Sie sind auf Seite 1von 30

Ship lay‐up.

A guide for owners on preparing


ships for lay-up and protecting
them while out of service
Contents.
1. Introduction 4
1.1 Using this guide 4
2. Choosing a lay-up condition 5
2.1 Hot ship lay-up (24-hour reactivation) 5
2.2 Hot ship lay-up (one-week reactivation) 5
2.3 Warm ship lay-up (one-week reactivation) 5
2.4 Cold ship lay-up (three-week reactivation) 5
2.5 Long-term lay-up (three-month reactivation) 5
3. Location considerations 6
4. Mooring arrangements 7
4.1 General requirements 7
4.2 Ships moored in groups 7
5. Class status during lay-up 8
5.1 Class status 8
5.2 ISM and ISPS certification 8
6. Insurance issues 9
6.1 Protection and indemnity cover 9
6.2 Hull and machinery cover 9
7. Manning levels 10
8. Record keeping 11
9. Navigation 11
10. Safety equipment, systems and alarms 12
11. Protection during lay-up 13
11.1 Wet or dry ballast tanks 13
11.2 External hull protection 13
11.3 Internal hull protection 13
11.4 Deck equipment 14
11.5 Accommodation areas and outfitting 14
11.5.1 Accommodation areas 14
11.5.2 Outfitting 14
11.6 Machinery 15
11.6.1 General machinery 15
11.6.2 Diesel machinery 15
11.7 Steam plant 16
11.8 Water systems 16
11.9 Propeller and shafting 16
11.10 Electrical, electronic and software systems 17
11.10.1 Electronic and software systems 17
11.10.2 Electrical equipment and machinery 17
11.10.3 High-voltage installations 17
11.11 Additional protection for LNG carriers (cold ship lay-up only) 18
11.11.1 Cargo containment and handling systems 18
11.11.2 Refrigeration and liquefaction plant 19
11.11.3 Main turbines (gas and steam) 19
11.11.4 Gearboxes 19
12. Spares 20
13. Periodic maintenance and operation 21
14. Periodic inspection 22
Appendix 1 – Summary of lay-up considerations 23
Appendix 2 – External hull lay-up checklist 24
Appendix 3 – Internal hull lay-up checklist 24
Appendix 4 – Equipment lay-up checklist 25
Appendix 5 – Accommodation lay-up checklist 25
Appendix 6 – Machinery lay-up checklist 26
Appendix 7 – Automation lay-up checklist 27
Appendix 8 – Electrical system and navigation gear lay-up checklist 28
1. Introduction
This is the fourth edition of Lloyd’s Preparations for lay-up should be Lloyd’s Register recommends that
Register’s lay-up guide, produced to carried out by crew members, the ships are laid-up with classification
help owners prepare their ships for owner’s technical shore staff or a maintained; this may either be as
lay-up and maintain them in a safe and contractor’s competent personnel, and normal for a hot lay-up or with ‘Laid
cost-effective condition during lay-up. in consultation with a local Lloyd’s Up’ status assigned for a longer term
Register office. Once the preparations lay-up. We gratefully acknowledge the
The guidelines this document contains are complete, a Lloyd's Register advice provided by International
are general – they are not classification surveyor will carry out an examination Shipcare Sdn. Bhd of Labuan Malaysia
requirements. Therefore, they may on board. If this is satisfactory, the during the revision of this guidance
need to be modified to suit a particular surveyor will issue a general report document.
ship type or lay-up location. The stating that the ship has been laid-up
specific requirements of original in accordance with the
equipment manufacturers may take recommendations detailed in this
precedence, and ships may also be guide.
subject to national, port and other
statutory requirements, which this
guide doesn’t cover.

1.1 Using this guide

We recommend reading Appendix 1 of this document on page 23 before proceeding to the main body.
Please read the detailed guidelines in the main body before using the checklists in Appendices 2 to 8.
If you have any queries or feedback about this guidance, please contact one of LR’s Ship Inspection
and Assessment (SIA) Centres, located in Piraeus, Ottawa, Singapore and Southampton. See the back
cover for contact details.

4 | Ship lay-up
2. Choosing a lay‐up condition
The lay-up condition you choose will 2.1 Hot ship lay-up 2.4 Cold ship lay-up
be determined by a combination of (24-hour reactivation) (three-week reactivation)
technical and commercial factors,
including: This lay-up condition is suitable for up This lay-up condition is suitable for up
to one month out of service. In this to five years out of service. In this
• the time the vessel will be in lay-up condition, the vessel is held within condition, the vessel manning is in line
condition normal classification survey and flag with emergency requirements to deal
state requirements although the with fire, flooding, mooring and
• the time that will be needed to number of crew may be reduced in line security watch. Cold ship lay-up
reactivate the vessel with the certified minimum safe locations are generally remote, so
manning limits. The machinery will be access to the vessel is likely to be
• the need to reduce overhead kept operational but various limited. On reactivation, the vessel
running costs economies may be made. The vessel may need to go directly to dry-dock
will usually be located in an area close before trading, depending on the
• the relocation of the vessel to its to potential cargo trade routes. extent of hull marine growth.
next intended destination, and
2.2 Hot ship lay-up It is important that all preparations
• the age of the vessel and its scrap (one-week reactivation) during cold ship lay-up are well
value. documented because crew changes
This lay-up condition is suitable for up may be significant. The owners should
to 12 months out of service. In this request the class status is changed to
condition, the vessel manning is ‘Laid up’ before actual lay-up, as the
reduced below the trading limit and in class survey requirements will need to
agreement with the flag state, the be confirmed with the class society
classification society and other local (see also 5.1). Before reactivation, the
authorities and insurance companies. survey and certification requirements
In this condition, most ports will only for the initial voyage to a dockyard will
grant a temporary permit to lay-up a need to be discussed with the class
vessel in port, provided that class and and the flag.
flag surveys are carried out. Under
these circumstances there may be 2.5 Long-term lay-up
local restrictions on vessel operations, (three-month reactivation)
e.g. restrictions on the transfer of oily
bilge water. This lay-up condition is suitable for
over five years out of service. In this
2.3 Warm ship lay-up extended condition, the preparations
(one-week reactivation) will be comprehensive, to the extent
that original equipment manufacturers
This lay-up condition is suitable for up should be consulted for critical
to 12 months out of service and is equipment. Furthermore, any remedial
similar to 2.2, with the exception that work required on reactivation is likely
the vessel would usually be moored at to be extensive and unpredictable, e.g.
a recognised lay-up location and the renewal of alarm systems due to
owners would have discussed the class obsolescence. Several vessels will be
status being changed to ‘Laid up’; laid-up in this condition side-by-side to
especially if any surveys are falling due minimise supervision costs. The
while the ship is out of service. Class owners should request the class status
survey requirements will need to be is changed to ‘Laid up’ before actual
confirmed with the class society (see lay-up, as the class survey
also 5.1). requirements will need to be
confirmed with the class society (see
also 5.1). Before reactivation, the
survey and certification requirements
for the initial voyage to a dockyard will
need to be discussed with the class
and the flag.

