Beruflich Dokumente
Kultur Dokumente
Research Article
Investigation of the Axial Force Compensation and Deformation
Control Effect of Servo Steel Struts in a Deep Foundation Pit
Excavation in Soft Clay
Honggui Di,1 Huiji Guo ,1 Shunhua Zhou ,1 Jinming Chen,2 and Lu Wen1
1
Shanghai Key Laboratory of Rail Infrastructure Durability and System Safety, Tongji University, Shanghai 201804, China
2
Ningbo Rail Transportation Group Co. Ltd., Ningbo 315012, China
Copyright © 2019 Honggui Di et al. This is an open access article distributed under the Creative Commons Attribution License,
which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
This study presents a comparative analysis of the deformation control effect of the hydraulic servo steel struts and ordinary steel
struts of a foundation pit based on the measured axial force of the steel struts, lateral wall deflection, and ground surface settlement
due to pit excavation. The results indicate that ordinary steel struts installed via axial preloading exhibit a disadvantageous axial
force loss with a maximum value equal to 86.7% of the axial preloading force. When compared with ordinary steel struts, the
hydraulic servo steel strut exhibits a superior supporting effect. The hydraulic servo steel strut adjusts the axial force in real time
based on the deformation of the retaining structure and the axial force of the struts. Thus, the ratio of maximum lateral deflection
to the excavation depth of a deep foundation pit in soft soil is less than 0.3%. Concrete struts undergo unsupported exposure
during the excavation process, leading to sharply increasing deformation of the retaining structure. Therefore, regarding a
foundation pit with strict requirements for deformation control, the use of hydraulic servo steel struts rather than concrete struts
is recommended.
are critical for deformation control of the foundation pit. standard section of Pit A and Pit B is 22.1 m, and the ex-
Tan and Wang [15] and Li et al. [16] proposed that exca- cavation depths vary from 24.7 m to 24.8 m.
vation by sections effectively controls the deflections of the A group of foundation pits (a pit complex) is under
diaphragm wall. construction on the northwest side of the Haiyan Road
Recently, engineers began improving deformation station of Line No. 5. The pit complex is 19 m deep and
control techniques for foundation pits from a support approximately 11–13 m from the edge of Pit A, and its
system standpoint. Yao et al. [17] illustrated that an increase excavation is complete. The Hongtai Building Group (lo-
in the stiffness and preaxial force of steel struts reduces cated on the southwest side of the station of Line No. 5) is
diaphragm wall deflections to a certain extent. Tanner approximately 10 m away from the edge of Pit B. The main
Blackburn and Richard [18] stated that the axial force of steel building of the Hongtai Building Group is a 24-story
struts is related to the mode and speed of excavation and the building with a 21.5 m–27.5 m bored pile foundation. The
installation of the adjacent strut. Chen [19] noted that the Muqi River flows on the east side of the station of Line No. 5,
use of concrete support effectively restrained the develop- approximately 60 m away from the edge of the foundation
ment of deformation in the retaining structure of the pit of Line No. 5. The surrounding environment is complex,
foundation pit. However, all traditional support methods thereby leading to higher requirements for deformation
exhibit shortcomings [20]. For example, the concrete strut is control on the project.
cast-in-place, and there is unsupported exposure during the Furthermore, the soft clay layer in the area is charac-
excavation process. Typically, there are high losses in axial terized by high natural water content, a high natural pore
force in the ordinary steel struts. ratio, high compressibility, low strength, and low perme-
To compensate for the flaws in traditional support ability, as shown in Figure 2. Consequently, the foundation
methods that exhibit axial force losses in ordinary steel pit of the station of Line No. 5 exhibited large deformation
struts, a hydraulic automatic servo control system (with a during excavation.
working mechanism that compensates for axial force loss in To reduce the impact of foundation pit excavation of
real time) is adopted to control the axial force of the steel Line No. 5 to the foundation pit group of Ningbo Center, the
struts and deformation during pit excavation [21]. However, Hongtai Building Group, and the current Line No. 1 station,
given its high cost, only a few engineering cases and studies hydraulic servo steel struts were adopted in this project.
have focused on introducing the engineering application of Although the diaphragm wall near corners featured much
hydraulic servo steel struts [22]. A focus problem in the field smaller displacements than those near the middle span of the
of pit engineering involves whether the hydraulic servo steel excavations [23], the hydraulic servo steel struts were
strut delivers a superior supporting effect to that from adopted in the section near the existing station of Line No. 1
traditional support methods. to preserve normal operations at the existing stations.
In this study, a new hydraulic servo steel strut system
with a working mechanism that simultaneously controls
axial force and displacement was designed and adopted to 2.2. Pit Supporting Structure. The primary foundation pit of
control deformation of a foundation pit excavated in soft the Line No. 5 station was constructed via the open-cut
soils. A comparative analysis of the deformation control method. The retaining structures consisted of diaphragm
effect of hydraulic servo steel struts and ordinary steel struts walls and an internal support system. The thickness of the
in pit excavation is presented based on measured data. diaphragm wall was 1000 mm (or 1200 mm), and its depth
Section 2 introduces the background of the project while was approximately 57.8 m. The internal support system
Sections 3–5 discuss the measured axial force of the steel consisted of concrete struts, ordinary steel struts, and hy-
strut, lateral wall deflection, and ground surface settlement draulic servo steel struts.
