Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology


covering 178 Local Government Units (LGUs) in the Manila Bay Region

Terms of Reference (TOR)


for the
Conduct of the Feasibility Study (F/S) for the Appropriate Waste-to-Energy (WTE)
Technology covering 178 Local Government Units (LGUs) in the Manila Bay Region

1. BACKGROUND/RATIONALE

1.1 Contracting Authority

The 2014 General Appropriations Act (GAA) has allocated the amount of
PhP400,000,000.00 for the conduct of F/S for non-public-private partnership
projects in the pipeline to be administered by the National Economic and
Development Authority (NEDA). NEDA shall be the Executing Agency and
contracting party while DENR-EMB shall be the Implementing Agency. The
proposed project is consistent with DENR-EMB’s major plans and programs,
particularly in formulating/developing strategic policies for better solid waste
management and in assisting LGUs in the availment/use of alternative
technologies for waste disposals.

1.2 Relevant Country / Sector Context

To improve the management of solid wastes in the country, Republic Act (RA)
No. 9003, otherwise known as the Ecological Solid Waste Management Act
(ESWMA)1, was enacted. However, despite the enactment of the Law, 923 open
and controlled dumpsites are still operating nationwide. The dumpsites, which are
generally classified as unmanaged or poorly managed, should have already been
closed and/or rehabilitated. At present, only 72 sanitary landfills (SLFs) are in
operation, serving 137 LGUs nationwide. This number is relatively small
compared to the more than 1,600 cities and municipalities in the Philippines. Due
to the high upfront costs for the development of Solid Waste Management (SWM)
facilities, which limit the capacity of LGUs in investing in such projects, there is a
need for the National Government (NG) to start-up the implementation of SWM
approaches towards increasing the service coverage of SWM facilities to more
LGUs.

The condition of the Manila Bay has worsened over the years due to the increasing
pollution load carried by rivers draining into the Bay, exacerbated by the
mismanagement of solid wastes. This has prompted the Supreme Court, through its
18 December 2008 decision, to issue a mandamus ordering relevant government
agencies, in coordination with the concerned LGUs surrounding the Manila Bay, to
clean up, rehabilitate and preserve the Bay. Furthermore, DENR, as the primary
government agency mandated to conserve, manage and develop the country’s

1
RA 9003, An Act Providing for an Ecological Solid Waste Management Program, Creating the Necessary
Institutional Mechanisms and Incentives, Declaring Certain Acts Prohibited and Providing Penalties,
Appropriating Funds Therefor, and for Other Purposes, 26 January 2001,
<http://www.lawphil.net/statutes/repacts/ra2001/ra_9003_2001.html>.
Page 2 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

environment and natural resources2, was directed to fully implement its


Operational Plan for the Manila Bay Coastal Strategy as well as to spearhead the
implementation of activities/interventions related to the cleanup, rehabilitation and
protection of the Manila Bay area.

With the need to study appropriate SWM measures and in compliance with the
continuing mandamus, DENR intends to immediately pursue SWM interventions
in the Manila Bay region to improve its water quality and condition and to ensure a
renewable and sustainable means of addressing the SWM problems in the region.
Since methane (a by-product of SLFs) has high potential to be converted into
energy, provided that its percentage in the landfill gas is enough to be processed by
power generators, DENR is exploring the possibility of adopting certain WTE
technologies as solutions to the SWM issue. However, past case studies show that
the WTE potential for new SLFs are limited by RA 9003 since the Act encourages
the diversion of biodegradable wastes from disposal facilities. As such, there is a
need to undertake a comprehensive study on the exploration of WTE solutions for
SWM problems in the country taking into consideration institutional, legal and
technical limits.

1.3 Current State of the Relevant Sector

Despite the effectivity of RA 9003 since 2001, the LGUs’ compliance with the
mandates of the Law is still very low. Moreso, finding suitable disposal sites for
SWM could be a challenge especially in highly urbanized cities (HUCs) and/or
urbanizing cities. LGU interventions, such as Materials Recovery Facilities
(MRFs), source reduction, and the likes, have already been implemented; however,
majority of the established MRFs, with composting and recycling components, are
in an “On and Off” operation. There is actually no continuity in the efforts initiated
by some LGUs, except perhaps those implemented by some non-government and
private entities. Based on the National Solid Waste Management Commission
(NSWMC) database, about 9,219 out of 42,000 barangays today have access to
MRFs in the country. For the LGUs in Metro Manila, an average of 42.0%
diversion rate has been achieved through source reduction, composting and
recycling while the rest of the LGUs in the country only reported a 36.9% average
diversion rate. This limitation has been a deterrent factor to the participation of
recycling industries, whose businesses rely on the steady supply of usable waste
materials.

The pressing concern on the increasing volume of wastes produced, its undeniable
impact on climate change, and the relatively unsustainable SWM interventions
among LGUs are some of the reasons why the Government should push for the
adoption of the appropriate WTE technologies to complement SLFs in the country.
WTE technologies will convert wastes into a genuine resource-generating and
sustainable renewable energy with minimal residues brought to SLFs, thus,
extending the latter’s life spans and minimizing land requirements for such.

2
Pursuant to Section 4 of Executive Order (EO) No. 192 (1987), which provides for the reorganization of
DENR, and Section 19 of RA 9275, otherwise known as the Clean Water Act of 2004, which delegates the
DENR as lead agency in the implementation and enforcement of a Comprehensive Water Quality
Management.
Page 3 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

1.4 Related Projects/Programs and Other Donor Activities

The following projects may complement the proposed F/S under this TOR:

1.4.1 Solid Waste Management Sector Project (SWMSP). The project, which
is now on its preparatory stage, aims to support SWM in the Philippines
by assisting LGUs through investments in related infrastructures,
complemented with technical assistance for capacity development. The
Project covers three (3) pilot LGUs to showcase appropriate models for
SWM in highly urbanized regions, tourist destination areas and cluster of
municipalities. The Asian Development Bank (ADB) loan, however, is
not specifically intended for the determination of WTE approaches but
more on opening a finance window for the waste sector in general; and

1.4.2 Nationally Appropriate Mitigation Actions (NAMA) Support Project.


The goal of the NAMA Support Project, which is a pipeline project of
NSWMC in partnership with the Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ) GmbH, is for the waste sector to
contribute to the Philippines’ transition towards a low carbon
development path as enshrined in the “Mitigation Pillar” of the National
Framework Strategy on Climate Change (NFSCC) and anchored on
strategies that offer the most co-benefits to stimulate sustainable
development. The collaboration focuses on opening a concessional
finance window for all LGUs and private entities that intend to
implement waste management projects with established and verifiable
greenhouse gases (GHG) mitigation impacts. While WTE projects could
be considered under NAMA, only certain WTE schemes could be pilot-
tested under the same, such as, inter alia, anaerobic digestion or
methane-to-electricity schemes.

