration : 142 DAYS ( Including Sundays and Holidays )

ITEM DESCRIPTION OF WORK DATE OF DURATION DATE OF


START ( Days ) FINISH

1.0 MOBILIZATION
1.1 Enclosure of project area/ Clearing of Site 9/14/2020 4 9/18/2020
1.2 Temporary Facilities/Warehouse 9/14/2020 2 9/16/2020

2.0 EARTHWORKS
2.1 Excavation ( Volume : 89 cu.m ) 9/19/2020 15 10/4/2020
1 cu.m per Monday ; pax = 6
2.2 Backfilling / Tampering ( 1200 cu.m ) 10/20/2020 6 10/26/2020

3.0 CONCRETE WORKS ( Phase 1 )


3.1 Footing and Column (Rebars Fabrication) 10/5/2020 7 10/12/2020
3.2 Footing and Column fabricated rebars Installation 10/7/2020 6 10/13/2020
3.3 Footing concrete pouring 10/10/2020 3 10/13/2020
3.4 Column Formworks 10/12/2020 6 10/18/2020
3.5 Columns Concrete pouring 10/16/2020 3 10/19/2020
3.6 Gravel Bedding of Gym Floor/Tampering 10/25/2020 3 10/28/2020

4.0 STEEL WORKS


4.1 Steel Plate Installation 10/29/2020 1 10/30/2020
4.2 Wide Flange Installation/Full Weld ( Columns) 10/31/2020 15 11/15/2020
4.3 Wide Flange Installation/Full Weld ( Beams ) 11/10/2020 15 11/25/2020
4.4 Wide Flange Installation/Full Weld (Roof Beams ) 11/26/2020 15 12/11/2020
4.5 Painting of Installed Wide Flange ( I-Beams ) 12/11/2020 4 12/15/2020
4.6 Fabrication of Roof Truss :
Strut Fabrication and installation 12/12/2020 10 12/22/2020
Arc Strut Rafter Fabrication and Installation 12/23/2020 20 1/12/2021
C- Purlins Installation 1/7/2021 15 1/22/2021
4.7 Roof Truss Painting Works 1/19/2021 2 1/21/2021

5.0 CONCRETE WORKS ( Phase 2 )


5.1 Floor Concreting ( Area =975 square meter )
Volume = 121.875 cu.m 1/22/2021 10 2/1/2021

6.0 DEMOBILIZATION / GENERAL CLEANING 2/2/2021 1 2/2/2021

Prepared by : Checked by :

Engr. Walter L. Garcia Ma. Cristina B. Santos


Project Engr. CDDC President
Date : 26-Nov-20
Project : PROPOSED MULTI-PURPOSE GYM ( STEEL STRUCTURE ) Phase 1
Location : C-5 Access Road, Brgy. IVC, Marikina City
Subject : PROJECT SCHEDULE
Duration :

ITEM DESCRIPTION OF WORK DATE OF DURATION DATE OF


START ( Days ) FINISH
1.0 CONCRETE WORKS ( Phase 1 )
1.1 Ground Beam Formworks and concrete pouring 11/23/2020 4 11/27/2020
1.2 CHB Laying ( Perimeter ) 11/23/2020 5 11/28/2020
1.3 Backfilling / Tampering ( 1200 cu.m ) 11/25/2020 4 11/29/2020
1.4 Gravel Bedding of Gym Floor/Tampering 11/30/2020 3 12/3/2020

2.0 STEEL WORKS


2.1 Steel Plate Installation 11/24/2020 1 11/25/2020
2.2 Wide Flange Installation/Full Weld ( Columns) 11/26/2020 10 12/6/2020
2.3 Wide Flange Installation/Full Weld ( Beams ) 12/7/2020 15 12/22/2020
2.4 Wide Flange Installation/Full Weld (Roof Beams ) 12/23/2020 15 1/7/2021
2.5 Painting of Installed Wide Flange ( I-Beams ) 1/8/2021 4 1/12/2021
2.6 Fabrication of Roof Truss :
Strut Fabrication and installation
1/5/2021 20 1/25/2021
Arc Strut Rafter Fabrication and Installation
C- Purlins Installation 1/20/2021 10 1/30/2021
2.7 Roof Truss Painting Works 1/31/2021 3 2/3/2021

3.0 CONCRETE WORKS ( Phase 2 )


3.1 Floor Concreting ( Area =975 square meter )
Volume = 121.875 cu.m 2/4/2021 6 2/10/2021

4.0 DEMOBILIZATION / GENERAL CLEANING 2/11/2021 1 2/12/2021


101

Prepared by : Checked by :

Engr. Walter L. Garcia Ma. Cristina B. Santos


Project Engr. CDDC President