caused by the pit excavation. Section 6 presents the dis- There were seven struts along the depth of the foun-
cussion, and the conclusions are presented in Section 7. dation pit, with the first and fifth struts being concrete struts,
while the other five were steel struts. The dimensions of the
2. Project Description first concrete strut were 0.8 m wide × 1.0 m high, and for the
fifth concrete strut, they were 1.0 m wide × 1.0 m high. The
2.1. Project Overview. The Haiyan Road station is a transfer diameter of the steel strut was 609 mm. Figure 3 presents the
station of Ningbo Metro Line No. 1 and Line No. 5. The plan view of the supporting system. The average distance
existing Haiyan Road station of Line No. 1 lies along the east- between the concrete struts in Pit A and Pit B was 8.5 m and
west direction and is an underground two-story island 7.5 m, respectively, and the average distance between the
station, as shown in Figure 1. The Haiyan Road station of steel struts in Pit A and Pit B was 3.0 m and 2.2 m,
Line No. 5 lies along the north-south direction and is an respectively.
underground three-story island station. The existing Haiyan Part 1 of Pit A (see Figure 3) is some distance from the
Road station of Line No. 1 has been in service since 2014, and existing station and is the ordinary steel struts section. Thus,
a transfer point reserved for Line No. 5 is in its design stage. all the steel struts in the cross section are ordinary steel
The Haiyan Road station of Line No. 5 consists of a north struts, as shown in Figure 4(a). Part 3 of Pit B and Part 2 of
foundation pit (Pit A) and a south foundation pit (Pit B) with Pit A (see Figure 3) are close to the existing station and are
lengths of 125 m and 33 m, respectively. The width of the hydraulic servo steel strut sections. Hence, hydraulic servo
Advances in Civil Engineering 3
10m 30 m
20m
No
The Hongtai
The foundation pit
r th
building group
group under construction
Station
of
line
No. 1
11 m
10 m
33 m 125 m
Haiyan
22.1m
Existing Station of line No. 5 Pit A
Road Pit B
station
Muqi river
Figure 1: Plan view of the foundation pit of the Haiyan Road station of Line No. 5.
Kv and Kh
w (%) γ (kN·m–3) e Es0.1-0.2 (MPa) c′cu (kPa) φ′ (°) (10–5 cm/s)
0 40 80 15 18 21 0 1 2 0 6 12 0 20 40 0 20 40 0 5 10
0 1 1-1
Fill
Ball clay 12
Muddy clay 13
10 Muddy clay 2 2-1
Muddy clay 2 2-2
Silt 31
20 Silty clay 32
Silty clay 4 1-2
Depth (m)
Ball clay 42
30 Ball clay 51
Silty clay 52
Sandy silt 53
40
Silty clay 62
Ball clay 63
50
Silty clay 82
60
w Kv
wl Kh
wp
Figure 2: Physical and mechanical index of the soil layer. w—moisture content; wl —liquid limit; wp —plastic limit; c—soil gravity;
Es0.1-0.2—compression modulus; c′cu—effective stress cohesion; ϕ′cu—effective stress friction angle; e—porosity; Kv —vertical perme-
ability coefficient; Kh—horizontal permeability coefficient.
steel struts are used for the third, fourth, sixth, and seventh hydraulic module is composed of a hydraulic pump station
steel struts in the cross section, as shown in Figure 4(b). and a hydraulic jack while the automatic control system
The bottom of the pit was reinforced with cement mixing module is composed of automatic control hardware and
piles (3 m wide × 2.5 m deep) placed at intervals of 3 m. The computer software. The field arrangement of the hydraulic
cement mixing pile was also used to reinforce the soil within servo steel strut is presented in Figure 5.
3 m below the fifth concrete strut. The hydraulic servo steel strut system adopts the working
The hydraulic servo steel strut system consists of a hy- mechanism of simultaneous control of axial force and dis-
draulic module and automatic control system module. The placement, as shown in Figure 6. The control of axial force
4 Advances in Civil Engineering
Existing
Pit B Pit A
station
Concrete strut
(a)
Existing
Pit B Pit A
station
Figure 3: Plan view of the foundation pit: (a) layout of 1st and 5th struts; (b) layout of 2nd strut; (c) layout of 3rd, 4th, 6th, and 7th struts.
Unit: m
Concrete strut
3.4
3.4
3.2
3.2
3.4
Ordinary steel strut
3.4
3.3
Diaphragm wall
3.3
Concrete strut
Diaphragm wall
3.4
3.4
57.8
57.8
Reinforced area
Lattice column
Lattice column
(a) (b)
Figure 4: Cross section of the foundation pit in the standard section: (a) part 1; (b) parts 2 and 3.
element of the working mechanism entails that when the mechanism optimizes the set axial force and actively updates
measured axial force of the strut is less than a set value, the the set axial force in the automatic control system module.
axial force is actively restored to the set axial force of the The working mechanism of control of displacement implies
strut. This reduces the increasing deformation of the that when the installation of a hydraulic servo steel strut is
retaining structure caused by loss of stress in the steel struts. completed, the displacement of the servo steel strut jack is set
Concurrently, the adopted control of displacement working as the displacement datum point, and subsequently, the
Advances in Civil Engineering 5
(a) (b)
Figure 5: Installed hydraulic servo steel strut system: (a) hydraulic servo struts; (b) control system.