2. OBJECTIVE, PURPOSE & EXPECTED RESULTS

2.1 Overall Objective of the Study

2.1.1 To provide a comprehensive basis for the establishment, development,


promotion, implementation and monitoring of WTE technologies
appropriate for the Manila Bay region, taking into consideration the
technical, financial, socio-political, legal and institutional factors. This
also includes the adoption of appropriate WTE technologies based on its
contribution in achieving the waste diversion goal as indicated in the
2011-2016 Philippine Development Plan (PDP), with the value-added
process of energy generation;

The results of the proposed F/S should serve as a catalyst for the public
sector to implement SWM in a holistic, economical and efficient manner.
The Study should be able to determine the most appropriate WTE
technologies for the Philippines, and in particular, the LGUs in the Manila
Bay area, that would help reduce the amount of residual waste delivered to
existing landfills. It shall serve as a test case to achieve an improved
Page 4 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

waste management system through reuse, recycling, composting and


other resource recovery activities by 2016; and

2.1.2 To contribute to meeting national renewable energy targets, with positive


impact on the environment, relative to SWM in the country.

2.2 Specific Objective/s

2.2.1 To conduct a full-blown and comprehensive F/S for the determination of


the most appropriate WTE scheme/s and/or system/s for the Manila Bay
region, i.e., cutting across NCR, Regions III and IV-A, including:

2.2.1.1 Undertaking a complete Waste Analysis and Characterization


Study (WACS) for the LGUs in the Manila Bay area, consistent
with DENR standards;

2.2.1.2 Determining, through Value Analysis (VA) / Options Analysis3,


the most appropriate and cost-effective WTE scheme/s and/or
system/s that are technically, socially, financially and economically
viable for a type of LGU, or a cluster of LGUs, in the coverage area
based on, but not limited to, the following: volume and
characteristics of wastes, space and logistical requirements, air and
hazardous emissions monitoring system requirements and required
operator competencies, LGU capacity and capitalization
(institutional), legal and social parameters, and type of energy
produced; and

2.2.1.3 Developing a decision planning tool, e.g., software or program, that


can be used to determine the viability of a WTE system based on a
given set of parameters;

2.2.2 To conduct a workshop on the use of the planning tool and provide on-the-
job capacity-building and technology transfer to relevant Government
technical personnel who shall be detailed to the Study; and

2.2.3 To provide recommendations that will optimize the use and application of
WTE technologies in the Philippines.

2.3 Expected Result/s

2.3.1 The Study should be able to produce the comprehensive WACS that will
cover 178 LGUs in the Manila Bay area. A list of the 178 LGUs is
attached, to form part of this TOR, as Annex A.

2.3.2 By the end of the contract period under this TOR, the Consulting Firm is
expected to produce a full and comprehensive F/S that will recommend,
among others, the following:

3
In undertaking the VA/Options Analysis as a component of the scope of work for the F/S, the Consulting
Firm shall be guided by the Value Analysis Handbook for NEDA (2009), which may be downloaded from
<http://www.neda.gov.ph/wp-content/uploads/2014/01/Value-Analysis-Handbook.pdf>.
Page 5 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

2.3.2.1 A comprehensive, comparative evaluation of all WTE technologies


applicable/appropriate for the Philippines, with clear definitions
and detailed descriptions, including recommendations that will
optimize the use and application of WTE technologies in the
country;

2.3.2.2 Most appropriate and cost-effective WTE scheme/s and/or system/s


(i.e., an applicable technology or a combination of technologies) for
the 178 LGUs or a cluster of LGUs in the Manila Bay region that
are technically, socially, institutionally, financially and
economically sound, including, but not limited to, the preliminary
designs of said system/s, corresponding cost estimates,
implementation arrangements, and the most appropriate financing
scheme; and

2.3.2.3 A decision planning tool, e.g., software or program, that can be


used to determine the viability of a WTE system based on a given
set of parameters. This tool may be utilized by relevant
stakeholders for succeeding WTE projects.

2.3.3 The Consulting Firm should be able to conduct a workshop on the use of
the planning tool and provide on-the-job capacity-building and
technology transfer to relevant Government technical personnel, e.g.,
from NEDA and DENR, who shall be detailed to the Study.

3. SCOPE OF WORKS

3.1 Conduct of a full-blown and comprehensive F/S for the determination of the
most appropriate and cost-effective WTE scheme/s and/or system/s for the
Manila Bay region, cutting across NCR, Regions III and IV-A covering 178
LGUs, determined through VA/Options Analysis

3.1.1 Assessment of the Current Situation. This includes, among others,


researching on and comprehensively presenting the existing waste
management methodologies, or the lack thereof, in the Philippines, i.e.,
SLFs, WTE technologies, etc., and in particular, within the Manila Bay
region covering the 178 LGUs, as well as those internationally accepted
and/or practiced;

3.1.2 Data Collection. This covers, among others, area profiling, detailed waste
production trends/characterization, researching on available WTE
technologies, conduct of relevant surveys, etc. necessary for the Study as
well as the conduct of comprehensive WACS for the concerned LGUs,
consistent with DENR standards, which shall serve, among others, as
primary data for the determination of the appropriate WTE technologies for
the target LGUs in the Manila Bay area;

3.1.3 VA/Options Analysis. This includes a comprehensive study and


comparative evaluation of all possible WTE technologies (or a
combination of technologies) as options for managing municipal solid
Page 6 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

wastes (MSWs), taking into consideration, among others, the unique


situations/conditions of various cities, municipalities or metropolitan
clusters in the Manila Bay area and the accompanying technical,
environmental, logistical, socio-political, legal, regulatory and institutional
requirements therein as well as the general financial and economic
feasibility. The Consulting Firm should be able to determine the most
appropriate and cost-effective WTE system/scheme for the LGUs in the
Manila Bay region. The suggested scope of the comprehensive and
comparative analysis of the different WTE technologies for solid waste
processing, treatment and energy generation is attached as Annex B;

3.1.4 Technical Analysis. A further technical analysis shall be undertaken for the
recommended scheme/s and/or system/s, providing details on the LGU
clustering (if necessary), proposed location of the facility/ies, overall
technical design/s of the WTE system/s (complete with drawings, etc.), its
operations and other requirements. The study should also include an
analysis of the by-products/emissions of the proposed plants and include in
the proposed design the necessary emissions/effluent control mechanisms,
among others. The Consulting Firm shall also determine the type of
energy to be produced/energy potential based on WACS and the possible
off-takers of the supplied energy;

3.1.5 Financial and Economic Analyses. The financial and economic analyses
shall be undertaken to determine the viability/feasibility of the proposed
scheme/s and/or system/s. This shall include the
identification/determination of the financial and economic costs and
benefits of the project as well as the determination of the resulting financial
and economic indicators, i.e., internal rate of returns (IRRs), net present
values (NPVs), etc.4 A detailed breakdown of the cost estimates should be
provided;