Lloyd’s Register May 2020 | 5


3. Location considerations
The local requirements that apply to • the proximity to corrosive waste or • the suitability of the mooring
specific lay-up locations and mooring effluent discharges pattern with respect to the number
arrangements are normally of lines, lengths, angles and leads
determined by the relevant port • the water depth with regard to keel and the ability to maintain even
authority and the appropriate salvage clearance at extreme low tides tensions on the lines
association. The classification society versus excessive water depth with
should also be advised in advance in regard to anchor chain limitations • the capacity and capability of the
case they have any special crew during normal and adverse
recommendations. However, the • the characteristics of the seabed weather conditions
shipowner should consider the with regard to anchor-holding
following factors before selecting capability (which may require • the reliability and frequency of local
lay-up locations: confirmation by diving inspection) weather forecasts and warnings

• the extent of shelter from open • the availability of local tug and • the proximity to other vessels and
seas, strong winds, swell, surge and fireboat assistance related traffic hazards in the vicinity
strong currents
• the characteristics of the windage • the scope of local emergency
• the proximity to shipping routes or area (including cargo container preparedness plans and services for
open roadstead anchorages considerations, if applicable) in potential fires, flooding, security
relation to changes in wind, tidal incidents, mooring failures or
• the proximity to known tropical and swell conditions medical emergencies, and
cyclone or hurricane areas, moving
ice, etc. • the weaknesses and limitations of • the risk of theft and piracy.
the specific type, design and
• the proximity to wrecks, submerged condition of mooring equipment, as
pipes, cables and other bottom well as access to and the readiness
projections of additional moorings, if required

6 | Ship lay-up
4. Mooring arrangements
4.1 General requirements • Anchor lights and fog signals should 4.2 Ships moored in groups
be fully operational and additional
The mooring arrangements will depend deck lighting will be required if When ships are to be laid-up in groups,
on the selected lay-up site conditions, lay-up is near shipping lanes. mooring arrangements should be in
the readiness of main machinery, and with the following additional
manning levels. The arrangements will • Ships should be sufficiently requirements:
include a ship’s own anchoring ballasted to reduce windage, roll
equipment augmented by stern and surge, with due regard to hull • Adjacent ships should be similar in
anchoring arrangements, permanent stresses. Furthermore, when size to avoid differential surging
buoying facilities or mooring to draught is finally established, it is motions and they should be
specially sited bollards on shore. advantageous to paint clearly ballasted to similar freeboards to
visible reference marks at bow and permit breast lines to be directly led.
The choice of mooring arrangements stern, just above the water line as
should be in line with the following an external indicator of hull • Ships should ideally be anchored in
general requirements: integrity (leakage). alternate directions (alongside bow
to stern), in even numbers to
• When ships are laid-up to buoys or • An emergency means for the quick provide equal anchor holding
anchored, they should be moored release of all moorings should be power at both ends of the group.
to prevent swinging in wind or as a provided and arrangements for
result of tidal changes. towing should be readily available if • The fore and aft direction of each
propulsion machinery cannot be vessel should be parallel to
• When ships are anchored, the chain bought into operation. prevailing strong winds.
cables must not be capable of
twisting or cross contact, and • All anchors should be provided with • Breast mooring lines should be
anchors must be placed to avoid marker buoys, depending on the provided, sufficiently tensioned and
tripping. local port and harbour authority of similar stretch characteristics.
requirements.
• Additional stern anchoring • Sufficiently sized fendering
arrangements will be required for • The windlass and mooring winches, arrangements should be provided
single anchor ships. if electronically driven, should be alongside at areas of possible
provided with an adequate source contact with other ships or shore
• Anchor cables should be led and of electrical power for intermittent structures.
protected to prevent chaffing and emergency operation.
against the ship. • If the auxiliary engine on one vessel
• Day and night anchor dragging GPS is used to supply power to other
• If laid-up ships are subjected to position fixing (or compass vessels, it is recommended that all
wave movement or surge, anchor bearings) should be established vessels are electrically connected to
cables should be periodically and monitored regularly. avoid stray currents.
moved at intervals to shift points of Consideration should be given to
wear on the cables. installing a drift alarm which alerts
a designated person ashore.
• Anchored ships should have ample
chain scope – i.e., cable lengths
should ideally be around seven
times the water depth. In any event,
the local port authorities should be
consulted for their knowledge of
prevailing conditions.

Lloyd’s Register May 2020 | 7


5. Class status during lay‐up
5.1 Class status 5.2 ISM and ISPS certification

Ships that are laid-up immediately If the vessel is laid-up for up to six
after service will be maintained in months, Lloyd's Register will suspend
class without periodic survey until the the vessel’s International Safety
due date for the annual survey. Management Code (ISM) and
However, the ship-owner should International Ship and Port Facilities
request continuance of class when a Security Code (ISPS) certificates. In the
vessel is taken out of service by event the vessel is later brought back
requesting the classification status into service, a ‘reactivation audit’ will
‘Classed (Laid Up)’ to be assigned in be required for ISM and ISPS.
case there are any requirements to be
fulfilled before ‘Laid Up’ status is If the vessel is laid-up for more than
granted. six months, the ISM and ISPS
certification will be withdrawn. In the
event the vessel is later brought back
Note: in the case of hot ship into service, an interim survey will be
lay-up, the normal required before Lloyd’s Register can
classification and statutory reactivate the ISM and ISPS
survey regime continues. certificates.

The exception is a situation where the


If the ship is to remain laid-up beyond shipowner has maintained the ship in
the due date for the annual survey, the a hot lay-up condition and maintained
‘Laid Up’ status can be maintained the crew in accordance with flag
provided that the class surveyor has requirements for safe manning, and
attended for general examinations of the ship has not changed class status
hull and machinery before the end of to ‘Laid Up’.
the annual survey range dates.

If the next survey after going into


lay-up is the Special Survey then an
underwater examination is to be held
in addition to the general
examinations of hull and machinery.
The owner will be given the option of
having class withdrawn, or carrying
out surveys to maintain the status
‘Classed (Laid Up)’, with surveys
overdue.

8 | Ship lay-up
6. Insurance issues
6.1 Protection and indemnity cover

Under all circumstances, the owner should keep the


relevant protection and indemnity (P&I) club fully informed
about a vessel’s changing status.

P&I club rules will vary but owners may expect to receive a
50% reimbursement of the P&I premium once a ship has
been laid-up for more than one month.

If the vessel is laid-up for an extended period of time, most


P&I clubs will reserve the right to inspect the condition of
the vessel on reactivation.

Most port authorities will require a letter from local P&I club
representatives to confirm that the laid-up vessel is covered
for port risks, e.g. oil pollution, wreck removal, salvage costs.

6.2 Hull and machinery cover

Typically, an owner may deal with a laid-up vessel’s hull and


machinery cover in two ways:

1. Opt for a laid-up return of premium; or

2. With the underwriter’s agreement, cancel the trading


policy and substitute this with a ports risk policy.