displacement is controlled from − 1 mm to 2 mm relative to The specific working mode of control of displacement is
the displacement datum point. The positive value indicates as follows: when the measured displacement of the servo
that the servo steel strut jack shrinks and the diaphragm wall steel strut jack exceeds the maximum displacement con-
moves to the inside of the pit. The negative value indicates straint of 2 mm (this implies that deformation of the di-
that the servo steel strut jack extends and the diaphragm wall aphragm wall to the inside of the foundation pit is high and
moves out of the pit, effectively decreasing the deformation the set axial force is low), the set axial force is actively in-
of foundation pit excavation caused by the improper initial creased. When the measured displacement of the servo steel
set axial force. strut jack is lower than the minimum displacement
6 Advances in Civil Engineering
constraint of − 1 mm (this implies that deformation of the Part 1 always exceeded that of CX13 in Part 2. Furthermore,
diaphragm wall to the outside of foundation pit is high and the maximum lateral deflection of CX11 and CX13 increased
the set axial force is high), the set axial force is actively with increase in excavation depth. Conversely, with respect
reduced. The working mechanism adjusts the hydraulic to the maximum lateral deflection development curve of
servo steel strut and dynamically compensates for the axial CX17, there is an evident turning point, which occurred at
force in real time, and thus the foundation pit excavation the completion of the fourth hydraulic servo steel strut
deformation meets the high control requirements. installation. The maximum lateral deflection of CX17 tends
to be stable following the completion of the installation of
the fourth hydraulic servo steel strut. The phenomenon is a
2.3. Construction Operation and Instrumentation. To clarify preliminary indication that the supporting effect of the
the excavation process of the foundation pit, Table 1 lists the hydraulic servo steel strut exceeds that of the ordinary steel
working conditions of the standard section. The overall strut.
excavation direction of the foundation pit ranged from north The relationship between the cumulative maximum
to south and from top to bottom. The soil above the fifth lateral wall deflection (δh ) and the corresponding excavation
concrete strut of Pit A was excavated downwards layer by depth (H) is plotted in Figure 10. The δh /H ratio of CX13
layer, and the soil beneath it was excavated via the slope. Pit (0.29%) and CX17 (0.11%), which meets the control stan-
B was excavated downwards layer by layer. During the dard of level I foundation pit (δh /H ≤ 0.3%), was smaller
excavation process, an inclinometer, settlement tester, and than that of CX11 (0.35%). Similarly, observation points
axial force tester were installed around the foundation pits to CX03 and CX19 were selected to represent End Well 1 and
monitor deformation in the retaining structures and soil and End Well 2, respectively. The δh /H ratio of CX19 (0.13%)
the axial force of the struts. As shown in Figure 7, there are close to Part 2 was smaller than that of CX03 (0.18%) close to
20 inclined monitoring points (CX01–CX20) for monitoring Part 2, illustrating that the hydraulic servo steel struts
the lateral deflection of diaphragm walls, 20 settlement provide a more stable support environment.
monitoring groups (D1–D20) for monitoring the ground Furthermore, with respect to the δh /H ratio of Pit A,
surface settlement, and 7 axial force monitoring groups there is an evident turning point with increase in excavation
(T1–T7) for monitoring the axial force of the struts. depth, as shown in Figure 10(a). The turning point occurred
between the completion of the installation of the fourth steel
3. Lateral Movement of the Diaphragm Walls strut and completion of the installation of the fifth concrete
strut. However, with respect to Pit B, there is no evident
Lateral diaphragm wall deflection was obtained from 20 turning point, as shown in Figure 10(b). Potential reasons
inclinometers (see Figure 7). However, it was a complex task, include the following: (1) The size of Pit B is smaller than that
considering the engineering environment on the west side of of Pit A, and thus the exposure period of the unsupported
the foundation pit (see Figure 1). Thus, the measured de- concrete strut in Pit B is shorter than that of the unsupported
formation data on the east side of the foundation pit were concrete strut in Pit A. Consequently, a large lateral de-
selected for analysis to reduce the effect of external factors. flection is absent during the exposure period of the un-
Figure 8 shows the variation in the measured cumulative supported fifth concrete strut, resulting in the absence of a
lateral deflection of the diaphragm walls with respect to δh /H turning point of in Pit B. (2) The supporting effect of
depth during construction. The cumulative lateral deflection Part 3 in Pit B exceeds that of the combination of Part 1 and
of the diaphragm walls increased with increase in the ex- Part 2 in Pit A. To verify this standpoint, the change in the
cavation depth, and the maximum cumulative lateral de- rate of maximum lateral wall deflection with respect to time
flection generally occurred near the position of excavation for points CX11, CX13, and CX17, representing Part 1, Part
depth. These observations agree well with the study per- 2, and Part 3, respectively, was analyzed.
formed on foundation pits in Zhejiang soft clay by Ding et al. As shown in Figure 11, the average value of the maxi-
[24]. Furthermore, between completion of the installation of mum lateral deflection rate of point CX13 (0.47 mm/day)
the fourth steel strut and completion of the installation of the and point CX17 (0.19 mm/day) is lower than that of point
fifth concrete strut, the cumulative lateral deflection of the CX11 (0.53 mm/day). The distribution of the maximum
diaphragm walls changed significantly, and its value reached lateral deflection rate of points CX13 and CX17 in the
19.7–34.1% of the final deflection. This is because the hydraulic servo steel strut section was more concentrated
foundation pit exhibits a space-time effect, and the concrete than that of point CX11 in the ordinary steel struts section.
strut requires a certain time to garner strength. Thus, there is This implies that the hydraulic servo steel struts restrain the
a period of unsupported exposure, which significantly in- development of deflection in diaphragm walls more
creases the lateral deflection of the diaphragm walls. effectively.
