Beruflich Dokumente
Kultur Dokumente
Chris Hendy, Head of Bridge Design and Technology Atkins
Forth Road Bridge
Bearing Replacement – Use of
Eurocodes
Chris Hendy – Head of Bridge Design and Technology
Forth Road Bridge Bearing
Replacement
• Need for bearing replacement
• Use of Eurocodes for assessment
• Bearing replacement scheme
• Use of Eurocodes for strengthening and
jacking
Introduction and Bearing replacement
Forth Road Bridge Bearing
Replacements
Existing structure:
• Three span suspension bridge
with a central span of 1005 m and
side spans of 408 m
North viaduct
• On both approaches to the bridge
there are multi-span viaducts
• The south viaduct consists of 11
spans and the north viaduct
consists of 6 spans. These spans
vary between 33 m and 39 m.
South viaduct
Forth Road Bridge Bearing
Replacements
Existing structure:
= rocker
= roller
Bearing condition
Existing structure - North Viaduct
• Roller Bearing at North side tower
• Rocker Bearing at north abutment and piers N1-N5
= rocker
= roller
Bearing condition
Roller Bearings:
• Not free to roll – uneven wear due to
stress and/or corrosion
• Higher stresses in pier than considered
in original design
• Justified by use of cracked section
properties but box stresses too high
• Bearings assessed according to
BS5400-9-1:1983 and BS EN 1337-4
• Modern geometrical limits not met
• Significant codified overstress
• Roller bearing at end of North viaduct Roller bearing at north side tower
near the side tower is near limit of
movement range limit
Bearing condition
Rocker Bearings:
• Bearing corrosion
• Generally compliant with BS EN
1337-6:2004
• Concrete delamination – (and at
rollers)
Options for replacement schemes?
Options for replacement schemes?
Bearing type for replacement:
Roller replacement options
• Pot bearings:
- Insufficient room on piers without significant widening
- Single pot overstresses diaphragm in hogging bending
- Twin pots – insufficient room to get adequate lever arm between
them
- Friction greater than rollers
• Rollers:
- No modifications to diaphragms
- No change to designed articulation
but concern over materials and space
• Sliding rockers:
- No modifications to diaphragms
- No change to designed articulation
Roller/Slider Pot
As built assessment of box girder –
Use of Eurocodes
As built assessment of box girder
• Box girder assessed initially
before jacking design started
• Significant overstresses
found to BS 5400 Part 3 but
not to BS EN 1993-1-5
• New BD 100 requires
strengthening to Eurocodes,
but designers need to justify
this
• Challenges are knowing
assumptions in Eurocodes;
for Forth, some relevant
considerations were:
- Steel ductility
- Torsional buckling of stiffeners
As built assessment of box girder
Bending - Eurocodes
• Effective section used for all
components in section properties
• Result is redistribution occurs
from heavily loaded parts
Usage factor
Check BS 5400 Part 3 Eurocode 3
Check
as strut
As built assessment of box girder
Shear - Eurocodes
• Same approach to design used as for
beams without longitudinal stiffeners
• Slenderness however comes from
weaker of sub-panels or overall web
buckling
Usage factor
Overall slenderness
Check BS 5400 Part 3 Eurocode 3 based on lowest cr
from:
Usage factor
Check BS 5400 Part 3 Eurocode 3 Resistance based on
lowest strength of:
Bending 0.95 0.90
Usage factor
Check BS 5400 Part 3 Eurocode 3
0.5b b
0.25b to
0.30b
b
As built assessment of piers
• Pier assessment – central point load
• Rebar is mild steel and lightly reinforced
• Only works if Eurocode strut and tie invoked with tensile strength
• Not long term solution due to deterioration
a
30
25
Bearing pressure (MPa)
20
0.5b b
15
10
0.25b to
0.30b
5
0
1 2 3 4 5 6 7 8
b/a
b
As built assessment of piers
• Two point loads at shared pier
• Same conclusions
~0.125b
0.5b
b
b
Replacement Solution
Replacement Solution
Design Concept
• Work part of FRB 15 year capital programme of works
• No provision for replacement in the original design
• Box girders need to be jacked up to allow removal of
bearings from the piers
• Piers must be widened to allow correct positioning of
jacks and pier tops also need to be strengthened
- Add corbels to edges of the piers
- Reinforce pier tops and make necessary concrete/reinforcement
repairs
• Box girders require strengthening for jacking
- Bolt external bearing stiffeners to outside of web directly above
jacks
- Some web strengthening to allow holes to be drilled
- Some box strengthening required independent of bearing
replacement scheme
Replacement Solution
Design Concept
• Strengthen/recast concrete
pier tops and widen pier edges
with addition of corbels to
allow correct positioning of the
jacks
• Bearing stiffeners installed on
outside of box webs near
diaphragm regions
• Jacks positioned directly
below bearing stiffeners
Ac0
b1
d1
Limiting
line of action
area for Ac1
Ac0
h d2 3d1
Load near an
Dispersal edge (plan)
b2 3b1 at 1H : 2V
Ac1
max
FRdu A c 0 f cd A c1 / A c 0 3.0f cd A c 0
• Bearing stresses used
Eurocode partially loaded area
rules to increase resistance
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Construction sequence
for corbels
• Drill in bars
• Cast corbels
• Install temporary
restraints
• Jack up deck
• Remove bearing
• Break out concrete
• Recast top of Pier
• Replace bearing
Replacement Solution
Before corbelling +
external stiffening:
Replacement Solution
After corbelling +
external stiffening:
Replacement Solution
Features of Scheme