Lloyd’s Register May 2020 | 9 Lloyd’s Register May 2020 | 9


7. Manning levels
Ideally, owners should conduct a risk Technical attendance on board will Owners should assess the flooding
assessment with regard to the planned usually be necessary and the extent of risks in the machinery spaces posed by
manning level. This should cover any this will depend on the location and various manhole doors being left open
hazardous events that might occur at expected duration of the lay-up, as to facilitate drying of salt water coolers
any time during lay-up. The risk well as the nature of the ship’s and other equipment in the engine
assessment should account for the dehumidification programme and the room.
following onboard scenarios: number of adjacent ships in a group.
It is recommended that the owner
• fire Staff will be required to carry out seeks guidance from the vessel’s flag
routine maintenance and monitoring state, insurer and local authorities to
• flooding which may be performed on a regular agree the final manning levels on
visitation basis. It is recommended board during lay-up.
• severe weather, and that at least one engineer officer and
one navigating officer be stationed on
• security breach. each vessel, unless vessels are laid-up
in a group.
The extent to which onboard risks can
be mitigated is largely determined by The deck and engineer officers must
the planned manning level - e.g. be capable of operating essential
maintaining a reduced crew on one equipment critical to the lay-up
vessel for vessels moored in a group. operation, e.g. electrical generating
sets, pumps, fire-fighting equipment.
Port authorities may have their own
requirements for the number of staff
on board. Table 1 on page 14 gives
example minimum manning
requirements.

10 | Ship lay-up
8. Record keeping
The owner should carefully prepare a log of all the
measures taken during the implementation of a lay-up
programme, to ensure easy and orderly reactivation in
future. In particular, an inventory of the entire vessel’s
equipment that is moved ashore should be prepared, to
monitor the extent of any transfers of spares to sister ships
in the fleet that are still trading.

9. Navigation
If there is a permanent lay-up crew onboard the vessel, they
should be provided with an updated chart of the lay-up
area, whereas all remaining chart folios may be landed
ashore. The correct navigation shapes and lights for the
condition of the ship should be provided.

Lloyd’s Register May 2020 | 11 Lloyd’s Register May 2020 | 11


10. Safety equipment,
systems and alarms
All safety equipment considered Bilge level and fire alarm systems Furthermore, no repairs should be
necessary for the safety of the vessel should be arranged to operate audible carried out in cargo or fuel tanks,
and the crew should be periodically and visible alarms, as follows: pump rooms, etc., unless special
examined and maintained in a arrangements have been made, and
satisfactory condition. For example, a. within the living quarters when the dangerous spaces have been proved
sufficient breathing apparatus and vessel is permanently attended; or gas free.
floatation escape devices should be
provided and maintained. b. where the vessel is unattended, to The owner should provide approved
operate the ship’s whistle or an oxygen and explosion meters where
Fire extinguishers should be regularly equivalent alarm. the type of ship requires such safety
inspected and where foam or CO2 equipment. It should be noted that
systems are installed, the system If a laid-up vessel is in ‘electrical dead reduced or nil ventilation increases the
should be maintained in a fully ship’ condition, bilge and fire alarms areas which could be lacking in oxygen
operable condition. must be independently powered. and also the potential for pockets of
Consideration should be given to other gases to accumulate.
All fire dampers should be inspected to installing a remote alarm which alerts
be freely operable and regularly a designated person ashore. A sufficient number of approved safety
greased whereas dampers not torches should be available onboard.
required for essential ventilation Warning notices should be placed in
should be closed. conspicuous places advising staff of In many ports, the harbour master will
the dangers of entering enclosed require bulk carriers and tanker
The emergency fire pump should be spaces. Pump rooms, tank spaces, vessels to be issued with a gas free
regularly inspected and maintained in cofferdams, etc., should not be certificate before lay-up and will
a fully working condition to ensure its entered unless they are proved to be expect that the gas free status be
reliable operation. An international gas free and with an atmosphere safe maintained during the lay-up. Some
shore connection should be retained in to enter, and the normal safety authorities may require the periodic
an accessible position. The fire main precautions have been taken. renewal of the gas free certificate
should be drained via a small-bore throughout the lay-up period, e.g. at
drain to prevent freezing (and three month intervals.
subsequent overpressure).

12 | Ship lay-up
11. Protection during lay‐up
11.1 Wet or dry ballast tanks 11.2 External hull protection 11.3 Internal hull protection

Ballasted tanks should be laid-up in The hull should always be protected Holds, cargo tanks and other hatch
either a wet or dry condition. Ballast against corrosion. The paintwork of covers, watertight doors and closing
tanks can be stored in a completely the parts above the water line, deck appliances should be securely closed
empty and dry condition with as much and superstructures should be made and sealed, unless required for access
water removed from the tank as good and should be examined and or ventilation. Flame screens on fuel
possible, e.g. the tanks can be dried by maintained at regular intervals during tank air pipes should be in good
forced venting. lay-up. To protect the external hull condition.
below the waterline (particularly in
Alternatively, ballast tanks should be contaminated waters) it is Empty tanks, holds, pump rooms,
completely filled by flooding (including recommended that the impressed small machinery spaces, storage
deck headers and vent pipes) with current system (if fitted) should be spaces, lockers and other similar areas
chemically treated water to inhibit continuously operated. should be kept in a dry condition. For
corrosion. Filled ballast tanks should this purpose, dehumidification is
then be checked at the air pipes for Impressed current cathodic protection recommended but the extent of its use
liquid loss on a weekly basis, and systems should be regularly examined, depends on the type of ship, its
topped up as required. Ideally, owners maintained and monitored condition, the lay-up location and the
should hang corrosion coupons (steel (specifically, current outputs and hull climatic conditions.
plates) within filled ballast tanks to potentials). Sacrificial anodes
monitor the effectiveness of the mounted on the hull should be Fuel oil bunker tanks should be kept
chemical corrosion inhibitor. These renewed where necessary before full or should be cleaned and gas
coupons will enable the crew to lay-up and these should be regularly freed. When kept full, a regular quality
monitor the inhibitors’ effectiveness examined. check should be made to assess
and to determine when further ongoing suitability for use. A biocide
chemical dosing is required. Corrosion If a laid-up vessel has no impressed may be added to the fuel to prevent
inhibitors should comply with local current protection, sacrificial anodes microbiological degradation. Good
environmental requirements. can be suspended at regular intervals housekeeping onboard is essential
around the hull below the waterline. such as draining of excess
This precaution is particularly accumulated water in bottoms of the
Note: the vessel must important if a laid-up vessel is moored fuel tanks.
undertake ballast water near a structure with its own
exchange before arrival at impressed current protection system Fresh water tanks should be cleaned
the lay-up location, to (such as a jetty or another vessel). In and recoated where necessary.
comply with local the event, the hull’s electrical potential
requirements. should be periodically checked along Chain lockers should be cleaned, dried
the underwater side area with portable and coated.
voltmeters.

