Update status on Engneering review meeting on dated 5.02.19 for ARP SS04 PGCIL A.

Sl NO. Activity Comment on meeting at PGCIL Status on 13.2.19


I. ARP-SS-04
A 132 kV Jairampur(new) S/s
1.        Soil investigation report
2.        Single Line Diagram

3.        Layout & Section drawing

4.        Clearance diagrams Submit on 05.02.19 Pending from client approval. Submit on
05.02,19

5.        Foundation Layout drawing

6.        Earthmat layout & calculation

7.        Structural layout (Plan & section)

Pending from client approval. Submit on


8.        Erection Key Diagram Submit on 05.02.19 05.02,19

9.        DSLP Design Calculations

10.    DSLP Layout Drawing

11.    Revise drawing incorporating the cable


Cable Trench Layout - Switchyard trench to be submitted on 15.02.19 To be submit on Monday 18.02.19

12.    SLD of LT Switchgear boards Extn.

13.    CRP drawings

14.    Gravel Layout drawing To be submit on 10.03.19 To be submit on Friday 15.02.19

15 Fire protection system-


Transformer/Reactor

Fire detection and alarm system for CRP Pending for approval from client. Submit on
16 Room 7.2.19

Drawing will be submit on 25.02.19.


17 Illumination system –Switchyard (Pending from Procurement team from
08.02.19

Drawing will be submit on 25.02.19.


18 AC System (Pending from Procurement team from
08.02.19

After SAS approaval. Pending from client


19 Cable schedule from 22.01.19 submit on 11.03.19

Civil/Structure Drawings

15.    Tower Foundation - 132kV

16.    Equipment Fabrication-132kV

17.    Equipment Foundation - 132kV

20 CRB, Transit Camp etc.

B 132 kV Miao(New) S./s


1.        Soil investigation report

2.        Single Line Diagram


3.        Layout & Section drawing

4.        Clearance diagrams After discussed with client.

5.        Foundation Layout drawing

6.        Revise layout submitted to be approved


Earthmat layout on 14.2.19

7.        Structural layout (Plan & section)

8.        Erection Key Diagram Approved


9.        DSLP Design Calculations
10.    DSLP Layout Drawing
11.    Cable Trench Layout - Switchyard Submit on 06 .03.19
12.    SLD of LT Switchgear boards Extn.
13.    CRP drawings

14.    After comment on Jairampur layout


Gravel Layout drawing submit on 10.03.19 drawing.we will submit on 10.03.19

Fire protection system-


15 Transformer/Reactor

Fire detection and alarm system for CRP Submitted on 07.02.19. Pending form client
16 Room approval

Drawing will be submit on 25.02.19.


17 Illumination system –Switchyard (Pending from Procurement team from
08.02.19

Drawing will be submit on 25.02.19.


18 AC System (Pending from Procurement team from
08.02.19

19 Cable schedule submit on 18.03.19 After SAS approaval. Pending from client
from 22.01.19 submit on 18.03.19

Civil/Structure Drawings

21 Tower Foundation - 132kV

22 Equipment Fabrication-132kV

23 Equipment Foundation - 132kV

24 CRB, Transit Camp etc.

C 132 kV Changlang (new) S/s


1.        Soil investigation report
2.        Single Line Diagram
3.        Layout & Section drawing
4.        After comment from Jairampur EKD. We will
Clearance diagrams submit the same 0n 20.02.19

5.        Foundation Layout drawing

Submitted on 7.02.19. Pending for approval


6.        Earthmat layout and calculations from client.

7.        Structural layout (Plan & section)


8.        132kV - Erection Key Diagram Submit on 20.02.19
9.        DSLP Design Calculations
10.    DSLP Layout Drawing
11.    Cable Trench Layout - Switchyard Submit on 10.03.19 for client approval.
12.    SLD of LT Switchgear boards Extn.
13.    CRP drawings

suubmit on 10.03.19 After approval of Jairampur drawing. We will


14.    Gravel Layout drawing submit.15.03.19

Fire protection system-


15.    Transformer/Reactor

Fire detection and alarm system for CRP


16 Room Submit on 7.02.19. pending for approval.

Vendor to be finalize- 20.02.19. Drawing will


17 Illumination system –Switchyard submit on 25.02.19

18 AC System Vendor to be finalize- 20.02.19. Drawing will


submit on 25.02.19

SAS submit on 22.01.19. After approval SAS


19 Cable schedule drawing. We wil submit the cable schedule on
18.03.19

Civil/Structure Drawings
20 Tower Foundation - 132kV
21 Equipment Fabrication-132kV
22 Equipment Foundation - 132kV
23 CRB, Transit Camp etc.