To compare the supporting effect of the hydraulic servo It should be noted that there are several negative points
steel strut with that of an ordinary steel strut, the measuring in Figure 11. When compared with the excavation of a pit
points CX11, CX13, and CX17 representing Part 1, Part 2, foundation that is supported by only concrete struts and
and Part 3, respectively, were selected for further analysis. ordinary steel struts [25], almost all the deflection rates were
Figure 9 shows the variation in maximum lateral deflection positive. This is potentially due to the high axial force of the
with respect to time at different observation points. It was hydraulic servo steel struts, which causes the diaphragm wall
observed that the maximum lateral deflection of CX11 in to move to the exterior of the foundation pit. When the
Advances in Civil Engineering 7
diaphragm wall moves to the exterior of the foundation pit, lower than that of point CX03 near the ordinary steel strut
the hydraulic servo steel struts maintain the stability of the section in Part 1. This further illustrates that the supporting
support system via elongation of its hydraulic jack. However, effect of the hydraulic servo steel struts exceeds that of
ordinary steel struts can exhibit support dislocation, which ordinary steel struts.
can lead to loss of axial force. This implies that the adjacent Figure 12 also shows that the final cumulative lateral
ordinary steel struts could function erroneously if the axial deflection of the east side of Pit A (End Well 1, Part 1, and
force of the hydraulic servo steel struts is not set correctly. Part 2) exceeds that of the west side, although the final
Therefore, when the hydraulic servo steel struts are utilized cumulative lateral deflection of the east side of Pit B (Part 3
together with ordinary steel struts, they may not work well and End Well 2) is lower than that of the west side. This is
together. because a foundation pit group (Ningbo Center) was under
To further examine the control effect of the deflection of construction near the west edge of Pit A, which led to
the hydraulic servo steel strut section, the final cumulative unloading on the ground near the west side of the Pit A.
lateral deflection of the diaphragm walls on the west side and Conversely, on the west side of the Pit B, there is a con-
east side of the foundation pit is plotted in Figure 12. The struction surcharge (Hongtai Building Group), resulting in
final cumulative lateral deflection of the hydraulic servo steel an overload on the ground near the west side of Pit B (see
strut section was lower than that of the ordinary steel struts Figure 1), which led to the differences between Pit A and Pit
section. Considering the space-time effect of the foundation B. The observed results are consistent with the results of
pit, the deformation data on the enclosure structure of the previous research [25, 26], which reported that different
two end wells were compared. From that, we can see the final existing structures around the foundation pit have different
cumulative lateral deflection of point CX19, near the hy- effects on the deformation of the foundation pit. Further-
draulic servo steel strut section in Part 3, was significantly more, it should be noted that CX13 develops much greater
8 Advances in Civil Engineering
Bottom
30
40
CX18 CX02
10 CX16 CX14 CX12 CX10 CX08 CX06 CX04
End Part 3 Existing Part 2 Part 1 End
CX20 Well 2 station Well 1 CX01
20
Depth (m)
30
40
CX19 CX03
50
2nd steel strut installation completed 3rd steel strut installation completed
4th steel strut installation completed 5th concrete strut installation completed
6th steel strut installation completed 7th steel strut installation completed
Figure 8: Curve of the measured cumulative lateral deflection of the diaphragm walls with respect to depth.
lateral wall displacement than CX17, although both were gradually with increase in the excavation depth, and the
retained by hydraulic servo struts. The reasons may be as maximum value occurred 10 m along the edge of the
follows: (1) On the right side of CX13, it is close to the foundation pit.
standard section of Pit A, while on the right side of CX17, it To study the relationship between the maximum ground
is close to the existing station, and the stiffness of the existing surface settlement (δv ) and the corresponding excavation
station is greater than the standard section of Pit A. (2) Pit B, depth (H), the δv /H ratio of points D11-2, D13-2, and D17-
where CX17 is located, was smaller than Pit A, where CX13 2, which represent Part 1, Part 2, and Part 3, respectively, is
is located, and its construction process was fast, thus leading selected for analysis, as shown in Figure 14. The δv /H ratio of
to smaller deformation. (3) Hydraulic servo steel struts in Pit D13-2 (0.38%) and D17-2 (0.17%) is lower than that of D11-
B work better than the mixed support system of hydraulic 2 (0.52%). Furthermore, there is an evident turning point
servo steel struts and ordinary steel struts in Pit A. with increase in excavation depth for Pit A and no turning
point for Pit B. The reason for the phenomenon is potentially
4. Ground Surface Settlement the same as that for the ratio of the maximum lateral de-
flection to excavation depth (δh /H).