Lloyd’s Register May 2020 | 13


11.4 Deck equipment 11.5 Accommodation areas and 11.5.2 Outfitting
outfitting
For deck machinery, all bright parts ‘On hire’ equipment such as gas
exposed to atmosphere should be 11.5.1 Accommodation areas bottles, etc., should be returned to
greased and machinery internals suppliers, or an agreement may be
should be protected with oil and Personnel living onboard should be reached regarding reduced hire
sealed to prevent ingress of moisture accommodated in one area to allow all charges and insurance premiums.
and air. other areas to be dehumidified, or at
least provided with heaters, to reduce Electricals on deck and telephones,
Any mooring ropes or soft fibre humidity to an acceptable level. telegraphs, etc., should be covered
materials which are sensitive to and sealed, with moisture-absorbing
ultraviolet (UV) light degradation If the ship’s galley is being used by desiccant bags within.
should be stowed out of the sun. lay-up staff, the galley exhaust fans
and grease trap should be regularly All loose navigational equipment,
Cargo and other lifting gear wires and inspected and cleaned. chronometers, sextants, etc., not
blocks not retained in use should be required during the lay-up period
dismantled, greased and stored, and For all unoccupied areas, the humidity should be removed and placed in
gear which is not dismantled should level in accommodation areas should locked storage.
be protected with grease and covered. be reduced and maintained at 45-55%
relative humidity (RH) by The engine workshop, electrician’s
dehumidifiers. workshop and deck workshop tools
and loose equipment not required
This is particularly important for during the lay-up should be cleaned,
spaces such as the radio room, greased and put into locked storage.
navigation bridge and other spaces
housing electrical machinery or All loose gear, lifeboat gear, rescue
electronic control equipment. boats and similar equipment should
be removed, protectively coated and
Ships’ linen and napery should be placed in locked storage, except for
stored in one single dry compartment retained safety equipment.
with mattresses stowed on their edge
to assist free air circulation. Medical and lifeboat perishables
should be removed ashore (or to
All provision room, cabin and cabinet another vessel, as required).
doors should be secured in the open
position. Any food stuffs, pyrotechnics
(particularly expiry date stamped),
Water services in unoccupied areas cotton waste, matches, etc., not
should be shut off and drained and required during lay-up should be
sanitary fittings and toilet bowls removed ashore.
should be sealed.
Broached drums of chemicals are to be
Scuppers and liquid seals should be removed ashore.
treated to prevent freezing under
normal climatic conditions.

14 | Ship lay-up
11.6 Machinery All lubricating oil in systems and used The steering gear should be power
oil storage tanks should be thoroughly operated hard-over to hard-over
11.6.1 General machinery centrifuged at temperatures above weekly and stopped with a tiller
82°C (180°F) to kill any microbes. amidships. The rams, bearings and
The temperature in machinery spaces Samples should be taken and analysed rudder carrier should be greased.
should be maintained above 0°C (32°F). by the oil suppliers to confirm stability,
freedom from moisture and Machinery space ventilators should be
Dehumidifying equipment should be microbiological contamination. closed and sealed.
installed to protect machinery spaces
from atmospheric corrosion, by Contaminated oil should be renewed. 11.6.2 Diesel machinery
maintaining relative humidity within
the range of 30-50% RH. Power should Where lubricating oil sumps and Main engine crankcases should be
be available for continuous operation storage tanks are vented to atmosphere supplied with dehumidified air which
of the dehumidifiers and the above deck-level, the venting is suitably vented at the opposite end
occasional turning of machinery. arrangements should be sealed, and of the engine. Reference should be
alternative ventilation should be made to the engine maker's
To achieve humidity control of the arranged into machinery spaces. recommendation for laying up.
machinery space, funnel openings,
grills, ventilator openings, doors, etc., All sea inlet valves and overboard Water cooled systems for the main
should be closed and sealed. Access to discharge valves should have spindles engine should be completely drained,
the space should be restricted to two greased, valves closed and hand washed with fresh water and left open
openings only and it is advantageous if wheels removed and wired to valves, to atmosphere.
these are double air lock doors. For except those required for use during
cold lay-up, main and auxiliary engine, lay-up in connection with fire Air starting valves should be
boiler and incinerator exhausts are to extinguishing, pumping out or watch dismantled and lubricated.
be closed off with ‘top hats’ to prevent personnel duties.
rain or moisture building up in the Fuel valves should be removed,
exhaust trunkings, exhaust gas In order to prevent excessive fouling, overhauled and stored outside the
economisers, etc. Suitable warning the sea suction openings (except for engine.
signage is to be provided at local and emergency fire pump) should be
remote control stations. blanked at the shell opening or All bright work should be protected
protected with a slow acting biocide. with a smear of grease or oil.
Certain types of gasket and seal
materials in the machinery room may Service tanks for fuel oil should be Engines including all shafting should
subsequently degrade if they are filled with centrifuged oil to ensure an be turned weekly to circulate oil (e.g.
exposed to dry dehumidified air over ample supply of reliable fuel for one complete turn plus one quarter
an extended period of time. reactivation. Inlet and outlet valves on turn). Cylinder lubricants should be
oil tanks that are not in use should be operated by hand before turning.
All bilge valves should be cleaned, shut and their hand wheels removed
overhauled and proved operable. and wired to valves. Ideally diesel generators should be
maintained in operational condition
Tank tops in engine rooms, boiler Air receivers should be drained and and operated (rather than simply
rooms, pump rooms, and hold areas mopped dry. If dehumidifiers are used, turned) once per week for about two
should be hosed down, and bilges air bottles should be left with the hours.
cleaned and dried. Any liquid leaks manhole covers removed. (Depending
should be repaired. on the lay-up strategy one air bottle The emergency generator should be
may be kept at full pressure at all times operated on a weekly basis under load.
Air conditioning and refrigerant to facilitate starting the auxiliary or
systems should be pumped down to main engines. In this case, the
the liquid receiver and all valves emergency air compressor should be
secured and tagged with a note of the operated weekly to top up the
liquid level. receiver.)

Note: long term


de-pressurisation is likely to
affect certain seal types and
this needs to be considered
when re-pressurising.