D 132 kV Khonsa (new) S/s


1.        Soil investigation report
2.        Single Line Diagram
3.        Layout & Section drawing
4.        Clearance diagrams After comment from Jairampur Submit on
28.03.19

5.        Foundation Layout drawing

6.        Earthmat layout submit on 15.02.19 Submit on………..

7.        Structural layout (Plan & section)


8.        Erection Key Diagram Approved

9.        DSLP Design Calculations


10.    DSLP Layout Drawing
11.    Cable Trench Layout - Switchyard

12.    SLD of LT Switchgear boards Extn.

13.    CRP drawings


14.    Gravel Layout drawing

16.    Fire protection system-


Transformer/Reactor

Fire detection and alarm system for CRP


17 Room Submit on 7.02.19. pending for approval.

Vendor to be finalize- 20.02.19. Drawing will


18 Illumination system –Switchyard submit on 25.02.19
Vendor to be finalize- 20.02.19. Drawing will
19 AC System submit on 25.02.19
SAS submit on 22.01.19. After approval SAS
Cable shedule drawing. We wil submit the cable schedule on
27.03.19
Civil/Structure Drawings
20 Tower Foundation - 132kV
21 Equipment Fabrication-132kV
22 Equipment Foundation - 132kV
23 CRB, Transit Camp etc.
24 Foundation filled up Soil Area

E 132 kV NAMSAI (EXTN) S/s


1 Soil investigation report
2 Single Line Diagram
3 Layout & Section drawing
4 Clearance diagrams not submitted
5 Foundation Layout drawing
6 Earthmat layout
7 Structural layout (Plan & section)
submitted on 12.02.19 Pending for client
8 Erection Key Diagram to be submit by 08.02.19 approval
9 DSLP Design Calculations
10 DSLP Layout Drawing
11 Cable Trench Layout - Switchyard
12 SLD of LT Switchgear boards Extn.
13 CRP drawings
14 Gravel Layout drawing
15 Illumination system –Switchyard 25.02.19 Vendor to be finalize- 20.02.19. Drawing will
submit on 25.02.19
Vendor to be finalize- 20.02.19. Drawing will
16 AC system 25.02.19 submit on 25.02.19

17 Cable schedule 25.02.19 We wil submit the cable schedule on 25.02.19

Civil/Structure Drawings
18 Tower Foundation - 132kV
19 Equipment Fabrication-132kV
20 Equipment Foundation - 132kV
.
EQUIPMENT STATUS UP TO ON DATED 13.02.19
Common 132kV & 33kV Equipment Status on 13.2.19
drawings
Sr. No. EQUIPMENT DESCRIPTION
145KV 1250A 31.5KA, DOUBLE BREAK
1
ISOLATOR WITH ONE E/S
145KV 1250A 31.5KA, DOUBLE BREAK
2
ISOLATOR WITHOUT E/S(TANDEM) Substation wiise spare list and TTR report
145KV 1250A 31.5KA, DOUBLE BREAK submission pending from Vendor end (12.02.19)
3
ISOLATOR WITHOUT E/S
36KV,1250A 25KA,3-PHASE DOUBLE
8
BREAK ISOLATOR WITH ONE E/S

132 KV RELAY AND PROTECTION PANEL


10
WITH AUTOMATION & DPC

DPC GTP submit on 13.02.19 for client approval


SAS approval pending from client from 22.01.19

400 KVA, 33/0.433kV , 3ph LT


11
TRANSFORMER Pending from Procuremt team on dated 11.02.19
20 415V MAIN SWITCHBOARD
21 415V AC DISTRIBUTION BOARD
415V MAIN LIGHTING DB(ALONG WITH 2
22 NOS 25KVA 415V/415V LIGHTING
TRANSFORMER) TTR approval pending from client from 05.02.19
415V EMERGENCY LIGHTING DB(ALONG
23 WITH 1NO 25KVA 415V/415V LIGHTING
TRANSFORMER)
24 110V DC DISTRIBUTION BOARD(DCDB)
110V , 60A/60A FLOAT CUM BOOST
26
BATTERY CHARGER
48V, 70A/70A FLOAT CUM BOOST
28
BATTERY CHARGER CUM DCDB Pending from Procuremt team on dated 11.02.19

30 Clamps and connectors Drawing pending from procurement team from


05.02.19

31 String hardware
vendor to finalize in this week

33KV XLPE CABLE TERMINATION EQUIPMENT


ALONG WITH STRUCTURE & ACCESSORIES
Enquiery has been fwd to Procument team on
32 FOR OUT DOOR TERMINATION (ONE SET 12.02.19 drawing will be submit on 1 03.19
CONSISTS OF COMPLETE REQUIREMENT FOR
ONE BAY)

33KV, 1C X240 SQMM XLPE AL ARMOURED


CABLE ALONG WITH ACC. AS PER TECH SPEC

33KV, 3C X90 SQMM XLPE AL ARMOURED Revise TTR is submit on 07.02.19


CABLE ALONG WITH ACC. AS PER TECH SPEC

33KV, 3C X240 SQMM XLPE AL ARMOURED


CABLE ALONG WITH ACC. AS PER TECH SPEC

1.1KV GRADE POWER CABLES (XLPE


33 INSULATED) ALONG WITH LUGS, GLANDS,
STRAIGHT JOINT & ACC

1.1KV GRADE POWER CABLES (PVC


INSULATED) ALONG WITH LUGS, GLANDS, Revise TTR is submit on 12.02.19
STRAIGHT JOINT & ACC

1.1KV GRADE CONTROL CABLES (PVC


INSULATED) ALONG WITH LUGS, GLANDS,
STRAIGHT JOINT & ACC