3.1.6 Institutional Analysis. A comprehensive analysis on the institutional and


legal aspects of the project is to be undertaken. The Consulting Firm shall
determine the most appropriate institutional set-up for the project’s
successful implementation and operation, which reaps the highest benefits,
noting the involvement of multiple institutions, i.e., DENR, LGUs and the
potential power up-takers, among others;

3.1.7 Social Analysis. A comprehensive analysis on the social aspects of the


project, including, but not limited to, the social acceptability of the
proposed waste collection mechanisms and corresponding fees, if any; and

3.1.8 Other components of the F/S such as, but not limited to, the necessary
Environmental and Risk Analyses.

3.2 Development of a decision planning tool that can determine the viability of a
WTE system based on a given set of parameters

4
The Social Discount Rate (SDR) to be used for the economic analysis is 15 percent, as prescribe by the
Project Development Evaluation Manual (PDEM).
Page 7 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

3.2.1 The Consulting Firm shall determine the set of basic parameters for the
program and develop a decision planning tool, e.g., software or program,
which can determine the viability of a WTE system based on the given set
of parameters. DENR/NSWMC/concerned LGUs and other relevant
stakeholders should be able to use this planning tool as a guide in the
determination of the appropriate WTE scheme/s and/or system/s for
succeeding WTE projects; and

3.2.2 The Consulting Firm shall conduct a capacity-building workshop for


DENR, NEDA and other relevant stakeholders on the use of the tool.

3.3. Conduct of capacity-building and technology transfer for Government on-


the-job technical personnel

The Consulting Firm shall accommodate at least two (2) Government on-the-job
technical personnel, e.g., from NEDA and DENR, who shall be detailed to the
Study for the purpose of capacity-building and technology transfer.

4. TIMELINES AND DELIVERABLES

4.1. Commencement Date & Period of Implementation

The Study shall be undertaken within a period of Eight (8) Months, commencing
on the date of receipt of the Notice to Proceed (NTP).

4.2. Table of Deliverables

4.2.1 The Consulting Firm shall submit a Monthly Progress Report to NEDA
and DENR within seven (7) calendar days from end of agreed month-
period. The Monthly Progress Reports shall include, among others, updates
on the physical and financial accomplishments of each of the activities
under the Detailed Work and Financial Plan, difficulties encountered, and
measures taken to overcome them.

4.2.2 The deliverables for the subject Study as enumerated below shall be
submitted by the Consulting Firm in four (4) hard copies to DENR for
review and two (2) hard copies to NEDA for monitoring purposes and/or
payment processing. An electronic/soft copy shall also be submitted to
DENR/NEDA on the date/period specified hereunder:

DELIVERABLES TIMELINE

Detailed Work and Financial Plan:

 The detailed Work and Financial Plan shall describe the Within 10 calendar days
approach and methodologies for the conduct of WACS, from from the date of receipt
sampling plan preparation to the actual conduct of WACS, of the NTP
including laboratory analytical protocols to be used in data
collection, among others, consistent with the DENR standards
Page 8 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

for WACS;

 The detailed Work and Financial Plan shall also describe the NEDA/DENR shall
approach and methodologies for the comprehensive study and provide comments, if
comparative evaluation of all possible WTE technologies that any, on the Draft Work
and Financial Plan
are applicable to cities or cluster of cities and municipalities in
the Manila Bay region, covering, but not limited to, the within 4 calendar days
suggested scope provided under Annex B. This includes the from receipt thereof; the
proposed approach and methodology for the conduct of the Consulting Firm shall
VA/Options Analysis in determining the most appropriate and finalize the revised
cost-effective WTE technologies for the region, guided by the Work and Financial Plan
Value Analysis Handbook; (taking into
consideration /
 The detailed Work and Financial Plan shall include the incorporating the
resources deployment plan for each of the above activities and comments from
the financial requirements for the same; NEDA/DENR)

 The detailed Work and Financial Plan shall further outline the
proposed program for the on-the-job capacity-building and
technology transfer of the Government technical personnel
detailed to the Study; and

 The detailed Work and Financial Plan shall include the


proposed schedule, i.e., Gantt chart, for all activities/programs
of work necessary for the delivery of the intended outputs of
the Study, including, but not limited to, the conduct of WACS,
VA/Options Analysis, field works related to applicable tasks,
workshop for the use of the planning tool, and the on-the-job
capacity-building program.

Draft Inception Report: Within 6 weeks from the


approval of the Detailed
The Draft Inception Report shall include, among others, the Work and Financial Plan
approved Detailed Work and Financial Plan and the description
of the corresponding activities/programs of work/milestones
already accomplished/fulfilled by the date of submission thereof,
as well as the fulfilment of the study conditions enumerated NEDA/DENR shall
herein and/or the approaches and methodologies to be utilized in provide comments, if
the development of the Study. any, on the Draft
Inception Report within
7 calendar days from
receipt thereof

First Interim Report: Within 8 weeks from the


date of acceptance of the
The Consulting Firm shall produce a First Interim Report that: Draft Inception Report
 Integrates the preliminary results of the comparative analysis
of the different WTE Technologies for solid waste processing, NEDA/DENR shall
treatment and energy generation; provide comments, if
any, on the First Interim
 Integrates the list of potential sites; and
Report within 7 calendar
days from receipt
Page 9 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

Integrate individual WACS data results. thereof

Within 4 weeks from the


Presentation to concerned/appropriate bodies, e.g., NSWMC. date of acceptance of the
First Interim Report

Second Interim Report: Within 6 weeks from the


date of acceptance of the
The Consulting Firm shall produce a Second Interim Report, First Interim Report
which includes:

 Updating of the status of implementation in relation to the NEDA/DENR shall


scope of work; and provide comments, if
 Integration of the preliminary results of the VA/Options
any, on the Second
Analysis/feasibility and applicability of the different WTE to
cities or cluster of LGUs. Interim Report within 7
calendar days from
receipt thereof

Draft Final Report: Within 6 weeks from the


date of acceptance of the
The Consulting Firm shall produce a Draft Final Report, Second Interim Report
including a final presentation of each item in the scope of work
and the detailed WTE Feasibility Studies in the Manila Bay
region (first versions). NEDA/DENR shall
provide comments on
The Consulting Firm shall submit the first version of the WTE
Feasibility Studies among the clustered LGUs with options the Draft Final Report, if
citing comparative analyses among different technologies. any, within 7 calendar
days from receipt
thereof

Presentation to concerned/appropriate bodies, e.g., NSWMC. Within 14 calendar days


from the date of
acceptance of the Draft
Final Report

Final Report: Within 3 weeks from


acceptance of the
The Consulting Firm shall produce a Final Report, including the comments from
final versions of the detailed WTE Feasibility Studies in the NEDA/DENR on the
Manila Bay region. Draft Final Report

5. EXPERTISE REQUIREMENTS AND QUALIFICATIONS

The Consulting Firm shall field-in a Team with the following composition and
qualifications:

5.1 Project Manager (1)

5.1.1 Must be a WTE expert with at least 10 years of professional experience


in the design, implementation and monitoring of WTE projects;
Page 10 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

5.1.2 Must be a licensed engineer, preferably with a degree in civil, chemical,


mechanical, energy or environmental engineering;

5.1.3 Must also have an excellent technical and planning background; and

5.1.4 Preferred skills include project management, technical writing, capacity-


building, facilitation, and project implementation.