The ground surface settlement values of the D11, D13, and Figure 15 presents further details on the final ground
D17 settlement monitoring groups were selected for analysis surface settlement at 10 m along the edge of the foundation
purposes to compare the effect of the hydraulic servo steel pit. The final settlement of the hydraulic servo steel strut
strut and ordinary steel strut on the control of surrounding section (Part 2 and Part 3) was significantly smaller than that
environment deformation. Figure 13 shows settlement of the ordinary steel struts section (Part 1), and this indicates
monitoring points D∗ − 1, D∗ − 2, and D∗ − 3, which are that the hydraulic servo steel struts control the surface
5 m, 10 m, and 15 m, respectively, away from the edge of the settlement more effectively and reduce the effect of foun-
foundation pit. The ground surface settlement increased dation pit excavation on the buildings in the surroundings.
Advances in Civil Engineering 9
100
60
40
20
0
01-May- 01-Jun.- 01-Jul.- 01-Aug.- 01-Sep.- 01-Oct.- 01-Nov.- 01-Dec.- 01-Jan.-
2017 2017 2017 2017 2017 2017 2017 2017 2018
Date
Part 1 CX11
Part 2 CX13
60
Maximum lateral deflection
of diaphragm walls (mm)
50
40
30
20
The time of completion of the 4th
10 hydraulic servo steel strut installation
0
01-Dec.-2018 01-Jan.-2019 01-Feb.-2019 01-Mar.-2019 01-Apr.-2019 01-May-2019
Date
Part 3 CX17
Figure 9: Curve of the maximum lateral deflection of the diaphragm wall with respect to time.
0 0
δh/H = 0.07%
δh/H = 0.12%
5 δh/H = 0.22% 5
Excavation depth (m)
Excavation depth (m)
10 10
δh/H = 0.13%
15 15
Turning interval
20 δh/H = 0.29% 20
Figure 10: Ratio of the maximum lateral deflection of the diaphragm wall to excavation depth (δh /H): (a) Pit A; (b) Pit B.
5. Axial Force of Struts the axial force of steel struts were characterized by three
stages: increasing stage (stage I), slowly decreasing stage
Subsequently, the axial force variation in the ordinary steel (stage II), and suddenly increasing stage (stage III).
strut and hydraulic servo steel strut was analyzed. Figure 16 The increase in stage I occurred prior to the installation of
shows the variation in the axial force of the third steel strut, the fifth concrete strut. The reason for the increase in axial
T4-3 (third steel strut of the T4 axial force group), and the force in stage I is that increments in the excavation depth
adjacent hydraulic servo steel strut, SF1-3. The changes in continuously increased the difference in soil pressure between
10 Advances in Civil Engineering
10-May-
2017
01-Jun-
2017
22-Jun-
2017
12-Aug-
2017
02-Sep-
2017
23-Sep-
2017
14-Nov-
2017
04-Dec-
2017
deflection with respect to time (mm/day)
Change rate of maximum lateral wall
CX11
01-Jun-
2017
22-Jun-
2017
12-Aug-
2017
02-Sep-
2017
23-Sep-
2017
14-Nov-
2017
04-Dec-
2017
CX13
10-Jan-
2019
31-Jan-
2019
21-Feb-
2019
14-Mar-
2019
04-Apr-
2019
25-Apr-
2019
Date
CX17
Figure 11: Change in the rate of maximum lateral wall deflection with respect to time.
150
West side
120
93.1 86.2
90 74.2 71.5 79.1 69.4
60
deflection of diaphragm walls (mm)
43.1 41.3
30 30.6
Final cumulative lateral
0
CX18 CX16 CX14 CX12 CX10 CX08 CX06 CX04 CX02
the inside and outside of the foundation pit. Thus, the pit and the installation of strut are carried out synchronously.
retaining structures exhibited a tendency to deform into the When the strut is installed, the soil pressure on the sidewall
pit in the horizontal direction, thus resulting in increments in also increases. Thus, despite the new strut installation, there
the axial force. Furthermore, the change of the axial force near will be no significant downward trend in the strut axial force.
the strut is not obvious after the installation of the next strut A slow decrease in stage II occurred after the installation
was completed. This is because the excavation of foundation of the fifth concrete strut. The reasons for that can potentially
Advances in Civil Engineering 11
180
settlement (mm)
Ground surface
120
60
0
01-May-
2017
01-Jun-
2017
01-Jul-
2017
01-Aug-
2017
01-Sep-
2017
01-Oct-
2017
01-Nov-
2017
01-Dec-
2017
01-Jan-
2018
Date
120
60
0
01-May-
2017
01-Jun
-2017
01-Jul-
2017
01-Aug
-2017
01-Sep-
2017
01-Oct-
2017
01-Nov-
2017
01-Dec
-2017
01-Jan
-2018
Date
40
20
0
01-Dec-
2018
01-Jan-
2019
01-Feb-
2019
01-Mar-
2019
01-Apr-
2019
01-May-
2019
Date
Figure 13: Curve of the measured ground surface settlement with respect to time.
