2.0 PAINTING:
Paint =0.11ltrs/ m2
Painter =0.25hrs/m2
3.0 CONCRETING
2 Bricklayers =0.68hrs
4 Helpers =0.68hrs
Mixer =0.68hrs
Vibrator =0.68hrs
7th day strength =14N/mm2
28th day strength =21N/ mm2
2 Bricklayers =0.68hrs
4 Helpers =0.68hrs
Mixer =0.68hrs
Vibrator =0.68hrs
7th day strength =17N/mm2
28th day strength =25.5N/ mm2
2 Bricklayers =0.68hrs
4 Helpers =0.68hrs
Mixer =0.68hrs
Vibrator =0.68hrs
7th day strength =20N/mm2
28th day strength =30N/ mm2 2
2 Bricklayers =0.68hrs
4 Helpers =0.68hrs
Mixer =0.68hrs
Vibrator =0.68hrs
7th day strength =8N/mm2
28th day strength =13N/ mm2
2 Bricklayers =0.68hrs
4 Helpers =0.68hrs
Mixer =0.68hrs
Vibrator =0.68hrs
7th day strength =8N/mm2
28th day strength =13N/ mm2
Bricklayer =0.16hrs
Helper =0.16hrs
Mixer =0.02hrs
Cement =0.32Pkts
River sand =0.022 m3
3
Bricklayer =0.37hrs
Helper =0.37hrs
Labourer =0.2hrs
Cement =0.19Pkts
River sand =0.018 m3
20mm stones =0.038 m3
Bricklayer =0.37hrs
Helper =0.37hrs
2x Laborers =0.4hrs
N.B: When finding quantities using the ratio always add 25% shrinkage ratio.
e.g; Mix 1:2:4 (quantities per cu.mtr of concrete)
Cement = (1 7 ) + 0.25
= (1.25 7 ) x 1
= 0.18 m3
Sand = (1.25 7 ) x 2
=0.36 m3
Stones = (1.25 7 ) x 4
= 0.71 m3
Bricklayer =0.6hrs
Helper =0.6hrs
Mixer =0.6hrs
4x Laborer =0.6hrs
4.4 200mm.thk decorated conc. brickwork/ brise soleil per m2 in 1:4 cement mortar
2x lab(mixing) =0.47hrs
Bricklayer =1.06hrs
Helper =1.06hrs
For brick force
bricklayer =0.50hrs
Laborer =0.50hrs
Bricklayer =1.33hrs
Labourer =1.33hrs
Cement =0.26pkts
Building sand =0.028m3
Bricklayer =0.42hrs
Helper =0.42hrs
2x lab(mixing) =0.25hrs
Cement =0.15pkts
Building sand =0.02m3
Bricklayer =0.3hrs
Helper =0.3hrs
2x lab(mixing) =0.2hrs
6.1 Rough-cast
Honeycomb bricks will require one tenth of mortar (material for block making) and half the labor of blocks.
Cement =155kg
Building sand =0.32m3
Labour =12hrs
Bricklayer =0.059hrs
Helper =0.095hrs.
Grader =83.6m2/0.5hrs
Roller =83.6m2/0.4hrs
Bowser =83.6m2/0.2hrs
F.E.L =76m2/2hrs
Truck(6m3) =76m2/15.6hrs
Primer =2litr/m2
Stellalite =18kg/m2
10.0 EXCAVATIONS
10.1 Miscellaneous
Laborer =2.67hrs/m3 .
loading =4x laborers @ 0.33hrs/m3
Tipper =0.67hrs/5.5m3 average distance of 3km.
10.2 waste rock/hardcore per cu. mtr (Collect, spread and compact)
F.E.L =0.17hrs/m3 .
loading =4x laborers @ 0.33hrs/m3
Tipper =0.67hrs/5.5m3 average distance of 3km.
(Spread and compact)
1x laborer =4hrs/m3
F.E.L =0.17hrs/m3 .
loading =4x laborers @ 0.33hrs/m3
Tipper =0.67hrs/5.5m3 average distance of 3km.
Spread and compact
1x Labourer =3.5/m3
a. concrete outputs
Mixing plant:
11
12