5.2 Senior SWM Specialist (1)

5.2.1 Must have at least five (5) years of professional experience in planning,
designing, evaluating, implementing and upscaling technologies and
approaches on municipal solid waste management as well as in SWM
monitoring;

5.2.2 Must have at least a bachelor’s degree in engineering, sciences or any


related discipline;

5.2.3 Must have technical expertise in scoping and evaluating the technical
and environmental merits of SWM systems;

5.2.3. Preferred skills include technical writing, capacity-building, facilitation,


and project implementation; and

5.2.4. Involvement in development of national policy/ies related to SWM or


supporting guidelines is a plus.

5.3. Senior WTE Specialist (1)

5.3.1 Must have at least five (5) years of professional experience in planning,
designing, evaluating, implementing and monitoring WTE projects;

5.3.2 Must have at least a bachelor’s degree in engineering, sciences or any


related discipline;

5.3.3 Must have technical expertise in scoping and evaluating the technical
and environmental merits of waste-to-energy systems;
5.3.4 Preferred skills include technical writing, capacity building, facilitation,
and project implementation; and

5.3.5 Involvement in development of national policy/ies related to WTE or


supporting guidelines is a plus.

5.4 SWM and/or WTE Junior Specialists (4)

5.4.1 Must have at least three (3) years of professional experience in planning,
evaluating, implementing and upscaling technologies and approaches on
municipal SWM with experience in WTE planning, designing,
implementation and monitoring;
Page 11 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

5.4.2 Must have at least a bachelor’s degree in engineering, sciences or any


related discipline;

5.4.3 Must have technical expertise in scoping and evaluating the technical
and environmental merits of WTE systems; and

5.4.4 Involvement in development of national policy/ies related to SWM/WTE


or supporting guidelines is a plus.

5.5 Financial Specialist (1)

5.5.1 Must have at least three (3) years of experience in the financial analysis
of urban infrastructure projects, preferably with a background on the
financial analysis of SWM and/or WTE projects;

5.5.2 Must have at least a bachelor’s degree in finance, accountancy or any


related discipline; and

5.5.3 Must be knowledgeable on, but not limited to, cost recovery
mechanisms, national-local government sharing scheme and climate
financing for SWM.

5.6 Economic Specialist (1)

5.6.1 Must have at least three (3) years of experience in economic analysis of
urban infrastructure projects, preferably with a background on the
economic analysis of SWM and/or WTE projects; and

5.6.2 Must have at least a bachelor’s degree in economics or any related


discipline.

5.7 Information Technology (IT) Specialist (1)

5.7.1 Must have at least three (3) years of experience in software


programming, database design and implementation, operating systems,
computer essentials and fundamentals, among others;

5.7.2 Must have at least a bachelor’s degree in computer engineering,


computer sciences, IT or any related discipline.

5.8 Other Specialists

The consultant shall employ other experts which he/she deems necessary for the
implementation of the Study to meet the deadline set for the Study.

At least one (1) of the senior consultants, preferably the Team Leader, must be
knowledgeable on VA/Options Analysis and have at least five (5) years of work
experience related thereto.
Page 12 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

6. CRITERIA FOR SELECTION

6.1 The prospective Consultancy Firms must have at least 10 years of relevant
experience related to this TOR and will be rated based on the criteria as shown
in Annex C (Rating Table for Shortlisting of Consulting Firms). Prospective
bidders are required to submit the following:

6.1.1 Copies of Certificate of Project Completion and Acceptance or


equivalent Certification from their previous related studies/projects
within the past five (5) years;

6.1.2 Company profile; and

6.1.3 Curriculum Vitae (CV) of key experts highlighting their relevant work
experience.

Note: Related experiences/studies include conduct of pre-FS and/or FS for the Team
Leader and relevant work experience as stated in item 7.1.1. for the WTE Expert;
and the key experts requested to indicate 1) his/her role in a specific project, 2)
the exact duration that they have worked on the project; and 3) a brief
description of the tasks that they have carried out (e.g., experience in the conduct
of VE/VA).

6.2 The Consulting Firm shall be selected using the Quality-Cost Based Selection
procedure under Republic Act (RA) 9184 (Government Procurement Reform
Act) and its Revised Implementing Rules and Regulations (IRR) and shall be
based on the following criteria: 80% Technical Proposal and 20% Financial
Proposal.

6.3 The prospective Consulting Firms shall follow the Guidelines in the Preparation
of Eligibility Requirements as attached in Annex D of this TOR.

7 SOURCE OF FUNDS

Funds for the conduct of the Study will be sourced from the F/S Fund being
administered by NEDA.

8 INSTITUTIONAL SET-UP / RESPONSIBILITIES

8.1 Executing Agency / NEDA

8.1.1 Shall be the Executing Agency (i.e., representative of the Government in


the Contract Agreement with the Consulting Firm);

8.1.2 Shall, through its NEDA Bids and Awards Committee (NBAC), be
responsible for facilitating the bidding and tendering of the consultancy
services in compliance with RA 9184 and its Revised IRR with the
Implementing Agency as End-User;
Page 13 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

8.1.3 Shall be responsible for the disbursement of the fund for the conduct of
the F/S once the contract becomes executed;

8.1.4 Shall reimburse or pay in behalf of the Consulting Firm for amounts paid
on account of all taxes, duties, levies and other impositions under the
laws and regulations of the Philippines or any political subdivision or
agency thereof (other than personnel who are citizens or permanent
residents of the Philippines), in respect of any payment made to the
Consulting Firm in connection with the carrying out of the services;

8.1.5 Shall be responsible for the preparation and submission of financial


reports as required by the Department of Budget and Management
(DBM) and other reportorial requirements regarding the F/S Fund
administration; and

8.1.6 Shall detail counterpart technical personnel to the Study for the purpose
of on-the-job capacity-building and technology transfer.