Lloyd’s Register May 2020 | 15


11.7 Steam plant 11.8 Water systems 11.9 Propeller and shafting

The fireside of boilers should be All SW and FW systems and pumps A routine system of regularly turning
cleaned – particularly the areas where which are not in use should be washed the shafting to prevent brinnelling of
soot accumulates. Fireside water with fresh water, drained and left open bearings should be instigated for ships
washing is best carried out with a to the atmosphere when a in long-term lay-up. At the time of the
water alkaline solution that neutralises dehumidifier is in use. (Otherwise they lay-up the stern tube oil should be
the acidic deposits, and on completion should be left full of suitably treated replaced with a fresh charge and the
the fireside insulation and brickwork clean water.) condition of the oil should be
should be thoroughly dried. monitored regularly.
Any pumps, for which power is not
For periods of up to three months, a available, should be turned weekly by If the vessel is to be laid-up for more
wet method can be used for laying-up hand. than one year, then it should be
boilers. This involves filling with boiler anticipated that the vessel may
feed water and venting the boiler drum Dehumidifiers should be suitably subsequently be towed to a dry dock
through the air vents, until the boiler is equipped with vent trunking to forcibly on reactivation, depending on hull
completely full. A slight hydraulic ventilate heat exchangers, condensers marine growth. In this event, it will be
pressure may be maintained to and steam piping, after the removal of prudent to prepare and have ready
preclude the ingress of any air into the appropriate inspections covers, crank some means of locking the vessel’s
boiler. The quality of the fill water doors, non-return valves, etc. main shafting before laying-up. (This
should be checked regularly. will ensure that the vessel meets
standard towing requirements on
For lay-ups over three months, boilers departure for the dry dock). If the
should be drained and stored with the vessel to be self-propelled out of the
drums and header doors open to lay-up location to dry dock, it is
ensure maximum air circulation. advisable to clean the propeller,
rudder and other apertures
The fuel oil system should be drained (sea-chests, inlets, etc.). There is a
and filled with gas or diesel oil. particular concern in the case of yachts
and certain types of smaller vessels
which have exposed stainless steel
shafting. These steels suffer greatly
from accelerated pitting from crevice
corrosion when shafting is not in use
and flow of water over the exposed
material is negligible. Areas prone to
corrosion are tail shaft seals, exposed
propeller/tailshaft tapers and
water-lubricated bearings. Oil
lubricated shafting may be prone to
corrosion in way of the bearings due to
water held in suspension in the stern
tube oils.

If possible, propulsion shafting should


be regularly operated using the main
engines when a vessel is in a shorter
lay- up.

16 | Ship lay-up
11.10 Electrical, electronic and d. all radio and navigational All circuits supplied from the main and
software systems equipment, and emergency switchboards and section
boards should be isolated in turn and
11.10.1 Electronic and software e. all engine, boiler and wheelhouse the insulation resistance (IR) between
systems control consoles. cores and earth should be measured
and recorded from each circuit on a
Of particular concern when laying-up It is concluded that an inventory of regular basis.
modern ships is the large amount of these systems will be prepared by the
computer processing equipment on shipowner before lay-up, as each All circuits of the inventoried systems
board. It is very important that the vessel will have different requirements. are to have the IR recorded at the time
following preventative measures are of lay-up.
taken: Where required, anti-condensation
heaters should be provided for those Ideally, electrical circuit breakers
• Equipment containing printed systems that are located outside any of should be left in the open position.
circuit boards should be kept dry the heated or dehumidified areas.
and free of moisture, and excessive 11.10.3 High-voltage installations
temperatures should be avoided. Electrical equipment on deck should
The electric supply systems in be covered and sealed, with a suitable Breakers, busbars and switchboards
modern ships consist of method in place to ensure that any
electrotechnical components, moisture within the sealed equipment Pre lay-up
equipment and systems which is absorbed, such as the use of a
could be susceptible to desiccant material. All high-voltage (HV) breakers must be
deterioration if the environmental withdrawn for a detailed visual
conditions are inappropriate. These Heaters should be distributed inspection of terminations, spouts and
systems may require specialist throughout the machinery spaces and mechanical linkages
protection and specialist testing those spaces that contain the electrical
during reactivation. and control/software-based systems to Electrical tests should be undertaken
maintain reasonable temperatures including contact resistance, insulation
• Software back-ups should be made (above 0°C) and prevent condensation. resistance and dielectric strength. This
available for reactivation should will provide equipment condition
computers fail to boot up or restart Batteries should be maintained in integrity and a fingerprint datum point.
on their own. This may take the accordance with the
form of keeping all programs and recommendations from the original All protective relays and master trip
databases (for planned equipment manufacturer (OEM). relays should be inspected and
maintenance, etc.) duplicated Where possible, the electrolyte should electrically tested in accordance with
ashore. be topped up. Lead acid batteries the Rules. They should then be
should either be removed from the removed, sealed and kept in dry
11.10.2 Electrical equipment and vessel, or should be trickle-charged on storage. The exposed openings in the
machinery board at a rate recommended by the switchboard should be sealed to
battery manufacturer. Alkaline prevent ingress of moisture and
Heating or dehumidification batteries should be fully charged and contamination.
techniques should be employed to disconnected from any possible load.
prevent condensation within During lay-up
electrotechnical systems where Lithium battery systems are to be laid
degradation could occur if the up and maintained in accordance with The HV breakers should be racked
environmental conditions are the requirements of the OEM. into their circuit earth positions
inappropriate. These systems include: Particular care is necessary where during lay-up.
stored energy remains within these
a. main and emergency generators systems which may be necessary as This will mean that the termination/
and switchboards some cell types can be harmed by a busbar shutters are locked and closed
full discharge. and essentially sealed to a suitable
b. all motors and starters associated level of ingress protection.
with propulsion machinery, Consideration should be given to the
pumping duties, steering gear, battery life and the duration of the
cargo handling, deck machinery lay-up. See Appendix 8 (Electrical
and domestic services System and Navigation Gear Lay-up
Checklist) on page 28 for guidance on
c. converters, harmonic filters and maintenance of batteries.
transformers

Lloyd’s Register May 2020 | 17


If the interlock system permits, bus Regeneration 11.11 Additional protection for LNG
couplers should all be closed. If for any carriers (cold ship lay-up only)
reason a switch cannot be closed onto Before re-commissioning an HV
circuit earth or a cable tie between installation, full inspection and testing 11.11.1 Cargo containment and
switchboards, the HV trucks should be should be carried out as per the handling systems
withdrawn, the spouts cleaned by requirements during lay-up, and
approved means according to OEM depending on the duration of the a. All cargo tanks must be in a gas-free
recommendations, and covered with lay-up. Any identified deviation from state, either fully filled with
plastic film to prevent ingress of the initial lay-up datum point(s) nitrogen gas with slight pressure
moisture or contaminants and stored should be addressed. As a minimum above atmospheric pressure or
in the de-humidified switchroom. there should be a general inspection, aerated with dry air at atmospheric
IR testing, and safety system testing, pressure. The cargo tanks may be
Regeneration including control systems and stops maintained with dehumidifying
(testing intensity will vary depending units with dry air condition where
Breakers should be closed and testing on whether the lay-up is hot (or warm), feasible according to the tank
requirements for switchboards, cold or long-term). Re-commissioning maker’s recommendation for cold
busbars, etc., should be carried out. should be carried out by competent lay-up.
See also the next section on system and authorised personnel.
re-commissioning. b. All insulation barrier spaces must
Special requirements for oil filled be in a gas-free state, either fully
HV equipment – propulsion motors, transformers filled with nitrogen gas with
converters and generators pressure safely for protection or
Heat exchangers need to be drained. aerated with dry air at atmospheric
Pre lay-up pressure. The insulation barrier
Oil coolant such as MIDEL needs to be spaces may be maintained using
With the equipment de-energised and drained. nitrogen quads for replenishing or
isolated, a fully detailed visual with dehumidifying units with dry
inspection should be undertaken. Anti-condensation heaters need air condition where feasible
activating. according to the tank maker’s
As a result of the internal inspection, recommendation for cold lay-up.
the systems may need cleaning. Regular IR checks are required.
c. All cargo system-related pipelines
During lay-up De- humidifiers must be installed. are to be either filled with nitrogen
gas with pressure monitoring or
Following the visual inspection, Temperature monitoring is to be used. aerated with dry air and/or with
electrical tests should be carried out in dehumidifying machines at an
accordance with an approved test Uninterruptible power supplies appropriate positive1 atmospheric
schedule, including: IR/polarisation pressure.
index (PI); Tan Delta¹; rotor and exciter See requirements for electronics and
winding IR/PI; AC impedance; and for batteries in 11.10.2. d. Cargo valves are to be operated at
off-line partial discharge analysis regular intervals to prevent
(where applicable) to determine seizures.
machine insulation integrity and
fingerprint datum point. e. The pressure and dew point of
cargo tanks and insulation barrier
spaces are to be checked regularly
through the sampling points. If
filled with nitrogen, oxygen content
is to be measured separately.