include three parts: (1) the concrete strut exhibits greater Furthermore, as shown in Figure 16, the axial force of the
stiffness and stability and bears most of the soil pressure; (2) ordinary steel struts was generally lower than the axial
with the installation of underpass struts, the soil pressure preloading force, and this indicates that there is axial force
behind the wall is shared with the underpass struts, and thus loss in the ordinary steel struts. Table 2 lists the axial force of
the axial force of the struts decreases slowly; (3) the ordinary some ordinary steel struts in the foundation pit. Axial force
steel strut exhibits the disadvantage of stress loss, and thus loss is a common phenomenon in ordinary steel struts, and
the axial force of the ordinary steel strut exhibits a slowly the maximum loss corresponds to 84.54% of the axial
decreasing trend. preloading force. In addition to the loss of axial force being
A sudden increase in stage III occurred after the removal caused by defects in the ordinary steel strut itself, it is also
of the sixth and seventh steel struts. The removal of the sixth caused by the unreasonable setting of the set axial force of
and seventh steel struts caused the remaining steel struts to the hydraulic servo steel strut. The diaphragm wall moves to
share more soil pressure from behind the wall, and this the exterior of the foundation pit if the set axial force of the
resulted in an increase in axial force. Therefore, the moni- hydraulic servo steel strut is excessively high. Subsequently,
toring frequency should be strengthened, and the internal the axial force of the hydraulic servo steel strut is maintained
structure should be installed quickly after the removal of the above the set axial force due to its control of axial force
struts. working mechanism. However, the ordinary steel struts can
12 Advances in Civil Engineering
0
δv/H = 0.17%
5 δv/H = 0.14%
15
Turning interval
δv/H = 0.38%
20
δv/H = 0.52%
25
30
0 30 60 90 120 150 180 210
Maximum ground surface settlement (mm)
Part 1 D11-2
Part 2 D13-2
Part 3 D17-2
Figure 14: Ratio of the maximum surface settlement to the excavation depth (δv /H).
240
West side
180 167.1 158.5
120 100.8 104.9 115.4
87.6
60 47.8
25.5
Final ground surface settlement (mm)
0
D16-2 D14-2 D12-2 D10-2 D8-2 D6-2 D4-2 D2-2
exhibit support dislocation, and this leads to axial force loss that the axial force of an ordinary steel strut varies with
in ordinary steel struts and an increase in the force on the temperature, and the value was 37.08 kN/°C. To prove that
adjacent struts. This is potentially the reason why the low amplitude fluctuation was caused by temperature, the
measured axial force of the hydraulic servo steel struts axial force and temperature of the hydraulic servo steel strut
exceeded the set axial force, although the measured axial during the period of the axial force fluctuation (August 2 to
force of ordinary steel strut was lower than the set axial force. August 22) are selected for analysis, as shown in Figure 17. It
Furthermore, as shown in Figure 16, low amplitude is evident in Figure 17 that the change in axial force is
fluctuation of steel strut axial force is observed. Based on consistent with the change in temperature. Furthermore,
measured data on a foundation pit, Chen et al. [27] reported Table 3 presents the axial force of some of the hydraulic servo
Advances in Civil Engineering 13
3000 30
Stage I Stage II Stage III
th
CX12 CX10 7 strut
3rd strut
1000 2nd strut 10
1st strut The 5th concrete The 6th and
strut installation 7th strut removal
0 0
25-May-
2017
25-Jun-
2017
25-Jul-
2017
25-Aug-
2017
25-Sep-
2017
25-Oct-
2017
25-Nov-
2017
25-Dec-
2017
Date
Axial force of ordinary steel strut T4-3 Preloading (set) axial force
Axial force of hydraulic servo strut SF1-3 Excavation depth
Figure 16: Changes in the trend of the axial force of the steel struts.
steel struts in this study. The results indicate that the rate of strut, Figure 19 shows the curve of the lateral deformation at
change in the hydraulic servo steel struts with temperature the elevation of the servo support in the section where the
corresponds to 12.6–31.5 kN/°C. SF1-3 support is located with respect to time. From Figure 19,
To verify the supporting effect of the hydraulic servo steel we can see that deformation to the outside of the foundation
struts under temperature variation, the axial force and pit occurred at the position when the servo strut was in-
displacement variation in the hydraulic jack are plotted in stalled. The reason for this phenomenon is that the set axial
Figure 18. Although the axial force fluctuation of the hy- force of the servo struts was large, which makes the retaining
draulic servo steel struts was high, the fluctuation value of structure deform outside the pit. Then, deformation of the
the hydraulic jack was always between 1.4 mm and 3.4 mm. servo strut position tends to be stable, which indicates that
Essentially, although the axial force of the hydraulic servo the hydraulic servo steel strut plays a beneficial role in
steel struts varies with temperature, the hydraulic servo steel controlling the deformation of the foundation pit. Fur-
strut adjusts in real time based on the hydraulic jack dis- thermore, the retaining structure at the elevation of the 6th
placement variation, and this prevents deformation of the and 7th struts experienced large deformation before the
retaining structure caused by change in axial force with concrete strut was put into use. However, when the 5th
respect to temperature fluctuation. concrete strut was put into use, the deformation tended to be
The relationship between the lateral deformation and stable. This phenomenon proves yet again that the exposure
ground settlement with the axial forces of hydraulic servo period without support caused by the long maintenance
steel strut is important for this topic. Considering the long period of the concrete strut leads to a sharp increase in the
interval between the two monitoring of ground surface deformation of the enclosure structure. However, the con-
settlement, we select the deformation of lateral wall for crete strut has good overall performance and can effectively
analysis. To investigate the relationship between lateral restrain the development of sidewall deformation after it has
deformation and the axial forces of hydraulic servo steel been put into use.