8.2 Implementing Agency / DENR

8.2.1 Shall be the beneficiary/End-User of the consultancy services;

8.2.2 Shall be responsible for contract implementation and management,


including ensuring the quality of outputs. Further, the Implementing
Agency shall be responsible for the monitoring and evaluation of the
progress of the Study and approval of reports to ensure delivery of
outputs as specified in Sections 2, 3 and 4 of this TOR;

8.2.3 Shall provide assistance in coordination with other agencies related to


the Study;
8.2.4 Shall warrant that the Consulting Firm shall have free and unimpeded
access to all lands and properties for the effective execution of the
services. Likewise, DENR shall be responsible for any damage to such
land or any property thereon resulting from such access (unless such
damage is caused by the wilful default or negligence of the Consulting
Firm or its staffs);

8.2.5 Shall provide the Consulting Firm the necessary/available


information/data and also, if available, copies of previous related studies;

8.2.6 Shall evaluate all request for payments/billings and endorse to NEDA
upon determination of the acceptability/correctness of the same;

8.2.7 Shall report to NEDA the progress (physical and financial) of the Study
on a quarterly basis for monitoring purposes; and

8.2.8 Shall detail counterpart technical personnel to the Study for the purpose
of on-the-job capacity-building and technology transfer.
Page 14 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

8.3 Consulting Firm

8.3.1 Shall be responsible for the conduct of the Study and the timely delivery
of results/outputs as indicated under Sections 2, 3 and 4 of this TOR;

8.3.2 Shall be responsible for the provision of the necessary office space,
which shall be within close proximity to NEDA, for the key personnel
and support staffs as well as the Government’s detailed personnel,
including the necessary office equipment (i.e., computers, printers, office
supplies, etc.) for the conduct of the Study. All equipment procured or
used in the conduct of the Study shall be transferred to NEDA at the end
of the Study;

8.3.3 Shall shoulder all expenses required in the conduct of the Study,
including, among others, the travel costs and lodging of detailed
Government personnel during field visits, except for their salaries;

8.3.4 Shall (a) carry out the services with sound engineering theories and
practices to ensure that the final works will provide the most economical
and feasible development for the Study, (b) accept full responsibility for
the consultancy services to be performed under this TOR for which the
Consulting Firm is liable to DENR, (c) perform the works required in an
efficient and diligent manner and shall use its best effort to keep
reimbursable costs down to the possible minimum without impairing the
quality of services rendered; and (d) comply with, and strictly observe
any law regarding workmen’s health and safety, workmen’s welfare,
compensation for injuries, minimum wage, hours of labor and other
labor laws;

8.3.5 Shall (a) keep accurate and systematic records and accounts in respect of
the services in such form and detail as is customary and sufficient to
establish accurately that the costs and expenditures under this TOR have
been duly incurred; and (b) permit the duly authorized representatives of
the Government from time to time to inspect its records and accounts as
well as to audit the same;

8.3.6 Shall not assign nor sub-contract any part of the professional engineering
services under this TOR to any person or firm, except with prior written
consent of DENR. The approval by the Government to the assignment of
any part of said services or to the engagement by Consulting Firm of
sub-contractors to perform any part of the same shall not relieve the
Consulting Firm of any obligations under this TOR;

8.3.7 Shall, during or after the termination of the Study, limit its role to the
provision of the services and hereby disqualifies itself and any other
contractor, consulting engineer or manufacturer with which it is
associated or affiliated, from the provision of goods and services other
than the Services herein, except as DENR may otherwise agree;
Page 15 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

8.3.8 Shall prohibit full-time foreign staff during his/her assignment under this
TOR to engage, directly or indirectly, either in his name or through the
Consulting Firm, in any business or professional activities in the
Philippines other than the performance of his duties or assignment under
this TOR;

8.3.9 Shall not, at any time, communicate to any person or entity any
information disclosed to the Consulting Firm for the purpose of this
services, nor shall the Consulting Firm make public any information as
to the recommendations formulated in the course of or as a result of the
services, except with prior consent of DENR;

8.3.10 Shall agree that nothing contained herein shall be construed as


establishing or creating between the Government and the Consulting
Firm, the relationship of employer and employee or principal and agent,
it being understood that the position of the Consulting Firm and anyone
else performing the services is that of an independent contractor;

8.3.11 Shall hold the Government free from any and all liabilities, suits, actions,
demands or damages arising from death or injuries to persons or
properties, or any loss resulting from or caused by said personnel
incident to or in connection with the services under this TOR. The
Consulting Firm shall agree to indemnify, protect and defend at its own
expense the Government and its agents from and against all actions,
claims and liabilities arising out of acts done by the Consulting Firm or
its staffs in the performance of the services, including the use of, or
violation of any copyrighted materials, patented invention, article or
appliance; and

8.3.12 Shall provide on-the-job capacity-building and technology transfer to the


Government’s technical personnel detailed to the Study.

9 APPROVED BUDGET FOR THE CONTRACT (ABC)

9.1 The ABC for the proposed F/S is FIFTY-THREE MILLION NINE
HUNDRED FORTY-FOUR THOUSAND NINE HUNDRED EIHTY and
00/100 PESOS ONLY (PhP53,944,980.00), inclusive of all applicable
government taxes and charges, professional fees, and other incidental and
administrative costs which shall be paid on a reimbursement basis (e.g., travel
expenses, communication expenses, office supplies/space and other expenses
deemed necessary for the completion of the Study as certified by the Executing
Agency). Attached, as Annex E, is the breakdown of the ABC.
9.2 Please note that the consulting contract shall be a fixed price contract. Any
extension of the contract time shall not involve any additional cost to the
Government.

9.3 All equipment, materials, etc., acquired for the Study shall be turned over to
NEDA at the conclusion of the Study.
Page 16 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

10 PAYMENT SCHEME/SCHEDULE

10.1 Billing for reimbursable items shall be on a monthly basis, based on the actual
expenses incurred and supported by official receipts/documents, including the
monthly progress reports.

10.2 Billing for non-reimbursable items, including professional fees, shall be in


accordance with the following delivery schedule, subject to the usual
Government accounting and auditing requirements.

Upon acceptance of Inception Report 10%


Upon acceptance of First Interim Report 10%
Upon acceptance of Second Interim Report and WACS 30%
Upon acceptance of Draft Final Report and the first versions
of WTE evaluation 30%
Upon acceptance of the Final Report 20%
100%

10.3 An advance payment shall be made to cover mobilization costs, but shall not
exceed 10% of the contract amount, subject to the posting of an irrevocable
standby letter of credit issued by an entity acceptable to NEDA and of an equal
amount to the advance payment. The advance payment shall be repaid by the
Consulting Firm by deducting from his subsequent billings / payments such sum
as agreed upon during contract negotiations until fully liquidated within the
duration of the contract.