f. Arrangements are to be made for


bilge detection (and condensation
monitoring) in the insulation barrier
space either by using the installed
detection system or by using a
manual device.

g. Gas compressors and heaters are to


be sealed off and filled with
nitrogen or dry air.

¹ Tan Delta is a diagnostic test conducted on the insulation of cables and windings

18 | Ship lay-up
h. Gas compressors are to be turned c. All steam valves associated with the 11.11.4 Gearboxes
over at regular intervals and the turbines are to be left in the open
associated lube oil system is to be position once the steam plant has a. Main engine gearboxes are to be
operated where feasible to prevent been completely shut down to inspected during shutdown before
static seizure. prevent cold down damage. lay-up of the vessel.

11.11.2 Refrigeration and liquefaction d. The gas turbine fuel system is to be b. The lube oil system is to be
plant properly flushed, removed and centrifuged to remove water
serviced. The fuel system is to be content and a sample is to be sent
a) All refrigerant is to be pumped down completely shut down and all for lab analysis.
and collected inside the main associate valves are to be secured.
condenser. Regular leak tests are to be c. Arrangements are to be made to
carried out during the lay-up period. e. Turbine internals are to be introduce dry air into the gearbox
dehumidified using dry air during the lay-up period to replace
b) Electric motors driving refrigeration circulation. Sufficient safe opening moisture in the gearbox casing
compressors are to be disconnected is to be provided with protection which may cause corrosion.
and the electric motor is to be hand gauze to prevent ingress of foreign
turned at regular intervals to prevent debris. d. The lube oil system is to be
static load damage. operated at regular intervals and all
f. The main turbine lube oil system is lube oil sprays are to be checked to
c) Liquefaction plant is to be either to be operated at regular intervals make sure they are functioning.
filled with nitrogen gas and preserved and all lubrication points are to be
or aerated using dry air and / or proved functional. e. The gearbox is to be turned with the
maintained using a dehumidifying main engine system as described in
machine. g. The main turbine is to be turned 11.11.3 (g).
using turning gear to at least one
11.11.3 Main turbines (gas and steam) full turn ahead and one full turn f. Six-monthly gearbox inspections
astern alternately, with all the are to be carried out where feasible
a. All turbines are to be properly associated lube oil systems to confirm the lube oil protection
cooled down and secured operating and stopping the shaft at remains satisfactory and there has
according to the maker’s a different position every time after been no corrosion formation.
recommended procedures. All drain operation to prevent static load
systems are to be properly operated damage. Axial displacement of the g. Lube oil is to be sent for lab analysis
to remove any fluid inside the main rotor shafts of the turbine are at regular intervals.
turbine casings and to make ready to be checked before, during and
for lay-up preservation. after the operation.

b. The Lube oil system is to be h. Turbine manouvering valves are to


centrifuged to remove water be operated manually at regular
accumulation before complete intervals.
shutdown of the system. Lab
analysis of the lube oil system is to
be carried out at regular intervals.

Lloyd’s Register May 2020 | 19


12. Spares
Experience has shown when vessels are in lay-up
that equipment can be used as a source for
spares for existing fleet requirements. The
removal of spares from a laid-up ship needs to be
strictly recorded and controlled to determine
spares purchases at the time of reactivation.
(Additionally, if the laid-up vessel is inspected by
potential purchasers, the obvious absence of
machinery components may affect any valuation
of the vessel.) If the vessel keeps spare main
shafts such as turbo charger, pumps, etc., bolted
and hung from bulkheads, it may be prudent
before a long lay-up to rotate these through 180
degrees to balance distortion (‘age droop’).
Finally, all spares should be protected in line with
the guidelines in Section 11 above.

20 | Ship lay-up 20 | Ship lay-up


13. Periodic maintenance
and operation
A programme for regular maintenance, • Sea valves should be periodically • The ship’s whistle should be
inspection, and periodic operation (or operated if the sea water system is operated periodically.
turning) of machinery should be intact without any leaks and the
prepared at the beginning of the overboard openings are blanked. • All rotating machinery, electric
lay-up, and a record of all maintenance motors, hydraulic motors and radar
work should be kept. • Ballast, cooling water and steam scanners should be turned or
systems in wet lay-up should be operated at monthly intervals by
Regular maintenance should be periodically sampled to verify the hand, mechanically or with normal
carried out every six months effectiveness of the chemical power. This includes propulsion
approximately, or more frequently in inhibitor, and corrosion coupons in shafting (see 11.9).
line with the guidelines in Section 11 ballast water tanks, etc., should be
above. Any regular maintenance periodically checked to monitor the • Air conditioning and reefer plant
programme should include the extent of any corrosion. refrigerant circuits should undergo
following, in addition to any activities regular leak testing.
deemed necessary by original • All safety equipment needed for
equipment manufacturers: the personnel on board should be • The main electrical circuit’s
regularly examined, including fire insulation continuity should be
• At least one stores or cargo crane extinguishers and fire dampeners. periodically measured.
should be kept operational (and (CO2 bottles and foam tank
regularly tested) for lay-up duties, contents may be examined less
e.g. lifting diesel oil on board for frequently, for example, on an
deck generator, etc. Note: annual basis.) Oxygen levels
certification may be required to be should be measured in any sealed
maintained as per flag or port spaces containing CO2 bottles,
authority requirements. before entry.

