Sie sind auf Seite 1von 2

I 002 Cranes

Rev 01 [Aug 04]


Construction Industry Council General Information Note
CDM Guidance for Designers

Provisions for the Safe Use of


Cranes on construction sites
for use on some types of terrain where a wheel
INTRODUCTION
mounted crane would not be appropriate.
1. Cranes are designed to lift freely suspended loads d) Tower Cranes are suitable for semi-permanent
in a vertical plane installation for covering large areas whilst taking up
relatively little room at ground level.
2. Lifting operations in construction are commonly
carried out using cranes and they should be covered in 9. Within each class of the above classes there is a
the Health and Safety Plan. When constructing the plan wide variation of types and lifting capacities.
consideration would need to be given to the ways in Descriptions of the various types and details of
which the cranes are intended to be used, ie, by the requirements for their safe use are given in the
manufacturer and hirer, and any limitations that would respective parts of BS 7121.
affect safety in the conditions expected on site. SELECTION OF CRANES
Consequently, information would need to be provided by
various parties so that factors influencing crane safety 10. While economic factors may influence the choice of
can be assessed at a sufficiently early stage. a crane, it is essential that the crane selected is capable
of lifting ALL loads that it would be expected to handle,
3. The purpose of this Guidance is to provide within its capacity and stability limits. Manufacturers
designers with basic information on crane types and the supply duty charts, which show the SWLs for specific
factors they should consider when designing a structure duties. These would give designers useful information
whose components will be delivered by cranes. It about the size of crane required and, consequently, the
includes typical site and environmental constraints to be space and loading requirements on the site.
taken into account at the design stage of a project that
are important for the safe use of cranes. FACTORS AFFECTING SAFETY WITH CRANES
4. The information in this note will help designers to 11. Some of the important factors affecting safety with
fulfil their responsibilities. They should study it and apply cranes are explained below.
the information with the assistance of expert advice [as
The characteristics of the load to be lifted
necessary] to their designs and modify them, to create
safe conditions for lifting operations. 12. For a safe lifting operation, it is necessary to know
the weight, dimensions and position of the Centre of
LIFTING ON SITES Gravity [CoG] of the load. Therefore, the information
provided should, at least, include:
5. Any plan should include information to everyone
a) The maximum weight to be lifted;
involved in the specification, installation or use of cranes
to be made aware of the fundamental criteria and b) Any non-routine handling instructions that are
planning issues needed to ensure that lifting operations necessary for a safe lift;
are initiated and proceed in a logical and safe manner. c) The position of the CoG of asymmetric loads or
loads of non-uniform mass [preferably marked].
6. While contractors have a duty to operate cranes
safely, these duties can be made extremely difficult by 13. Special lifting accessories may have to be
thoughtless design, which puts pressure on them to use designed for lifting asymmetric loads or loads of
cranes at their operating limits and beyond. non-uniform mass. Lifting is made safer when
designated lifting points are either provided or
7. Information relating to the site is an important
marked on the load.
contribution to a safe system of work particularly with
regard to planning the lifting operation and selection of 14. deleted
the correct crane and associated equipment.
15. The weight and dimensions of lifting accessories
TYPES OF CRANES add to the weight to be lifted.
8. There are many types of crane and a detailed The crane position
classification is given in ISO 4306. However, the vast 16. Where the load is to be lifted from, the route it will
majority of cranes used for construction work in the UK take during the lift and where it will be landed should be
can be classed as: taken into account. Therefore potential obstructions,
a) Lorry Loaders, which are suitable for delivery either permanent or temporary, should be taken into
purposes and routine lifting operations associated account. Obstacles include: buildings and other
with the vehicle on which they are fitted. structures, trees, overhead power lines, etc;
b) Truck Mounted/Mobile Cranes, which are suitable 17. If the crane is to be positioned on or next to an
for short duration operations where mobility around existing structure it may overload such a structure - a
site is important. design calculation check may be required to establish
c) Crawler Cranes, which are suitable for longer whether temporary strengthening or propping is needed.
duration operations and ‘pick and carry duties’ and

____________________________________________________________________________________________________________
This series of notes is available on www.safetyindesign.org Page 1 of 2
I 002 Cranes
Rev 01 [Aug 04]
18. The radius over which a crane has to lift will have a Site weather conditions
significant effect on the loads that can be lifted and to 25. Prevailing weather conditions and exposure of the
what height they can be lifted. Table 1, below, for a site can affect a lifting operation. Wind, in particular, can
particular type of crane, illustrates this point: affect how a load behaves when it is lifted. Structural
items, which offer a large effective area to the wind can
Tabel 1: Illustrating the relationship between lifting
be difficult to control, even in very moderate winds, eg,
capacity and lifting radius shutters for concrete.