11 RETENTION PAYMENT

11.1 A retention payment of 10% shall be withheld. It shall be based on the total
amount due to the Consulting Firm prior to any deduction and shall be retained
from every progress payment until 50% of the value of Study, as determined by
NEDA, are completed. If, after 50% completion, the Study is satisfactorily done
and on schedule, no additional retention shall be made; otherwise, the 10%
retention shall be imposed.

11.2 The total “retention money” shall be due for release upon approval of the Final
Report. The Consulting Firm may, however, request the substitution of the
retention money for each progress billing with irrevocable standby letters of
credit from a commercial bank, bank guarantees or surety bonds callable on
demand, of amounts equivalent to the retention money substituted for and
acceptable to NEDA, provided that the project is on schedule and is
satisfactorily undertaken. Otherwise, the 10% retention shall be made. Said
irrevocable standby letters of credit, bank guarantees and/or surety bonds, to be
posted in favor of NEDA shall be valid for the duration of the contract.

12 LIQUIDATED DAMAGES

12.1 Where the Consulting Firm refuses or fails to satisfactorily complete the work
within the specified contract time, plus any time extension duly granted and is
Page 17 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

hereby in default under the contract, the Consulting Firm shall pay NEDA for
liquidated damages, and not by way of penalty, an amount, as provided in the
conditions of contract, equal to at least one tenth (1 /10) of 1% of the cost of the
unperformed portion of the works for every day of delay. Should the amount of
liquidated damages reach 15% of the contract amount, NEDA shall, at its own
discretion, terminate the contract without prejudice to any further action it may
take to recover whatever losses incurred due to non-performance of the
Consulting Firm.

12.2 To be entitled to such liquidated damages, NEDA does not have to prove that it
has incurred actual damages. Such amount shall be deducted from any money
due or which may become due the Consulting Firm under the contract and/or
collect such liquidated damages from the retention money or other securities
posted by the Consulting Firm, whichever is convenient to NEDA.
Page 18 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

ANNEX A

MANILA BAY REGION


REGION PROVINCE NO. MUNICIPALITY/CITY Income City
1 DINALUPIHAN 1st
2 HERMOSA 1st
3 MARIVELES 1st
BATAAN
4 ORANI 1st
5 LIMAY 1st
6 ORION 2nd
3 7 ABUCAY 3rd
8 BAGAC 3rd
9 MORONG 3rd
10 PILAR 3rd
11 CITY OF BALANGA (Capital) 4th Component
12 SAMAL 4th
1 ANGAT 1st
2 BALAGTAS (BIGAA) 1st
3 BULACAN 1st
4 CITY OF SAN JOSE DEL MONTE 1st Component
5 HAGONOY 1st
6 MARILAO 1st
7 NORZAGARAY 1st
8 SAN RAFAEL 1st
BULACAN

9 DOÑA REMEDIOS TRINIDAD 1st


10 BALIUAG 1st
11 BOCAUE 1st
12 CALUMPIT 1st
3 13 GUIGUINTO 1st
14 PLARIDEL 1st
15 PULILAN 1st
16 SAN ILDEFONSO 1st
17 SAN MIGUEL 1st
18 SANTA MARIA 1st
19 BUSTOS 2nd
20 PANDI 2nd
21 OBANDO 2nd
22 CITY OF MALOLOS (Capital) 3rd Component
23 CITY OF MEYCAUAYAN 3rd Component
24 PAOMBONG 3rd
Page 19 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

REGION PROVINCE NO. MUNICIPALITY/CITY Income City


1 GENERAL TINIO (PAPAYA) 1st
2 GUIMBA 1st
3 PANTABANGAN 1st
4 SAN ANTONIO 1st
5 SAN LEONARDO 1st
6 SANTA ROSA 1st
7 CABANATUAN CITY 1st Component
NUEVA ECIJA 8
9
TALAVERA
CABIAO
1st
1st
10 CARRANGLAN 1st
11 ALIAGA 2nd
12 JAEN 2nd
13 BONGABON 2nd
14 RIZAL 2nd
15 SAN ISIDRO 2nd
3 16 LAUR 3rd
17 LUPAO 3rd
18 SAN JOSE CITY 3rd Component
19 SANTO DOMINGO 3rd
20 ZARAGOZA 3rd
21 GABALDON (BITULOK & SABANI) 3rd
22 LICAB 4th
23 LLANERA 4th
24 SCIENCE CITY OF MUÑOZ 4th Component
25 PEÑARANDA 4th
26 QUEZON 4th
27 TALUGTUG 4th
28 CITY OF GAPAN 4th Component
29 GENERAL MAMERTO NATIVIDAD 4th
30 PALAYAN CITY (Capital) 5th Component
1 SAN SIMON -
2 MABALACAT CITY - Component
3 ANGELES CITY 1st Highly
4 MACABEBE 1st
5 MAGALANG 1st
6 MEXICO 1st
PAMPANGA

7 PORAC 1st
8 CITY OF SAN FERNANDO (Capital) 1st Component
9 APALIT 1st
10 ARAYAT 1st
11 CANDABA 1st
3 12 FLORIDABLANCA 1st
13 GUAGUA 1st
14 LUBAO 1st
15 MASANTOL 2nd
16 SAN LUIS 3rd
17 SANTA ANA 3rd
18 BACOLOR 3rd
19 MINALIN 4th
20 20. SANTA RITA 4th
21 21. SANTO TOMAS 4th
22 22. SASMUAN (Sexmoan) 4th
Page 20 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

REGION PROVINCE NO. MUNICIPALITY/CITY Income City


1 CITY OF TARLAC (Capital) 1st Component

TARLAC
2 CAPAS 1st
3 CONCEPCION 1st
3 4 VICTORIA 2nd
5 2. BAMBAN 2nd
6 7. LA PAZ 2nd
1 CITY OF DASMARIÑAS - Component
2 BACOOR CITY - Component
3 IMUS CITY - Component
4 ALFONSO 1st
5 CARMONA 1st
6 GEN. MARIANO ALVAREZ 1st
7 GENERAL TRIAS 1st
8 NAIC 1st
CAVITE

9 ROSARIO 1st
10 SILANG 1st
11 KAWIT 1st
4A 12 TANZA 1st
13 INDANG 1st
14 TAGAYTAY CITY 2nd Component
15 MARAGONDON 3rd
16 NOVELETA 3rd
17 AMADEO 4th
18 CAVITE CITY 4th Component
19 MAGALLANES 4th
20 MENDEZ (MENDEZ-NUÑEZ) 4th
21 TERNATE 4th
22 TRECE MARTIRES CITY (Capital) 4th Component
23 GENERAL EMILIO AGUINALDO 5th
1 CABUYAO CITY - Component
2 CITY OF BIÑAN - Component
3 CITY OF CALAMBA 1st Component
4 SANTA CRUZ (Capital) 1st
5 CITY OF SANTA ROSA 1st Component
6 LOS BAÑOS 1st
LAGUNA