Lloyd’s Register May 2020 | 21


14. Periodic inspection
In addition to periodic maintenance A regular inspection and testing • visual checks of mooring, fenders,
and operations activities, owners programme should include: etc.
should conduct specific inspections
and testing on structures, machinery • visual checks on controlled space • visual checks of storage tank levels
and equipment through established sealing arrangements
techniques, to ensure that the • visual checks of open machinery,
standard of preservation is • measurements of relative humidity pressure vessels, heat exchangers,
maintained. levels within controlled spaces etc., within dehumidified spaces

The owner should receive detailed • visual checks on protective coatings • underwater visual checks of the
monthly reports from the crew or of all external machinery and external hull by a qualified diving
contractors on the findings of equipment contractor
scheduled inspections and tests. The
report should also contain details of • visual checks on oil levels in • visual checks of boiler fire sides and
any essential remedial work machinery sumps water sides (for drained boilers) for
considered necessary to repair faults dryness
or restore adequate lay-up protection. • visual checks on all filled or wet
systems for leaks (e.g. hydraulic • electrical measurements of the
Ideally, the owner will periodically fluids, fuel, lubrication oil, cathodic protection system
prepare consolidated summary refrigerant, water, etc.)
reports detailing such repairs (or • visual checks of essential fire,
decisions to postpone repairs until the • electrical measurements of flooding, and security
time of reactivation). batteries arrangements fire (including fire
dampers, fixed and portable
Any repairs or remedial work to • visual checks during testing of equipment, and detection systems)
equipment or lay-up protection that is emergency fire pumps, life boats
essential to maintaining the integrity engines, emergency generators, • checks of engine exhaust and boiler
and safety of the vessel or crew should bilge and fire alarms, etc. flue covers, to make sure they are in
be immediately undertaken. place and secured.

Table 1: Example minimum manning requirements for laid-up ships in port at anchorage

Tanker or chemical carrier Other motorised vessel

Vessel gross Deck Engineering DK/GP ER/GP Total Deck Engineering DK/GP ER/GP Total
tonnage (gt) officers* officers crew crew officers* officers crew crew

< 500 2 1 2 1 6 1 1 1 1 4

500-3,000 2 1 1 1 7 1 1 2 1 5

3,001-6,000 2 2 3 1 8 2 1 2 1 6

6,001-10,000 2 2 3 1 8 2 1 3 1 7

10,001-20,000 2 2 3 2 9 2 1 3 2 8

20,001-35,000 2 2 3 2 9 2 1 4 2 9

35,001-60,000 2 2 3 3 10 2 2 4 2 10

60,001-100,000 2 2 3 3 10 2 2 5 2 11

> 100,001 2 2 3 4 11 2 2 5 3 12

Note: check with flag state, local port and harbour authority for specific lay-up location requirements.
* The number of deck officers includes the master.

22 | Ship lay-up
Appendix 1 – Summary of lay-up considerations

Hot ship, Hot ship, Warm ship Cold ship, Long-term,


<1 month <12 months <12 months <5 years >5 years

Lay-up period Up to 1 month 1-12 months 1-12 months 12-60 months 60 months or longer

Reactivation period ~24 hours ~1 week ~1 week ~3 weeks ~3 months

Class status Classed – full trading Classed – full trading ‘Laid Up' status ‘Laid Up' status ‘Laid Up' status
certificates certificates or short
term certificates

Class attendance Normal survey regime Normal survey regime After 'Laid Up' status assigned and any survey requirements fulfilled.
frequency if crew on board and Annual General Examination of hull and machinery to be held within
'Laid Up' status not survey window period plus an underwater examination to be held at
assigned – flag to be Special Survey due date.
consulted regarding
For reactivation, all overdue surveys are to be brought up to date and
statutory certification
any conditions of class (recommendations) are to be dealt with. If the
vessel is required to sail to a dockyard to complete overdue surveys then
the class society to be contacted for permission and any special
requirements before sailing. Flag requirements are also to be confirmed.

Insurance status Full trading insurance Port risks only Port risks only Port risks only Port risks only

ISM and ISPS Regular scheduled Regular scheduled Reactivation after 3- 6 Interim Verification Interim Verification
certificates audit when due audit when due if months out of service Audit before Audit before
crew on board – Additional reactivation reactivation
Verification Audit.
Reactivation after
more than 6 months
out of service –
Interim Verification
Audit*

MLC Regular scheduled Regular scheduled Regular scheduled Interim MLC Inspection before reactivation
inspections when due inspections when due inspections when due
if crew on board if crew on board. If no
crew on board then
Interim MLC
Inspection before
reactivation.

Port authorities Normal trade status Refer to local lay-up Refer to local lay-up Refer to local lay-up Refer to local lay-up
in port requirements requirements requirements requirements

Optimum manning Minimum safe Engineering and Engineering and Fire, flood, mooring, Fire, flood, mooring,
levels** manning certification navigation officers navigation officers security watch only security watch only
and some crew

Vessel spares control Owner’s crew on Owner’s crew on Owner’s crew on Strict procedures to Strict procedures to
board to control board to control board to control be in place to control be in place to control
spares removal spares removal spares removal spares removal spares removal

Lay-up equipment None As required As required Deck generator Deck generator


onboard generator

Lay-up equipment None As required As required Dehumidifiers with Dehumidifiers with


onboard trunking trunking
dehumidifier

Combustible Normal operation Normal operation Normal operation All combustibles All combustibles
materials control removed removed

Note: this table assumes that the same owner/manager reactivates the ship under the same flag
* The type of audit will depend on the number of ship's crew on board and, consequently, whether the SMS has been maintained
** Refer to local port and harbour authority requirements

Lloyd’s Register May 2020 | 23


Appendix 2 – External hull lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Painting scheme Routine maintenance Maintained by lay-up crew Painted before lay-up Painted before lay-up

Impressed current Routine monitoring Routine monitoring Frequent monitoring Frequent monitoring
cathodic protection

Sacrificial anodes Routine monitoring Routine monitoring Frequent monitoring Frequent monitoring

Hull condition Visual examination above Diver examination before Periodic diver examination Diver examination
waterline lay-up

Appendix 3 – Internal hull lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Ballast tanks Normal operating Emptied (or 100% filled* Emptied (or 100% filled* Emptied (or 100% filled*
(hull stress allowing) condition with water plus corrosion with water plus corrosion with water plus corrosion
inhibitor) inhibitor) inhibitor)

Internal tanks and spaces Normal operating Certified gas free Certified gas free Certified gas free
condition

* Subject to limitations on hull stresses

24 | Ship lay-up
Appendix 4 – Equipment lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Steering gear and bow Routine maintenance Operated monthly Operated or turned Operated or turned
thruster monthly monthly

Anchoring and Routine maintenance Operated monthly Operated or turned Operated or turned
mooring equipment monthly monthly

Deck outfitting Routine maintenance Routine maintenance All moving parts grease All moving parts grease
coated coated

Hatch covers Routine maintenance Routine maintenance All moving parts grease All moving parts grease
coated coated

Life-saving appliances* Fully operational Fully operational Operational for lay-up Operational for lay-up
personnel personnel

Ventilation fire shut-off Routine maintenance Routine maintenance Sealed but exercise Sealed but exercise
dampers regularly regularly