14 Advances in Civil Engineering
2200 60
55
2000
50
Temperature (°C)
Axial force (kN) 1800 45
40
1600 35
30
1400
25
1200 20
05-Aug-
2017
09-Aug-
2017
13-Aug-
2017
17-Aug-
2017
21-Aug-
2017
Date
Axial force
Temperature
Figure 17: Changes in the trend of the axial force and temperature of the hydraulic servo steel struts.
2200 4
The displacement variation of
2000
3
hydraulic jack (mm)
Axial force (kN)
1800
2
1600
1
1400
1200 0
05-Aug.-2017 09-Aug.-2017 13-Aug.-2017 17-Aug.-2017 21-Aug.-2017
Date
Axial force
Displacement
Figure 18: Trend of the axial force and displacement variation in the hydraulic servo steel struts.
6. Discussion (1) A definite design method for the set axial force of the
hydraulic servo steel strut is absent, and it is nec-
Compared to an ordinary steel strut, a hydraulic servo steel essary to investigate how to optimize the design of a
strut is better at controlling deformation in a foundation pit. hydraulic servo steel strut based on its working
However, a few problems still persist in its application: mechanism.
Advances in Civil Engineering 15
80 40
Depth (m)
6th strut
40 5th strut 20
0 0
01-Jun.-2017
01-Jul.-2017
01-Aug.-2017
01-Sep.-2017
01-Oct.-2017
01-Nov.-2017
01-Dec.-2017
Date
(2) In the application process of a hydraulic servo steel 86.7% of the designed axial force. Therefore, in
strut, the actual axial force typically exceeds the foundation pit engineering with strict deformation
design axial force, and this leads to an increase in the control, the use of hydraulic servo steel struts, which
internal force of the diaphragm wall. Future studies overcome the axial force loss, is recommended.
should investigate whether the reinforcement setting (3) A concrete strut is typically used in a deep foun-
of the diaphragm wall should be adjusted accord- dation pit and is cast-in-place. Thus, there is un-
ingly in the design stage. supported exposure during the excavation process,
(3) Presently, the working mechanism of the hydraulic leading to a sharp increase in deformation of the
servo steel strut is based on a single strut, but the retaining structure of the foundation pit. Thus, the
deformation effect of the foundation pit is affected by construction organization design should be opti-
the entire support system. Consequently, it is of great mized to the maximum possible extent to reduce the
significance to study the influence of the axial force unsupported exposure period of the foundation pit.
adjustment of the hydraulic servo steel strut on the The use of a hydraulic servo steel strut rather than a
adjacent support and to propose a new servo ad- concrete strut can accelerate construction and pre-
justment method based on the support system. clude an unsupported exposure period.
construction,” Engineering Failure Analysis, vol. 83, pp. 117– [17] Y. M. Yao, S. H. Zhou, W. Sun et al., “Influence of brace
124, 2018. stiffness and pre-axial force on the deformation and internal
[2] G. Zheng, H. H. Zhu, X. R. Liu et al., “Control of safety of deep force of foundation pit,” Underground Space, vol. 23, no. 4,
excavations and underground engineering and its impact on pp. 401–404, 2003, in Chinese.
surrounding environment,” China Civil Engineering Journal, [18] J. Tanner Blackburn and J. F. Richard, “Three-dimensional
vol. 49, no. 6, pp. 1–24, 2016, in Chinese. responses observed in an internally braced excavation in soft
[3] R. W. Clough and T. D. O’Rourke, “Construction induced clay,” Journal of Geotechnical and Geoenvironmental Engi-
movements of in situ walls,” in Proceedings of the ASCE neering, vol. 133, no. 11, pp. 1364–1373, 2007.
Conference on Design and Performance of Earth Retaining [19] J. Chen, “Retaining structure deformation characteristics of
Structures, Geotechnical Special Publication No. 25, pp. 439– long and narrow type deep foundation pit in the expansive
470, Ithaca, NY, USA, June 1990. soil,” Chinese Journal of Underground Space and Engineering,
[4] M. Long, “Database for retaining wall and ground movements vol. 11, no. 2, pp. 440–445, 2015, in Chinese.
due to deep excavations,” Journal of Geotechnical and Geo- [20] L. N. Guo, B. Hu, F. C. Li, and H. Xu, “The study on axial force
environmental Engineering, vol. 127, no. 3, pp. 203–224, 2001. of steel shotcrete protective structures on deep foundation pit
[5] E. H. Y. Leung and W. W.N. Charles, “Wall and ground in Wuhan subway,” Chinese Journal of Underground Space
movements associated with deep excavations supported by and Engineering, vol. 9, no. 6, pp. 1386–1393, 2013, in Chinese.
cast in situ wall in mixed ground conditions,” Journal of [21] J. Jia, X. L. Xie, F. Y. Luo, and J.-Q. Zhai, “Support axial force
Geotechnical and Geoenvironmental Engineering, vol. 133, servo system in deep excavation deformation control,”
no. 2, pp. 129–143, 2007. Journal of Shanghai Jiaotong University, vol. 43, no. 10,
[6] G. B. Liu, J. J. Rebecca, W.W. N. Charles, and Y. Hong, pp. 1589–1594, 2009, in Chinese.