Radius [m] Capacity [t] Max height [m] 26. Manufacturers will specify maximum wind speeds
for erection, lifting, out of service and dismantling
3 30 50 operations. In very exposed areas (eg.cliff tops) or areas
subject to wind turbulence (eg. built-up areas), these
10 7.3 47 speeds may have to be reduced.

20 2.2 44 TOWER CRANES FOUNDATIONS


27. The design of tower crane foundations requires
30 0.5 35
close consultation between a number of parties such as
the Crane Manufacturer, Temporary Works Designer,
Clearances
Permanent Works Designer and Structural Engineer.
19. Safe distances of the crane from the structure under
construction, adjacent buildings, roads and pedestrian
accesses must be maintained.
28. Sometimes, due to limitations of the tower crane or
its foundation it is necessary to tie the crane tower to
20. Mobile cranes need adequate space for the correct another structure to achieve sufficient height to complete
deployment of outriggers. In addition, they should be the project under construction. Most tower sections can
able to slew and manoeuvre the load with adequate only be connected to a tie at certain points and the
clearance from obstructions. A minimum clearance of designer will need to consult the Crane Manufacturer for
600mm should be allowed for. the maximum allowable shear forces on the tower.

21. Other, equally important, considerations include: ROUTES TO AND ACCESS ONTO THE SITE
a) Clearance to overhead electric cables: Cranes must 29. Cranes need access routes and space for erecting
never be positioned in the exclusion zone around and extending them and vehicles delivering the loads.
overhead electricity cables. Lifting operations close Special access may be required for both the crane and
to electricity cables or pylons may have to be high capacity trailers often used for deliveries such as
scheduled during power off conditions. counter-weights and jib sections.
b) Clearance to railway tracks, overhead catenaries
and public highways: If a crane is to be positioned 30. When working in city centres, getting the crane on
adjacent to a railway, canal or public highway an and off the site will require advance planning often in
independent design check may be required, proving conjunction with police and local authorities and will
that the scheme has been planned and engineered possibly require facilities for overnight working.
such that no damage will occur to existing
USEFUL REFERENCES
structures, property or to the public.
c) Clearance for aircraft near airfields: cranes ISO 4306-1:1990 Cranes- Vocabulary Part 1: General
operating within 6km can be a hazard to air traffic, ISO 4306-2:1994 Lifting Appliances- Vocabulary Part
especially if their height exceeds 10m, or when the 2: Mobile Cranes
top of the crane is higher than the surrounding BS 7121:Part 1:1989 Code of practice for the safe use
structures or trees. [Notify the Airfield Manager] of cranes – General requirements.
BS 7121:Part 3:2000 Code of practice for the safe use
Erection and dismantling constraints
of cranes – Mobile Cranes.
22. Cranes have to be erected and dismantled. BS 7121:Part 4:1997: Code of practice for the safe use
Normally more space will be needed for these of cranes – Lorry Loaders
operations. BS 7121:Part 5:1997 Code of practice for the safe use
Ground conditions and foundations of cranes – Tower Cranes
23. In order to operate safely, cranes need adequate BS 1377: Methods of test for soil for civil engineering
foundations or support. Therefore, the ground purposes
conditions on a site are important. Crane operators BS 5930: Code of Practice for Site Investigations
need to know about: BS 1377: Methods of test for soil for civil engineering
a) Character of the ground including water conditions; purposes
Crane stability on Site: CIRIA publication 131
b) Engineering properties of strata relevant to the
support of the crane or design of the foundations;
c) Location of any underground hazards eg open or
back-filled excavations, services, drainage pipes,
tunnels, trenches and basements.

24. Some of these factors may govern the design; many


of them can be removed or made easier to control by
considering them during the design.

____________________________________________________________________________________________________________
This series of notes is available on www.safetyindesign.org Page 2 of 2

Das könnte Ihnen auch gefallen