7 SAN PABLO CITY 1st Component


8 SAN PEDRO 1st
9 BAY 2nd
10 CALAUAN 2nd
4A 11 SINILOAN 2nd
12 NAGCARLAN 2nd
13 ALAMINOS 3rd
14 CAVINTI 3rd
15 KALAYAAN 3rd
16 LUMBAN 3rd
17 PAGSANJAN 3rd
18 PILA 3rd
19 LUISIANA 4th
20 MAGDALENA 4th
Page 21 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

REGION PROVINCE NO. MUNICIPALITY/CITY Income City


21 MAJAYJAY 4th

LAGUNA
22 PAETE 4th
23 PANGIL 4th
24 SANTA MARIA 4th
4A 25 LILIW 4th
26 VICTORIA 4th
27 FAMY 5th
28 MABITAC 5th
29 RIZAL 5th
1 BINANGONAN 1st
2 CAINTA 1st
3 CITY OF ANTIPOLO 1st Component
4 PILILLA 1st
RIZAL

5 TAYTAY 1st
6 ANGONO 1st
4A 7 RODRIGUEZ (MONTALBAN) 1st
8 SAN MATEO 1st
9 TANAY 1st
10 MORONG 2nd
11 TERESA 2nd
12 CARDONA 3rd
13 JALA-JALA 4th
1 MANILA - Highly
4TH DISTRICT

2 CITY OF LAS PIÑAS 1st Highly


3 CITY OF MAKATI 1st Highly
4 CITY OF MUNTINLUPA 1st Highly
5 CITY OF PARAÑAQUE 1st Highly
6 PASAY CITY 1st Highly
7 TAGUIG CITY 1st Highly
8 PATEROS 1st
NCR
2ND DISTRICT

1 CITY OF MANDALUYONG 1st Highly


2 CITY OF MARIKINA 1st Highly
3 3. CITY OF PASIG 1st Highly
4 5. CITY OF SAN JUAN 1st Highly
5 4. QUEZON CITY Spe Highly
3RD DIST

1 1. CALOOCAN CITY 1st Highly


2 2. CITY OF MALABON 1st Highly
3 4. CITY OF VALENZUELA 1st Highly
4 3. CITY OF NAVOTAS 2nd Highly
Page 22 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

ANNEX B

Comprehensive, Comparative Analysis of the Different Waste-to-Energy (WTE)


Technologies for Solid Waste Processing, Treatment and Energy Generation

 WTE technology evaluation consists of a comprehensive review of the technical,


environmental (including climate change), logistical, financial and economic, socio-
political, legal, regulatory, institutional, and capacity-building requirements. In addition,
the Study shall be conducted within the context of national development plans and goals.

 Technology description includes, among others, the operating capacity of each system,
energy generation rate, recycling or compost production rate (where applicable), material
and energy flow analysis, and other conditions and requirements that dictate its feasibility
which include, but not limited to, the following:

 Conventional Thermal Treatment Technologies, such as, Gasification, Plasma Arc,


and Pyrolysis;
 Emerging Technologies, such as, Gasplasma, Thermal Cracking, Thermal Oxidation,
and Waste-to-Fuels; and
 Non-Burn Technologies, such as, Anaerobic Digestion and Non-burn Pyrolysis.

 Provision of information on the other available or emerging WTE technologies and


systems for the management of MSWs and their energy-generation potential.

 Identification of conditions that will render WTE schemes appropriate to certain


LGUs/clusters, including, but not limited to, capitalization, space requirements, logistical
requirements, air and hazardous emissions monitoring systems and required operator
competencies as well as the provision of technical recommendations that will optimize the
use and application of WTE technologies.
Page 26 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

ANNEX C

RATING TABLE FOR SHORTLISTING OF CONSULTING FIRMS


Conduct of the Feasibility Study (F/S) for the Appropriate Waste-to-Energy (WTE) Technology covering 178
Local Government Units (LGUs) in the Manila Bay Region
Name of Firm :
HURDLE RATE FOR SHORTLISTING = 70 points
POINTS/
RATING FACTORS Remarks
WEIGHT
I Qualification of Firm Subtotal 20
a. No. of years of relevant Firm's experience 20
- more than 20 years
- 11 to 20 years
- 10 years
- less than 10 years (disqualified)
II Project Manager Qualifications (1) 20
a. Work Experience in Waste-to-Energy 10
- more than 20 years
- 11 to 20 years
- 10 years
- less than 10 years (disqualified)
b. With 5 years VA / Options Analysis experience 5
c. Licensed Engineer with Degree on related field 5
- Ph.D.
- Master's
- Bachelor's
III Senior Specialists Qualifications (2) 20
a. Degree on related field 5
- Ph.D.
- Master's
- Bachelor's
b. Work Experience in WTE/SWM 10
- More than 15 years
- 5 to 15 years
- less than 5 years (disqualified)
c. With 5 years VA / Options Analysis experience 5
IV Other Specialists Qualifications (5) 20
a. Degree on related field 5
- Ph.D.
- Master's
- Bachelor's
b. Work Experience in related discipline 15
- More than 10 years
- 3 to 10 years
- less than 3 years (disqualified)
Page 26 of 29
Feasibility Study for the Appropriate Waste-to-Energy (WTE) Technology
covering 178 Local Government Units (LGUs) in the Manila Bay Region

V Job Capacity 20
a. Ongoing Contracts of the Firm 8
- 0
- 1
- 2 -3
- more than 3
b. Ongoing Contracts of the Team Leader 12
- 0
- 1
- 2-3
- more than 3
TOTAL 100
Page 17 of 29
Feasibility Study for the Appropriate
WTE Technology covering178 LGUs
in the Manila Bay Region

ANNEX D

Guidelines in the Preparation of Eligibility Requirements

The Eligibility Statement of the Consulting Firm interested to be considered for the services
contemplated shall fill up the enclosed form in six (6) copies and shall be submitted to the NEDA Bids
and Awards Committee (NBAC).

The numbers below correspond to the numbers contained in the form.

1. Type complete name of firm, year established, country of registry if foreign, and type of
organization whether individual, proprietorship, partnership, corporation or others.

2. Name of affiliate firms, their year established, countries of origin, and type of organization.

3. Type exact and complete home office, business address, telephone number and cable address.
For consulting firms of foreign registry, indicate if there is any branch office/s established in
the Philippines and where established.

4. If present firm is the successor to or outgrowth of one or more predecessor firms, type name/s
of former entity/ies and the year/s of their original establishment.

5. Present a brief narrative description of the firm.

6. Indicate clearly and accurately the names of the principals of the Consulting Firm and key
personnel. This must be accompanied by the curriculum vitae showing experience, professional
affiliations and language capability of the key personnel listed.