Fire-fighting system* Fully operational Fully operational Fully operational Fully operational

Deck cargo and stores Fully operational Fully operational At least one crane At least one crane
crane operational operational

* Or as required by flag of ship, or local flag administration in the lay-up location

Appendix 5 – Accommodation lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Cabins and public rooms Normal operation Normal operation Dehumidifiers in selected Dehumidifiers in selected
spaces spaces

Accommodation alleys Normal operation Covered in polythene Covered in polythene Covered in polythene
sheets sheets sheets

External doors and Normal operation Unused spaces sealed Sealed spaces, controlled Sealed spaces, controlled
windows access access

Cabin linen, towels Normal operation Normal operation Stored in one dry location Stored in one dry location
and napery

Cabin mattresses Normal operation Normal operation Stored on edge Stored on edge

Sanitary fittings in Normal operation Normal operation Blanked-off and sealed Blanked-off and sealed
accommodation

Refrigerated provision Normal operation Routine maintenance Chambers empty and Chambers empty and
chamber doors open doors open

Refrigeration and Normal operation Routine maintenance Freon gas pumped Freon gas pumped
air conditioning down to condenser down to condenser

Lloyd’s Register May 2020 | 25


Appendix 6 – Machinery lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Engine room ventilating Routine maintenance Reduced air flow De-humidifiers deployed De-humidifiers deployed
system

Main and auxiliary Routine maintenance Operated monthly Lubricated and operated or Lubricated and operated
engines turned monthly or turned monthly

Main and auxiliary engine Routine maintenance Routine maintenance Opened and force ventilated Opened and force ventilated
crankcase condition* with dry air with dry air

Propeller and shafting Routine maintenance Operated monthly Operated or turned Shaft locking devices
monthly installed

Steam generating plant Routine maintenance Emptied (or 100% filled with Emptied and opened for Emptied and opened for
water plus corrosion natural ventilation natural ventilation
inhibitor)

Purifiers and gearboxes Routine maintenance Oil changed and run Oil changed and gear case Oil changed and gear case
monthly left open for drying left open for drying

Sea water cooling system Routine maintenance Emptied (or 100% filled with Emptied and opened for Emptied and opened for
pumps and coolers water plus corrosion natural ventilation natural ventilation
inhibitor)

Fresh water cooling Routine maintenance Emptied (or 100% filled with Emptied and opened for Emptied and opened for
system pumps and water plus corrosion natural ventilation natural ventilation
coolers inhibitor)

Fuel oil system Flushed with diesel oil Flushed with diesel oil Flushed with diesel oil and Flushed with diesel oil and
fuel oil injectors removed fuel oil injectors removed

Lubricating oil system Routine maintenance Routine maintenance Visual check level and Visual check level and
condition condition

Hydraulic oil systems Routine maintenance Operated monthly Operated or turned Operated or turned
monthly monthly

Compressed air system Routine maintenance Routine maintenance Emptied and opened for Emptied and opened for
natural ventilation natural ventilation

Exhaust gas system Routine maintenance Routine maintenance Engine exhaust line Engine exhaust line
blanked blanked

Steam and condensate Shut down Emptied (or 100% filled with Emptied and opened for Emptied and opened for
system water plus corrosion natural ventilation natural ventilation
inhibitor)

Tanks in ER** Routine maintenance Emptied (or 100% filled) Emptied (or 100% filled) Emptied (or 100% filled)

Engine room bilges Routine maintenance Clean for visual leak Clean for visual leak Clean for visual leak
detection detection detection

Engine and cargo space Routine maintenance Routine maintenance Fully operational with Fully operational with
bilge alarms alarm relay alarm relay

Exhaust stack outlet Routine maintenance Routine maintenance To be sealed air tight To be sealed air tight
pipes

* In accordance with the maker’s recommendation


** Different requirements apply for oil and water tanks

26 | Ship lay-up
Appendix 7 – Automation lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Automation equipment Normal operation Normal operation Turned off and kept in a Turned off and kept in a
and computers dry atmosphere dry atmosphere

Power, e.g. uninterrupted Normal operation Normal operation Lithium batteries Lithium batteries
power supply (UPS) disconnected but kept disconnected but kept
lithium batteries charged charged

Main engine remote Normal operation Normal operation Turned off and kept in a Turned off and kept in a
control wheelhouse dry atmosphere dry atmosphere

Main engine remote Normal operation Normal operation Kept dry with desiccant Kept dry with desiccant
control on bridge wing bags bags

Main engine control room Normal operation Normal operation Turned off and kept in dry Turned off and kept in dry
atmosphere atmosphere

Emergency control at Normal operation Normal operation Turned off and kept in dry Turned off and kept in dry
engine side atmosphere atmosphere

Lloyd’s Register May 2020 | 27


Appendix 8 – Electrical system and navigation
gear lay-up checklist

Hot ship, Hot ship or warm ship, Cold ship, Long-term,


<1 month <12 months <5 years >5 years

Alternators, transformers Routine maintenance Routine maintenance De-humidified atmosphere De-humidified atmosphere
and switchboards

Lead acid engine start Routine maintenance Routine maintenance Disconnected and trickle- Renew batteries on
batteries charged reactivation

Electric cabling Routine maintenance Routine maintenance Regular electrical Regular electrical
insulation checks insulation checks

Electric motors and Routine maintenance Local heating of spaces Local heating of spaces Local heating of spaces
starters

External electric motors Routine maintenance Local heating plus motors Motors turned and Motors turned and
turned removed* intodryspace removed* intodryspace

Vessel lighting system Normal operation Reducedin unmanned Turned off except for Turned off except for
spaces inspections inspections

Fire detection and alarm Routine maintenance Routine maintenance Fully operational** and Fully operational** and
able to relay alarms able to relay alarms
required required

CO2 alarm Fully operational Fully operational Fully operational Fully operational

Nautical equipment Normal operation Normal operation Turned off and kept in dry Turned off and kept in dry
atmosphere atmosphere

Radar scanner array Normal operation Operated monthly Operated monthly or Operated monthly or
turned by hand turned by hand

Radio equipment Normal operation Normal operation Turned off and kept in dry Turned off and kept in dry
atmosphere atmosphere

VHF radio Operational Operational Operational Operational

EPIRB and radar Normal operation Normal operation Removed ashore Removed ashore
transponders

* If insulation is inadequate
** Or other alternative measures in place

28 | Ship lay-up
Lloyd’s Register May 2020 | 29
For further information please contact us in the
normal way to discuss any questions or help you
would like from us

info.lr.org/layup

May 2020
Except as permitted under current legislation no part of this work
may be photocopied, stored in a retrieval system, published,
performed in public, adapted, broadcast, transmitted, recorded
or reproduced in any form or by any means, without the prior
permission of the copyright owner.
Enquiries should be addressed to Lloyd’s Register,
71 Fenchurch Street, London, EC3M 4BS.
© Lloyd's Register 2020

Das könnte Ihnen auch gefallen