“Deformation characteristics of a 38 m deep excavation in soft [22] S. M. Zhang, X. M. Jia, T. K. Yuan, W. G. Liu, and Y. Jun,
clay,” Canadian Geotechnical Journal, vol. 48, no. 12, “Application of axial force compensation for steel support
pp. 1817–1828, 2011. system in practical project,” Applied Mechanics and Materials,
[7] L. N. Sun, Y. Liu, and L. M. Zhang, “Analysis on deformation vol. 477-478, pp. 503–508, 2013.
of foundation excavation considering of time-space effect,” [23] Y. Tan, W. Bin, L. Ye, and Y. Bo, “Is basal reinforcement
Applied Mechanics and Materials, vol. 291–294, pp. 1135– essential for long and narrow subway excavation bottoming
1139, 2013. out in Shanghai soft clay?,” Journal of Geotechnical and
[8] G. Xu, J. Zhang, H. Liu, and R. Changqin, “Shanghai center Geoenvironmental Engineering, vol. 145, no. 5, Article ID
project excavation induced ground surface movements and 05019002, 2019.
deformations,” Frontiers of Structural and Civil Engineering, [24] Z. Ding, D. Wang, J. Y. Wang, and X. J. Wei, “Deformation
vol. 12, no. 1, pp. 26–43, 2018. characteristics of Zhejiang soft soil deep foundation pits and
[9] Y. Tan and B. Wei, “Observed behaviours of a long and deep their predictive analysis,” Rock and Soil Mechanics, vol. 36,
excavation constructed by cut-and-cover technique in pp. 506–512, 2015, in Chinese.
Shanghai soft clay,” Journal of Geotechnical and Geo- [25] Y. Tan and B. Wei, “Performance of an over excavated metro
environmental Engineering, vol. 138, no. 1, pp. 69–88, 2012. station and facilities nearby,” Journal of Performance of
[10] J. Shi, G. Liu, P. Huang, and C.W.W. Ng, “Interaction between Constructed Facilities, vol. 26, no. 3, pp. 241–254, 2012.
a large-scale triangular excavation and adjacent structures in [26] Z. Ding, J. Jin, and T.-C. Han, “Analysis of the zoning ex-
Shanghai soft clay,” Tunnelling and Underground Space cavation monitoring data of a narrow and deep foundation pit
Technology, vol. 50, pp. 282–295, 2015. in soft soil area,” Journal of Geophysics and Engineering,
[11] I. H. Wong, T. Y. Poh, and H. L. Chuah, “Performance of vol. 15, no. 4, pp. 1231–1241, 2018.
excavations for depressed expressway in Singapore,” Journal [27] Z. C. Chen, S. D. Liu, and S. B. Fan, “Effect of temperature on
of Geotechnical and Geoenvironmental Engineering, vol. 123, axial force of steel support in subway foundation pit,” Journal
no. 7, pp. 617–625, 1997. of Shijiazhuang University, vol. 31, pp. 6–9, 2018, in Chinese.
[12] Z. Luo, H. Di, M. Kamalzare, and Y. Li, “Effects of soil spatial
variability on structural reliability assessment in excavations,”
Underground Space, 2018.
[13] Z. Luo, B. Hu, Y. Wang, and H. Di, “Effect of spatial variability
of soft clays on geotechnical design of braced excavations: a
case study of Formosa excavation,” Computers and Geo-
technics, vol. 103, pp. 242–253, 2018.
[14] Y. Tan, B. Wei, X. Zhou, and D. Yanping, “Lessons learned
from construction of Shanghai metro stations: importance of
quick excavation, promptly propping, timely casting and
segmented construction,” Journal of Performance of Con-
structed Facilities, vol. 29, no. 4, Article ID 04014096, 2015.
[15] Y. Tan and D. Wang, “Characteristics of a large-scale deep
foundation pit excavated by the central-island technique in
Shanghai soft clay. II: top-down construction of the peripheral
rectangular pit,” Journal of Geotechnical and Geoenvironmental
Engineering, vol. 139, no. 11, pp. 1894–1910, 2013.
[16] M.-G. Li, Z.-J. Zhang, J.-J. Chen, J.-H. Wang, and A.-J. Xu,
“Zoned and staged construction of an underground complex
in Shanghai soft clay,” Tunnelling and Underground Space
Technology, vol. 67, pp. 187–200, 2017.
International Journal of
Rotating Advances in
Machinery Multimedia
The Scientific
Engineering
Journal of
Journal of
Hindawi
World Journal
Hindawi Publishing Corporation Hindawi
Sensors
Hindawi Hindawi
www.hindawi.com Volume 2018 http://www.hindawi.com
www.hindawi.com Volume 2018
2013 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
Journal of
Control Science
and Engineering
Advances in
Civil Engineering
Hindawi Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
Journal of
Journal of Electrical and Computer
Robotics
Hindawi
Engineering
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018
VLSI Design
Advances in
OptoElectronics
International Journal of
International Journal of
Modelling &
Simulation
Aerospace
Hindawi Volume 2018
Navigation and
Observation
Hindawi
www.hindawi.com Volume 2018
in Engineering
Hindawi
www.hindawi.com Volume 2018
Engineering
Hindawi
www.hindawi.com Volume 2018
Hindawi
www.hindawi.com www.hindawi.com Volume 2018
International Journal of
International Journal of Antennas and Active and Passive Advances in
Chemical Engineering Propagation Electronic Components Shock and Vibration Acoustics and Vibration
Hindawi Hindawi Hindawi Hindawi Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018