7. List not more than two (2) principals who may be contacted by this Office. Listed principals
must be empowered to speak for the firm on policy and contractual matters.

8. Indicate the number of employees by discipline. While some personnel may be qualified in
several disciplines, each person should be countered only once in accordance with his/her
primary functions.

a. Under this item, indicate the volume of gross consultancy fees per year for the last five
years. Gross fees received may be as Prime Consultant or in association or joint venture
with consulting firms.
b. Indicate bank references and bank address. It is a must that the latest balance sheet duly
signed by an independent Certified Public Accountant or accounting firm be submitted with
this form.
c. The chart listed under this item represents the ranges of professional Service Fee. The
indices should be indicated under item no. 10, last column.

9. Indicate appropriate types of services and fields of specialization the Consulting Firm is
technically and financially qualified to undertake.

10. This item represents the ongoing/committed consultancy projects of the Consulting Firm and
those handled in the last five years. First column represents the name of the project, the date the
project was started and how it was accomplished, i.e., as Prime Consultant or through joint
venture or in association with other Consulting Firms. If it was implemented in association with
other Consulting Firm, indicate name of Consulting Firm. Second column represents the
consulting services rendered, defined as clearly as possible. Third, column represents the Client
Page 18 of 29
Feasibility Study for the Appropriate
WTE Technology covering178 LGUs
in the Manila Bay Region

whom the services were rendered. Indicate the address of the Client. Last column represents the
level of fee received by the Consulting Firm as referred to under item 8c — INDEX FEE.

11. List of projects the firm has been engaged in consulting services.

NEW FIRMS (not reorganized or recently amalgamated but only established for less than two
(2) years reckoned from the date of preparation of this form) may accomplish this form and
questions on the form dealing with personnel or experience may be answered by citing
experience and capabilities of the principals and key staff of the firm based on performance and
responsibility while in the employ of others. In item 10, representative projects of key
personnel and principal offices for the last three (3) years plus consulting services rendered by
the New Firm may be indicated.

NOTE: Additional data, brochures, photos, etc. should not accompany this form unless specifically
requested.

CONSULTANT'S ELIGIBILITY DATE


FORM
CONSULTANT Year Country Type of Organization
Established Indiv. Part. Corp. Other
1) NAME
2) AFFILIATED FIRMS
3) HOME OFFICE/BUSINESS ADDRESS / TEL. NOS. CABLE ADDRESS
4)FORMER CONSULTANT'S NAME & YEAR ESTABLISHED FIRM
OWNERSHIP
5) NARRATIVE DESCRIPTION OF FIRM (Use other sheet if necessary)
6) PARTNERS, DIRECTORS, OFFICERS, KEY PERSONNEL OF
FIRM
NAME AND TITLE DEGREES(S) YEARS AGE
WITH FIRM
(ADD CURRICULUM VITAE
SHOWING EXPERIENCE,
PROFESSIONAL AFFILIATION AND
LANGUAGE CAPABILITY)
7) NAMES OF NOT MORE THAN TWO (2) PRINICPALS TO CONTACT
TITLE AND TELEPHONE NUMBER

8) NUMBER OF PERSONNEL IN PRESENT ORGANIZATION


DISCIPLINE NUMBER
PRINCIPAL
KEY TECHNICAL
a. Civil Engineers
b. Structural Engineers
c. Electrical Engineers
d. Mechanical Engineers
e. Architects
f. Economists
g. Others (Specify)
Page 19 of 29
Feasibility Study for the Appropriate
WTE Technology covering178 LGUs
in the Manila Bay Region

SUPPORT TECHNICAL
(Indicate as in above)

ADMINISTRATIVE STAFF
Indicate type, e.g. typist)

8a) ANNUAL VOLUME OF GROSS FEES 8b) FINANCIAL RATING OR


(LAST 5 YEARS) BANK REFERENCE

8c) RANGES OF PROFESSIONAL FEES INDEX


1. Less than P100,000
2. P100,000 to P250,000
3. P250,000 to P500,000
4. P500,000 to PI million
5. PI million to P2 million
6. P2 million to P5 million
7. P5 million to PIO million
8. 1110 million or greater

9) FIELDS OF SPECIALIZATION AND TYPES OF SERVICES


FIELDS OF SPECIALIZATION TYPES OF SERVICES
ABCDE
I. Engineering
2. Architecture
3. Finance
4. Management
5. Agriculture
6. Law
7. Others (Please Specify)

A - Advisory and Review Services


B - Pre-Investment or Feasibility Studies
C - Design
D — Construction Supervision
E - Other Technical Services or Special Studies

10) PROJECTS HANDLED BY THE CONSULTANT FOR THE LAST FIVE YEARS
PROJECT NAME/YEAR SERVICE CLIENT INDE
PRIME CONSULTANT/JOINT VENTURE RENDERED X FEE

11) TYPICAL PROJECTS FOR WHICH CONSULTING SERVICES HAVE BEEN FURNISHED BY
THE CONSULTANT (REFERENCE SHEETS MAY BE SUBMITTED FOR AS MANY PROJECTS
AS DESIRED)
NAME OF OVERALL PROJECT __________________________________________
LOCATION OF OVERALL PROJECT ______________________________________
CONSULTANT'S LEVEL OF EFFORT ______________________________________
(CONSULTANT'S FEE)
OWNER'S NAME AND ADDRESS
Page 20 of 29
Feasibility Study for the Appropriate
WTE Technology covering178 LGUs
in the Manila Bay Region

YEAR SERVICES COMPLETED


(INDICATE IF ESTIMATED OR ACTUAL)
ASSOCIATED FIRMS

DESCRIPTION OF PROJECT
DESCRIPTION OF SERVICES FIRM
PROVIDED
LIST TYPES OF SERVICES FOR ASSOCIATED ASPECTS OF OVERALL
PROJECTS
Page 21 of 29
Feasibility Study for the Appropriate
WTE Technology covering178 LGUs
in the Manila Bay Region

ANNEX E

Breakdown of the Approved Budget for the Contract (ABC)

Remuneration Expenses PhP17,940,000.00


(1) Project Manager
(1) Senior SWM Specialist
(1) Senior WTE Specialist
(4) SWM/WTE Specialist
(1) Financial Specialist
(1) Economic Specialist
(1) IT Specialist
Other Specialists

Reimbursable Expenses PhP33,807,600.00


Workshops for the WACS
Transportation Costs
Project Office Space
Supplies, Materials, Equipment, Drawings, etc.
Field Allowance (including housing, per diem of specialists/other
staffs/Government Counterparts during fieldworks, etc.)
Conduct of WACS
DENR/NEDA Representative Expenses (i.e., meals, travel expense, lodging)
Communication Expenses

Total Reimbursable Expenses PhP51,747,600.00


Contingency (5%) PhP2,197,380.00
GRAND TOTAL PhP53,944,980.00